CN104878764B - Ecological curtain laying and planting method - Google Patents

Ecological curtain laying and planting method Download PDF

Info

Publication number
CN104878764B
CN104878764B CN201510140561.6A CN201510140561A CN104878764B CN 104878764 B CN104878764 B CN 104878764B CN 201510140561 A CN201510140561 A CN 201510140561A CN 104878764 B CN104878764 B CN 104878764B
Authority
CN
China
Prior art keywords
ecological curtain
row
bearing bar
soil
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510140561.6A
Other languages
Chinese (zh)
Other versions
CN104878764A (en
Inventor
孙淑英
辛胜利
孙明文
孙德森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inner Mongolia University
Original Assignee
Inner Mongolia University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inner Mongolia University filed Critical Inner Mongolia University
Priority to CN201510140561.6A priority Critical patent/CN104878764B/en
Publication of CN104878764A publication Critical patent/CN104878764A/en
Application granted granted Critical
Publication of CN104878764B publication Critical patent/CN104878764B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses an ecological curtain laying and planting method. The method is characterized in that two ends of an ecological curtain can be pressed by additionally arranging load-bearing rods, connection fixing iron wires and connection fixing rings to enable the ecological curtain to be close to a slope, connecting lines at two ends of water-soil blocking belts on the ecological curtain are connectedly fixed to the fixing rings on the connection fixing iron wires, and the connection fixing iron wires are connectedly fixed at the bottoms of the load-bearing rods to enable the ecological curtain and the slope to be a whole. When wind blows, the ecological curtain can protect the slope from being directly blown by high wind, stabilize the slope and block soil-seed loss; when heavy rain and rapid rain fall, rain speed can be reduced, scouring of the slope by rainwater can be reduced, rainwater can be blocked and dispersed, the slope can be reinforced to prevent soil of the slope from sliding down, radial flow and landslide are avoided, water-storage and -retention capability of soil of the slope is improved, plants are enabled to grow exuberantly and distributed uniformly, and vegetation covering degree is increased. The ecological curtain laying and planting method has the advantages of wide material source, simple laying and planting process, easy operation, quick progress and high efficiency.

Description

A kind of ecological curtain cover plant method
Technical field
The present invention relates to grassland desertification improvement, the section water and soil conservation of high hillside fields and revegetation, refer in particular to one kind outdoor Reclaim for soil and slope protection on ore deposit refuse dump the cover plant method of afforestation ecological curtain.
Background technology
At present, known open-pit mine blast side slope is reclaimed and afforested cover plant ecological curtain is longitudinally spaced on individual layer straw screen or mat 50cm-300cm is laterally fixedly installed grass water and soil barrier tape processed, fixed into the soil with 2-4 root long 20cm-40cm branch, curtain and Grass water and soil barrier tape wiring processed between curtain is connected, and sows grass, fills seed, side seam covers fine earth below straw screen or mat, due to The big arid of grassland ecological wind, 6-7 level strong wind, sand happen occasionally, and ecological curtain cover plant, in high hillside fields section, is easily started by strong wind, Wipe out good domatic of cover plant, cause the waste of human and material resources, affect ecological management process, reduce ecological engineering quality, increase multiple Cultivate greening cost, a kind of wind resistance power of development is strong, the cover plant method of efficiency high is to ensure that ecological construction quality, accelerate ecological management and enter Journey is badly in need of.
Content of the invention
Patent of the present invention technical problem to be solved is a kind of cover plant method providing ecological curtain, and this cover plant method can make Ecological curtain is combined into one with domatic, strengthens its wind resistance power, it is to avoid swept by strong wind, soil and slope protection, prevent soil, plant subflow Lose, improve afforestation project quality, increase vegetation coverage.
The technical problem to be solved in the present invention to be realized by following scheme: a kind of ecological curtain cover plant method, it is characterized in that: Square position at slope earth-retaining wall 15cm-100cm, by setting 2 at the parallel inside 3cm-10cm of the width transverse ends of ecological curtain The long 50cm-150cm of root, diameter 1cm-10cm bearing bar, bearing bar in depth descends 20cm-70cm, each solid 2 bearing bar bottoms A fixed 12#-20# is connected iron wire, retaining wall, domatic laterally draws plantation ditch sowing, ecological curtain and two bearing bars pair Together, be layered on below two iron wires that are connected, front end is real with soil pressure, ecological curtain longitudinally spaced 40cm-300cm transverse horizontal to Upper volume ties up the water and soil barrier tape of a high 3cm-15cm, and water and soil barrier tape lateral separation 20cm-40cm reinforces a wiring, water and soil The wiring at barrier tape two ends leaves long 10cm-30cm connecting line, is connected iron wire with water and soil barrier tape relatively upward at two The position of 1cm-5cm, turns round three-sixth turn the iron wire that is connected and makes a diameter 0.3cm-1.5cm and be connected ring, uses water and soil The retainer ring that the wiring at barrier tape two ends and two ends are connected on iron wire is connected, and longitudinally spaced 3m-15m, by ecological curtain The parallel inside 3cm-10cm of width transverse ends two bearing bars are set, two iron wires that are connected are fixed on the bottom of bearing bar Portion, pushing down ecological curtain two ends makes it be close to sow domatic, covering thick layer 1cm-2cm in cover plant good ecological curtain water and soil barrier tape Soil, paving the first row ecological curtain uses 2 bearing bars, 2 iron wires that are connected, the second row ecological curtain and the first row ecological curtain phase The both sides crimping 2cm-8cm connecing, ties up water and soil barrier tape by the position volume of the first row, connecting line is by the first row bearing bar, connection Fixing iron wire, retainer ring are connected, the another side of the second row longitudinally spaced with the first row bearing bar apart from equal, by ecological curtain The inside 3cm-10cm of width transverse horizontal position fix bearing bar, be connected with the iron wire that is connected, by this side Method cover plant successively, except the double bearing bar of the first row setting, dual link fix iron wire, the often row of follow-up cover plant is all to arrange single load-bearing The single iron wire that is connected of bar, according to size, the length of the live gradient, the first row arranges 6-16 root bearing bar, and often row sets later Put 3-8 root bearing bar.
The invention has the advantage that bearing bar, the iron wire that is connected are set up by development, the ring that is connected can be by ecological curtain Two ends are pushed down so as to be close to domatic, the connecting line at water and soil barrier tape two ends on ecological curtain and the fixation being connected on iron wire Ring is connected, and the iron wire that is connected is fastened on the bottom of bearing bar, makes ecological curtain and domatic formation one, when blowing, Ecological curtain can protect domatic prevent from strong wind from directly blowing scraping domatic, consolidate domatic stop soil seed and run off, energy when fall heavy rain, anxious rain Reduction rain speed, reduces rainwater and domatic is washed away, and intercepts dispersion rainwater, and reinforcing is domatic to prevent Soil Slope from gliding, it is to avoid runoff And landslide, increase Soil Slope and retain and conserve soil moisture ability, make luxuriant growth, be evenly distributed, increase vegetation coverage, through 1- The growth of 2 years, the limb of plant, root system and ecological curtain are integrally formed, can preferably cut storage sleet, attracting dust, assemble withered Branch fallen leaves, provide more moisture and nutrient for plant growth, and have material source extensively, cover plant program is simple, easily grasp Make, progress is fast, efficiency high, the advantages of.
Brief description
Below in conjunction with the accompanying drawings for an embodiment:
The structure chart that Fig. 1 is that the present invention is domatic when being embodied as.
Fig. 2 is retaining wall cover plant schematic diagram.
Fig. 3 be connected iron wire, be connected ring.
Fig. 4 is bearing bar.
In Fig. 1: 1, straw screen or mat 2, the iron wire 3 that is connected, the ring 4 that is connected, water and soil barrier tape 5, bearing bar 6, gear soil Wall
Specific embodiment
As depicted in figs. 1 and 2, in square position apart from slope earth-retaining wall 6.5cm-100cm position, the width by straw screen or mat 1 is horizontal The parallel inside 3cm-10cm position in two ends, arranges, fixes 2 bearing bars 5, bearing bar 5 in depth descends 50cm, and the bottom 5 is each Fix a 12#-20# to be connected iron wire 2, retaining wall 6, domatic laterally draw plantation ditch sowing, straw screen or mat 1 and two bearing bars 5 alignment, are layered on below two iron wires 2 that are connected, and front end is real with soil pressure, and the longitudinally spaced 70cm transverse horizontal of straw screen or mat 1 is upwards Volume ties up the water and soil barrier tape 4 of a high 8cm, and water and soil barrier tape 4 lateral separation 25cm reinforces a wiring, water and soil barrier tape 4 Two ends wiring leaves 10cm-30cm connecting line, in the position of two line 2 and water and soil barrier tape 4 1cm-5cm relatively upward that are connected Put, make a diameter 0.3cm-0.6cm and be connected ring 3, with the connection relative with two ends of the wiring at water and soil barrier tape 4 two ends Retainer ring 3 is connected, longitudinally spaced 5m, by the parallel inside 3cm-10cm setting of the width transverse ends of straw screen or mat 1, fixes 2 Bearing bar 5, two iron wires 2 that are connected are fixed on the bottom of bearing bar 5, push down the two ends of straw screen or mat 1, above water and soil barrier tape 4 Cover one layer of thick soil of native 1cm-2cm, the both sides crimping 2cm-8cm that paving the second row straw screen or mat 1 is connected with the first row straw screen or mat 1, water and soil Barrier tape 4 and the first row water and soil barrier tape volume 4 interval tied up, positions are equal, and connecting line and the first row are connected iron wire 2, even Connect retainer ring 3, bearing bar 5 is connected, the another side of the second row longitudinally spaced with the first row bearing bar 5 apart from equal, by grass Bearing bar 5 is fixed in the position of the inside 3cm-10cm of width transverse horizontal of curtain 1, connects fixing iron wire 2 with one fixing with bearing bar 5 Connect, the connecting line of water and soil barrier tape 4 is connected with the iron wire 2 that is connected, the ring 3 that is connected, the first row arranges, fixes 12 Root bearing bar 5, subsequently often 6 bearing bars 5 are fixed in capable setting.

