CN104631492A - Underground arch top plate mounting method - Google Patents

Underground arch top plate mounting method Download PDF

Info

Publication number
CN104631492A
CN104631492A CN201510004194.7A CN201510004194A CN104631492A CN 104631492 A CN104631492 A CN 104631492A CN 201510004194 A CN201510004194 A CN 201510004194A CN 104631492 A CN104631492 A CN 104631492A
Authority
CN
China
Prior art keywords
arch top
top board
mounting method
underground
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510004194.7A
Other languages
Chinese (zh)
Other versions
CN104631492B (en
Inventor
王国富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Rail Transit Group Co Ltd
Original Assignee
Jinan Rail Transit Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Rail Transit Group Co Ltd filed Critical Jinan Rail Transit Group Co Ltd
Priority to CN201510004194.7A priority Critical patent/CN104631492B/en
Publication of CN104631492A publication Critical patent/CN104631492A/en
Application granted granted Critical
Publication of CN104631492B publication Critical patent/CN104631492B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Abstract

The invention relates to the technical field of construction engineering, in particular to an underground arch top plate mounting method. The method mainly comprises the steps that a pipe roof is driven into soil for forepoling, a groove is drilled, longitudinal beams are mounted, and a prefabricated arch top plate is mounted. By means of the underground arch top plate mounting method, the quality is reliable, cost is low, the effects of environment protection and energy conservation are achieved, construction is easy and safe, the construction period is short, and the waterproof effect is good.

Description

The mounting method of a kind of underground arch top board
Technical field
The present invention relates to construction engineering technical field, specifically the mounting method of a kind of underground arch top board.
Background technology
The construction in current interval tunnel mainly contains shield method or shallow burial hidden digging.Wherein, shield method is applicable to middle Soft Soil Layer and the larger running tunnel of buried depth, adopts shield duct piece to carry out supporting, has that cost is higher, time is longer, shield structure well affects the defects such as road traffic.Shallow burial hidden digging adopts steel grating, sprayed mortar, form concrete composition support system, need at underground cast-in-place steel concrete, exist long in time limit, poor working environment, security risk are many, quality is difficult to ensure the defects such as card.
Summary of the invention
The object of the invention is to overcome above-mentioned the deficiencies in the prior art, providing that a kind of reliable in quality, with low cost, environmental protection and energy saving, construction are simple and safe, short construction period and the technical scheme of the mounting method of the underground arch top board of good water-proof effect.
Technical problem to be solved by this invention realizes by the following technical solutions: the mounting method of a kind of underground arch top board, comprises the following steps:
A: be drilled with groove to projected depth in the soil body;
B: two longerons are inserted in groove, makes two longerons be overlapped on the concrete precast pile of both sides, tunnel respectively;
C: inserted one by one in groove by prefabricated arch top board, makes the both sides of prefabricated arch top board be overlapped on longeron, and multiple prefabricated arch top board connects as one.
Technical scheme of the present invention also has: in the soil body, set pipe canopy before described step a carry out advance support.Adopt the technical program, can prevent from being drilled with soil body landslide in groove process.
Technical scheme of the present invention also has: after described step c completes, extract pipe canopy and inject the hole that cement grout backfill pipe canopy formed at soil layer.Adopt the technical program, can realize the recovery of pipe canopy, the secondary contributing to pipe canopy utilizes, and has saved steel.
Technical scheme of the present invention also has: described concrete precast pile is provided with bracket, and the both sides of described prefabricated arch top board are overlapped on bracket.
Technical scheme of the present invention also has: be provided with water proof rubber pad between adjacent two prefabricated arch top boards in described step c, and described water proof rubber pad arranges continuously along the end face of prefabricated arch top board and bonds with the end face of adjacent two prefabricated arch top boards fixing respectively.Adopt the technical program, ensure the waterproof effect of underground arch top board.
Technical scheme of the present invention also has: the installation using hanging device false longeron and prefabricated arch top board in described step b and step c.
Technical scheme of the present invention also has: the material of described prefabricated arch top board is fibrous concrete.Adopt the technical program, the toughness of prefabricated arch top board is high, reduces the possibility of prefabricated arch roof break.
Technical scheme of the present invention also has: the span of described prefabricated arch top board is 4.5-7 rice, and the length of prefabricated arch top board is 2-6 rice.
Relative to prior art, beneficial effect of the present invention is:
(1) due to prefabricated arch top board of the present invention be tie up muscle, formwork in the factory, build, maintenance forms, therefore its quality is better than cast in situs, ensure that workmanship.
(2) because prefabricated arch top board of the present invention is in factory's centralized production, the dispersion avoiding the resource such as material, electric power uses, and waste reduces, with low cost, also reduces the impact of cast in situs construction on surrounding environment, shortens construction period.
(3) mounting method of underground of the present invention arch top board is assembled by multiple volume, the rational prefabricated arch top board of weight, and the process of the therefore transport of prefabricated arch top board, lifting, installation is simple, safety.
Accompanying drawing explanation
Fig. 1 is the schematic longitudinal section after pipe canopy has set.
Fig. 2 be Fig. 1 along A-A to sectional view.
Fig. 3 be drilled with groove complete after schematic longitudinal section.
Fig. 4 be Fig. 3 along B-B to sectional view.
Longeron is pushed the schematic longitudinal section after groove by Fig. 5.
Fig. 6 be Fig. 5 along C-C to sectional view.
Prefabricated arch top board is pushed the schematic longitudinal section after groove by Fig. 7.
Fig. 8 be Fig. 7 along D-D to sectional view.
Fig. 9 extracts pipe canopy out and schematic longitudinal section after injecting the hole that cement grout backfill pipe canopy formed at the soil body.
In figure: 1, prefabricated arch top board, 2, groove, 3 concrete precast piles, 4, bracket, 5, Guan Peng, 6, longeron, 7, water proof rubber pad, 8, cement grout.
Detailed description of the invention
For the technical characterstic of this programme can be clearly demonstrated, with reference to the accompanying drawings the specific embodiment of the invention is described further below.
A mounting method for underground arch top board, comprises the following steps:
A: set pipe canopy 5 and carry out advance support (as shown in Figure 1 and Figure 2) in the soil body, be then drilled with groove 2 to projected depth (as shown in Figure 3, Figure 4) below pipe canopy 5;
B: two longerons 6 are inserted in groove 2, make two longerons 6 be overlapped on the concrete precast pile 3 of both sides, tunnel respectively, described concrete precast pile 3 is provided with bracket 4, and described longeron 6 is overlapped on (as shown in Figure 5, Figure 6) on bracket 4;
C: prefabricated arch top board 1 is inserted in groove 2 one by one, the both sides of prefabricated arch top board 1 are made to be overlapped on longeron 6, multiple prefabricated arch top board 1 connects as one, be provided with water proof rubber pad 7 between adjacent two prefabricated arch top boards 1, described water proof rubber pad 7 arranges continuously along the end face of prefabricated arch top board 1 and bonds with the end face of adjacent two prefabricated arch top boards 1 respectively fixing (as shown in Figure 7, Figure 8); Extract pipe canopy 5 and inject cement grout 8 and backfill the hole (as shown in Figure 9) that pipe canopy 5 formed at soil layer.
The installation of hanging device false longeron 6 and prefabricated arch top board 1 can be used in described step b and step c.
The material of described prefabricated arch top board 1 is fibrous concrete, and the span of prefabricated arch top board is 5.4 meters, and the length of prefabricated arch top board is 3 meters.
By reference to the accompanying drawings embodiments of the invention are elaborated above, but the present invention is not limited to above-described embodiment, in the ken that those of ordinary skill in the art possess, can also makes a variety of changes under the prerequisite not departing from present inventive concept.

Claims (8)

1. a mounting method for underground arch top board, comprises the following steps:
A: be drilled with groove to projected depth in the soil body;
B: two longerons are inserted in groove, makes two longerons be overlapped on the concrete precast pile of both sides, tunnel respectively;
C: inserted one by one in groove by prefabricated arch top board, makes the both sides of prefabricated arch top board be overlapped on longeron, and multiple prefabricated arch top board connects as one.
2. the mounting method of underground according to claim 1 arch top board, is characterized in that: in the soil body, set pipe canopy before described step a carry out advance support.
3. the mounting method of underground according to claim 1 arch top board, is characterized in that: after described step c completes, extract pipe canopy and inject the hole that cement grout backfill pipe canopy formed at soil layer.
4. the mounting method of underground according to claim 1 arch top board, is characterized in that: described concrete precast pile is provided with bracket, and the both sides of described prefabricated arch top board are overlapped on bracket.
5. according to the mounting method of the arbitrary described underground arch top board of claim 1-4, it is characterized in that: be provided with water proof rubber pad between adjacent two prefabricated arch top boards in described step c, described water proof rubber pad arranges continuously along the end face of prefabricated arch top board and bonds with the end face of adjacent two prefabricated arch top boards fixing respectively.
6., according to the mounting method of the arbitrary described underground arch top board of claim 1-4, it is characterized in that: the installation using hanging device false longeron and prefabricated arch top board in described step b and step c.
7., according to the mounting method of the arbitrary described underground arch top board of claim 1-4, it is characterized in that: the material of described prefabricated arch top board is fibrous concrete.
8., according to the mounting method of the arbitrary described underground arch top board of claim 1-4, it is characterized in that: the span of described prefabricated arch top board is 4.5-7 rice, the length of prefabricated arch top board is 2-6 rice.
CN201510004194.7A 2015-01-06 2015-01-06 A kind of installation method of underground arch top board Active CN104631492B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510004194.7A CN104631492B (en) 2015-01-06 2015-01-06 A kind of installation method of underground arch top board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510004194.7A CN104631492B (en) 2015-01-06 2015-01-06 A kind of installation method of underground arch top board

