CN104863613B - Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method - Google Patents

Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method Download PDF

Info

Publication number
CN104863613B
CN104863613B CN201510095971.3A CN201510095971A CN104863613B CN 104863613 B CN104863613 B CN 104863613B CN 201510095971 A CN201510095971 A CN 201510095971A CN 104863613 B CN104863613 B CN 104863613B
Authority
CN
China
Prior art keywords
steel
collar tie
tie beam
pipe pile
prestress anchorage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510095971.3A
Other languages
Chinese (zh)
Other versions
CN104863613A (en
Inventor
宋超业
熊田芳
张先锋
杜道龙
徐福东
宋仪
王宁
张美琴
李利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRTG Survey and Design Institute Co Ltd filed Critical CRTG Survey and Design Institute Co Ltd
Priority to CN201510095971.3A priority Critical patent/CN104863613B/en
Publication of CN104863613A publication Critical patent/CN104863613A/en
Application granted granted Critical
Publication of CN104863613B publication Critical patent/CN104863613B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention belongs to tunneling and underground engineering technique of design and construction fields more particularly to a kind of rocky stratum tunneling underground structure flash joist anchor to draw just branch structure and construction method, it is characterised in that:It is closed by gunite concrete face layer between the steel-pipe pile surface and adjacent steel-pipe pile, the top of the steel-pipe pile is longitudinally connected using top ring beam, collar tie beam mud jacking steel pipe is embedded in the top ring beam, the collar tie beam prestress anchorage cable, steel-pipe pile prestress anchorage cable are vertically arranged, one end of the collar tie beam prestress anchorage cable is installed in top ring beam and is locked by collar tie beam fixing piece, the steel-pipe pile prestress anchorage cable is located at the lower section of the collar tie beam prestress anchorage cable, and the collar tie beam prestress anchorage cable is fixed on by concrete fixing piece on the gunite concrete face layer.The present invention is suitable for the straight flange wall preliminary bracing structure of weak rocky stratum Large span tunnel and underground structure, and straight flange wall construction is stablized, and construction efficiency is improved.