Claims (1)

1. a kind of ecological curtain cover plant method, is characterized in that: in square position at slope earth-retaining wall 15cm-100cm, by ecological curtain 1 long 50cm-150cm of each setting, diameter 1cm-10cm bearing bar, bearing bar at the parallel inside 3cm-10cm of width transverse ends In depth descend 20cm-70cm, fix a 12#-20# and be connected iron wire the bottom of 2 bearing bars is each, retaining wall, domatic Laterally draw plantation ditch sowing, ecological curtain is alignd with two bearing bars, is layered on below two iron wires that are connected, front end soil Compacting, ecological curtain longitudinally spaced 40cm-300cm transverse horizontal scrolls up the water and soil barrier tape tying up a high 3cm-15cm, water and soil Barrier tape lateral separation 20cm-40cm reinforces a wiring, and the wiring at water and soil barrier tape two ends leaves long 10cm-30cm and connects Line, is connected on iron wire at two, and apart from the position of water and soil barrier tape 1cm-5cm relatively upward, being connected, iron wire is turned round Three-sixth turn is made a diameter 0.3cm-1.5cm and is connected ring, is connected with two ends with the wiring at water and soil barrier tape two ends Retainer ring on iron wire is connected, the longitudinally spaced 3m-15m of bearing bar, parallel inwardly by the width transverse ends of ecological curtain 3cm-10cm respectively arranges a bearing bar, and two iron wires that are connected are fixed on the bottom of bearing bar, and pushing down ecological curtain two ends makes It is close to sow domatic, covering thick layer 1cm-2cm soil in cover plant good ecological curtain water and soil barrier tape, spreads the first row ecological curtain Using 2 row bearing bars, 2 iron wires that are connected, the both sides crimping 2cm- that the second row ecological curtain is connected with the first row ecological curtain 8cm, ties up water and soil barrier tape by the position volume of the first row, and connecting line is by the first row bearing bar, the iron wire that is connected, retainer ring even Connect fixation, the another side of the second row longitudinally spaced with the first row bearing bar apart from equal, by ecological curtain width transverse horizontal to Bearing bar is fixed in the position of interior 3cm-10cm, is connected with the iron wire that is connected, according to said method cover plant successively, except first Row setting duplicate rows bearing bar, dual link fix iron wire, and the often row of follow-up cover plant is all that single file bearing bar is single is connected for setting Iron wire, according to size, the length of the live gradient, the first row arranges 6-16 root bearing bar, and often row arranges 3-8 root bearing bar later.
CN201510140561.6A 2015-03-24 2015-03-24 Ecological curtain laying and planting method Active CN104878764B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510140561.6A CN104878764B (en) 2015-03-24 2015-03-24 Ecological curtain laying and planting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510140561.6A CN104878764B (en) 2015-03-24 2015-03-24 Ecological curtain laying and planting method

Publications (2)

Publication Number Publication Date
CN104878764A CN104878764A (en) 2015-09-02
CN104878764B true CN104878764B (en) 2017-01-18

Family

ID=53946425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510140561.6A Active CN104878764B (en) 2015-03-24 2015-03-24 Ecological curtain laying and planting method

Country Status (1)

Country Link
CN (1) CN104878764B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106342433B (en) * 2016-08-04 2019-04-19 孙明文 A kind of curtain fragrant plant combination slope vegetation restoration method
CN109691336A (en) * 2018-12-30 2019-04-30 内蒙古蒙草生态环境(集团)股份有限公司 A kind of Mine production shade water-retaining method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2877271Y (en) * 2006-02-27 2007-03-14 邢雪森 Disposable grass shade
CN201567580U (en) * 2009-12-16 2010-09-01 孙明文 Ecological net
CN202139582U (en) * 2011-06-21 2012-02-08 孙德森 Ecological curtain
CN103821152A (en) * 2013-12-30 2014-05-28 青岛润国生态科技发展有限公司 Combined construction method for anti-shock ecological blankets and W-OH and slope protection structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100920027B1 (en) * 2007-08-03 2009-10-06 주식회사 벽진지오테크닉스 Vegetation Method Reinforced Soil Slopes with Geotextile Curtain Wall combined with steel buckel and anchor Nails

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2877271Y (en) * 2006-02-27 2007-03-14 邢雪森 Disposable grass shade
CN201567580U (en) * 2009-12-16 2010-09-01 孙明文 Ecological net
CN202139582U (en) * 2011-06-21 2012-02-08 孙德森 Ecological curtain
CN103821152A (en) * 2013-12-30 2014-05-28 青岛润国生态科技发展有限公司 Combined construction method for anti-shock ecological blankets and W-OH and slope protection structure

Also Published As

Publication number Publication date
CN104878764A (en) 2015-09-02

Similar Documents

Publication Publication Date Title
CN103806454B (en) Method for pollution control and vegetation recovery of metal sulfide ore solid waste storage yard
CN101818499B (en) Revegetation system on steep rocky slopes and implementing method thereof
CN106638630B (en) Flexible ceramsite board slope ecological afforestation equipment and its greening method
CN108901648A (en) Ecological grass mat and its construction method protected for soil-slope
CN102318538A (en) Rain collection self-pressure irrigation system for loess plateau hilly area step greenhouses
CN105874959A (en) Edge slope vegetation ecological restoration method and system
CN101949222B (en) Movable lotus root-cultivating pool and manufacture method thereof
CN206599772U (en) A kind of cover type biological checkboard
CN109287386A (en) A kind of Football Field Turf and method of construction built using building waste
CN101518186A (en) Method of recovering and reconstructing vegetation of mining land
CN103362135B (en) Fang Beng hilllock, protect water and soil net grass bank protection
CN104878764B (en) Ecological curtain laying and planting method
CN105544567B (en) A kind of civil engineering structure of the full slope greening engineering method of steep rocky slope
CN111254952A (en) Ecological restoration structure of high and steep side slope of refuse dump
CN106193068A (en) A kind of biodegradable assembled lattice for slope ecological greening and using method
CN211816332U (en) Ecological restoration structure of high and steep side slope of refuse dump
CN202139582U (en) Ecological curtain
CN210184018U (en) Strong acid heavy metal mine stope rock slope ecological restoration plant growth bag structure
CN112012229A (en) Ecological restoration system for high steep slope rock slope of limestone mine stope
CN103975738B (en) Based on the vegetation construction method of bastard coal clitter
CN204206808U (en) Defend and control sand straw ecological blanket in a kind of high and cold area
CN111213552A (en) Method for restoring soil of abandoned mine
CN206289637U (en) Flexible ceramsite board slope ecological afforestation equipment
CN206034464U (en) A lattice is assembled to biodegradable for side slope ecological greening
CN106342433B (en) A kind of curtain fragrant plant combination slope vegetation restoration method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant