CN104539044A - Power distribution equipment state control method and device - Google Patents
Power distribution equipment state control method and device Download PDFInfo
- Publication number
- CN104539044A CN104539044A CN201410771725.0A CN201410771725A CN104539044A CN 104539044 A CN104539044 A CN 104539044A CN 201410771725 A CN201410771725 A CN 201410771725A CN 104539044 A CN104539044 A CN 104539044A
- Authority
- CN
- China
- Prior art keywords
- state
- equipment
- circuit
- carrying
- equipment state
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/242—Home appliances
Abstract
The invention provides a power distribution equipment state control method and device. The method comprises the steps of obtaining an equipment state operation task, checking whether the equipment state operation task is suitable for state operation on a whole line, generating an operation order according to the checking result, regarding a state operation line recorded by the operation order as the line suitable for state operation, and carrying out equipment state operation according to the operation order. According to the technical scheme, the system automatically generates the operation order according to the equipment operation task, a dispatcher does not need to work a lot, and the operation order obtaining efficiency is improved; in addition, before the operation order is generated, the system automatically checks the whole line operated when the equipment state is abnormal, the problem that due to improper operation, equipment and the line are damaged or resources are wasted is avoided, and the problem that accuracy of an operation order manufactured manually is low is solved.
Description
Technical field
The application relates to field of power distribution, in particular to a kind of controller switching equipment condition control method and device.
Background technology
Power distribution automation device end O&M mainly rely on equipment formally put into operation driving front test, and run time unit exception trouble hunting.In electrical power distribution automatization system actual motion, when scheduled outage, temporary interruption, troubleshooting, often because controller switching equipment does not carry out action for a long time, management and running personnel apply distribution main website remote distribution device discovery equipment can not correct operation, affects the application of electrical power distribution automatization system.
In legacy equipment state of operation, dispatcher manually makes operation order according to connections figure, for once many line statuss operation and connections complicated situation time, dispatcher needs to spend huge workload, and easily omit operating equipment, can not ensure that whether operating procedure is reasonable.
In conventional method, when carrying out equipment state operation according to operation order, carry out control operation by means of only distribution main website, lack the rear security verification of operation.
In addition, traditional power distribution automation main website is for the status information data receiving automation equipment, and Application comparison is single, is generally applied to Real-time Alarm, fully do not excavate the incidence relation between its history data and data, fail to provide support for dispatcher fully grasps equipment state.
Obtain inefficient problem for above-mentioned owing to relying on the operation order that manually making operation order causes, not yet propose effective solution at present.
Summary of the invention
The application aims to provide a kind of controller switching equipment condition control method and device, obtains inefficient problem to solve operation order of the prior art.
To achieve these goals, according to an aspect of the application, provide a kind of controller switching equipment condition control method, above-mentioned control method comprises: obtain equipment state operation task; Check whether the said equipment state of operation task is adapted at whole piece circuit carries out state of operation; According to above-mentioned check result, generating run ticket, the circuit carrying out above-mentioned state of operation of aforesaid operations ticket record is the circuit of applicable above-mentioned state of operation; And according to aforesaid operations ticket, carry out the said equipment state of operation.
Further, the said equipment operation task is in units of wall scroll distribution wire.
Further, check whether the said equipment state of operation task is adapted at whole piece circuit carrying out state of operation and comprises: check the current equipment of above-mentioned circuit, if exception does not appear in above-mentioned circuit, then above-mentioned line status is applicable to carrying out above-mentioned state of operation; And the current equipment state on above-mentioned circuit is checked, if exception does not appear in current equipment, then the state of above-mentioned current equipment is applicable to carrying out above-mentioned state of operation.
Further, according to aforesaid operations ticket, also comprise before carrying out the said equipment state of operation and safety check is carried out to the operating procedure in aforesaid operations ticket, when aforesaid operations step is dangerous, editor's adjustment is carried out to above-mentioned manipulation ticket.
Further, according to aforesaid operations ticket, after carrying out the said equipment state of operation, analytic statistics is carried out to the result of carrying out after equipment state operation, form assessment report.
To achieve these goals, according to the another aspect of the embodiment of the present application, provide a kind of controller switching equipment behavior control device, above-mentioned control device comprises: acquiring unit, for obtaining equipment state operation task; Inspection unit, for checking whether the said equipment state of operation task is adapted at whole piece circuit carries out state of operation; Generation unit, for according to above-mentioned check result, generating run ticket, the circuit carrying out above-mentioned state of operation of aforesaid operations ticket record is the circuit of applicable above-mentioned state of operation; And performance element, for according to aforesaid operations ticket, carry out the said equipment state of operation.
Further, the equipment state operation task of above-mentioned acquiring unit acquisition is in units of wall scroll distribution wire.
Further, above-mentioned inspection unit comprises: inspection of line module, and for checking the current equipment of above-mentioned circuit, if exception does not appear in above-mentioned circuit, then above-mentioned line status is applicable to carrying out above-mentioned state of operation; And equipment inspection module, for checking the current equipment state on above-mentioned circuit, if exception does not appear in current equipment, then the state of above-mentioned current equipment is applicable to carrying out above-mentioned state of operation.
Further, above-mentioned control device also comprises correction verification module, for according to aforesaid operations ticket, carries out safety check before carrying out the said equipment state of operation to the operating procedure in aforesaid operations ticket, when aforesaid operations step is dangerous, editor's adjustment is carried out to above-mentioned manipulation ticket.
Further, above-mentioned control device also comprises evaluation module, for according to aforesaid operations ticket, carries out analytic statistics after carrying out the said equipment state of operation to the result of carrying out after equipment state operation, forms assessment report.
The technical scheme of application the application, system is according to equipment operating task, and automatic generating run ticket, does not need dispatcher to spend a large amount of workloads, improves the efficiency that operation order obtains; In addition, before generating run ticket, system checks the whole piece circuit of operation when existing abnormal in equipment state automatically, generate corresponding to the operation order being applicable to the circuit carrying out state of operation, avoid occurring that abnormal equipment or circuit generate identical operation order, and then avoid misoperation damage equipment and circuit or cause the problem of the wasting of resources, the problem that the accuracy of the operation order of manual manufacture is lower can be overcome like this.
Accompanying drawing explanation
The Figure of description forming a application's part is used to provide further understanding of the present application, and the schematic description and description of the application, for explaining the application, does not form the improper restriction to the application.In the accompanying drawings:
Fig. 1 shows the flow chart of the controller switching equipment condition control method in a kind of preferred embodiment of the application; And
Fig. 2 shows the controller switching equipment behavior control device schematic diagram in a kind of preferred embodiment of the application.
Embodiment
It is noted that following detailed description is all exemplary, be intended to provide further instruction to the application.Unless otherwise, all technology used herein and scientific terminology have the identical meanings usually understood with the application person of an ordinary skill in the technical field.
It should be noted that used term is only to describe embodiment here, and be not intended to the illustrative embodiments of restricted root according to the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative is also intended to comprise plural form, in addition, it is to be further understood that, " comprise " when using term in this manual and/or " comprising " time, it indicates existing characteristics, step, operation, device, assembly and/or their combination.
Now, the illustrative embodiments according to the application is described with reference to the accompanying drawings in more detail.But these illustrative embodiments can be implemented by multiple different form, and should not be interpreted as being only limited to execution mode set forth herein.Should be understood that, there is provided these execution modes be in order to make the application open thorough and complete, and the design of these illustrative embodiments is fully conveyed to those of ordinary skill in the art, in the accompanying drawings, for the sake of clarity, expand the thickness in layer and region, and use the device that identical Reference numeral represents identical, thus will omit description of them.
Introduce as background technology, in conventional electrical distribution equipment state control method, need to rely on dispatcher and manually make operation order, the acquisition efficiency of operation order is low, the accuracy of operation order is lower, in order to solve the above problems, present applicant proposes a kind of controller switching equipment condition control method.
Fig. 1 is the flow chart of the controller switching equipment condition control method according to the embodiment of the present invention.As shown in the figure, this control method comprises the steps:
Step S102, obtains equipment state operation task;
Step S104, checks whether the said equipment state of operation task is adapted at whole piece circuit carries out state of operation, obtains check result;
Step S106, according to above-mentioned check result, generating run ticket, the circuit carrying out above-mentioned state of operation of aforesaid operations ticket record is the circuit of applicable above-mentioned state of operation; And
Step S108, according to aforesaid operations ticket, carries out the said equipment state of operation.
In above-mentioned controller switching equipment condition control method, first, dispatch and to be read by file or manual typing mode obtains equipment operating task at electrical power distribution automatization system; Then, system checks the whole piece circuit of equipment state operation automatically, when having abnormal in check result display whole piece circuit, then equipment state operation task is not suitable for carrying out state of operation on whole piece circuit, otherwise can carry out state of operation on whole piece circuit; Secondly, according to above-mentioned check result, generating run ticket, the circuit carrying out above-mentioned state of operation of aforesaid operations ticket record is the circuit of applicable above-mentioned state of operation, when the said equipment state of operation task is adapted at whole piece circuit carrying out state of operation, system generates the operation order of whole piece circuit automatically, and when the said equipment state of operation task is not suitable for carrying out state of operation on whole piece circuit, system generates the corresponding operation order being applicable to the circuit carrying out state of operation; Finally, according to aforesaid operations ticket, carry out the said equipment state of operation.
In the method, system is according to equipment operating task, and automatic generating run ticket, does not need dispatcher to spend a large amount of workloads, improves the efficiency that operation order obtains; In addition, before generating run ticket, system checks the whole piece circuit of operation when existing abnormal in equipment state automatically, generate corresponding to the operation order being applicable to the circuit carrying out state of operation, avoid occurring that abnormal equipment or circuit generate identical operation order, and then avoid misoperation damage equipment and circuit or cause the problem of the wasting of resources, the problem that the accuracy of the operation order of manual manufacture is lower can be overcome like this.
When the operation order generated according to operation task needs amendment, conveniently the operation task of each distribution wire in operation order is modified, need preferred the said equipment operation task in units of wall scroll distribution wire.
The application another preferred embodiment in, whether preferred inspection the said equipment state of operation task is adapted at whole piece circuit carrying out state of operation comprises: check above-mentioned circuit, if exception does not appear in above-mentioned circuit, then above-mentioned line status is applicable to carrying out above-mentioned state of operation; And the current equipment state as three distant device ends control power supply, handle position, passages etc. on above-mentioned circuit is checked, if exception does not appear in current equipment, then the state of above-mentioned current equipment is applicable to carrying out above-mentioned state of operation.Like this equipment in whole piece circuit and circuit are all checked, can judge whether the said equipment state of operation task is adapted at whole piece circuit carries out state of operation exactly, and then generate the operation of recording the circuit being applicable to above-mentioned state of operation, the circuit avoided being not suitable for above-mentioned state of operation operates, and then improve the accuracy of operation order, avoid the problem causing damage equipment or circuit and cause the wasting of resources.
In order to obtain operation order more accurately, not to occurring that abnormal circuit or equipment carry out state of operation, and then avoid equipment or circuit and cause the problem of the wasting of resources.The application, preferably according to aforesaid operations ticket, also comprises before carrying out the said equipment state of operation and carries out safety check to the operating procedure in aforesaid operations ticket, when aforesaid operations step is dangerous, carries out editor's adjustment to above-mentioned manipulation ticket.
The application another preferred embodiment in, preferably according to aforesaid operations ticket, after carrying out the said equipment state of operation, analytic statistics is carried out to the result of carrying out after equipment state operation, formed assessment report.
The a certain moment presence of controller switching equipment does not normally represent that the state of this equipment in whole service process is all normal, this is because the factor such as terminal abnormal state and device context running environment, weather, air humidity, communication module stability is closely related, intermittent abnormal by causing the state of some equipment to occur.Carry out analytic statistics to the result of carrying out after equipment state operation in the application, form assessment report, this report comprises: warping apparatus abnormal cause before operation; History run state labile device inventory before operation; Abnormal unit exception reason is controlled in state of operation process; Operating process remote control accuracy, remote signalling performance factor, terminal webmaster index (frame timeout rate, terminal communication time and terminal communication time delay rate etc.), make forecast failure according on off state and remote control result and be processed into the statistical indicators such as power.So comprehensive report content facilitates and follow-uply carries out mining analysis to device history service data, and then reasonably can predict the state of equipment, generates operation order exactly.
In addition, after actuating equipment state of operation ticket task terminates, system, according to the operating conditions of switchgear, is analyzed the forecast failure disposition of circuit.Circuit forecast failure, thinks a forecast failure by the section that automation switch on circuit surrounds.Fault Isolation success or not judges according to equipment state operating result.
The application another aspect provides a kind of controller switching equipment behavior control device.As shown in Figure 2, this generating apparatus comprises: acquiring unit 10, inspection unit 30, generation unit 50 and performance element 70.Wherein,
Acquiring unit 10, for obtaining equipment state operation task;
Inspection unit 30, for checking whether the said equipment state of operation task is adapted at whole piece circuit carries out state of operation;
Generation unit 50, for according to above-mentioned check result, generating run ticket, the circuit carrying out above-mentioned state of operation of aforesaid operations ticket record is the circuit of applicable above-mentioned state of operation; And
Performance element 70, for according to aforesaid operations ticket, carries out the said equipment state of operation.
Above-mentioned device, system is according to equipment operating task, and automatic generating run ticket, does not need dispatcher to spend a large amount of workloads, improves the efficiency that operation order obtains; In addition, before generating run ticket, system checks the whole piece circuit of operation when existing abnormal in equipment state automatically, generate corresponding to the operation order being applicable to the circuit carrying out state of operation, avoid occurring that abnormal equipment or circuit generate identical operation order, and then avoid misoperation damage equipment and circuit or cause the problem of the wasting of resources, the problem that the accuracy of the operation order of manual manufacture is lower can be overcome like this.
Conveniently modify to the operation task of each distribution wire in operation order, the equipment state operation task that preferred above-mentioned acquiring unit obtains is in units of wall scroll distribution wire.
The application another preferred embodiment in, preferred above-mentioned inspection unit comprises: inspection of line module, and for checking the current equipment of above-mentioned circuit, if exception does not appear in above-mentioned circuit, then above-mentioned line status is applicable to carrying out above-mentioned state of operation; And equipment inspection module, for checking the current equipment state on above-mentioned circuit, if exception does not appear in current equipment, then the state of above-mentioned current equipment is applicable to carrying out above-mentioned state of operation.Like this equipment in whole piece circuit and circuit are all checked, can judge whether the said equipment state of operation task is adapted at whole piece circuit carries out state of operation exactly, and then generate the operation of recording the circuit being applicable to above-mentioned state of operation, the circuit avoided being not suitable for above-mentioned state of operation operates, and then improve the accuracy of operation order, avoid the problem causing damage equipment or circuit and cause the wasting of resources.
In order to obtain operation order more accurately, not to occurring that abnormal circuit or equipment carry out state of operation, and then avoid equipment or circuit and cause the problem of the wasting of resources.The preferred above-mentioned control device of the application also comprises verification unit, for according to aforesaid operations ticket, before carrying out the said equipment state of operation, safety check is carried out to the operating procedure in aforesaid operations ticket, when aforesaid operations step is dangerous, editor's adjustment is carried out to above-mentioned manipulation ticket.
The application another preferred embodiment in, preferred above-mentioned control device also comprises assessment unit, for according to aforesaid operations ticket, carries out analytic statistics after carrying out the said equipment state of operation to the result of carrying out after equipment state operation, formed assessment report.The a certain moment presence of controller switching equipment does not normally represent that the state of this equipment in whole service process is all normal, this is because the factor such as terminal abnormal state and device context running environment, weather, air humidity, communication module stability is closely related, intermittent abnormal by causing the state of some equipment to occur.Carry out analytic statistics to the result of carrying out after equipment state operation in the application, form assessment report, this report comprises: warping apparatus abnormal cause before operation; History run state labile device inventory before operation; Abnormal unit exception reason is controlled in state of operation process; Operating process remote control accuracy, remote signalling performance factor, terminal webmaster index (frame timeout rate, terminal communication time, terminal communication time delay rate etc.), make forecast failure according on off state and remote control result and be processed into the statistical indicators such as power.So comprehensive report content facilitates and follow-uply carries out mining analysis to device history service data, and then reasonably can predict the state of equipment, generates operation order exactly.
In addition, said apparatus also comprises anticipation unit, and for after actuating equipment state of operation ticket task terminates, system, according to the operating conditions of switchgear, is analyzed the forecast failure disposition of circuit.Circuit forecast failure, thinks a forecast failure by the section that automation switch on circuit surrounds.Fault Isolation success or not judges according to equipment state operating result.
As can be seen from the above description, the application's the above embodiments achieve following technique effect:
In above-mentioned controller switching equipment condition control method and device, first, dispatch and to be read by file or manual typing mode obtains equipment operating task at electrical power distribution automatization system; Then, system checks the whole piece circuit of equipment state operation automatically, when having abnormal in check result display whole piece circuit, then equipment state operation task is not suitable for carrying out state of operation on whole piece circuit, otherwise can carry out state of operation on whole piece circuit; Secondly, according to above-mentioned check result, generating run ticket, the circuit carrying out above-mentioned state of operation of aforesaid operations ticket record is the circuit of applicable above-mentioned state of operation, when the said equipment state of operation task is adapted at whole piece circuit carrying out state of operation, system generates the operation order of whole piece circuit automatically, and when the said equipment state of operation task is not suitable for carrying out state of operation on whole piece circuit, system generates the corresponding operation order being applicable to the circuit carrying out state of operation; Finally, according to aforesaid operations ticket, carry out the said equipment state of operation.
In the method and device, system is according to equipment operating task, and automatic generating run ticket, does not need dispatcher to spend a large amount of workloads, improves the efficiency that operation order obtains; In addition, before generating run ticket, system checks the whole piece circuit of operation when existing abnormal in equipment state automatically, generate corresponding to the operation order being applicable to the circuit carrying out state of operation, avoid occurring that abnormal equipment or circuit generate identical operation order, and then avoid misoperation damage equipment and circuit or cause the problem of the wasting of resources, the problem that the accuracy of the operation order of manual manufacture is lower can be overcome like this.
The foregoing is only the preferred embodiment of the application, be not limited to the application, for a person skilled in the art, the application can have various modifications and variations.Within all spirit in the application and principle, any amendment done, equivalent replacement, improvement etc., within the protection range that all should be included in the application.
Claims (10)
1. a controller switching equipment condition control method, is characterized in that, described control method comprises:
Obtain equipment state operation task;
Check whether described equipment state operation task is adapted at whole piece circuit carries out state of operation, obtains check result;
According to described check result, generating run ticket, the circuit carrying out described state of operation of described operation order record is the circuit of applicable described state of operation; And
According to described operation order, carry out described equipment state operation.
2. control method according to claim 1, is characterized in that, described equipment state operation task is in units of wall scroll distribution wire.
3. control method according to claim 1, is characterized in that, checks whether described equipment state operation task is adapted at whole piece circuit carrying out state of operation and comprises:
Check the current equipment of described circuit, if exception does not appear in described circuit, then described line status is applicable to carrying out described state of operation; And
Check the current equipment state on described circuit, if exception does not appear in current equipment, then the state of described current equipment is applicable to carrying out described state of operation.
4. control method according to claim 1, it is characterized in that, according to described operation order, also comprise before carrying out described equipment state operation and safety check is carried out to the operating procedure in described operation order, when described operating procedure is dangerous, editor's adjustment is carried out to described operation order.
5. control method according to claim 1, is characterized in that, according to described operation order, carries out analytic statistics after carrying out described equipment state operation to the result of carrying out after equipment state operation, forms assessment report.
6. a controller switching equipment behavior control device, is characterized in that, described control device comprises:
Acquiring unit, for obtaining equipment state operation task;
Inspection unit, for checking whether described equipment state operation task is adapted at whole piece circuit carries out state of operation, obtains check result;
Generation unit, for according to described check result, generating run ticket, the circuit carrying out described state of operation of described operation order record is the circuit of applicable described state of operation; And
Performance element, for according to described operation order, carries out described equipment state operation.
7. control device according to claim 6, is characterized in that, the equipment state operation task that described acquiring unit obtains is in units of wall scroll distribution wire.
8. control device according to claim 6, is characterized in that, described inspection unit comprises:
Inspection of line module, for checking the current equipment of described circuit, if exception does not appear in described circuit, then described line status is applicable to carrying out described state of operation; And
Equipment inspection module, for checking the current equipment state on described circuit, if exception does not appear in current equipment, then the state of described current equipment is applicable to carrying out described state of operation.
9. control device according to claim 6, it is characterized in that, described control device also comprises verification unit, for according to described operation order, before carrying out the operation of described equipment state, safety check is carried out to the operating procedure in described operation order, when described operating procedure is dangerous, editor's adjustment is carried out to described operation order.
10. control device according to claim 6, is characterized in that, described control device also comprises assessment unit, for according to described operation order, carries out analytic statistics after carrying out described equipment state operation to the result of carrying out after equipment state operation, forms assessment report.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410771725.0A CN104539044A (en) | 2014-12-12 | 2014-12-12 | Power distribution equipment state control method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410771725.0A CN104539044A (en) | 2014-12-12 | 2014-12-12 | Power distribution equipment state control method and device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104539044A true CN104539044A (en) | 2015-04-22 |
Family
ID=52854534
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410771725.0A Pending CN104539044A (en) | 2014-12-12 | 2014-12-12 | Power distribution equipment state control method and device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104539044A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105372538A (en) * | 2015-12-15 | 2016-03-02 | 国网北京市电力公司 | Method and device for power distribution network detection |
CN109408152A (en) * | 2018-11-01 | 2019-03-01 | 国网江苏省电力有限公司扬州供电分公司 | A kind of generation method and generating means of equipment starting step |
CN109409646A (en) * | 2018-09-07 | 2019-03-01 | 中国铁路北京局集团有限公司天津动车客车段 | A kind of task management method and device and readable storage medium storing program for executing |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101183802A (en) * | 2007-02-06 | 2008-05-21 | 深圳职业技术学院 | Main-branch station mode based intelligent power system scheduling command ticket automatic generation system |
CN101566846A (en) * | 2009-05-27 | 2009-10-28 | 江西九江供电公司 | Distribution grid switching operation bill generation and anti-error system |
CN102169570A (en) * | 2011-05-12 | 2011-08-31 | 东北电力大学 | Two tickets combined inference billing method of power grid based on work task analysis |
CN202041837U (en) * | 2011-04-22 | 2011-11-16 | 武汉大学 | Intelligent power distribution grid operation ticket generation management system |
-
2014
- 2014-12-12 CN CN201410771725.0A patent/CN104539044A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101183802A (en) * | 2007-02-06 | 2008-05-21 | 深圳职业技术学院 | Main-branch station mode based intelligent power system scheduling command ticket automatic generation system |
CN101566846A (en) * | 2009-05-27 | 2009-10-28 | 江西九江供电公司 | Distribution grid switching operation bill generation and anti-error system |
CN202041837U (en) * | 2011-04-22 | 2011-11-16 | 武汉大学 | Intelligent power distribution grid operation ticket generation management system |
CN102169570A (en) * | 2011-05-12 | 2011-08-31 | 东北电力大学 | Two tickets combined inference billing method of power grid based on work task analysis |
Non-Patent Citations (1)
Title |
---|
高阳等: "电网调度故障恢复操作票的研究", 《继电器》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105372538A (en) * | 2015-12-15 | 2016-03-02 | 国网北京市电力公司 | Method and device for power distribution network detection |
CN105372538B (en) * | 2015-12-15 | 2020-04-24 | 国网北京市电力公司 | Detection method and device for power distribution network equipment |
CN109409646A (en) * | 2018-09-07 | 2019-03-01 | 中国铁路北京局集团有限公司天津动车客车段 | A kind of task management method and device and readable storage medium storing program for executing |
CN109408152A (en) * | 2018-11-01 | 2019-03-01 | 国网江苏省电力有限公司扬州供电分公司 | A kind of generation method and generating means of equipment starting step |
CN109408152B (en) * | 2018-11-01 | 2022-04-08 | 国网江苏省电力有限公司扬州供电分公司 | Method and device for generating equipment starting step |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104155970B (en) | A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof | |
CN103176084B (en) | Intelligent substation simulation system in panoramic replace mode and integration testing method for intelligent substation simulation system | |
KR101224324B1 (en) | Management system for distributing board and the method thereof | |
CN103414251A (en) | Substation network communication simulation system based on IEC 61850 | |
CN105184442A (en) | Power distribution network dispatching management statistical analysis system | |
CN104135070A (en) | Diagnosis method for pre-channel fault of power distribution automation system | |
CN110568284B (en) | Intelligent substation one-key sequential control automatic test verification method, device and system | |
US20190372352A1 (en) | Method and device for controlling solar energy system, central controller and solar energy system | |
CN105656685A (en) | Automatic deployment and operation and maintenance monitoring method based on zabbix system oracle | |
CN110086251B (en) | Monitoring method and system for improving operation safety of power grid | |
CN104460589A (en) | Mobile debugging system with simulation dispatching master station | |
CN105049223A (en) | Electric power communication network defect and fault processing decision-aided analysis method | |
CN103227662A (en) | Safety detection method and system of electric power communication equipment based on state control | |
CN104539044A (en) | Power distribution equipment state control method and device | |
CN106843125A (en) | A kind of production line data exchange system | |
CN111052087A (en) | Control system, information processing device, and abnormality factor estimation program | |
CN105759150A (en) | Test system and method for transformer substation secondary device prefabricated cabin | |
CN104951884A (en) | Visual display method of accident emergency repair and inversion based on distribution network | |
CN105117984A (en) | Data analysis-based power grid lean management system | |
CN105849699B (en) | Method for controlling data center architecture equipment | |
CN105743695A (en) | Monitoring method and system based on IEC 104 protocol | |
CN105738803B (en) | A kind of method of protective relaying device remote control remote communication joint debugging | |
CN104795804A (en) | Auxiliary relay protection monitoring processing system and processing method thereof | |
CN103454994B (en) | Adapt to the control method of many 500kV transformer substation remote-control transmission | |
CN109685682A (en) | The method of regulator control system inspection operation ticket is intelligently generated based on relational database |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150422 |