Background technology
At present, along with the continuous development of urban construction and infrastructure, the development and utilization of the extensive underground space, the deep foundation pit support engineering under the complicated geological environment is increasing thus, and the scale of deep-foundation pit engineering and the degree of depth all continue to increase.Panzhihua City Taizhou commercial building deep foundation pit support engineering, original design unit adopts design, the construction supporting engineering of soil nailing wall in conjunction with sample project in the antislide pile combined supporting scheme.Pattern foundation pit supporting structure closes on highway one side and adopts the antislide pile supporting, and other three are adopted soil-nail wall support.Construction progress in early stage is very smooth, the antislide pile of highway one side and the construction of soil-nailed wall on other two sides are finished substantially, when last side soil nailing wall of construction, engineering geological conditions changes and worsens rapidly, cause the soil nailing wall to lose support action, and cause side slope top existing building composition deformation and can not continue the construction, after taking to stablize supporting measure, engineering was stopped work nearly one month comprehensively temporarily.
As shown in Figure 1, the expropriation of land red line of last side soil nailing wall is the boundary with former rubble barricade 8 outer rims of building, rubble barricade 8 is high 2.5 meters, bullet stone barricade 8 outer rims are two residential buildings 9 that Floor 12 is high for 3.0 meters, bullet stone barricade 8 outer rims will be provided with the underground shear wall exterior wall 10 of agent structure below 0.5 meter, therefore, need supporting and protection structure 11 be set below rubble barricade 8 and be beneficial to building of shear wall exterior wall 10.But the support space 12 between shear wall exterior wall 10 and the supporting and protection structure 11 only is 0.5 meter; And dependents' district, rubble barricade 8 back living water use oozes out continuous immersion, washes away soil mass of foundation pit (soil mass of foundation pit comprises plain fill layer 13, soft mud matter fill stratum 14, cobble soil layer 15, the chiltern mud stone 16 moulded) from the spilled water hole of rubble barricade 8 in a large number.Owing to ooze out underground water from rubble barricade 8 spilled water holes and soak soil mass of foundation pit for a long time, excavation slope soil body engineering geological conditions changes and worsens rapidly, makes soil nailing wall (being supporting and protection structure 11) lose support action and caves in.The life water that oozes has also changed the soil structures when building rubble barricade 8 down, becomes soft mould even stream is moulded after the disturbance, and intensity reduces, and the mud matter soil body that bankets is stream and moulds shape and outwards flow out and cause original part building and rubble barricade 8 to ftracture; Serious threat is to building safety above the rubble barricade 8.
The utility model content
Technical problem to be solved in the utility model provides a kind of deep foundation pit supporting structure that can play firm support action to foundation ditch.
The technical scheme that its technical problem that solves the utility model adopts is: deep foundation pit supporting structure, comprise by many mini piles and be arranged in juxtaposition the support wall that forms, supporting inboard in support wall is provided with anchor cable and fixed body, one end of anchor cable is connected on the mini pile, and the other end is connected on the fixed body.
As the preferred version of technique scheme, adjacent two mini piles overlap the formation integrative-structure mutually.
Further be, the mini pile that is connected with anchor cable is the plain stake that mortar injection forms, and the mini pile that is positioned at plain stake both sides comprises shaped steel and mortar cover, the mortar cover be poured in shaped steel around.
Further be that described fixed body comprises the basement rock that is positioned at support wall supporting inboard and be fixedly connected on mortar post on the basement rock that anchor cable places in the mortar post.
Further be, in the supporting arranged outside of support wall supporting beam arranged, anchor cable passes mini pile and is fixedly connected on the supporting beam.
The beneficial effects of the utility model are: be connected on the mini pile by the end with anchor cable, the other end is connected on the fixed body, like this, when soil mass of foundation pit is washed away by living water use, this foundation pit earth is known from experience outside extruding force of support wall formation, but because the setting of anchor cable, can produce a reverse pulling force to support wall, prevent that support wall from tilting to cave in, thereby can well finish building of shear wall exterior wall, can not cause damage to rubble barricade top building, guarantee normally carrying out of construction, can economize the land resource, reduce land expropriation cost, it is narrow to be particluarly suitable for boundary of works area, the construction environment complexity, rich water and have very strong sensitivity and thixotropic soft moulding in the geological conditions that mud matter bankets applied.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
As Fig. 2~shown in Figure 4, deep foundation pit supporting structure of the present utility model comprises by many mini piles being arranged in juxtaposition the support wall that forms, and is provided with anchor cable 2 and fixed body in the supporting inboard of support wall, one end of anchor cable 2 is connected on the mini pile, and the other end is connected on the fixed body.Be connected on the mini pile by a end anchor cable 2, the other end is connected on the fixed body, like this, when soil mass of foundation pit was washed away by living water use, this foundation pit earth was known from experience outside extruding force of support wall formation, but because the setting of anchor cable 2, can produce a reverse pulling force to support wall, prevent that support wall from tilting to cave in, thus can well finish building of shear wall exterior wall 10, can not cause damage, guarantee normally carrying out of construction rubble barricade 8 top buildings.
In the above-described embodiment, can at interval certain distance between adjacent two mini piles, but this moment, the living area living water use can ooze out between adjacent two mini piles, influence the normal construction of shear wall exterior wall 10, therefore, as preferred mode, adjacent two mini piles overlap the formation integrative-structure mutually.Be to have formed a stifled gapless support wall after many mini piles overlap mutually, like this, living water use can not ooze out from support wall, is convenient to the normal construction of shear wall exterior wall 10.
In the above embodiment, mini pile can adopt steel column to make, and as preferred mode, the mini pile that is connected with anchor cable 2 is the plain stake 6 that mortar injection forms, the mini pile that is positioned at plain stake 6 both sides comprises shaped steel 1 and mortar cover 5, mortar cover 5 be poured in shaped steel 1 around.The mini pile that is connected with anchor cable 2 is the plain stake 6 (plain stake 6 is not within it, and portion is provided with reinforcing bar) that mortar injection forms, and like this, can be convenient to boring in plain stake 6 and anchor cable 2 is passed from this element stake 6 fix; And the mini pile that is positioned at plain stake 6 both sides comprises shaped steel 1 and mortar cover 5, mortar cover 5 be poured in shaped steel 1 around, like this, shaped steel 1 the bulk strength that can improve mini pile is set, strengthen the resistance of deformation of mini pile.
In the above embodiment, fixed body can adopt any anchor cable 2 fixedly connected structures all can, as the stanchion substantially parallel with mini pile can be set in soil mass of foundation pit, one end of anchor cable 2 is connected on the mini pile, one end then is connected on this stanchion and realizes, as preferred mode, described fixed body comprises the basement rock 3 that is positioned at support wall supporting inboard and is fixedly connected on mortar post 4 on the basement rock 3 that anchor cable 2 places in the mortar post 4.Because basement rock 3 itself just maintains static in soil mass of foundation pit, when mortar post 4 is fixedly connected on the basement rock 3, and after placing anchor cable 2 in the mortar post 4, no matter soil mass of foundation pit is much to the outside extruding force of support wall, basement rock 3 and mortar post 4 all can provide one with this extruding force opposite effect power, prevent that support wall from toppling over laterally.
In order on support wall, to form fixing to anchor cable 2 better, in the supporting arranged outside of support wall supporting beam 7 is arranged, anchor cable 2 passes mini pile 1 and is fixedly connected on the supporting beam 7.As shown in Figure 1, each supporting beam 7 can adopt two i iron and a block plate to form, and steel plate is welded on two i iron and forms integrative-structure, and anchor cable 2 is fixed on the steel plate after passing mini pile 1, can play the traction action to support wall well.
Deep foundation pit supporting structure work progress of the present utility model is:
1, the construction of mini pile
First erection construction platform before the miniature pile construction is set up and is finished unwrapping wire behind the operation platform, beginning mini pile bore operation is prepared in the location.Boring two YT150 geological drilling rigs are construction from left to right simultaneously, plans every bench drill machine drill and advances 50 mini pile borings.For reducing the mutual disturbance of holing of adjacent mini pile, guarantee that adjacent mini pile boring 50mm has a common boundary quality, adopting per 5 mini piles boring is one group of jump space construction, every group 1,5,3,2,4 jump space constructure scheme.To pass because of mini pile boring and to have very strong sensitivity and the soft mud matter of moulding of thixotropy is banketed, if mini pile boring adopts the feedwater drilling technology will cause the soft mud matter thixotroping of banketing of moulding for reducing cost, may bring out the further increasing of barricade distortion of craze and transfiguration of side slope top, so mini pile boring adopts the moving Φ 150mm eccentric hammer drilling tool of the higher full blast of cost to advance technology with pipe bit.Rapid high-voltage tube with grouting was strapped in the shaped steel 1 outer insertion boring and to it and fixes after mini pile boring was finished, and preparation is toward the slip casting of high-voltage tube inner high voltage immediately.For ease of the boring of next process anchor cable, the mini pile that is laid with the anchor cable position does not insert shaped steel 1 and is made as plain stake 6.The mini pile mortar adopts the M30 mortar that is added with the early strength micro expansion agent, and the mortar water/binder ratio is controlled at the 0.55-0.6 scope.In mini pile slip casting process, guarantee that for reaching purpose of design slip casting effect strengthens mini pile slurry infiltration radius, make slurries can improve the soft mechanical index that mud matter is banketed of moulding, essential strict control grouting pressure and grouting amount.Grouting pressure generally is controlled at the 0.8-1.2MPa scope; Grouting amount is controlled at 3-5 times of theoretical grouting amount, and the grouting amount of minority stake can reach tens times.Grouting process adopts at the bottom of the hole slip casting method under water, and marginal not slurry limit is extracted grouting high pressure tube edge and extracted steel sleeve (the grouting high-voltage tube is a grouting, steel sleeve borehole wall-protection with); The lower end mouth of pipe of steel sleeve generally is controlled at the following 30-50 of slurries centimetre, extracts the too fast mini pile hole of collapsing of causing, and crossing influences slip casting effect slowly.100 mini pile external surfaces that should guaranteeing in the miniature pile construction constructs finishes on same plane and the stake verticality less than 4 centimetres; Because supporting beam 7 is rigidity, if the mini pile external surface is not on same plane, make the prestressing force that when prestress anchorage cable 2, applies well to pass to mini pile, when mini pile bears the pressure of soil mass of foundation pit, can cause the distortion of part mini pile excessive by reinforcing beam; And if the mini pile perpendicularity deviation is excessive, make adjacent mini pile have a common boundary imprecision, cause whole prop part to leak and weaken the curtain water stop effect.
2, anchor cable construction
After the three days length of time is finished in the slip casting of mini pile core sand slurry, the side slope of beginning deep pit excavation supporting (being the support wall of mini pile formation and the support space 12 between the shear wall exterior wall 10).Divide excavation three times according to designing requirement, each cutting depth is the design anchor cable following 500mm in 2 positions (three anchor cables 2 promptly are set from top to bottom) on the mini pile that is provided with anchor cable 2.Rapid rigging up began anchor cable construction (promptly holing on the basement rock 3 that gets into the support wall inner side edge) after cutting depth reached construction requirement in plain stake 6, adopted reverse construction during anchor cable construction.Anchor cable design boring aperture 130mm after boring is finished, arranges anchor cable 2 in the hole, inject mortar in the past hole and form mortar post 4, and the boring of anchor cable, injecting paste material, grouting process, slip casting controlled pressure are all identical with mini pile.Anchor cable is 15.24mm with the diameter that steel strand adopt.Mortar slip casting begins stretch-draw prestressing force anchor cable 2 (even anchor cable 2 is in extended state all the time after finishing the 7 days length of time, when support wall is squeezed in run-off the straight, anchor cable 2 action immediately provides an opposite force to stop its inclination), anchor cable 2 tensioning process adopt post stretching.For making anchor cable 2 prestressing force evenly pass to the mini pile support system, reduce the mini pile distortion excessive during stretch-draw because of discontinuity produces by supporting beam 7, with two vertically-displacable synchronous hydraulic jack from synchronous, the at the same level stretch-draw in supporting beam 7 two ends.The stretch-draw end condition is to survey elongation more than or equal to theoretical elongation when steel strand.
3, supporting beam construction
Prestress anchorage cable is first construction supporting beam 7 before stretch-draw is afterwards finished in slip casting.Because this support system is the temporary lining measure, after 10 constructions of underground shear wall exterior wall are finished with backfill support space 12; Institute thinks accelerating construction progress, and design supporting beam 7 is welded on the steel plate and is formed by two HW#200 * 204 * 12 * 12 type i iron.