CN101518186A - Method of recovering and reconstructing vegetation of mining land - Google Patents

Method of recovering and reconstructing vegetation of mining land Download PDF

Info

Publication number
CN101518186A
CN101518186A CN200910068023A CN200910068023A CN101518186A CN 101518186 A CN101518186 A CN 101518186A CN 200910068023 A CN200910068023 A CN 200910068023A CN 200910068023 A CN200910068023 A CN 200910068023A CN 101518186 A CN101518186 A CN 101518186A
Authority
CN
China
Prior art keywords
slash
soil
mining
peat
reconstruction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910068023A
Other languages
Chinese (zh)
Inventor
李银
刘凤明
张艳文
冯保华
刘长伟
吕宝山
李志坚
刘金明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIXIAN INQUISITION&PROGRAMMING DESIGN INSTITUTE OF FORESTRY
Original Assignee
JIXIAN INQUISITION&PROGRAMMING DESIGN INSTITUTE OF FORESTRY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIXIAN INQUISITION&PROGRAMMING DESIGN INSTITUTE OF FORESTRY filed Critical JIXIAN INQUISITION&PROGRAMMING DESIGN INSTITUTE OF FORESTRY
Priority to CN200910068023A priority Critical patent/CN101518186A/en
Publication of CN101518186A publication Critical patent/CN101518186A/en
Pending legal-status Critical Current

Links

Landscapes

  • Cultivation Of Plants (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention relates to a method of recovering and reconstructing vegetation of mining land, which comprises the following steps: clearing float stones and flattening broken stones; laying reticular fiber ecological mats along the slope; and punching holes on the laid ecological mats, mixing and uniformly stirring grass seeds, shrub seeds and loam soil, sowing the mixture into the holes, and then covering the holes by sun-shading nets. The invention can protect water and soil, i.e. prevent soil which is artificially covered on the slope of the broken stones from losing by covering the reticular fiber ecological mats, balance temperature, improve efficiency and prevent sand and dust from blowing.

