CN104460589A - Mobile debugging system with simulation dispatching master station - Google Patents
Mobile debugging system with simulation dispatching master station Download PDFInfo
- Publication number
- CN104460589A CN104460589A CN201410568998.5A CN201410568998A CN104460589A CN 104460589 A CN104460589 A CN 104460589A CN 201410568998 A CN201410568998 A CN 201410568998A CN 104460589 A CN104460589 A CN 104460589A
- Authority
- CN
- China
- Prior art keywords
- mobile terminal
- scheduling station
- main website
- industrial switch
- operation simulation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000004088 simulation Methods 0.000 title claims abstract description 30
- 238000000034 method Methods 0.000 claims description 11
- 238000013461 design Methods 0.000 claims description 6
- 230000008569 process Effects 0.000 claims description 5
- 238000000605 extraction Methods 0.000 claims description 4
- 230000009466 transformation Effects 0.000 claims description 4
- 238000012795 verification Methods 0.000 claims description 3
- 230000005540 biological transmission Effects 0.000 abstract description 38
- 238000010276 construction Methods 0.000 abstract description 11
- 238000007689 inspection Methods 0.000 abstract 2
- 238000012544 monitoring process Methods 0.000 abstract 2
- 230000006870 function Effects 0.000 description 5
- 238000004891 communication Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 206010021703 Indifference Diseases 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000005457 optimization Methods 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 238000010977 unit operation Methods 0.000 description 2
- 230000000007 visual effect Effects 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000033228 biological regulation Effects 0.000 description 1
- 230000009351 contact transmission Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000007943 implant Substances 0.000 description 1
- 230000007257 malfunction Effects 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 230000011664 signaling Effects 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/04—Programme control other than numerical control, i.e. in sequence controllers or logic controllers
- G05B19/042—Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
- G05B19/0421—Multiprocessor system
-
- H02J13/0079—
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B90/00—Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
- Y02B90/20—Smart grids as enabling technology in buildings sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
Abstract
The invention discloses a mobile debugging system with a simulation dispatching master station, and relates to the technical field of power supply or power distribution devices or systems. The mobile debugging system comprises a mobile terminal, an industrial switch, a serial port server and multiple telecontrol devices. The simulation dispatching master station is installed on the mobile terminal of the system, the telecontrol devices are directly connected with the industrial switch through network connecting lines and indirectly connected with the industrial switch through the serial port server, and the industrial switch is connected with the mobile terminal through a network connecting line. Through arranging the simulation dispatching master station on the mobile terminal, the system automatically achieves on-site automatic construction transmission of monitoring information, working quality and inspection and acceptance efficiency of the monitoring information are improved, the power failure time of a transformer substation is shortened, and the correctness of information inspection and acceptance and secure and stable operation of a power grid are guaranteed.
Description
Technical field
The present invention relates to device or the systems technology field of power supply or distribution, particularly relate to a kind of moving analog scheduling station debug system.
Background technology
Newly-built or enlarging transformer station before putting into operation, all remote signalling, remote measurement, remote control, remote regulating signal should carry out pointwise transmission examination.Under traditional mode, supervisory control of substation information checking and accepting after passage erection debugging is unimpeded, must could carries out pointwise by scheduling station end commissioning staff and plant stand end (transformer station) commissioning staff and check.Because scheduling station is in electric company's regulation and control central machine room, carrying out information examination with transformer station can only by the mode of phone, limitation due to phone causes transformer substation end cannot see scheduling station picture data, dispatching terminal cannot see field condition, need to be described and explain cooperation, when there is problem one end, other end personnel will wait for, inefficiency, it is very large that mutual restriction involves energy.Along with transformer substation construction quantity increases and the quickening of construction speed, how to improve information examination efficiency, guarantee that transformer station puts into operation on schedule, become the technical barrier that monitor message checking and accepting need solve as early as possible.
Summary of the invention
Technical matters to be solved by this invention is to provide a kind of moving analog scheduling station debug system, described system is by arranging operation simulation main website on mobile terminals, realize automatically-monitored Information Field independently to construct transmission, improve the examination efficiency of work quality and monitor message, decrease the power off time of transformer station, the safe and stable operation of the correctness that the information that ensure that is checked and accepted and electrical network.
For solving the problems of the technologies described above, the technical solution used in the present invention is: a kind of moving analog scheduling station debug system, it is characterized in that comprising mobile terminal, industrial switch, serial server and several telemechanical apparatus, the mobile terminal of described system is provided with operation simulation main website, several telemechanical apparatus are directly connected by network connection with industrial switch and are indirectly connected with industrial switch by serial server, and described industry control switch is connected with mobile terminal by network connection.
Further technical scheme is, described mobile terminal is notebook computer, PC or minicomputer.
Further technical scheme is, the process of establishing of described operation simulation main website is as follows:
(1) the preposition program of scheduling station is extracted from the automation of transformation substations regulator control system of actual motion and SCADA applies substantially, the associated with that two kinds are applied is extracted, form minimization system, associated with is configured and process of compilation, ensure that operation simulation main website can start normally and apply on mobile terminals, carry out the compiling of source code and the amendment of configuration file;
(2) by the installing DB of scheduling station on mobile terminal, run independently database instance, and carry out database design, the consistance of the scheduling station system ensureing and run at present, carries out the verification of database;
(3) the scheduling station file of extraction and configuration file are installed on the mobile terminal of linux operating system, carry out the compiling of secondary source code, ensure the optimum of system, form operation simulation main website.
The beneficial effect adopting technique scheme to produce is: described debug system is by arranging operation simulation main website on mobile terminals, achieve the transmission of scheduling station model and actual schedule main website indifference, unit operation can be carried out, and in conjunction with industrial switch, telemechanical apparatus and serial server realize simulative debugging, thus the scene realizing monitor message is checked and accepted from main transmission on the spot, shorten transformer station to put into operation the time, improve the efficiency that monitor message is checked and accepted, ensure that correctness and the reliability of information transmission simultaneously, saving manpower, material resources, the transformer substation construction time is additionally reduced while financial resources, sound assurance power grid security, stable operation.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the present invention is further detailed explanation.
Fig. 1 is the theory diagram of described debug system of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, be clearly and completely described the technical scheme in the embodiment of the present invention, obviously, described embodiment is only a part of embodiment of the present invention, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.
Set forth a lot of detail in the following description so that fully understand the present invention, but the present invention can also adopt other to be different from alternate manner described here to implement, those skilled in the art can when without prejudice to doing similar popularization when intension of the present invention, therefore the present invention is by the restriction of following public specific embodiment.
As shown in Figure 1, the invention discloses a kind of moving analog scheduling station debug system, comprise mobile terminal, industrial switch, serial server and several telemechanical apparatus, described mobile terminal can be notebook computer, PC or minicomputer.The mobile terminal of described system is provided with operation simulation main website, several telemechanical apparatus are directly connected by network connection with industrial switch and are indirectly connected with industrial switch by serial server, and described industry control switch is connected with mobile terminal by network connection.
Corresponding to said system has a kind of supervisory control of substation information adjustment method based on moving analog scheduling station, said method comprising the steps of:
(1) operation simulation main website is set up in the terminal;
(2) operating personnel operate above-mentioned operation simulation main website, form several VLANs with switch and telemechanical apparatus, carry out the debugging of supervisory control of substation information.
Concrete, described procedure is as follows:
(1) extraction document, encodes
The preposition program of scheduling station and SCADA(data acquisition and supervisor control is extracted from the automation of transformation substations regulator control system of actual motion) substantially apply, the associated with that two kinds are applied is extracted, form minimization system, associated with is configured and process of compilation, ensure that operation simulation main website can start normally and apply on mobile terminals, carry out the compiling of source code and the amendment of configuration file;
(2) database debugging
By the installing DB of scheduling station on mobile terminal, run independently database instance, and carry out database design, the consistance of the scheduling station system ensureing and run at present, carries out the verification of database;
(3) secondary coding, optimization system
The scheduling station file of extraction and configuration file are installed on the mobile terminal of linux operating system, carry out the compiling of secondary source code, ensure the optimum of system, form operation simulation main website;
(4) channel pattern configuration
Debugging switch is configured, and divide multiple virtual LAN VLAN in conjunction with telemechanical apparatus and operation simulation main website, realize operation simulation main website and can receive the real time data that biplane uploads, carry out special line setting, by special line data access to operation simulation main website.
Mobile terminal is equipped with linux operating system, interface routine is write by Visual C Plus Plus, be used for carrying out the electrical network CIM foundation based on G language and XML format data processing, by scheduling station installing DB on mobile terminal, and carry out design and the optimization of self contained data base, can realize and operation simulation main website database one-way transmission, accept the data of scheduling station database and artwork.QT bis-compilings are carried out to operating system and implant system, achieves one-touch startup, a key synchronization scheme library model, the function of a bond bundle filing.
Design and assemble communication module, the transmission channel of transformer station generally comprises 2 kinds of network channels, a kind of special line passage.Accessing multiple passage for realizing a mobile terminal, devising the combination of industrial switch and serial server as communication transmission module.By to switch configuration design, mobile terminal accesses a netting twine and just can realize multi-channel data and transmit simultaneously from industrial switch Single port.
Effect:
1, solve newly-built or transform transformer station because of the obstructed restriction that communicates, the reduction of erection time.
After automatically-monitored information transmission that is newly-built or transformation transformer station all will wait passage construction erection debugging unimpeded in the past, the construction that just carrying out dispatches and stand holds and examination transmission work.After adopting the method, mobile terminal directly can be carried out construction transmission at station end, no longer by the restriction of passage, rectification duration shorten in average 3-5 days.
2, reduce robotization transmission and coordinate the work efficiency of personnel, significant increase work efficiency.
The transmission of current automatically-monitored information needs converting station debugging personnel and dispatching automation personnel two ends telephonic communication to carry out, transformer substation end can't see picture data, dispatching terminal can't see field condition, need to be described and explain cooperation, when there is problem one end, other end personnel will wait for, inefficiency, and it is very large that mutual restriction involves energy.Run into 220kV station and will relate to three Levels Scheduling, respectively phone contact transmission.By the use of described method, graph data is illustrated in face of field personnel intuitively, no longer need the cooperation of dispatching terminal, decrease manpower simultaneously, improve efficiency about 60%, and field personnel's job placement is more autonomous, dosage transmission while can arranging simultaneously to carry out telemechanical main frame and background system, work on the spot efficiency significant increase.
3, responsibility is more clear, ensure that the safe operation of the correct of information and electrical network.
The information at current 220kV station is at about 1500, and the information at 110kV station, at about 700, needs dosage actual transmission, acceptance following construction often, after the problem of operation generation below scene adjusts, work above can not ensure correctly, sometimes to need transmission again.The use of operation simulation main website can divide on-the-spot construction transmission and the examination transmission of dispatching terminal clearly from management, after site operation transmission is errorless, scheduling can be checked and accepted according to the historical record of operation simulation main website transmission and transmission report, and checks and accepts the correct of transmission guarantee information targetedly.Rectification construction transmission is carried out in transformer station in addition, can not cause the malfunction at other stations, ensure that the safety of electrical network.
4, operation simulation master function is intuitively easy to use.
Operation simulation main website adopts linux operating system, ensure that safety and the stability of system, and debug function uses simple, and three buttons just can complete installment and debugging and the filing-up work of required substation data figure.A button is the synchronous artwork of a key, the substation data figure of dispatch automated system is synchronously imported operation simulation main website, does not need odd word; Second pushbutton enable field adjustable function, carries out visual debugging; 3rd button terminates filing, terminates debug function and the record of transmission is carried out preservation filing.
Current information transmission mode, plant stand end commissioning staff and main website commissioning staff carry out telephonic communication, transformer substation end can't see the picture data sent, dispatching terminal can't see field condition, a plant stand needs the complete all data of transmission to need transtelephonic more than 25 hours, and need and multiple main website carry out transmission, cause transmission efficiency low.After adopting operation simulation main website, the end personnel that stand can carry out transmission test and Information Authentication work anywhere or anytime, by the restriction of communicate restriction and main website, can carry out optimized transmission scheme, decrease a large amount of time according to field condition.By transmission report reporting after transmission, monitor staff carries out taking a sample test of information, and the transmission that the phone transmission of more than 20 hours can be become 30 minutes is checked and accepted.
To sum up, described debug system is by arranging operation simulation main website on mobile terminals, achieve the transmission of scheduling station model and actual schedule main website indifference, unit operation can be carried out, and in conjunction with industrial switch, telemechanical apparatus and serial server realize simulative debugging, thus the scene realizing monitor message is checked and accepted from main transmission on the spot, shorten transformer station to put into operation the time, improve the efficiency that monitor message is checked and accepted, ensure that correctness and the reliability of information transmission simultaneously, saving manpower, material resources, the transformer substation construction time is additionally reduced while financial resources, sound assurance power grid security, stable operation.
Claims (3)
1. a moving analog scheduling station debug system, it is characterized in that comprising mobile terminal, industrial switch, serial server and several telemechanical apparatus, the mobile terminal of described system is provided with operation simulation main website, several telemechanical apparatus are directly connected by network connection with industrial switch and are indirectly connected with industrial switch by serial server, and described industry control switch is connected with mobile terminal by network connection.
2. moving analog scheduling station debug system according to claim 1, is characterized in that, described mobile terminal is notebook computer, PC or minicomputer.
3. moving analog scheduling station debug system according to claim 1, is characterized in that, the process of establishing of described operation simulation main website is as follows:
(1) the preposition program of scheduling station is extracted from the automation of transformation substations regulator control system of actual motion and SCADA applies substantially, the associated with that two kinds are applied is extracted, form minimization system, associated with is configured and process of compilation, ensure that operation simulation main website can start normally and apply on mobile terminals, carry out the compiling of source code and the amendment of configuration file;
(2) by the installing DB of scheduling station on mobile terminal, run independently database instance, and carry out database design, the consistance of the scheduling station system ensureing and run at present, carries out the verification of database;
(3) the scheduling station file of extraction and configuration file are installed on the mobile terminal of linux operating system, carry out the compiling of secondary source code, ensure the optimum of system, form operation simulation main website.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410568998.5A CN104460589B (en) | 2014-10-23 | 2014-10-23 | Mobile debugging system with simulation dispatching master station |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410568998.5A CN104460589B (en) | 2014-10-23 | 2014-10-23 | Mobile debugging system with simulation dispatching master station |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104460589A true CN104460589A (en) | 2015-03-25 |
CN104460589B CN104460589B (en) | 2017-04-26 |
Family
ID=52906814
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410568998.5A Expired - Fee Related CN104460589B (en) | 2014-10-23 | 2014-10-23 | Mobile debugging system with simulation dispatching master station |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104460589B (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105262230A (en) * | 2015-11-26 | 2016-01-20 | 国网辽宁省电力有限公司大连供电公司 | Method for establishing portable scheduling master station system to debug newly-built substation |
CN105680441A (en) * | 2016-01-25 | 2016-06-15 | 许继集团有限公司 | Simulated replacement technique-based simulated point-alignment device |
CN105827437A (en) * | 2016-03-10 | 2016-08-03 | 积成电子股份有限公司 | System for enhancing debugging efficiency in accessing plant station to master station and method thereof |
CN107492240A (en) * | 2016-06-13 | 2017-12-19 | 国网天津市电力公司 | A kind of method that distribution automation transformation debugging is carried out using 4G networks |
CN107733090A (en) * | 2017-11-23 | 2018-02-23 | 国网上海市电力公司 | A kind of power distribution automation movement simulation main website and its Application way |
CN109246392A (en) * | 2018-09-21 | 2019-01-18 | 南京七宝机器人技术有限公司 | A kind of transformer substation sequence control capacity checking device based on machine vision |
CN110112831A (en) * | 2019-06-03 | 2019-08-09 | 国网四川省电力公司电力科学研究院 | A kind of supervisory control of substation information automation checks and accepts device and its acceptance method |
CN110244638A (en) * | 2019-06-27 | 2019-09-17 | 宁波三星医疗电气股份有限公司 | Data monitoring device and method |
CN113741374A (en) * | 2021-09-14 | 2021-12-03 | 中国长江电力股份有限公司 | Debugging platform and debugging method of giant hydropower station monitoring system |
CN114612079A (en) * | 2022-05-16 | 2022-06-10 | 国网江西省电力有限公司电力科学研究院 | Automatic checking method for monitoring information graph library of centralized control station |
CN114785680A (en) * | 2022-06-17 | 2022-07-22 | 深圳市信润富联数字科技有限公司 | Wind power industrial control equipment transformation method and terminal transformation method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050033481A1 (en) * | 2003-08-08 | 2005-02-10 | Budhraja Vikram S. | Real-time performance monitoring and management system |
CN101546472A (en) * | 2009-04-29 | 2009-09-30 | 安徽省电力公司芜湖供电公司 | Integrated universal simulation test system and implement method for electric network scheduling and electric quantity collection |
CN103488835A (en) * | 2013-09-26 | 2014-01-01 | 国家电网公司 | Simulation platform and method for dispatching automation system |
-
2014
- 2014-10-23 CN CN201410568998.5A patent/CN104460589B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050033481A1 (en) * | 2003-08-08 | 2005-02-10 | Budhraja Vikram S. | Real-time performance monitoring and management system |
CN101546472A (en) * | 2009-04-29 | 2009-09-30 | 安徽省电力公司芜湖供电公司 | Integrated universal simulation test system and implement method for electric network scheduling and electric quantity collection |
CN103488835A (en) * | 2013-09-26 | 2014-01-01 | 国家电网公司 | Simulation platform and method for dispatching automation system |
Non-Patent Citations (1)
Title |
---|
王峰,张智锐,任春梅,陈志光,张冉: "继电保护故障信息系统子站自助测试系统设计开发", 《电力系统保护与控制》 * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105262230A (en) * | 2015-11-26 | 2016-01-20 | 国网辽宁省电力有限公司大连供电公司 | Method for establishing portable scheduling master station system to debug newly-built substation |
CN105680441A (en) * | 2016-01-25 | 2016-06-15 | 许继集团有限公司 | Simulated replacement technique-based simulated point-alignment device |
CN105680441B (en) * | 2016-01-25 | 2018-03-20 | 许继集团有限公司 | Simulation based on stimulated replacement technology is to a device |
CN105827437A (en) * | 2016-03-10 | 2016-08-03 | 积成电子股份有限公司 | System for enhancing debugging efficiency in accessing plant station to master station and method thereof |
CN107492240A (en) * | 2016-06-13 | 2017-12-19 | 国网天津市电力公司 | A kind of method that distribution automation transformation debugging is carried out using 4G networks |
CN107733090A (en) * | 2017-11-23 | 2018-02-23 | 国网上海市电力公司 | A kind of power distribution automation movement simulation main website and its Application way |
CN109246392A (en) * | 2018-09-21 | 2019-01-18 | 南京七宝机器人技术有限公司 | A kind of transformer substation sequence control capacity checking device based on machine vision |
CN110112831A (en) * | 2019-06-03 | 2019-08-09 | 国网四川省电力公司电力科学研究院 | A kind of supervisory control of substation information automation checks and accepts device and its acceptance method |
CN110244638A (en) * | 2019-06-27 | 2019-09-17 | 宁波三星医疗电气股份有限公司 | Data monitoring device and method |
CN113741374A (en) * | 2021-09-14 | 2021-12-03 | 中国长江电力股份有限公司 | Debugging platform and debugging method of giant hydropower station monitoring system |
CN114612079A (en) * | 2022-05-16 | 2022-06-10 | 国网江西省电力有限公司电力科学研究院 | Automatic checking method for monitoring information graph library of centralized control station |
CN114612079B (en) * | 2022-05-16 | 2022-09-02 | 国网江西省电力有限公司电力科学研究院 | Automatic checking method for monitoring information graph library of centralized control station |
CN114785680A (en) * | 2022-06-17 | 2022-07-22 | 深圳市信润富联数字科技有限公司 | Wind power industrial control equipment transformation method and terminal transformation method |
Also Published As
Publication number | Publication date |
---|---|
CN104460589B (en) | 2017-04-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104460589B (en) | Mobile debugging system with simulation dispatching master station | |
CN104269934B (en) | Based on the supervisory control of substation information adjustment method of moving analog scheduling station | |
CN201608541U (en) | Solar-energy photovoltaic intelligent power station based on Ethernet | |
CN104269924A (en) | Power distribution terminal system based on IEC 61850 and realizing plug and play mechanism | |
CN103412533B (en) | The mechanical check system of intelligent grid dispatching and monitoring information | |
CN104459476B (en) | Fault detection system based on source data maintenance mechanism | |
CN106532935B (en) | For carrying out the method and its system of secondary system of intelligent substation fault diagnosis | |
CN108923953A (en) | A kind of virtual main station system of power remote machine debugging | |
CN103441570A (en) | One-button type sequential control operation control method based on integrated information platform | |
CN102981087B (en) | RTDS and intelligent relay protection device interface system | |
CN104133443A (en) | Method for automatically generating power grid dispatching operation order through power grid overhaul application forms | |
CN102709894A (en) | On-line checking method and system for relay protection setting value | |
CN105069587A (en) | Mobile Internet-based relay protection verification device | |
CN105262230A (en) | Method for establishing portable scheduling master station system to debug newly-built substation | |
CN104580245A (en) | Power distribution terminal 104 message parsing system and parsing method thereof | |
CN104063761A (en) | SCADA data development system based on smart grid | |
CN102169343B (en) | Programmed remote operation system and method of grid centralized monitoring center | |
CN203366087U (en) | Automated control and monitoring system for digital cinema equipment | |
CN204906004U (en) | Distributed intelligent regional power grid of network layering | |
CN106685759A (en) | High-efficiency and zero-error updating and upgrading verification test method for scheduling main station | |
CN105738803B (en) | A kind of method of protective relaying device remote control remote communication joint debugging | |
CN204856181U (en) | Long -range program -controlled system of high -low pressure cabinet | |
CN101924392B (en) | Bipolar automatic power control method of high-voltage direct-current transmission | |
CN112636947B (en) | Data network shutdown point table information checking management method | |
CN203232270U (en) | Automatic restart system of electrical energy collection terminal of transformer station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170426 Termination date: 20211023 |