Description

Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
Technical field
The invention belongs to tunneling and underground engineering technique of design and construction field more particularly to a kind of rocky stratum tunneling Lower structure flash joist anchor draws just branch structure and construction method.
Background technology
With the development of the causes such as economic construction and national defence, the exploitation of the large space underground structure of different function disclosure satisfy that It is continuously increased in China's urban construction with applying, such as subway station, underground power house and civil air defense constructions and installations.
Large Underground Structure is built in rocky stratum, mean level lateral pressure is limited, for the ease of using, reducing investment outlay With easy for construction, generally use straight flange wall arch section structure.In wall rock condition preferably and under the conditions of be buried, tunneling is using new Method construction difficult to understand, preliminary bracing use anchor pole+gunite concrete structure.But complex environment builds subway station and people's air defense work in city When the Large Underground Structures such as journey, influenced by geological conditions and buried depth limitation, the stratum that general tunnel or underground structure pass through is Entirely, strong, middle weathered rock formation, developmental joint fissure, Grades of Surrounding Rock are IV~V grades.General subway station uses two layers or three layers (Transfer stop)Design, for the height of straight flange wall in 8~15m, the isostructural straight peripheral wall height of underground power house is likely to be breached 30~40m. For in the shallower soft stratum of buried depth or straight peripheral wall height is more than the Large Underground Structure of 15m, the place of high straight flange wall Reason is exactly the key points and difficulties position in engineering construction, mishandling to be easy to cause the engineering accidents such as landslide, unstability.
Simultaneously as tunnel is still in rocky stratum, the intensity of rock mass is much larger than the soil body, and straight flange wall excavation in tunnel is applied It also needs to take blasting construction method in work.Therefore, in the structural shape and scheme choice of high straight flange wall, guarantee should be based oneself upon Under conditions of safety, while considering construction efficiency and economic benefit, uses construction method rapidly and efficiently as possible.
For the underground structure of high side wall in weak rocky stratum, abutment wall supporting construction generally uses grid steel frame or type Steel steelframe combination gunite concrete and anchor pole form preliminary bracing structure, and currently used construction method is shallow burial hidden digging. The construction method that high straight flange wall construction is most suitable in shallow burial hidden digging is undoubtedly benching tunnelling method, but by wall rock condition, buried depth and week The influence of surrounding environment factor, benching tunnelling method construction is often it is difficult to ensure that abutment wall rock mass and stable structure, and Deformation control energy force difference.This When construction in mainly using intersect median septum(CRD), two side-wall pilot tunnel, the substeps cross-cut such as the holes middle hole Fa Hece method method, These construction methods are required for that a large amount of lateral and vertical temporary support is arranged to realize that substep subtracts high cross-cut, and tunnel span is larger When also need setting mid-board.It results in abandoned project amount so significantly to increase, while lateral and vertical temporary support setting, sternly Construction space and construction speed are affected again, and work efficiency is extremely low, can not achieve big machineryization construction.Moreover, tunnel lower layer and The temporary support on upper layer is difficult to retain before when ensuing blast, and also safe thing can be caused since explosion damages temporary support when serious Therefore.
Traditional straight flange wall uses steelframe gunite concrete structure, applies man-hour requirement and is connect according to the height excavated every time Leg is constructed, and the excavation of each step height increases the sedimentation of arch structure and stratum there are one the hanging operating mode in abutment wall bottom Deformation, and there are certain security risks.Meanwhile each step abutment wall excavate after need the regular hour set up grid and into Row construction of shotcrete, is unfavorable for country rock and the quick closure of structure, and working procedure also has certain intersection.
Invention content
Stringent control under the mechanics feature and complicated environmental condition of the high straight flange wall construction in present invention combination shallow embedding lithostratigraphy System requires, and to ensure that straight flange wall construction is stablized, improves construction efficiency, proposes a kind of rocky stratum tunneling underground structure flash joist anchor Just branch structure and construction method are drawn, realizes that big machineryization carries out lithostratigraphy high retaining wall underground structure construction.
The technical solution adopted in the present invention is:A kind of first branch structure of rocky stratum tunneling underground structure flash joist anchor drawing, It is characterized in that:Including steel-pipe pile, gunite concrete face layer, top ring beam, collar tie beam prestress anchorage cable, steel-pipe pile prestressed anchor Rope, collar tie beam fixing piece, concrete fixing piece are sealed between the steel-pipe pile surface and adjacent steel-pipe pile by gunite concrete face layer It closes, the top of the steel-pipe pile is longitudinally connected using top ring beam, and collar tie beam mud jacking steel pipe is embedded in the top ring beam, described Collar tie beam prestress anchorage cable, steel-pipe pile prestress anchorage cable are vertically arranged, and one end of the collar tie beam prestress anchorage cable is installed on top circle It is locked on beam and by collar tie beam fixing piece, the steel-pipe pile prestress anchorage cable is located at the lower section of the collar tie beam prestress anchorage cable, institute Collar tie beam prestress anchorage cable is stated to be fixed on the gunite concrete face layer by concrete fixing piece.
The steel duct filling concrete mortar of the steel-pipe pile, the steel-pipe pile use diameter 219mm, thickness 8mm steel pipes, Steel pipe 800~1500mm of spacing, steel pipe lower part are embedded in bottom of foundation ditch >=2m, and steel pipe top anchors into top ring beam depth >=1m.
The gunite concrete face layer is C20 gunite concretes face layer.
The top ring beam is reinforced concrete structure.
The collar tie beam fixing piece is channel steel or I-steel waist rail, and the concrete fixing piece is channel steel or I-steel waist rail.
The quantity of the collar tie beam prestress anchorage cable is together.
A kind of rocky stratum tunneling underground structure flash joist anchor draws the construction method of just branch structure, which is characterized in that including Following steps:
(1)The arch preliminary bracing of underground structure upper layer is performed, according to strata condition using superpower slip casting ductule, grid steel Frame and construction of shotcrete;
(2)After the completion of the preliminary bracing of upper layer arch, is excavated in abutment wall and set steel-pipe pile on the outside of position, made using down-the-hole drill Hole, underthrust steel pipe, then pressure injection 1:1 cement mortar;
(3)Steel-pipe pile top rebars concrete top collar tie beam is poured, and buries collar tie beam mud jacking steel pipe in longeron, waits for top Collar tie beam carries out supplement slip casting after reaching design strength, fills top ring beam bottom gap, reinforces top ring beam bottom country rock, simultaneously Embedded casing is reserved in top ring beam applies prestress anchorage cable condition;
(4)Collar tie beam prestress anchorage cable and collar tie beam fixing piece are applied in top ring beam position, collar tie beam prestress anchorage cable is first Road anchor cable carries out tensioning and anchoring by design requirement;
(5)The structure bottom step soil body is excavated apart from sidewall profile certain distance kerve, is not less than 1.5m models close to abutment wall Interior Mining in Rock Mass photoface exploision or non-explosive excavation are enclosed, the layer supporting of abutment wall gunite concrete face is applied when excavating, is excavated to the Steel-pipe pile prestress anchorage cable and waist rail are applied at two anchor cable positions, tensioning and anchoring are carried out by design requirement;
(6)Repeating said steps(5)Continue to be layered and excavate rock mass downwards, applies abutment wall gunite concrete face layer and anchor cable branch Shield so far forms flash joist anchor and draws just branch structure until being excavated to underground structure substrate absolute altitude.
The step(2)Middle steel pipe pile driving construction is constructed using hole is jumped.
Beneficial effects of the present invention are:
1, rocky stratum tunneling underground structure flash joist anchor of the invention draws just branch structure and construction method, anchor to draw just branch knot Structure is combined and is formed by steel-pipe pile, gunite concrete face layer, top ring beam, collar tie beam prestress anchorage cable, steel-pipe pile prestress anchorage cable, is fitted For the straight flange wall preliminary bracing structure of weak rocky stratum Large span tunnel and underground structure, straight flange wall construction is stablized, and width is provided Spacious space and raising construction efficiency;
2, construction applies steel-pipe pile in tunneling space, reinforcing bar is used at the top of steel-pipe pile in advance using the theory of open-cut foundation ditch The connection of concrete collar tie beam is integral, then carries out underground structure lower layer excavation, and gunite concrete face layer is carried out when excavating abutment wall And prestressing anchor support carries out underground structure main body reinforcing bar from lower to upper therewith until carrying out back cover behind underground structure bottom Concreting removes prestress anchorage cable according to each layer structure construction height and monitoring measurement result;
3, the rocky stratum tunneling underground structure flash joist anchor in the present invention draws first branch structure to have structure type simple, holds Loading capability is strong, and control deformability is good, reduces abandoned project amount, convenient and quick construction and construction period can provide open operation The features such as space, construction organization facilitates;
4, the rocky stratum tunneling underground structure flash joist anchor in the present invention draws the construction method of just branch structure, the engineering method work Skill is simple and convenient to operate, and well controls stratum deformation, and can be that entire underground structure engineering construction realizes that big machinery is turned into industry Offer condition improves work efficiency, saves project cost;
5, the present invention provides a kind of shallow embedding or the high side wall branch in weak rocky stratum Large span tunnel or Large Underground space The combination application of the multinomial technology of protection structure form, construction method and innovation, structure is reasonable, construction procedure it is simple and implement into Degree is fast, solves that weak rocks quality floor height straight flange wall hole room stability is poor, and traditional steelframe and temporary support structures form are complicated, Construction efficiency and environmental condition are poor, and stratum deformation is larger in digging process, and construction safety risk is big and construction organization inconvenience etc. Many problems have preferably expanded the application space of Excavation Method Under Shallow, are later shallow buried covered excavation high retaining wall underground knot The design and construction of structure provides new approaches, has higher reference value.
6, it in the case where high side wall steel pipe anchor draws just branch structural defence, safely and fast completes tunnel lower part excavation and agent structure is poured It builds.
Description of the drawings
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the construction schematic diagram of steel-pipe pile in the present invention;
Fig. 3 is the construction schematic diagram of top ring beam in the present invention;
Fig. 4 is the construction schematic diagram of Girth prestress anchorage cable of the present invention;
Fig. 5 is that anchor of the present invention draws just branch structure abutment wall lower layer's bench excavation and supporting construction schematic diagram;
Fig. 6 is that the anchor of the present invention draws just branch structure abutment wall substrate construction schematic diagram.
Specific implementation mode
The invention will be further described below in conjunction with the accompanying drawings:
In figure, 1- steel-pipe piles, 2- gunite concretes face layer, 3- top ring beams, 4- collar tie beam prestress anchorage cables, 5- steel-pipe piles are pre- Stress anchor cable, 6- collar tie beam fixing pieces, 7- concrete fixing pieces, 8- collar tie beam mud jacking steel pipes, the preliminary bracing of the arch 9-.
Embodiment
As shown in Figure 1, a kind of rocky stratum tunneling underground structure flash joist anchor draws just branch structure, including steel-pipe pile 1, injection Concrete topping 2, top ring beam 3, collar tie beam prestress anchorage cable 4, steel-pipe pile prestress anchorage cable 5, collar tie beam fixing piece 6, concrete are solid Determine part 7, closed by gunite concrete face layer 2 between 1 surface of steel-pipe pile and adjacent steel-pipe pile 1, the top of steel-pipe pile 1 is using top Portion's collar tie beam 3 is longitudinally connected, and collar tie beam mud jacking steel pipe 8, collar tie beam prestress anchorage cable 4, steel-pipe pile prestressed anchor are embedded in top ring beam 3 Rope 5 is vertically arranged, and one end of collar tie beam prestress anchorage cable 4 is installed in top ring beam 3 and is locked by collar tie beam fixing piece 6, steel pipe Stake prestress anchorage cable 5 is located at the lower section of collar tie beam prestress anchorage cable 4, and collar tie beam prestress anchorage cable 4 is fixed on by concrete fixing piece 7 On gunite concrete face layer 2.
The steel duct filling concrete mortar of steel-pipe pile 1, steel-pipe pile 1 is using diameter 219mm, thickness 8mm steel pipes, between steel pipe Away from 800~1500mm, steel pipe lower part is embedded in bottom of foundation ditch >=2m, and steel pipe top anchors into 3 depth of top ring beam >=1m.
Gunite concrete face layer 2 is C20 gunite concretes face layer.
Top ring beam 3 is reinforced concrete structure.
Collar tie beam fixing piece 6 is channel steel or I-steel waist rail, and concrete fixing piece 7 is channel steel or I-steel waist rail.
The quantity of collar tie beam prestress anchorage cable 4 is together.
Collar tie beam prestress anchorage cable 4, steel-pipe pile prestress anchorage cable 5 longitudinal pitch according to steel-pipe pile 1 determine, vertically away from It should be calculated and be determined according to practical geologic parameter from, parameters such as length, diameter, anchorage depth and prestressing force size.
Above-mentioned rocky stratum tunneling underground structure high side wall steel pipe anchor draws first branch structure, the structure drafted to can be used for tunnel With the straight flange wall preliminary bracing of 8~30m of underground structure height, should ensure that vertical precision when steel pipe is set, bottom answer build-in in On firm rock foundation, intensification and consolidation process otherwise should be carried out.
A kind of rocky stratum tunneling underground structure flash joist anchor draws the construction method of just branch structure, includes the following steps:
(1)Underground structure upper layer arch advance support and arch preliminary bracing 9 are performed, advance support can be according to strata condition Using advance anchor bolt, superpower slip casting ductule or pipe shed support, arch preliminary bracing 9 is applied using grid steel frame and gunite concrete Work, arch preliminary bracing 9 should close cyclization in time;
(2)It is excavated in abutment wall and sets steel-pipe pile 1 on the outside of position, putting distance outside should determine according to construction precision and error, beat If the circular hole of diameter 250mm is first made when steel-pipe pile 1 with down-the-hole drill, underthrust diameter 219mm, thickness 8mm steel pipes, pipe shaft drill straight diameter 20mm apertures, quincuncial arrangement, then pressure injection 1:1 cement mortar fills the gap between steel duct and steel pipe and pore-forming, steel Pile pile 1 longitudinal pitch 800mm, bottom building-in depth 2.5m, top are embedded in 3 1.2m of top ring beam, the drilling of steel-pipe pile 1 take every Pile driving construction;
(3)Pour the top ring beam 3 of steel-pipe pile 1, every section of longitudinal length about 10m, 3 size 1.5m × 1.8m of top ring beam, Steel pipe is welded with ring beam reinforcing steel bar, and collar tie beam mud jacking steel pipe 8 is buried in top ring beam 3, waits for that 3 concrete of top ring beam reaches Supplement slip casting is carried out after design strength, fills longeron bottom gap, reinforces longeron bottom country rock, while being buried in top ring beam 3 4 condition of collar tie beam prestress anchorage cable is applied if casing is reserved, the also foundation longitudinal beam as arch secondary lining of top ring beam 3;
(4)First of anchor cable i.e. collar tie beam prestress anchorage cable 4 is applied, first of anchor cable is arranged in steel-pipe pile 1 and top longitudinal beam It overlaps in range, using 3 φ s15.2 steel strand wires, pre-applied force 200KN transfers steel strand wires after pore-forming, and installation collar tie beam fixing piece 6 is pressed Design requirement carries out tensioning and anchoring, and anchor cable longitudinal pitch combination steel-pipe pile 1 is arranged as 1.6m, and vertical 3~4m of spacing is together;
(5)The structure bottom step soil body is excavated apart from sidewall profile certain distance kerve, is not less than 1.5m models close to abutment wall Interior Mining in Rock Mass photoface exploision or non-explosive excavation are enclosed, 2 supporting of layer of gunite concrete face are applied when excavating, are excavated to second 0.5m applies collar tie beam prestress anchorage cable 4 and concrete fixing piece 7 under anchor cable position, and tensioning and anchoring are carried out by design requirement;
(6)Continue to excavate rock mass downwards, when excavation answers longitudinal framing, vertical layered, symmetrical to excavate, while applying abutment wall spray Concrete layer 2 and cable bolting are penetrated, until being excavated to underground structure substrate absolute altitude, appearance infiltration is larger between pile lining in digging process When, timely ejection for water plugging is answered, high side wall steel pipe anchor structure is ultimately formed.
(7)It is excavated to timely flat bottom after substrate, bed course and waterproof layer is applied, then applies secondary lining from lower to upper Reinforced concrete structure removes prestress anchorage cable according to each layer structure construction height and monitoring measurement result.
Structure of the invention and engineering method are suitable for the Gao Zhi of the underground spaces such as rocky stratum large span section subway station or tunnel Abutment wall supporting and construction, should strictly control excavation height in construction, weak blast reinforces Vault settlement and abutment wall horizontal distortion prison It surveys.
1 embodiment of the present invention is described in detail above, but the content is only the preferable implementation of the present invention Example should not be construed as limiting the practical range of the present invention.It is all according to all the changes and improvements made by the present patent application range Deng should all still fall within the scope of the patent of the present invention.

Claims (7)

1. a kind of rocky stratum tunneling underground structure high side wall steel pipe anchor draws the construction method of just branch structure, the anchor to draw just branch knot Structure includes that steel-pipe pile, gunite concrete face layer, top ring beam, collar tie beam prestress anchorage cable, steel-pipe pile prestress anchorage cable, collar tie beam are fixed Part, concrete fixing piece are closed between the steel-pipe pile surface and adjacent steel-pipe pile by gunite concrete face layer, the steel pipe The top of stake is longitudinally connected using top ring beam, and collar tie beam mud jacking steel pipe, the collar tie beam prestressing force are embedded in the top ring beam Anchor cable, steel-pipe pile prestress anchorage cable are vertically arranged, and one end of the collar tie beam prestress anchorage cable is installed in top ring beam and passes through Collar tie beam fixing piece is locked, and the steel-pipe pile prestress anchorage cable is located at the lower section of the collar tie beam prestress anchorage cable, and the collar tie beam is answered in advance Power anchor cable is fixed on by concrete fixing piece on the gunite concrete face layer, which is characterized in that is included the following steps:
(1)Perform the arch preliminary bracing of underground structure upper layer, according to strata condition using superpower slip casting ductule, grid steel frame and Construction of shotcrete;
(2)After the completion of the preliminary bracing of upper layer arch, is excavated in abutment wall and set the steel-pipe pile with building-in depth on the outside of position, used Down-the-hole drill pore-creating, underthrust steel pipe, then pressure injection 1:1 cement mortar;
(3)Steel-pipe pile top rebars concrete top collar tie beam is poured, and buries collar tie beam mud jacking steel pipe in longeron, waits for top ring beam Supplement slip casting is carried out after reaching design strength, fills top ring beam bottom gap, reinforces top ring beam bottom country rock, while pushing up Embedded casing is reserved on portion's collar tie beam applies prestress anchorage cable condition;
(4)Collar tie beam prestress anchorage cable and collar tie beam fixing piece are applied in top ring beam position, collar tie beam prestress anchorage cable is first of anchor Rope carries out tensioning and anchoring by design requirement;
(5)The structure bottom step soil body is excavated apart from sidewall profile certain distance kerve, close to abutment wall not less than within the scope of 1.5m Mining in Rock Mass photoface exploision or non-explosive excavation apply the layer supporting of abutment wall gunite concrete face when excavating, are excavated to second Steel-pipe pile prestress anchorage cable and waist rail are applied at anchor cable position, and tensioning and anchoring are carried out by design requirement;
(6)Repeating said steps(5)Continue to be layered and excavate rock mass downwards, applies abutment wall gunite concrete face layer and cable bolting, Until being excavated to underground structure substrate absolute altitude, so far forms flash joist anchor and draw just branch structure.
2. a kind of rocky stratum tunneling underground structure flash joist anchor according to claim 1 draws the construction party of just branch structure Method, it is characterised in that:The steel duct filling concrete mortar of the steel-pipe pile, the steel-pipe pile is using diameter 219mm, thickness 8mm steel pipes, steel pipe 800~1500mm of spacing, steel pipe lower part are embedded in bottom of foundation ditch >=2m, and steel pipe top anchors into top ring beam depth ≥1m。
3. a kind of rocky stratum tunneling underground structure flash joist anchor according to claim 1 draws the construction party of just branch structure Method, it is characterised in that:The gunite concrete face layer is C20 gunite concretes face layer.
4. a kind of rocky stratum tunneling underground structure flash joist anchor according to claim 1 draws the construction party of just branch structure Method, it is characterised in that:The top ring beam is reinforced concrete structure.
5. a kind of rocky stratum tunneling underground structure flash joist anchor according to claim 1 draws the construction party of just branch structure Method, it is characterised in that:The collar tie beam fixing piece is channel steel or I-steel waist rail, and the concrete fixing piece is channel steel or I-steel Waist rail.
6. a kind of rocky stratum tunneling underground structure flash joist anchor according to claim 1 draws the construction party of just branch structure Method, it is characterised in that:The quantity of the collar tie beam prestress anchorage cable is together.
7. a kind of rocky stratum tunneling underground structure flash joist anchor according to claim 1 draws the construction party of just branch structure Method, it is characterised in that:The step(2)Middle steel pipe pile driving construction is constructed using hole is jumped.
CN201510095971.3A 2015-03-04 2015-03-04 Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method Active CN104863613B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510095971.3A CN104863613B (en) 2015-03-04 2015-03-04 Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510095971.3A CN104863613B (en) 2015-03-04 2015-03-04 Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method

Publications (2)

Publication Number Publication Date
CN104863613A CN104863613A (en) 2015-08-26
CN104863613B true CN104863613B (en) 2018-08-28

Family

ID=53909736

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510095971.3A Active CN104863613B (en) 2015-03-04 2015-03-04 Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method

Country Status (1)

Country Link
CN (1) CN104863613B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013171B (en) * 2016-06-30 2019-02-01 大连理工大学 A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN110566228B (en) * 2019-09-24 2024-02-09 中铁第六勘察设计院集团有限公司 Tunnel middle partition wall with repeated supporting and locking functions and construction method thereof
CN111537258B (en) * 2020-05-22 2022-07-15 中国水利水电第十六工程局有限公司 Dam concrete prestress anchor cable blasting demolition sampling method
CN113339004B (en) * 2021-06-03 2023-01-24 上海市城市建设设计研究总院(集团)有限公司 Construction method of prestressed steel structure advanced support

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2481759Y (en) * 2001-06-29 2002-03-13 孙洪涛 Steel-pipe pile and anchor bar combined foundation pit supporting member
KR100805189B1 (en) * 2006-09-12 2008-02-21 신일씨엔아이(주) Construction method of underground structure characterized by going side by side wall construction and excavation
CN201406687Y (en) * 2009-04-13 2010-02-17 中冶实久建设有限公司 Deep foundation pit supporting structure
CN201991017U (en) * 2011-03-30 2011-09-28 中铁一局集团有限公司 Subway large-span station body structure based on arch cover method construction forming
CN202466594U (en) * 2011-12-29 2012-10-03 标力建设集团有限公司 Horizontal jet grouting soil anchoring and cast-in-place pile compound foundation pit supporting structure
CN102758632B (en) * 2012-07-19 2014-10-29 中铁隧道集团有限公司 Rock stratum double initial support layering method for establishing large-scale underground structure
CN202830942U (en) * 2012-08-27 2013-03-27 中铁二院工程集团有限责任公司 Combined supporting structure with anchor cables and cast-in-situ bored piles
CN202969392U (en) * 2012-12-06 2013-06-05 中铁四局集团有限公司 Combined support for complex geological deep foundation pit
CN103132531A (en) * 2013-02-28 2013-06-05 四川省长源建筑工程有限责任公司 Foundation pit supporting system construction method
CN204059372U (en) * 2014-08-07 2014-12-31 青岛海川建设集团有限公司 A kind of vertical permanent suspension device of rock mass
CN204000901U (en) * 2014-08-07 2014-12-10 青岛海川建设集团有限公司 The vertical high slope prestressing anchor support of a kind of massif device

Also Published As

Publication number Publication date
CN104863613A (en) 2015-08-26

Similar Documents

Publication Publication Date Title
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN105888703B (en) Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN102226403B (en) Construction method of large-span subway station main body by using arched cover method and station main body structure
CN102758632B (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN102644466B (en) Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
CN202969392U (en) Combined support for complex geological deep foundation pit
CN201991017U (en) Subway large-span station body structure based on arch cover method construction forming
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN104612162A (en) Subway station deep foundation pit excavation construction method
WO2022122052A1 (en) Comprehensive construction method for shallow buried section of tunnel using urban railway mine tunneling method
CN104612696B (en) Construction method for large-section underground excavation subway station to pass through viaduct in fine sand layer by using column hole method
CN205100989U (en) Utilize oblique access structure of subway access & exit double as construction
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN103362513A (en) Transformation and construction method for existing cavity in underground excavation region
CN112663625A (en) Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN201801872U (en) Deep foundation pit excavated on corrode geology through combined support
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN110566223A (en) deep-buried PBA subway station section design method
CN203229955U (en) Foundation pit enclosure structure allowing supporting while excavating
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190203

Address after: 300000 Tianjin Free Trade Test Zone (Airport Economic Zone) No. 36 West Central Road

Patentee after: CHINA RAILWAY LIUYUAN GROUP CO., LTD.

Address before: No. 1 Hebei street, Hongqiao District, Tianjin City, Tianjin

Patentee before: Zhongtie Tunnel Survey and Design Inst., Ltd.

TR01 Transfer of patent right