Description

Mining slash vegetation restoration and reconstruction method
Technical field:
The invention belongs to the recovery of a kind of vegetation and rebuild technology, particularly a kind of mining slash vegetation restoration and reconstruction method.
Background technology:
Because the urban construction paces are accelerated, for mining industry has been created business opportunity, form unordered exploitation and excessive exploitation husky, stone ore, caused the breakage of large tracts of land massif, vegetation deterioration, water and soil loss, sand to play ecological environment problems such as dirt.
At mining slash debris flow slope actual conditions, taked manually to assemble that Ba Tai, explosion dig pit, soil moved in to improve the original is planted; Use bulk container nursery stock, Pt bush mycorrhiza agent, ABT root-inducing powder, SAP water-loss reducer, mulch film soil moisture conservation; Select the drought-resistant plant material for use, tall (the wealthy color leaf tree of pin), irritate, grass, climb the comprehensive that engineering such as rattan tree arrangement and biological treating combine carries out revegetation to the ore faces massif.
1, the mycorhiza agent is used.
Use the Chinese Pt of forest-science academy mycorhiza technology to the tall seeds material of irritating such as arbor-vitae, Chinese pine, rubber Mongolian oak, torch, adopt the direct indirect inoculation methods of inoculating or spraying, irritate, broadcast such as dipping in, soak, mix, all nursery stocks, seed are inoculated processing.
2, select to use the resistance material.
Remove and make good use of existing improvement achievement, outside the advantage of indigenous tree speciess such as performance arbor-vitae, Chinese pine, torch, grass seeds, introduction has shrub and grass seeds cold-resistant, that drought resisting has better economic worth again.
3, the drought resisting water absorbing agent is used.
Use a kind of macromolecule resin material-water absorbing agent, suction and can be plant behind the water and supplied water 30-70 days.Application method has root to execute, dip in three kinds of root and seed treatment.
Problems and shortcomings: through the continuous improvement in 5 years, tree survived, and mining debris flow slope, slash has obtained preliminary containment, and landscape effect has had certain improvement.But owing to all be that stone riprap does not have soil on the mountain, vacant lot between tree and the tree all is rubble, and noon, temperature was up to 60-70 ℃ under shining upon, and the treelet that survives of planting lacks nutrition and moisture just as being grown in the flowerpot, the weather arid time earns a bare living all compares difficulty, does not have amount of growth substantially.If fundamentally do not improve the environmental condition of arboreal growth as early as possible,, also cause the part trees withered dead unavoidably even trees increase the maintenance cost.
Summary of the invention:
Purpose of the present invention just is to overcome above-mentioned the deficiencies in the prior art, and provide a kind of mining slash vegetation restoration and reconstruction method, this method can solve ventilative, not water conservation part, the too high harm of growth season temperature of mining slash stone riprap fragment height to trees.
Technical scheme of the present invention is; A kind of mining slash vegetation restoration and reconstruction method is characterized in that: carry out according to the following step: 1. clear up float stone, smooth rubble; 2. lay the reticular fibre ecological pad along sloping gesture; 3. punching kind of grass punches on the ecological pad of having spread, grass seeds and shrub seeds is mixed with loam mix thoroughly in kind of the hand-hole then, covers the sunshade net then, gets final product.
Above the soil that quality is high covers behind the above-mentioned smooth rubble, 10-15 centimetre of thickness of earth covering average out to.
The aperture of punching on the above-mentioned ecological pad is 5 * 10cm, and pitch of holes is 30cm, and averag density is 10 holes/m 2
Behind the above-mentioned cleaning float stone drill rod is fixed on the stone slope, again wire netting is fixed on the drill rod, on wire netting, stick with paste peat then.
Above-mentioned peat is according to soil 73.6%, the peat composed of rotten mosses 26.26%, xylem fibre 0.12%, water-loss reducer 0.015%, adhesive 0.005% with soil, the peat composed of rotten mosses, xylem fibre, water-loss reducer and sticker.Ratio be mixed and made into; The peat average thickness is 15cm.
The present invention has following advantage and good effect:
1, protection water and soil.
With reticular fibre matter ecological pad artificial earth backing on the stone riprap fragment is domatic is carried out covering protection, effectively prevented the loss of loam, conserved the moisture of soil simultaneously,, promote revegetation for trees and the vegetation that newly recovers provides necessary growth conditions.
2, equilibrium temperature.
Domatic the going up of stone riprap fragment covers after the ecological pad, prevents sun direct projection stone at torridity summer, effectively reduces surface temperature (generally can reduce more than 5 ℃), reduced the injury of ground high temperature to plant; Play the effect (can improve ground temperature 1-2 ℃) of stabilizing and increasing ground temperature winter, reduce the generation of plant frozen injury, improved greatly planting shrub and grass storage rate, increased year increment.
3, improve effect.
Mining slash massif breakage, stone riprap stand in great numbers, lack soil, and condition is very abominable.Although taked multiple measures such as engineering, biology, still be difficult to survival after the planting trees and grass.Ecological pad protect soil, water conservation, temperature adjustment, comprehensive function such as long-acting, created a comparatively adapt circumstance for the forest cover that recover in the mining slash, make mining slash vegetation restoration and reconstruction receive the effect of getting twice the result with half the effort.The ecological pad method is used in mining slash revegetation, can make the duration shorten 1/3-1/2, saves investment 40-50%.
4, prevent sand, a dirt.
Embodiment:
1,, adopt ecological pad to cover and punching kind of grass greenization haplotype governance model to slow plot, debris flow slope, mining slash.
Smooth and the earthing of rubble: the float stone of mining slash broken stone slope and the place of being uneven are carried out smooth, loam is unlucky preferably goes up a hill quality, spills thickness of earth covering average out to 10-15cm on whole domatic upper berth of getting well.
Lay ecological pad: lay ecological pad along sloping gesture, ecological pad fix, prevent the ecological pad downslide or swept by wind every the timber of a long 60cm of 1-1.5m nail.
Punching kind of grass: on the ecological pad of having spread, punch, aperture 5 * 10cm, the spacing 30cm in hole, averag density is 10 holes/m 2With grass seeds such as high wool and chaste tree slightly, shrub seedses such as wild jujube, shrub lespedeza, wych-elm mix with loam and mix thoroughly in kind of the hand-hole, cover the sunshade net then and look the timely maintenance of damage caused by a drought, guarantee the seed germination growth.
2, the sheer that the gradient precipitous (gradient is more than 50 degree), water and soil are difficult to keep in the mining slash adopts linked network to stick with paste peat+ecological pad governance model.
Cleaning float stone: mainly be that float stone loosening on the sheer is cleared up, discharge dangerous situation, for safe construction is carried out preliminary preparation.
Fixing metal net: make drill rod with 12# steel gold earlier, drill rod is fixed on the stone slope, again specification is fixed on the drill rod for the thick 2mm in footpath, mesh 50 * 50mm wire netting by design density.
The online peat of sticking with paste: with sticker, xylem fibre, water-loss reducer, the peat composed of rotten mosses and soil, mix, make the peat paste in the ratio of specification requirement.Stick with paste peat the enterprising pedestrian worker of wire netting then, the peat average thickness is 15cm, to guarantee filling, grass seed germination and growth.
Lay ecological pad, punching kind of grass: with 1.
3, domatic or at the stone riprap fragment than the ratchel district, by the design seeding row spacing stone inspection is opened earlier, build tree well dark, each 80cm of length and width then, bottom and around spread ecological pad, fill and lead up with loam then.Plant evergreen, color leaf in the hole or climb the rattan seeds, the back that plants trees covers with ecological pad under tree.
The reticular fibre matter biological environmental production material ecological pad that above-mentioned reticular fibre ecological pad selects for use Malaysia benefit fruit group company to produce, its thickness be 1 centimetre, wide be 100 centimetres, long 10 meters.

Claims (5)

1, a kind of mining slash vegetation restoration and reconstruction method is characterized in that: carry out according to the following step: 1. clear up float stone, smooth rubble; 2. lay the reticular fibre ecological pad along sloping gesture; 3. punching kind of grass punches on the ecological pad of having spread, grass seeds and shrub seeds is mixed with loam mix thoroughly in kind of the hand-hole then, covers the sunshade net then, gets final product.
2, mining according to claim 1 slash vegetation restoration and reconstruction method is characterized in that: above the soil that quality is high covers behind the above-mentioned smooth rubble, and 10-15 centimetre of thickness of earth covering average out to.
3, mining according to claim 1 slash vegetation restoration and reconstruction method, it is characterized in that: the aperture of punching on the above-mentioned ecological pad is 5 * 10cm, and pitch of holes is 30cm, and averag density is 10 holes/m 2
4, mining according to claim 1 slash vegetation restoration and reconstruction method is characterized in that: behind the above-mentioned cleaning float stone drill rod is fixed on the stone slope, wire netting is fixed on the drill rod again, stick with paste peat then on wire netting.
5, mining according to claim 4 slash vegetation restoration and reconstruction method is characterized in that: above-mentioned peat is according to soil 73.6%, the peat composed of rotten mosses 26.26%, xylem fibre 0.12%, water-loss reducer 0.015%, adhesive 0.005% with soil, the peat composed of rotten mosses, xylem fibre, water-loss reducer and sticker.Ratio be mixed and made into; The peat average thickness is 15cm.
CN200910068023A 2009-03-04 2009-03-04 Method of recovering and reconstructing vegetation of mining land Pending CN101518186A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910068023A CN101518186A (en) 2009-03-04 2009-03-04 Method of recovering and reconstructing vegetation of mining land

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910068023A CN101518186A (en) 2009-03-04 2009-03-04 Method of recovering and reconstructing vegetation of mining land

Publications (1)

Publication Number Publication Date
CN101518186A true CN101518186A (en) 2009-09-02

Family

ID=41079149

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910068023A Pending CN101518186A (en) 2009-03-04 2009-03-04 Method of recovering and reconstructing vegetation of mining land

Country Status (1)

Country Link
CN (1) CN101518186A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102668836A (en) * 2012-05-07 2012-09-19 青岛高次团粒生态技术有限公司 Spray-sowing greening method for red mud stacking areas
CN102668835A (en) * 2012-05-07 2012-09-19 青岛高次团粒生态技术有限公司 Revegetation method for tailings dams in northern region
CN103814646A (en) * 2014-03-03 2014-05-28 九州生态股份有限公司 Gobi revegetation method
CN104081908A (en) * 2014-07-03 2014-10-08 中国地质调查局西安地质调查中心 Soilless matrix refitting technology for vegetation recovery of serpentinite waste rock ballast field
CN104396522A (en) * 2014-11-25 2015-03-11 魏建群 Ecological protection method of road slope
CN106234136A (en) * 2016-08-12 2016-12-21 宁波海逸园林工程有限公司 A kind of restoration of the ecosystem Tending methods of high density Diplopterygium glaucum (Thunb ex Houtt) Nakai degeneration evergreen broadleaf forest
CN107047173A (en) * 2017-01-05 2017-08-18 江西省科学院生物资源研究所 A kind of method that utilization shrub lespedeza container seedling quickly repairs southern metal tail sand storage
CN110089382A (en) * 2019-04-11 2019-08-06 唐山明辉企业管理咨询有限公司 A kind of vegetation arrangement method based on ecological restoration of mine
CN116267079A (en) * 2023-03-22 2023-06-23 美丽华夏生态环境科技有限公司 Method for recovering vegetation of coal gangue mountain by using starch-based biodegradable plant-growing bag

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102668836A (en) * 2012-05-07 2012-09-19 青岛高次团粒生态技术有限公司 Spray-sowing greening method for red mud stacking areas
CN102668835A (en) * 2012-05-07 2012-09-19 青岛高次团粒生态技术有限公司 Revegetation method for tailings dams in northern region
CN102668836B (en) * 2012-05-07 2013-10-16 青岛冠中生态股份有限公司 Spray-sowing greening method for red mud stacking areas
CN103814646A (en) * 2014-03-03 2014-05-28 九州生态股份有限公司 Gobi revegetation method
CN104081908A (en) * 2014-07-03 2014-10-08 中国地质调查局西安地质调查中心 Soilless matrix refitting technology for vegetation recovery of serpentinite waste rock ballast field
CN104081908B (en) * 2014-07-03 2016-04-06 中国地质调查局西安地质调查中心 The nothing soilization matrix remodeling method of serpentinite barren rock slag field revegetation
CN104396522A (en) * 2014-11-25 2015-03-11 魏建群 Ecological protection method of road slope
CN106234136A (en) * 2016-08-12 2016-12-21 宁波海逸园林工程有限公司 A kind of restoration of the ecosystem Tending methods of high density Diplopterygium glaucum (Thunb ex Houtt) Nakai degeneration evergreen broadleaf forest
CN107047173A (en) * 2017-01-05 2017-08-18 江西省科学院生物资源研究所 A kind of method that utilization shrub lespedeza container seedling quickly repairs southern metal tail sand storage
CN110089382A (en) * 2019-04-11 2019-08-06 唐山明辉企业管理咨询有限公司 A kind of vegetation arrangement method based on ecological restoration of mine
CN116267079A (en) * 2023-03-22 2023-06-23 美丽华夏生态环境科技有限公司 Method for recovering vegetation of coal gangue mountain by using starch-based biodegradable plant-growing bag
CN116267079B (en) * 2023-03-22 2024-01-02 美丽华夏生态环境科技有限公司 Method for recovering vegetation of coal gangue mountain by using starch-based biodegradable plant-growing bag

Similar Documents

Publication Publication Date Title
CN106900342B (en) Integrated semi-lithologic high slope vegetation reconstruction protection method
CN101518186A (en) Method of recovering and reconstructing vegetation of mining land
US9089097B2 (en) Method for improving survival rate of directly-planted seedling and transplanting seedling of haloxylon plant in desert or semi-desert environment
CN107700429B (en) Slope runoff erosion preventing device and slope runoff erosion preventing method
WO2021175263A1 (en) Fully-ecological slope spray-seeding structure and construction method
CN104196006B (en) Desertification soil remediation method
KR101224632B1 (en) The environment-friendly vegetative soil composition and method of slope afforestantion using thereof
CN206189228U (en) Moving walkways tree well with it collects filtration slowly -releasing function to subtract dirt and rainwater
CN108464215B (en) Large-size woody plant transplanting method for coastal saline-alkali soil
CN109832074B (en) Method for recovering vegetation in karst region lead-zinc ore polluted rocky desertification area
CN104314086A (en) Highly-steep rock slope ecological restoration structure and implementation method
CN107964963B (en) Repair technology and construction method for high-steep slope wound surface fiber skeleton aggregate structure
CN103708776A (en) Ecological recovery method with combination application of planting ecological concrete and high-molecular aggregates
KR101419494B1 (en) Planting composition for greening a slope and greeningmethod using same
CN111011093A (en) High rainfall rapid and steep rocky slope greening method
CN112211203A (en) High-strength structure organic fiber composite repair method for high and steep slope
CN111173008A (en) Ecological restoration method for joint development high and steep rocky slope
CN102257945A (en) Wicker basket hole fixing planting method for mine side slope
CN107232003B (en) Construction method for planting water-resistant arbor in water
CN102199921B (en) Method for greening semi-weathered rocky side slope by using indigenous plants
CN111576453A (en) Slope anchor hanging net and exposed rock mass ecological restoration method using same
CN204570710U (en) A kind of ecological revetment system
CN104737738B (en) Method of greening bare slope by utilizing local herbaceous plants
CN112012229A (en) Ecological restoration system for high steep slope rock slope of limestone mine stope
CN106717226A (en) One kind application Stalk blanket carries out method for greening desert

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20090902