CN104155970B - A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof - Google Patents

A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof Download PDF

Info

Publication number
CN104155970B
CN104155970B CN201410379246.4A CN201410379246A CN104155970B CN 104155970 B CN104155970 B CN 104155970B CN 201410379246 A CN201410379246 A CN 201410379246A CN 104155970 B CN104155970 B CN 104155970B
Authority
CN
China
Prior art keywords
iec61850
host computer
monitoring host
testing
test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410379246.4A
Other languages
Chinese (zh)
Other versions
CN104155970A (en
Inventor
彭志强
张小易
袁宇波
曾飞
陈磊
杨明
李虎成
樊海锋
高磊
卜强生
宋亮亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410379246.4A priority Critical patent/CN104155970B/en
Publication of CN104155970A publication Critical patent/CN104155970A/en
Priority to PCT/CN2014/092742 priority patent/WO2016019662A1/en
Application granted granted Critical
Publication of CN104155970B publication Critical patent/CN104155970B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B23/00Testing or monitoring of control systems or parts thereof
    • G05B23/02Electric testing or monitoring

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Testing And Monitoring For Control Systems (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a kind of intelligent substation monitoring host computer closed loop test system, comprise IEC61850 and protect observing and controlling simulator, monitoring host computer, station level switch, IEC61850 network message recorder analyser and testing workstation, described IEC61850 protects observing and controlling simulator, monitoring host computer and IEC61850 network message recorder analyser to be all connected with station level switch, and described testing workstation and IEC61850 protect observing and controlling simulator to be connected; Also disclose the method for testing of this system.Test Strategy, analysis bulletin and export are compared by testing workstation by the present invention, automatically test report is generated according to comparison result, accurately, the test to monitoring host computer is achieved reliably, fast, solve and the test macro of perfect in shape and function and good method of testing are lacked to realize the problem of comprehensive quantitative test for monitoring host computer, meet the demand of intelligent substation test.

Description

A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof
Technical field
The present invention relates to a kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof, belong to power system automation technology field.
Background technology
Intelligent substation is intelligent grid important component part, along with the development that intelligent grid is built, newly-built intelligent substation gets more and more, monitoring host computer realizes whole transformer station one secondary device supervisory and control function, whether its function and dependable performance directly concern substation safety production run, carry out intelligent substation monitoring host computer Testing Technology Study and have very important practical value.At present monitoring host computer test is still undertaken by the debugging acid of some function singlenesses, the test macro and the good method of testing that lack perfect in shape and function realize comprehensive quantitative test, to monitoring host computer function and performance test without intact solution, the demand of intelligent substation test can not be met completely.
Summary of the invention
The invention provides a kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof, solve and the test macro of perfect in shape and function and good method of testing are lacked to realize the problem of comprehensive quantitative test for monitoring host computer.
In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is:
A kind of intelligent substation monitoring host computer closed loop test system, comprise IEC61850 and protect observing and controlling simulator, monitoring host computer, station level switch, IEC61850 network message recorder analyser and testing workstation, described IEC61850 protects observing and controlling simulator, monitoring host computer and IEC61850 network message recorder analyser to be all connected with station level switch, and described testing workstation and IEC61850 protect observing and controlling simulator to be connected; Described monitoring host computer is measurand, can derive in test process the file recording station level interaction data, and export is sent to testing workstation; Described IEC61850 protects observing and controlling simulator can emulate multiple stage protection supervisory equipment according to SCD file, and information interaction is simulated information input and output based on IEC61850 protection and measurement and control equipment completely; Receive the configuration file of testing workstation, make station level communication message customizable, interbehavior is controlled; The Test Strategy that record testing workstation configures also forms original test data file; The start and stop instruction of described IEC61850 network message recorder analyser acceptance test workstation; By the network message of network monitoring mode recording station control layer switch, the network message of analysis station control layer switch also generates analyzes bulletin; Bulletin and network message data feedback will be analyzed to testing workstation; Described testing workstation protects observing and controlling simulator to send configuration file to IEC61850; Start and stop instruction is sent to IEC61850 network message recorder analyser; Configuration testing strategy; Receive the analysis bulletin and network message data that send to IEC61850 network message recorder analyser, receive the export that monitoring host computer sends, and Test Strategy, analysis bulletin and export are compared, automatically generate test report according to comparison result.
IEC61850 is adopted to carry out communication interaction between described IEC61850 network message recorder analyser and testing workstation.
Described analysis bulletin is XML file.
Described analysis bulletin content comprises the communications status of IED, event report description, control procedure description, setting value process prescription, file service process tracking and statistical information.
Described testing workstation is computing machine.
A method of testing for intelligent substation monitoring host computer closed loop test system, comprises the following steps,
Step one, Test Strategy is also handed down to IEC61850 protection observing and controlling simulator by testing workstation configuration testing strategy, and IEC61850 protects observing and controlling simulator to carry out information interaction according to Test Strategy and monitoring host computer;
Step 2, testing workstation sends enabled instruction, and IEC61850 network message recorder analyser is by the network message of network monitoring mode recording station control layer switch, and the network message of analysis station control layer switch also generates analyzes bulletin;
Step 3, testing workstation sends halt instruction, and IEC61850 network message recorder analyser will analyze bulletin and network message data feedback to testing workstation;
Step 4, monitoring host computer derives the file recording station level interaction data in test process, and export is sent to testing workstation;
Step 5, Test Strategy, analysis bulletin and export are compared by testing workstation, automatically generate test report according to comparison result.
The beneficial effect that the present invention reaches: Test Strategy, analysis bulletin and export are compared by testing workstation by the present invention, automatically test report is generated according to comparison result, accurately, the test to monitoring host computer is achieved reliably, fast, solve and the test macro of perfect in shape and function and good method of testing are lacked to realize the problem of comprehensive quantitative test for monitoring host computer, meet the demand of intelligent substation test.
Accompanying drawing explanation
Fig. 1 is system connection layout of the present invention.
Fig. 2 is method flow diagram of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the invention will be further described.Following examples only for technical scheme of the present invention is clearly described, and can not limit the scope of the invention with this.
As shown in Figure 1; a kind of intelligent substation monitoring host computer closed loop test system; comprise IEC61850 and protect observing and controlling simulator, monitoring host computer, station level switch, IEC61850 network message recorder analyser and testing workstation, testing workstation is generally common computing machine.
IEC61850 protects observing and controlling simulator, monitoring host computer and IEC61850 network message recorder analyser to be all connected with station level switch; testing workstation and IEC61850 protect observing and controlling simulator to be connected, and adopt IEC61850 to carry out communication interaction between IEC61850 network message recorder analyser and testing workstation.
The function of said apparatus is as follows:
Monitoring host computer: be measurand, the file recording station level interaction data can be derived in test process, and export is sent to testing workstation.
IEC61850 protects observing and controlling simulator: IEC61850 protects observing and controlling simulator can emulate multiple stage protection supervisory equipment according to SCD file, information interaction is simulated information input and output based on IEC 61850 protection and measurement and control equipment completely, can flexible configuration be carried out to outgoing message, be convenient to that backstage is monitored to intelligent substation, protection information substation is carried out comprehensively, quantitative test; Receive the configuration file of testing workstation, make station level communication message customizable, interbehavior is controlled; The Test Strategy that record testing workstation configures also forms original test data file, and this raw data is as a data source of subsequent contrast.
IEC61850 network message recorder analyser: the start and stop instruction of acceptance test workstation; By the network message of network monitoring mode recording station control layer switch, the network message of analysis station control layer switch also generates analyzes bulletin; Bulletin and network message data feedback will be analyzed to testing workstation.
Testing workstation: protect observing and controlling simulator to send configuration file to IEC61850; Start and stop instruction is sent to IEC61850 network message recorder analyser; Configuration testing strategy; Receive the analysis bulletin and network message data that send to IEC61850 network message recorder analyser, receive the export that monitoring host computer sends, and Test Strategy, analysis bulletin and export are compared, automatically generate test report according to comparison result.
Above-mentioned analysis bulletin is XML file, and its content comprises the communications status of IED, event report description, control procedure description, setting value process prescription, file service process tracking and statistical information; Particular content is as follows:
(1) communications status of IED
A. communication interruption time, the communication recovery time;
B. communication disruption reason: client disconnects or service end disconnects, long-time countless certificate (comprising tcp keep-alive);
(2) event report describes
A. according to report blocks sorted generalization: can comprise multiple state-event in report time, each report, state-event comprises event description, event quality, is worth, quotes, event time;
(3) control procedure describes
A. control operation result: control object, controlling value, result, failure cause (comprising AddCause reason), time;
(4) setting value process prescription
A. revise definite value, switch definite value result;
(5) file service process tracking
A. file name, download time, transmission duration (unit second), transmission file size (unit byte);
(6) statistical information
A. associated TCP linking number;
B. service end TCP disconnecting number of times;
C. client TCP disconnecting number of times;
D. report-control block initialization times (comprise successfully, failure);
E. straighforward operation number of success, the frequency of failure.
The method of testing of above-mentioned intelligent substation monitoring host computer closed loop test system, concrete steps are as follows:
Step one, Test Strategy is also handed down to IEC61850 protection observing and controlling simulator by testing workstation configuration testing strategy, and IEC61850 protects observing and controlling simulator to carry out information interaction according to Test Strategy and monitoring host computer;
Step 2, testing workstation sends enabled instruction, and IEC61850 network message recorder analyser is by the network message of network monitoring mode recording station control layer switch, and the network message of analysis station control layer switch also generates analyzes bulletin;
Step 3, testing workstation sends halt instruction, and IEC61850 network message recorder analyser will analyze bulletin and network message data feedback to testing workstation;
Step 4, monitoring host computer derives the file recording station level interaction data in test process, and export is sent to testing workstation;
Step 5, Test Strategy, analysis bulletin and export are compared by testing workstation, automatically generate test report according to comparison result.
In sum, Test Strategy, analysis bulletin and export are compared by testing workstation by the present invention, automatically test report is generated according to comparison result, accurately, the test to monitoring host computer is achieved reliably, fast, solve and the test macro of perfect in shape and function and good method of testing are lacked to realize the problem of comprehensive quantitative test for monitoring host computer, meet the demand of intelligent substation test.
The above is only the preferred embodiment of the present invention; it should be pointed out that for those skilled in the art, under the prerequisite not departing from the technology of the present invention principle; can also make some improvement and distortion, these improve and distortion also should be considered as protection scope of the present invention.

Claims (6)

1. an intelligent substation monitoring host computer closed loop test system, it is characterized in that: comprise IEC61850 and protect observing and controlling simulator, monitoring host computer, station level switch, IEC61850 network message recorder analyser and testing workstation, described IEC61850 protects observing and controlling simulator, monitoring host computer and IEC61850 network message recorder analyser to be all connected with station level switch, and described testing workstation and IEC61850 protect observing and controlling simulator to be connected;
Described monitoring host computer is measurand, can derive in test process the file recording station level interaction data, and export is sent to testing workstation;
Described IEC61850 protects observing and controlling simulator can emulate multiple stage protection supervisory equipment according to SCD file, and information interaction is simulated information input and output based on IEC61850 protection and measurement and control equipment completely; Receive the configuration file of testing workstation, make station level communication message customizable, interbehavior is controlled; The Test Strategy that record testing workstation configures also forms original test data file;
The start and stop instruction of described IEC61850 network message recorder analyser acceptance test workstation; By the network message of network monitoring mode recording station control layer switch, the network message of analysis station control layer switch also generates analyzes bulletin; Bulletin and network message data feedback will be analyzed to testing workstation;
Described testing workstation protects observing and controlling simulator to send configuration file to IEC61850; Start and stop instruction is sent to IEC61850 network message recorder analyser; Configuration testing strategy; Receive the analysis bulletin and network message data that send to IEC61850 network message recorder analyser, receive the export that monitoring host computer sends, and Test Strategy, analysis bulletin and export are compared, automatically generate test report according to comparison result.
2. a kind of intelligent substation monitoring host computer closed loop test system according to claim 1, is characterized in that: adopt IEC61850 to carry out communication interaction between described IEC61850 network message recorder analyser and testing workstation.
3. a kind of intelligent substation monitoring host computer closed loop test system according to claim 1, is characterized in that: described analysis bulletin is XML file.
4. a kind of intelligent substation monitoring host computer closed loop test system according to claim 1, is characterized in that: described analysis bulletin content comprises the communications status of IED, event report description, control procedure description, setting value process prescription, file service process tracking and statistical information.
5. a kind of intelligent substation monitoring host computer closed loop test system according to claim 1, is characterized in that: described testing workstation is computing machine.
6., based on the method for testing of a kind of intelligent substation monitoring host computer closed loop test system according to claim 1, comprise the following steps,
Step one, Test Strategy is also handed down to IEC61850 protection observing and controlling simulator by testing workstation configuration testing strategy, and IEC61850 protects observing and controlling simulator to carry out information interaction according to Test Strategy and monitoring host computer;
Step 2, testing workstation sends enabled instruction, and IEC61850 network message recorder analyser is by the network message of network monitoring mode recording station control layer switch, and the network message of analysis station control layer switch also generates analyzes bulletin;
Step 3, testing workstation sends halt instruction, and IEC61850 network message recorder analyser will analyze bulletin and network message data feedback to testing workstation;
Step 4, monitoring host computer derives the file recording station level interaction data in test process, and export is sent to testing workstation;
Step 5, Test Strategy, analysis bulletin and export are compared by testing workstation, automatically generate test report according to comparison result.
CN201410379246.4A 2014-08-04 2014-08-04 A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof Active CN104155970B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201410379246.4A CN104155970B (en) 2014-08-04 2014-08-04 A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof
PCT/CN2014/092742 WO2016019662A1 (en) 2014-08-04 2014-12-02 Closed loop test system for monitoring host of intelligent substation and test method therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410379246.4A CN104155970B (en) 2014-08-04 2014-08-04 A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof

Publications (2)

Publication Number Publication Date
CN104155970A CN104155970A (en) 2014-11-19
CN104155970B true CN104155970B (en) 2015-09-30

Family

ID=51881494

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410379246.4A Active CN104155970B (en) 2014-08-04 2014-08-04 A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof

Country Status (2)

Country Link
CN (1) CN104155970B (en)
WO (1) WO2016019662A1 (en)

Families Citing this family (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104155970B (en) * 2014-08-04 2015-09-30 国家电网公司 A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof
CN106771775A (en) * 2017-01-17 2017-05-31 贵州大学 A kind of object test device of same intelligent substation protection device half
CN106921522B (en) * 2017-03-15 2023-06-30 国网安徽省电力公司电力科学研究院 Networking information model detection device of intelligent substation network message recording and analyzing device
CN107918294A (en) * 2017-12-19 2018-04-17 贵州大学 A kind of intelligent grid Protection simulation platform and its emulation mode based on RTDS
CN110266553A (en) * 2018-03-12 2019-09-20 南京南瑞继保电气有限公司 A kind of device operation/maintenance data automatic obtaining method
CN108873735B (en) * 2018-06-29 2021-11-19 许继集团有限公司 Power distribution main station system component simulation test device and method
CN110021995A (en) * 2019-01-30 2019-07-16 国网浙江宁波市鄞州区供电有限公司 A kind of distribution network automated information joint debugging emulation test system
CN110493079B (en) * 2019-08-14 2022-06-28 长园深瑞继保自动化有限公司 Production automation test method of industrial Ethernet switch
CN110691008B (en) * 2019-09-30 2022-07-19 北京博电新力电气股份有限公司 Intelligent management unit test system and test method
CN111600756A (en) * 2020-05-14 2020-08-28 南瑞集团有限公司 Communication interface device, system and method for control system in-loop real-time simulation experiment
CN111708700B (en) * 2020-06-17 2023-10-20 南京太司德智能电气有限公司 Intelligent remote machine closed loop comprehensive test method
CN111987794A (en) * 2020-07-09 2020-11-24 国网山东省电力公司青岛供电公司 Intelligent substation on-line monitoring and fault analysis system
CN111950747B (en) * 2020-08-28 2022-03-18 深圳市鸿泰盛合科技有限公司 Intelligent router automatic test system and method
CN112230079A (en) * 2020-09-07 2021-01-15 许昌开普检测研究院股份有限公司 Automatic testing system for information of relay protection device
CN112637001B (en) * 2020-12-03 2022-04-19 国网浙江省电力有限公司衢州供电公司 Function pre-test method and system for data communication network shutdown
CN112737115A (en) * 2020-12-25 2021-04-30 国网辽宁省电力有限公司辽阳供电公司 Remote signaling joint debugging decoupling method for main station and plant station of transformer substation
CN113079051A (en) * 2021-04-09 2021-07-06 国网浙江省电力有限公司电力科学研究院 Parallel simulation method based on transformer substation localization communication protocol
CN113315222A (en) * 2021-04-21 2021-08-27 北京四方继保工程技术有限公司 Intelligent substation automation equipment operation and maintenance management and control system suitable for electric power system
CN113343446B (en) * 2021-05-25 2022-07-01 国网湖北省电力有限公司荆门供电公司 Data analysis and verification method and system for transformer substation monitoring system
CN113507436B (en) * 2021-06-02 2022-08-23 中国人民解放军63880部队 Power grid embedded terminal fuzzy test method aiming at GOOSE protocol
CN114123482A (en) * 2021-09-18 2022-03-01 贵州电网有限责任公司 Main plant station information joint debugging decoupling method
CN114710431A (en) * 2021-12-24 2022-07-05 深圳供电局有限公司 Automatic closed-loop test method for intelligent Internet of things terminal
CN114401212B (en) * 2022-01-22 2023-08-04 海南电网有限责任公司电力科学研究院 Method for testing double-master-station communication protocol
CN116346655A (en) * 2022-12-20 2023-06-27 中国电力科学研究院有限公司 Network abnormal movable mould test system and method for new generation transformer substation and centralized control station