Publications (2)

Publication Number Publication Date
CN104631492A true CN104631492A (en) 2015-05-20
CN104631492B CN104631492B (en) 2016-08-17

Family

ID=53210690

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510004194.7A Active CN104631492B (en) 2015-01-06 2015-01-06 A kind of installation method of underground arch top board

Country Status (1)

Country Link
CN (1) CN104631492B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107191677A (en) * 2017-06-22 2017-09-22 中交二公局第五工程有限公司 A kind of oil-gas pipeline protector and its construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1179501A (en) * 1997-10-24 1998-04-22 北京城建地铁地基工程有限责任公司 Construction method for supporting and excavating of plate inserting floor of soil based tunnel and its plate inserting machine
JPH11152761A (en) * 1997-11-19 1999-06-08 Kajima Corp Underground structure and construction method thereof
CN101725155A (en) * 2009-12-02 2010-06-09 李宪奎 Multi-direction rotary jetting stirring grouting reinforcement construction method for constructing underground structure and soil body by cover excavation and underground excavation and supporting structure thereof
CN201991017U (en) * 2011-03-30 2011-09-28 中铁一局集团有限公司 Subway large-span station body structure based on arch cover method construction forming
CN202989952U (en) * 2012-11-12 2013-06-12 中铁二院工程集团有限责任公司 Tunnel lining structure with pile-foundation bearing arch
CN103670442A (en) * 2012-09-04 2014-03-26 苏国建 Prefabricated concrete hyperbolical thin-shell arch type assembled underground space engineering supporting structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1179501A (en) * 1997-10-24 1998-04-22 北京城建地铁地基工程有限责任公司 Construction method for supporting and excavating of plate inserting floor of soil based tunnel and its plate inserting machine
JPH11152761A (en) * 1997-11-19 1999-06-08 Kajima Corp Underground structure and construction method thereof
CN101725155A (en) * 2009-12-02 2010-06-09 李宪奎 Multi-direction rotary jetting stirring grouting reinforcement construction method for constructing underground structure and soil body by cover excavation and underground excavation and supporting structure thereof
CN201991017U (en) * 2011-03-30 2011-09-28 中铁一局集团有限公司 Subway large-span station body structure based on arch cover method construction forming
CN103670442A (en) * 2012-09-04 2014-03-26 苏国建 Prefabricated concrete hyperbolical thin-shell arch type assembled underground space engineering supporting structure
CN202989952U (en) * 2012-11-12 2013-06-12 中铁二院工程集团有限责任公司 Tunnel lining structure with pile-foundation bearing arch

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107191677A (en) * 2017-06-22 2017-09-22 中交二公局第五工程有限公司 A kind of oil-gas pipeline protector and its construction method

Also Published As

Publication number Publication date
CN104631492B (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN108204240B (en) Anti-floating reinforcement system and reinforcement method for newly-built tunnel to span existing tunnel in short distance
CN102002956B (en) Multi-level fully-closed reinforcement technology of exposed fault zone of excavated side slope
CN103114857A (en) Shield tunnel construction method
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN104612696B (en) Overpass column hole method construction method is passed through in big cross section tunneling subway station in fine sand layer
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN103924793A (en) Old house reinforcing structure and reinforcing method thereof
CN107165661A (en) A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method
CN110004981A (en) A kind of combined assembled underground structure and reversed construction method
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN102425155B (en) Method for reinforcing overlying shallow rockmass in mined-out area
CN106988760A (en) Facility-sliding strata tunnel portal reinforcing construction and construction method
CN204959762U (en) Barricade formula portal crane track girder construction
CN203161244U (en) Existing subway underground excavation running tunnel protection structure
CN109056810A (en) The transverse direction that open cut or lid dig underground main structure below existing building digs construction and its construction method
CN103233753A (en) Pipe curtain shed frame method used for full-face excavation of construction of shallow-buried large-scale subsurface structure
RU2485318C1 (en) Method to construct station tunnels with low subsidence of earth surface
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN106640155A (en) Large-span underground space structure and construction method thereof
CN104695966B (en) A kind of construction method of underground arch top board
CN105240023A (en) Method of adopting curved pipe-jacking supporting structure for extension of shield-driven subway station
CN205036388U (en) Block of four encircles knot hunch construction structures that PBA secretly dug subway station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant