CN104895570A - 软弱富水地层地铁竖井加固开挖方法 - Google Patents

软弱富水地层地铁竖井加固开挖方法 Download PDF

Info

Publication number
CN104895570A
CN104895570A CN201510298873.XA CN201510298873A CN104895570A CN 104895570 A CN104895570 A CN 104895570A CN 201510298873 A CN201510298873 A CN 201510298873A CN 104895570 A CN104895570 A CN 104895570A
Authority
CN
China
Prior art keywords
excavation
shaft
vertical shaft
floor
weak water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510298873.XA
Other languages
English (en)
Other versions
CN104895570B (zh
Inventor
吴波
何梦超
姚志雄
李静
黄建华
臧万军
张丙强
陈军浩
王启云
赵文娟
催双双
黄惟
王鸣涛
张九香
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian University of Technology
Original Assignee
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian University of Technology filed Critical Fujian University of Technology
Priority to CN201510298873.XA priority Critical patent/CN104895570B/zh
Publication of CN104895570A publication Critical patent/CN104895570A/zh
Application granted granted Critical
Publication of CN104895570B publication Critical patent/CN104895570B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了一种软弱富水地层地铁竖井加固开挖方法,包括如下步骤:步骤1),竖向加固;步骤2),竖向局部开挖;步骤3),横向加固;步骤4),横向扩挖;步骤5),竖井内衬;步骤6),变形监测;步骤7),重复步骤1)-步骤6),开挖至设计标高;步骤8),浇筑底板,开挖至设计标高后,对竖井底部进行浇筑。本发明与传统的开挖方法相比,分层、分部开挖方法能较好保证竖井的稳定性,极大地提高了施工的安全性。分层、分部的加固、开挖有更好的止水效果,避免了开挖过程中出现涌水、突泥等现象,特别适用于软弱富水地层的竖井开挖。分层、分部开挖极大地提高了竖井的稳定性,并且大大降低施工风险,社会、经济效益显著。

Description

软弱富水地层地铁竖井加固开挖方法
技术领域
本发明涉及一种竖井开挖的新方法,具体涉及一种在软弱富水地层中地铁竖井加固开挖方法。
背景技术
我国有相当一部分地区的地质情况较为复杂,这对竖井的顺利开挖带来一定困难,特别是在城市环境下在软弱富水地层中进行竖井开挖时极易出现涌水、突泥、大变形等工程灾害,地面沉降难以控制,进而危及结构及周边建筑安全,使施工无法顺利进行。而现有的竖井开挖技术中,较少涉及如何保证在软弱富水地层中安全、稳定地开挖竖井的方法。
发明内容
本发明的目的就在于弥补现有技术的不足,提供一种在软弱富水地层中地铁竖井加固开挖的新方法。该方法采用预加固,再分层、分部开挖的方式,可以有效地防止开挖过程中井内出现涌水、突泥、大变形等不良现象,降低施工风险。另外采用逆筑法进行内衬施工,节省了临时支撑,不仅避免了因在竖井内搭设横撑导致的作业空间狭小而施工不便的问题,而且大大降低了施工费用。
为达到上述技术效果,本发明的技术方案是:
一种软弱富水地层地铁竖井加固开挖方法,包括如下步骤:
步骤1),竖向加固;采用三轴搅拌桩对竖井设计尺寸区域进行注浆加固,形成第一层1#加固区;
步骤2),竖向局部开挖;进行竖向开挖,开挖第一层1#加固区中间区域,形成第一层1#竖井;
步骤3),横向加固;沿1#竖井井壁向四周插入小导管进行横向的注浆加固,形成第一层2#加固区;
步骤4),横向扩挖;对第一层1#竖井井壁向四周进行横向扩挖至竖井的设计尺寸,形成2#竖井,
步骤5),竖井内衬;开挖完成后立即浇筑冠梁,并进行竖井内衬的施工;
步骤6),变形监测;待围护结构达到设计强度,监测结果无异常则进入下一循环;
步骤7),重复步骤1)-步骤6),开挖至设计标高;
步骤8),浇筑底板,开挖至设计标高后,对竖井底部进行浇筑。
本发明的优点:
1、与传统的开挖方法相比,分层、分部开挖方法能较好保证竖井的稳定性,极大地提高了施工的安全性。
2、与传统的开挖方法相比,分层、分部的加固、开挖有更好的止水效果,避免了开挖过程中出现涌水、突泥等现象,特别适用于软弱富水地层的竖井开挖。
3、与传统的开挖方法相比,分层、分部开挖极大地提高了竖井的稳定性,并且大大降低施工风险,社会、经济效益显著。
4、与传统的开挖方法相比,采用逆筑法进行内衬施工,节省了临时支撑,不仅增大了作业面积,使施工更加方便快捷,而且降低了施工费用。
附图说明
图1总体施工流程图;
图2第二层竖向局部开挖平面示意图;
图3第一层竖向加固示意图;
图4第一层竖向局部开挖示意图;
图5第一层横向加固示意图;
图6第一层横向扩挖示意图;
图7下一层竖向加固示意图;
图8下一层竖向局部开挖示意图;
图9下一层横向加固示意图;
图10下一层横向扩挖示意图;
其中11-1#加固区;12-2#加固区;13-3#加固区;14-4#加固区;Ⅰ-1#竖井;Ⅱ-2#竖井;Ⅲ-3#竖井;Ⅳ-4#竖井;2-冠梁;3-内衬。
具体实施方式
如附图1,完成在软弱富水地层的地铁竖井加固开挖,主要分七步:步骤1),竖向加固;步骤2),竖向局部开挖;步骤3),横向加固;步骤4),横向扩挖;步骤5),竖井内衬;步骤6),变形监测;步骤7),重复步骤1)-步骤6),开挖至设计标高;步骤8),浇筑底板。具体如下。
如附图3所示,步骤1),竖向加固,对第一层1#加固区11进行竖向加固,采用三轴搅拌桩对竖井设计尺寸区域注浆加固约3m~4.5m;
如附图4,步骤2),竖向局部开挖,对第一层1#竖井Ⅰ进行竖向开挖。此阶段只开挖中间区域,四周及底部预留约1.5m~2m厚度的已加固区不挖,以保证竖井的稳定性及抗渗性。
如附图5,步骤3),横向加固,沿1#竖井I井壁向四周插入小导管进行横向的注浆加固,形成第一层2#加固区12,2#加固区12厚度约为1.5m~2m。
如附图6,步骤4),横向扩挖,对第一层1#竖井I井壁向四周进行横向扩挖竖井的设计尺寸,形成2#竖井Ⅱ,步骤5),开挖完成后立即浇筑冠梁2,并进行竖井内衬3的施工;并进行步骤6),进行变形监测。待围护结构达到设计强度,如监测结果无异常则进入下一循环。
结合附图2和附图7,步骤7),重复步骤1),竖向加固,对第二层进行竖向加固,采用三轴搅拌桩对2#竖井II进行竖向加固,形成第二层3#加固区13;
附图8,重复步骤2),竖向局部开挖,对第二层3#竖井III进行竖向开挖。此阶段只开挖中间区域,四周及底部预留约1.5m~2m厚度的已加固区不挖,以保证竖井的稳定性及抗渗性。
附图9,重复步骤3),横向加固,沿3#竖井III井壁向四周插入小导管进行横向的注浆加固,形成第二层4#加固区14,4#加固区14厚度约为1.5m~2m。
附图10,重复步骤4),横向扩挖,对第二层3#竖井III井壁向四周进行横向扩挖竖井的设计尺寸,形成4#竖IV,重复步骤5),开挖完成后立即浇筑冠梁2,并进行竖井内衬3的施工;并进行步骤6),进行变形监测。待围护结构达到设计强度,如监测结果无异常则进入下一循环。
如此循环施工,直至完成步骤7)的循环,开挖至设计标高,实施步骤8),对底板进行浇筑。
以上实例的说明只是用于帮助理解本发明的核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处,综上所述,本说明书内容不应理解为对本发明的限制。

Claims (2)

1.一种软弱富水地层地铁竖井加固开挖方法,其特征在于,包括如下步骤:
步骤1),竖向加固;采用三轴搅拌桩对竖井设计尺寸区域进行注浆加固,形成第一层1#加固区;
步骤2),竖向局部开挖;进行竖向开挖,开挖第一层1#加固区中间区域,形成第一层1#竖井;
步骤3),横向加固;沿1#竖井井壁向四周插入小导管进行横向的注浆加固,形成第一层2#加固区;
步骤4),横向扩挖;对第一层1#竖井井壁向四周进行横向扩挖至竖井的设计尺寸,形成2#竖井,
步骤5),竖井内衬;开挖完成后立即浇筑冠梁,并进行竖井内衬的施工;
步骤6),变形监测;待围护结构达到设计强度即进行变形监测,监测结果无异常则进入下一循环;
步骤7),重复步骤1)-步骤6),开挖至设计标高。
2.根据权利要求1所述的一种软弱富水地层地铁竖井加固开挖方法,其特征在于,还包括步骤8),浇筑底板,开挖至设计标高后,对竖井底部进行浇筑。
CN201510298873.XA 2015-06-03 2015-06-03 软弱富水地层地铁竖井加固开挖方法 Expired - Fee Related CN104895570B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510298873.XA CN104895570B (zh) 2015-06-03 2015-06-03 软弱富水地层地铁竖井加固开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510298873.XA CN104895570B (zh) 2015-06-03 2015-06-03 软弱富水地层地铁竖井加固开挖方法

Publications (2)

Publication Number Publication Date
CN104895570A true CN104895570A (zh) 2015-09-09
CN104895570B CN104895570B (zh) 2017-04-05

Family

ID=54028485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510298873.XA Expired - Fee Related CN104895570B (zh) 2015-06-03 2015-06-03 软弱富水地层地铁竖井加固开挖方法

Country Status (1)

Country Link
CN (1) CN104895570B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114703921A (zh) * 2020-09-11 2022-07-05 北京住总集团有限责任公司 一种基于临时封底结构防突涌的施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1037652A (ja) * 1996-07-26 1998-02-10 Toyo Constr Co Ltd 竪穴の掘削工法
JPH11350474A (ja) * 1998-06-09 1999-12-21 Yuji Kaneko ライナープレート立杭の築造方法
JP2001241287A (ja) * 2000-02-24 2001-09-04 Obayashi Road Corp 立坑の構築方法及び同構築方法に使用する構体の組み立て方法並びに同組み立て方法に使用する組み立て装置
CN101082217A (zh) * 2006-06-02 2007-12-05 韩国石油公社 挖掘垂直孔的方法
CN101598022A (zh) * 2009-05-13 2009-12-09 隋忠良 立井一次成巷的施工方法
CN101638898A (zh) * 2009-08-19 2010-02-03 郑州市市政工程总公司 顶管竖井悬挂式施工方法
CN102305075A (zh) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 一种不良地质条件下的竖井施工方法
CN103758524A (zh) * 2013-12-30 2014-04-30 安徽水安建设集团股份有限公司 一种分段爆破掘进竖井施工方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1037652A (ja) * 1996-07-26 1998-02-10 Toyo Constr Co Ltd 竪穴の掘削工法
JPH11350474A (ja) * 1998-06-09 1999-12-21 Yuji Kaneko ライナープレート立杭の築造方法
JP2001241287A (ja) * 2000-02-24 2001-09-04 Obayashi Road Corp 立坑の構築方法及び同構築方法に使用する構体の組み立て方法並びに同組み立て方法に使用する組み立て装置
CN101082217A (zh) * 2006-06-02 2007-12-05 韩国石油公社 挖掘垂直孔的方法
CN101598022A (zh) * 2009-05-13 2009-12-09 隋忠良 立井一次成巷的施工方法
CN101638898A (zh) * 2009-08-19 2010-02-03 郑州市市政工程总公司 顶管竖井悬挂式施工方法
CN102305075A (zh) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 一种不良地质条件下的竖井施工方法
CN103758524A (zh) * 2013-12-30 2014-04-30 安徽水安建设集团股份有限公司 一种分段爆破掘进竖井施工方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114703921A (zh) * 2020-09-11 2022-07-05 北京住总集团有限责任公司 一种基于临时封底结构防突涌的施工方法

Also Published As

Publication number Publication date
CN104895570B (zh) 2017-04-05

Similar Documents

Publication Publication Date Title
CN102644466B (zh) 岩质地层中修建超浅埋大跨度暗挖地铁车站的托梁拱盖法
CN105298507B (zh) 一种上部明挖下部掘进机施工的地下管廊施工方法
CN204552747U (zh) 一种煤矿立井井壁结构
CN102979531B (zh) 加固大型岩质边坡深部软弱结构面的施工方法和结构
CN105735322A (zh) 一种刚柔复合防渗可回收支护结构的设计施工方法
CN108547639B (zh) 隧道临近既有构筑物的超前同孔多导管分层注浆施工方法
CN103590406A (zh) 一种超大型深基坑分区同步开挖的施工方法
CN102660955B (zh) 一种基坑边坡支护的快速施工方法
CN104131565B (zh) 一种逆作土方正作开挖的施工方法
CN107190752A (zh) 一种柔性复合防渗装配式可回收矩形截面排桩支护结构的设计施工方法
CN104806251A (zh) 一种用于复杂环境下城市地铁车站附属仰挖施工方法
CN107881995A (zh) 不良地质条件下地下厂房岩壁吊车梁开挖施工方法
CN106088154A (zh) 预制装配式地下筒仓复合井筒施工方法及筒仓结构
CN107130611A (zh) 一种柔性复合防渗装配式可回收圆截面排桩支护结构的设计施工方法
CN112727466A (zh) 一种无支护预制拼装式盾构隧道风井结构施工方法
CN102943488A (zh) 软土地区大面积绿化下非开挖实施地下空间的施工方法
CN105909256A (zh) 一种采用掌子面预加固留核心土三台阶临时仰拱技术的大跨软弱围岩隧道施工方法
JP4132442B2 (ja) トンネル施工法
CN109056810A (zh) 既有建筑下方明挖或盖挖地下主体结构的横向扩挖构造及其施工方法
CN101705685B (zh) 地下结构周边梁板踏步式逆作施工方法
CN204457789U (zh) 一种用桩拱墙支撑扩挖大直径盾构隧道建造的地铁车站
CN204851266U (zh) 一种暗挖车站正上方竖井结构
CN204311456U (zh) 基坑加固结构
CN104763437B (zh) 一种强透水地层隧道开挖方法
CN208815560U (zh) 一种地铁暗挖车站施工期间全车站止水的结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170405

Termination date: 20200603