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5740105B2 (en) * 2010-06-29 2015-06-24 株式会社東芝 Application monitoring method for communication system
CN102291277B (en) * 2011-08-09 2013-06-19 上海思源弘瑞自动化有限公司 Automatic test system and method for intelligent substation spacing apparatus
CN102624089A (en) * 2012-03-18 2012-08-01 山西省电力公司电力科学研究院 Total digitized transformer station closed loop dynamic real-time simulation testing system
JP2014054081A (en) * 2012-09-07 2014-03-20 Toshiba Corp Transformer substation automation system
CN103200051B (en) * 2013-04-27 2015-12-09 国家电网公司 Intelligent substation message emulating is tested and is associated message analysis system and method
CN103312035B (en) * 2013-05-21 2015-04-22 国家电网公司 Integrated simulation adjusting-testing system and simulation adjusting-testing method for intelligent substation
CN103412208B (en) * 2013-07-15 2016-04-20 国家电网公司 The method of intelligent substation electric power telemechanical device closed loop test
CN103439612B (en) * 2013-09-02 2015-11-11 上海毅昊自动化有限公司 Based on the intelligent substation Auto-Test System of SCD
CN103746882B (en) * 2014-01-14 2015-12-09 国家电网公司 The method of intelligent substation station level test
CN103885438B (en) * 2014-03-20 2016-08-31 国家电网公司 The Auto-Test System of a kind of transformer station measuring and controlling equipment and method
CN104155970B (en) * 2014-08-04 2015-09-30 国家电网公司 A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof

Also Published As

Publication number Publication date
CN104155970A (en) 2014-11-19
WO2016019662A1 (en) 2016-02-11

Similar Documents

Publication Publication Date Title
CN104155970B (en) A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof
CN111143308B (en) High-low voltage motor data processing method, system and device based on federal learning
CN112366818B (en) Automatic checking and accepting method and system for monitoring information of intelligent substation
EP2478380B1 (en) A method and a system for simulation in a substation
CN107180314B (en) Operation and maintenance business model modeling method based on primary and secondary system incidence relation
CN203070033U (en) PLC remote monitoring system based on Web
CN110568284B (en) Intelligent substation one-key sequential control automatic test verification method, device and system
CN110071577A (en) Supervisory control of substation information acceptance method and system
CN103926917A (en) Intelligent transformer substation master control device testing system and method
CN103051065A (en) Distribution-automation distributed type FA (feeder automation) linkage test method and system
CN104578408A (en) State monitoring and tendency estimation device for secondary equipment of intelligent substation
CN106953719A (en) A kind of automation of transformation substations wide area O&M interoperability test system and method for testing
CN105093017B (en) Intelligent substation GOOSE integrated testabilities device and its method of testing
CN108923953A (en) A kind of virtual main station system of power remote machine debugging
CN104483842A (en) Regulation and control integrated automatic master station comparison method
CN109613906B (en) Third-generation intelligent substation measurement and control submachine test system and application method thereof
CN106647703A (en) Power fault intelligent analysis and inversion system and method
CN105630620A (en) Machine fault automated processing method
CN103425116A (en) Method for removing power dispatching automation system fault
CN105094120A (en) Testing device capable of simulating action behaviors of primary equipment
CN105759150A (en) Test system and method for transformer substation secondary device prefabricated cabin
CN100498618C (en) Computer network monitoring system for flexible electric PC board stitching machine
CN104638761A (en) Packet sensing and packet simulation verification based GOOSE (generic object oriented substation event) virtual terminal connection method
CN104579817A (en) Communication loop test method based on GOOSE (generic object-oriented substation event) logics
CN109193616A (en) A kind of substation's telecontrol information distribution acceptance method and system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant