CN103758524A - 一种分段爆破掘进竖井施工方法 - Google Patents

一种分段爆破掘进竖井施工方法 Download PDF

Info

Publication number
CN103758524A
CN103758524A CN201310744066.7A CN201310744066A CN103758524A CN 103758524 A CN103758524 A CN 103758524A CN 201310744066 A CN201310744066 A CN 201310744066A CN 103758524 A CN103758524 A CN 103758524A
Authority
CN
China
Prior art keywords
hole
easer
blasting
order
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310744066.7A
Other languages
English (en)
Other versions
CN103758524B (zh
Inventor
叶炜
李峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ASCG Co Ltd
Original Assignee
ASCG Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ASCG Co Ltd filed Critical ASCG Co Ltd
Priority to CN201310744066.7A priority Critical patent/CN103758524B/zh
Publication of CN103758524A publication Critical patent/CN103758524A/zh
Application granted granted Critical
Publication of CN103758524B publication Critical patent/CN103758524B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

本发明公开了一种分段爆破掘进竖井施工方法,具体包括如下步骤:通过钻孔工艺;清孔、封孔工艺;掏孔;爆破工艺;装药结构及爆破顺序;填塞;起爆方法与网路等步骤进行施工操作。本发明竖(导)井深孔爆破一次钻孔分段爆破成井,即在竖(导)井设计范围内,采用中深孔凿岩设备,一次钻好竖(导)井内全部炮孔,然后分段爆破成井,工艺新颖合理;炮孔一次性钻成,既能加快施工进度,又有利于安全;在小断面难以进行深孔爆破的情况下,采用分段进行爆破,逐段成井;适应于浅井掘进,小断面竖(导)井的掘进;简易可行,设备轻便,机动灵活,劳动强度;与其他现有的掘进方法相比较,具有更大的机动性、适应性、安全性。

Description

一种分段爆破掘进竖井施工方法
技术领域:
本发明涉及竖(导)井使用方法,尤其涉及一种分段爆破掘进竖井施工方法。
背景技术:
竖(导)井施工过程的常规方法是掘进,主要采用分层钻孔爆破,掘进速度慢,工效低,劳动强度大,木材消耗量大,粉尘浓度高,安全性差。
发明内容:
为了弥补现有技术问题,本发明的目的是提供一种分段爆破掘进竖井施工方法,简易可行,设备轻便,机动灵活,劳动强度低,掘进速度慢,工效高,木材消耗量大,粉尘浓度低,安全性提高。
本发明的技术方案如下: 
分段爆破掘进竖井施工方法,其特征在于,具体包括如下步骤:
1)钻孔工艺:
(1)钻孔设备:采用SKD70和SKD100潜孔钻或100型地质钻机,由上向下钻孔;
(2)钻孔实施:开钻前根据设计要求,测定好竖井方位和倾角,给出中心点和孔位;然后将潜孔钻就位,并调整好钻杆的方位和倾角,使之符合设计要求;开孔时首先用采用柱齿钻头,Φ130mm开门钻头,将孔口附近凿平,然后开孔,开孔要慢速、减压、精心操作;当孔深钻到原岩深0.1~0.2m时,停止钻进,校核钻杆的方位和倾角,使之符合设计要求,以控制炮孔偏斜;
2)清孔、封孔工艺:
(1)清孔:钻孔结束后,需立即将提水筒用绳拴挂放入孔内,将残存的冲洗液提出孔外,使钻孔大体干燥、干净;
(2)封孔:清孔后进行封孔,封孔方法如下:
填料选用干燥黏土;
操作方法:填料在下入孔内之前先用锤子砸碎,并过筛除去杂物,以防堵在钻孔中途;投填料时,可备一个漏斗,使其慢慢下落;如发生堵孔,可用绳子拴一根钢钎下入孔内,上下提动几下便可,投入填料直到接近孔口位置,不必砸实;
(3)掏孔:
工具选用套筒、一字钢钎、尖头钢钎和掏勺;
操作方法:先把工作面清理干净,找出钻孔位置,用尖头钢钎把孔口碎石撬松、捣碎,然后下入套筒把碎渣、黏土捞出;所掏炮孔的深度,按照每次爆破需要确定,所掏的孔段必须把泥浆刮干净;
3)爆破工艺:
(1)掏槽方式:双螺旋方式;
(2)爆破参数的确定:
孔径:根据使用的钻孔、钻具,装药孔径定为Φ60mm,以Φ130mm孔径组成两孔的掏槽空孔;
孔距:施工时按设计在竖井中心打两个中心距为380mm的空孔;
第一序掏槽孔至空孔的距离,取250mm;
第二序掏槽孔至空孔间的距离,取300mm;
第三序掏槽孔取400mm;
第四序掏槽孔取500mm;
其中第一序掏槽孔、第二序掏槽孔、第三序掏槽孔、第四序掏槽孔均为两个且对称分布在空孔的外周;
炸药单耗:单位体积炸药消耗量与岩性、竖井断面、分段高度、药包直径及装药结构等因素有关,一般竖(导)井的单耗为4~6kg/m3左右;
每米炮孔装药量:槽孔采用间隔装药,药包Φ480mm;药包长350mm;间隔为200mm,槽孔每米装药量分别为1.1kg,周边孔采用连续柱状装药结构时,每米装药量为1.7~1.8kg;
(3)一次爆破分段高度:一次爆破分段高度主要与爆破条件有关,分段高度一般可达3~5m;
4)装药结构及爆破顺序
(1)炸药:采用乳化炸药,药包规格为48mm×350mm,药包重量0.6kg/个;
(2)装药结构:掏槽孔采用间隔装药,每个药包间隔一个200mm,并在装药全长敷设导爆索,周边孔采用连续柱状装药,采用双起爆药包,一个装在底部,另一个装在装药段上部1/3处;
(3)起爆顺序:按槽孔顺序先放第一序掏槽孔,再依次放第二、三、四序掏槽孔,最后进行周边孔爆破,一般掏槽孔超前周边孔一个分段;
5)填塞:
装药时下填塞高度以不超过该孔最小抵抗线为宜,试验中槽孔下填塞高度一般为0.3~0.4m,周边孔为0.4~0.5m ,上填塞高度为0.5m以上,填塞材料为木楔、炮泥和碎岩渣;
6)起爆方法与网路:
每个炮孔装2发导爆管雷管,用起爆器击发电雷管再反向起爆导爆管,孔内各药包用导爆索连接,毫秒延时间隔时间,考虑炮孔爆破后有充裕的排渣时间,掏槽孔取10~200ms,周边孔取100~250ms。
本发明的优点是: 
1、本发明竖(导)井深孔爆破一次钻孔分段爆破成井,即在竖(导)井设计范围内,采用中深孔凿岩设备,一次钻好竖(导)井内全部炮孔,然后分段爆破成井,工艺新颖合理;
2、本发明竖(导)井炮孔一次性钻成,既能加快施工进度,又有利于安全。在小断面难以进行深孔爆破的情况下,采用分段进行爆破,逐段成井;
3、本发明适应于浅井掘进(一般井深不大于20m),小断面(2m×2m以下)竖(导)井的掘进;
4、本发明方法简易可行,设备轻便,机动灵活,劳动强度;与其他现有的掘进方法相比较,具有更大的机动性、适应性、安全性。
附图说明:
图1为本发明的分段爆破成井示意图, A为竖(导)井,B为隧道。
图2为本发明的炮孔布置图,1为空孔,2为第一序掏槽孔,3为第二序掏槽孔,4为第三序掏槽孔,5为第四序掏槽孔。 
图3为本发明的周边孔连续装药结构示意图,6为导爆管,7为药包。 
图4为本发明的掏槽孔间隔装药结构示意图,6为导爆管,7为药包。 
具体实施方式:
参见附图:
分段爆破掘进竖井施工方法,具体包括如下步骤:
1)钻孔工艺:
(1)钻孔设备:采用SKD70和SKD100潜孔钻或100型地质钻机,由上向下钻孔;
(2)钻孔实施:开钻前根据设计要求,测定好竖井方位和倾角,给出中心点和孔位;然后将潜孔钻就位,并调整好钻杆的方位和倾角,使之符合设计要求;开孔时首先用采用柱齿钻头,Φ130mm开门钻头,将孔口附近凿平,然后开孔,开孔要慢速、减压、精心操作;当孔深钻到原岩深0.1~0.2m时,停止钻进,校核钻杆的方位和倾角,使之符合设计要求,以控制炮孔偏斜;
钻孔中的注意事项:钻孔质量是保证井深孔爆破的关键,为消除或减少钻孔开门时炮孔偏斜,钻头采用柱齿钻头,保证开孔时钻孔不移位,同时提高钻头的使用寿命减少粉尘浓度、提高凿岩效率、降低凿岩成本。
在用支架式潜孔钻孔时,这种钻架轻便,但稳定性差,炮孔偏斜较大,特别是打掏槽孔时,易于相互贯穿,造成炮孔报废,不能满足工艺要求,应自行设计钻架,改善炮孔质量。 
2)清孔、封孔工艺: 
(1)清孔:钻孔结束后,需立即将提水筒用绳拴挂放入孔内,将残存的冲洗液提出孔外,使钻孔大体干燥、干净;
(2)封孔:清孔后进行封孔,封孔方法如下:
填料选用干燥黏土;
操作方法:填料在下入孔内之前先用锤子砸碎,并过筛除去杂物,以防堵在钻孔中途;投填料时,可备一个漏斗,使其慢慢下落;如发生堵孔,可用绳子拴一根钢钎下入孔内,上下提动几下便可,投入填料直到接近孔口位置,不必砸实;
(3)掏孔:
工具选用套筒、一字钢钎、尖头钢钎和掏勺;
操作方法:先把工作面清理干净,找出钻孔位置,用尖头钢钎把孔口碎石撬松、捣碎,然后下入套筒把碎渣、黏土捞出;所掏炮孔的深度,按照每次爆破需要确定,所掏的孔段必须把泥浆刮干净;
3)爆破工艺:
深孔竖(导)井爆破系一次钻孔,分段爆破成井,因每次爆破后要求所有的炮孔畅通,故掏槽应相当可靠,因此使用双空孔方案,来增大了空孔面积,改善了爆破条件,使装药槽孔允许偏差增大,提高了爆破的可靠性;
(1)掏槽方式:双螺旋方式;
(2)爆破参数的确定:
孔径:根据使用的钻孔、钻具,装药孔径定为Φ60mm,以Φ130mm孔径组成两孔的掏槽空孔;
孔距:施工时按设计在竖井中心打两个中心距为380mm的空孔;
第一序掏槽孔至空孔的距离,取250mm;
第二序掏槽孔至空孔间的距离,取300mm;
第三序掏槽孔取400mm;
第四序掏槽孔取500mm;
其中第一序掏槽孔、第二序掏槽孔、第三序掏槽孔、第四序掏槽孔均为两个且对称分布在空孔的外周;
炸药单耗:单位体积炸药消耗量与岩性、竖井断面、分段高度、药包直径及装药结构等因素有关,一般竖(导)井的单耗为4~6kg/m3左右;
每米炮孔装药量:槽孔采用间隔装药,药包Φ480mm;药包长350mm;间隔为200mm,槽孔每米装药量分别为1.1kg,周边孔采用连续柱状装药结构时,每米装药量为1.7~1.8kg;
(3)一次爆破分段高度:一次爆破分段高度主要与爆破条件有关,分段高度一般可达3~5m;
4)装药结构及爆破顺序
(1)炸药:采用乳化炸药,药包规格为48mm×350mm,药包重量0.6kg/个;
(2)装药结构:掏槽孔采用间隔装药,每个药包间隔一个200mm,并在装药全长敷设导爆索(导爆管),周边孔采用连续柱状装药,采用双起爆药包,一个装在底部,另一个装在装药段上部1/3处;
(3)起爆顺序:按槽孔顺序先放第一序掏槽孔,再依次放第二、三、四序掏槽孔,最后进行周边孔爆破,一般掏槽孔超前周边孔一个分段;
5)填塞:
装药时下填塞高度以不超过该孔最小抵抗线为宜,试验中槽孔下填塞高度一般为0.3~0.4m,周边孔为0.4~0.5m ,上填塞高度为0.5m以上,填塞材料为木楔、炮泥和碎岩渣;
6)起爆方法与网路:
竖(导)井深孔爆破一次钻孔分段爆破成井,即在竖(导)井设计范围内,采用中深孔凿岩设备,一次钻好竖(导)井内全部炮孔,然后分段爆破成井:
每个炮孔装2发导爆管雷管,用起爆器击发电雷管再反向起爆导爆管,孔内各药包用导爆索连接,毫秒延时间隔时间,考虑炮孔爆破后有充裕的排渣时间,掏槽孔取10~200ms(1段、3段、5段、7段),周边孔取100~250ms(5段、7段、9段)。
本发明的应用实例: 
宁国市社坞坑调压井导井开挖,深18m,其中从隧洞向上开挖了4m,从上而下开挖14m,导井尺寸2*2m;
佛子岭抽水蓄能电站上库进出口闸门井,深16m,导井尺寸2*2m;
上述两例工程都由于工期紧迫,采用竖(导)井与隧洞同时开挖,与隧洞贯通后再扩大开挖,有效的保证施工进度,实用性强。

Claims (1)

1.一种分段爆破掘进竖井施工方法,其特征在于,具体包括如下步骤:
1)钻孔工艺:
(1)钻孔设备:采用SKD70和SKD100潜孔钻或100型地质钻机,由上向下钻孔;
(2)钻孔实施:开钻前根据设计要求,测定好竖井方位和倾角,给出中心点和孔位;然后将潜孔钻就位,并调整好钻杆的方位和倾角,使之符合设计要求;开孔时首先用采用柱齿钻头,Φ130mm开门钻头,将孔口附近凿平,然后开孔,开孔要慢速、减压、精心操作;当孔深钻到原岩深0.1~0.2m时,停止钻进,校核钻杆的方位和倾角,使之符合设计要求,以控制炮孔偏斜;
2)清孔、封孔工艺:
(1)清孔:钻孔结束后,需立即将提水筒用绳拴挂放入孔内,将残存的冲洗液提出孔外,使钻孔大体干燥、干净;
(2)封孔:清孔后进行封孔,封孔方法如下:
填料选用干燥黏土;
操作方法:填料在下入孔内之前先用锤子砸碎,并过筛除去杂物,以防堵在钻孔中途;投填料时,可备一个漏斗,使其慢慢下落;如发生堵孔,可用绳子拴一根钢钎下入孔内,上下提动几下便可,投入填料直到接近孔口位置,不必砸实;
(3)掏孔:
工具选用套筒、一字钢钎、尖头钢钎和掏勺;
操作方法:先把工作面清理干净,找出钻孔位置,用尖头钢钎把孔口碎石撬松、捣碎,然后下入套筒把碎渣、黏土捞出;所掏炮孔的深度,按照每次爆破需要确定,所掏的孔段必须把泥浆刮干净;
3)爆破工艺:
(1)掏槽方式:双螺旋方式;
(2)爆破参数的确定:
孔径:根据使用的钻孔、钻具,装药孔径定为Φ60mm,以Φ130mm孔径组成两孔的掏槽空孔;
孔距:施工时按设计在竖井中心打两个中心距为380mm的空孔;
第一序掏槽孔至空孔的距离,取250mm;
第二序掏槽孔至空孔间的距离,取300mm;
第三序掏槽孔取400mm;
第四序掏槽孔取500mm;
其中第一序掏槽孔、第二序掏槽孔、第三序掏槽孔、第四序掏槽孔均为两个且对称分布在空孔的外周;
炸药单耗:单位体积炸药消耗量与岩性、竖井断面、分段高度、药包直径及装药结构等因素有关,一般竖(导)井的单耗为4~6kg/m3左右;
每米炮孔装药量:槽孔采用间隔装药,药包Φ480mm;药包长350mm;间隔为200mm,槽孔每米装药量分别为1.1kg,周边孔采用连续柱状装药结构时,每米装药量为1.7~1.8kg;
(3)一次爆破分段高度:一次爆破分段高度主要与爆破条件有关,分段高度一般可达3~5m;
4)装药结构及爆破顺序
(1)炸药:采用乳化炸药,药包规格为48mm×350mm,药包重量0.6kg/个;
(2)装药结构:掏槽孔采用间隔装药,每个药包间隔一个200mm,并在装药全长敷设导爆索,周边孔采用连续柱状装药,采用双起爆药包,一个装在底部,另一个装在装药段上部1/3处;
(3)起爆顺序:按槽孔顺序先放第一序掏槽孔,再依次放第二、三、四序掏槽孔,最后进行周边孔爆破,一般掏槽孔超前周边孔一个分段;
5)填塞:
装药时下填塞高度以不超过该孔最小抵抗线为宜,试验中槽孔下填塞高度一般为0.3~0.4m,周边孔为0.4~0.5m ,上填塞高度为0.5m以上,填塞材料为木楔、炮泥和碎岩渣;
6)起爆方法与网路:
每个炮孔装2发导爆管雷管,用起爆器击发电雷管再反向起爆导爆管,孔内各药包用导爆索连接,毫秒延时间隔时间,考虑炮孔爆破后有充裕的排渣时间,掏槽孔取10~200ms,周边孔取100~250ms。
CN201310744066.7A 2013-12-30 2013-12-30 一种分段爆破掘进竖井施工方法 Active CN103758524B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310744066.7A CN103758524B (zh) 2013-12-30 2013-12-30 一种分段爆破掘进竖井施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310744066.7A CN103758524B (zh) 2013-12-30 2013-12-30 一种分段爆破掘进竖井施工方法

Publications (2)

Publication Number Publication Date
CN103758524A true CN103758524A (zh) 2014-04-30
CN103758524B CN103758524B (zh) 2016-06-29

Family

ID=50525823

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310744066.7A Active CN103758524B (zh) 2013-12-30 2013-12-30 一种分段爆破掘进竖井施工方法

Country Status (1)

Country Link
CN (1) CN103758524B (zh)

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104482816A (zh) * 2014-12-03 2015-04-01 中国矿业大学(北京) 一种立井周边切缝药包梯度预裂爆破方法及装置
CN104819670A (zh) * 2015-05-19 2015-08-05 重庆交通建设(集团)有限责任公司 预钻中孔竖井开挖爆破方法
CN104895570A (zh) * 2015-06-03 2015-09-09 福建工程学院 软弱富水地层地铁竖井加固开挖方法
CN105401946A (zh) * 2015-10-27 2016-03-16 中国水利水电第三工程局有限公司 一种竖井导井的反向爆破开挖方法
CN105486181A (zh) * 2015-11-19 2016-04-13 中国华冶科工集团有限公司 竖井深孔分段爆破方法
CN105674816A (zh) * 2016-01-22 2016-06-15 河北钢铁集团矿业有限公司 用于非煤矿山的中深孔爆破一次成井方法
CN106382120A (zh) * 2016-09-14 2017-02-08 中石化石油工程技术服务有限公司 一种爆破掘进顶管施工方法
CN106677786A (zh) * 2017-01-14 2017-05-17 中铁隧道集团有限公司 一种基于电子雷管的超深大断面竖井一次爆破成井方法
CN107575234A (zh) * 2017-09-07 2018-01-12 长沙有色冶金设计研究院有限公司 一种深井支护设计方法
CN108132006A (zh) * 2017-12-25 2018-06-08 中南大学 防堵塞快速成井掏槽炮孔布置结构及其爆破方法
CN108374661A (zh) * 2018-02-06 2018-08-07 浙江省隧道工程公司 一种中导井一次爆破成井方法
CN109029168A (zh) * 2018-08-20 2018-12-18 河北钢铁集团矿业有限公司 一种井下悬顶的爆破处理方法
CN109539915A (zh) * 2018-12-27 2019-03-29 攀钢集团工程技术有限公司 切割天井爆破施工方法
CN109870084A (zh) * 2019-03-20 2019-06-11 中南大学 一种vcr采矿法免扫孔爆破装药结构及其施工方法
CN110578465A (zh) * 2019-08-27 2019-12-17 湖南柿竹园有色金属有限责任公司 一次成井凿岩布孔方法
CN111089518A (zh) * 2019-12-18 2020-05-01 武汉大学 基于数码电子雷管的小孔间距爆破用起爆装置及安装方法
CN111101952A (zh) * 2019-12-16 2020-05-05 中铁十六局集团路桥工程有限公司 一种复杂层状岩层隧道爆破的施工方法
CN111594174A (zh) * 2020-05-08 2020-08-28 中电建十一局工程有限公司 一种全断面一次成孔分段爆破竖井开挖方法
CN112211639A (zh) * 2020-10-13 2021-01-12 宝钢集团新疆八一钢铁有限公司 一种高深度大断面中深孔一次成井方法
CN112943257A (zh) * 2021-01-25 2021-06-11 中铁十四局集团建筑工程有限公司 一种深大竖井反向钻孔坍塌处理的方法
CN113686215A (zh) * 2021-09-09 2021-11-23 昆明理工大学 一种岩巷大直径双空孔装药精确延时逐孔垂直掏槽爆破方法
CN114961734A (zh) * 2022-07-14 2022-08-30 山东黄金矿业科技有限公司深井开采实验室分公司 适用于超深竖井的钻孔卸压方法
CN115355785A (zh) * 2022-09-15 2022-11-18 中南大学 一种考虑炮孔偏斜的分段爆破成井方法

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4701073A (en) * 1984-12-05 1987-10-20 Sainsbury Garrett Michael Shaft sinking method
JPH0835389A (ja) * 1994-07-25 1996-02-06 Shimizu Corp 地中構造物の掘削工法
JP2000145354A (ja) * 1998-11-11 2000-05-26 Kumagai Gumi Co Ltd 岩盤に於ける深礎掘削工法
CN1434191A (zh) * 2002-01-25 2003-08-06 中国人民解放军工程兵第四十一旅 深井爆破成井施工方法
KR100743453B1 (ko) * 2006-06-02 2007-07-30 한국석유공사 수직 갱 굴착방법
CN101487376A (zh) * 2009-02-14 2009-07-22 中国葛洲坝集团股份有限公司 大直径、大深度调压井导井一次性开挖施工方法
CN102305075A (zh) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 一种不良地质条件下的竖井施工方法
CN102401616A (zh) * 2011-10-11 2012-04-04 中国矿业大学(北京) 立井爆破掘进方法
CN103046931A (zh) * 2012-12-03 2013-04-17 云南建工水利水电建设有限公司 一种竖井/导井冲击式钻机冲击成孔施工方法
CN103184872A (zh) * 2013-03-20 2013-07-03 中国水利水电第十四工程局有限公司 一种大断面竖井一次开挖施工方法

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4701073A (en) * 1984-12-05 1987-10-20 Sainsbury Garrett Michael Shaft sinking method
JPH0835389A (ja) * 1994-07-25 1996-02-06 Shimizu Corp 地中構造物の掘削工法
JP2000145354A (ja) * 1998-11-11 2000-05-26 Kumagai Gumi Co Ltd 岩盤に於ける深礎掘削工法
CN1434191A (zh) * 2002-01-25 2003-08-06 中国人民解放军工程兵第四十一旅 深井爆破成井施工方法
KR100743453B1 (ko) * 2006-06-02 2007-07-30 한국석유공사 수직 갱 굴착방법
CN101487376A (zh) * 2009-02-14 2009-07-22 中国葛洲坝集团股份有限公司 大直径、大深度调压井导井一次性开挖施工方法
CN102305075A (zh) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 一种不良地质条件下的竖井施工方法
CN102401616A (zh) * 2011-10-11 2012-04-04 中国矿业大学(北京) 立井爆破掘进方法
CN103046931A (zh) * 2012-12-03 2013-04-17 云南建工水利水电建设有限公司 一种竖井/导井冲击式钻机冲击成孔施工方法
CN103184872A (zh) * 2013-03-20 2013-07-03 中国水利水电第十四工程局有限公司 一种大断面竖井一次开挖施工方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
吴伟林等: "一次钻孔分次分段爆破技术在竖井开挖中的应用", 《水利科技》, no. 1, 31 January 2007 (2007-01-31), pages 29 - 31 *
张电吉: "深井掘进一次成孔分段爆破试验研究", 《爆破》, vol. 19, no. 3, 30 September 2002 (2002-09-30), pages 36 - 37 *
田爱军等: "深孔掏槽爆破技术在竖井开挖中的应用", 《现代矿业》, no. 8, 31 August 2012 (2012-08-31), pages 63 - 64 *

Cited By (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104482816A (zh) * 2014-12-03 2015-04-01 中国矿业大学(北京) 一种立井周边切缝药包梯度预裂爆破方法及装置
CN104819670A (zh) * 2015-05-19 2015-08-05 重庆交通建设(集团)有限责任公司 预钻中孔竖井开挖爆破方法
CN104895570B (zh) * 2015-06-03 2017-04-05 福建工程学院 软弱富水地层地铁竖井加固开挖方法
CN104895570A (zh) * 2015-06-03 2015-09-09 福建工程学院 软弱富水地层地铁竖井加固开挖方法
CN105401946A (zh) * 2015-10-27 2016-03-16 中国水利水电第三工程局有限公司 一种竖井导井的反向爆破开挖方法
CN105486181A (zh) * 2015-11-19 2016-04-13 中国华冶科工集团有限公司 竖井深孔分段爆破方法
CN105674816A (zh) * 2016-01-22 2016-06-15 河北钢铁集团矿业有限公司 用于非煤矿山的中深孔爆破一次成井方法
CN106382120A (zh) * 2016-09-14 2017-02-08 中石化石油工程技术服务有限公司 一种爆破掘进顶管施工方法
CN106677786A (zh) * 2017-01-14 2017-05-17 中铁隧道集团有限公司 一种基于电子雷管的超深大断面竖井一次爆破成井方法
CN106677786B (zh) * 2017-01-14 2017-11-14 中铁隧道集团有限公司 一种基于电子雷管的超深大断面竖井一次爆破成井方法
CN107575234A (zh) * 2017-09-07 2018-01-12 长沙有色冶金设计研究院有限公司 一种深井支护设计方法
CN108132006A (zh) * 2017-12-25 2018-06-08 中南大学 防堵塞快速成井掏槽炮孔布置结构及其爆破方法
CN108132006B (zh) * 2017-12-25 2019-10-25 中南大学 防堵塞快速成井掏槽炮孔布置结构及其爆破方法
CN108374661A (zh) * 2018-02-06 2018-08-07 浙江省隧道工程公司 一种中导井一次爆破成井方法
CN109029168A (zh) * 2018-08-20 2018-12-18 河北钢铁集团矿业有限公司 一种井下悬顶的爆破处理方法
CN109539915A (zh) * 2018-12-27 2019-03-29 攀钢集团工程技术有限公司 切割天井爆破施工方法
CN109870084A (zh) * 2019-03-20 2019-06-11 中南大学 一种vcr采矿法免扫孔爆破装药结构及其施工方法
CN109870084B (zh) * 2019-03-20 2020-05-08 中南大学 一种vcr采矿法免扫孔爆破装药结构及其施工方法
CN110578465A (zh) * 2019-08-27 2019-12-17 湖南柿竹园有色金属有限责任公司 一次成井凿岩布孔方法
CN111101952A (zh) * 2019-12-16 2020-05-05 中铁十六局集团路桥工程有限公司 一种复杂层状岩层隧道爆破的施工方法
CN111089518A (zh) * 2019-12-18 2020-05-01 武汉大学 基于数码电子雷管的小孔间距爆破用起爆装置及安装方法
CN111594174A (zh) * 2020-05-08 2020-08-28 中电建十一局工程有限公司 一种全断面一次成孔分段爆破竖井开挖方法
CN112211639A (zh) * 2020-10-13 2021-01-12 宝钢集团新疆八一钢铁有限公司 一种高深度大断面中深孔一次成井方法
CN112943257A (zh) * 2021-01-25 2021-06-11 中铁十四局集团建筑工程有限公司 一种深大竖井反向钻孔坍塌处理的方法
CN113686215A (zh) * 2021-09-09 2021-11-23 昆明理工大学 一种岩巷大直径双空孔装药精确延时逐孔垂直掏槽爆破方法
CN113686215B (zh) * 2021-09-09 2022-06-21 昆明理工大学 一种岩巷大直径双空孔装药精确延时逐孔垂直掏槽爆破方法
CN114961734A (zh) * 2022-07-14 2022-08-30 山东黄金矿业科技有限公司深井开采实验室分公司 适用于超深竖井的钻孔卸压方法
CN115355785A (zh) * 2022-09-15 2022-11-18 中南大学 一种考虑炮孔偏斜的分段爆破成井方法
CN115355785B (zh) * 2022-09-15 2024-04-19 中南大学 一种考虑炮孔偏斜的分段爆破成井方法

Also Published As

Publication number Publication date
CN103758524B (zh) 2016-06-29

Similar Documents

Publication Publication Date Title
CN103758524B (zh) 一种分段爆破掘进竖井施工方法
CN102758633B (zh) 一种围岩情况较好的大断面隧道的施工方法
RU2081313C1 (ru) Устройство для разрушения материалов твердых плотных скальных пород и бетона и способ разрушения материалов твердых плотных скальных пород и бетона
CN109209472B (zh) 一种冲孔、爆破、注水相互耦合的煤层卸压防突方法
CN109341449B (zh) 一种大段高天井一次凿岩分段控制爆破成井方法
CN108590688B (zh) 一种带有液压钻机的tbm掘进机及其掘进施工方法
CN102031775B (zh) 硬斜岩中孔爆破钻孔桩施工方法
CN108132006A (zh) 防堵塞快速成井掏槽炮孔布置结构及其爆破方法
CN107120137B (zh) 一种煤巷掘进沿煤层底板深孔预裂爆破抽采方法
CN109000525A (zh) 一种盾构掘进上软下硬地层预裂爆破施工方法
CN109855496B (zh) 隧道中硬岩综合破瓜式深孔掏槽爆破方法
CN111058847B (zh) 一种厚大矿体连续大孔径深孔爆破机械化开采方法
CN115749713A (zh) 岩层变频脉冲缝网压裂方法与装备
CN105423832A (zh) 一种厚壁砖烟囱定向窗的爆破施工方法
RU2699102C1 (ru) Подвесная скважинная забойка
CN102778183B (zh) 一种爆破施工方法
CN108252651B (zh) 综采工作面多点分散平行式炮眼预裂顶板的方法
CN103868420A (zh) 一种矿山平巷掘进掏槽爆破方法
US4069760A (en) Method for driving a shaft with shaped charges
KR20160091291A (ko) 수중암반의 발파공법
RU2444625C1 (ru) Способ разработки трубкообразных и мощных рудных тел
KR101885869B1 (ko) 쏘일 테크를 이용한 암반발파방법
CN110618045B (zh) 一种计算岩石开挖参数的试验方法
CN102486090A (zh) 采场的上部边邦余矿回收以及下部采矿覆盖层形成的方法
CN112964143B (zh) 一种中空孔直眼掏槽三次爆破方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant