CN104495205A - Two-working procedure assembling production line of air compressor component - Google Patents

Two-working procedure assembling production line of air compressor component Download PDF

Info

Publication number
CN104495205A
CN104495205A CN201410738939.8A CN201410738939A CN104495205A CN 104495205 A CN104495205 A CN 104495205A CN 201410738939 A CN201410738939 A CN 201410738939A CN 104495205 A CN104495205 A CN 104495205A
Authority
CN
China
Prior art keywords
conveyer belt
annular conveyer
annular
assembling
air compressor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410738939.8A
Other languages
Chinese (zh)
Inventor
吴其强
徐太林
年方圆
耿昌胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHU FUMA AUTO SPARE PARTS Co Ltd
Original Assignee
WUHU FUMA AUTO SPARE PARTS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHU FUMA AUTO SPARE PARTS Co Ltd filed Critical WUHU FUMA AUTO SPARE PARTS Co Ltd
Priority to CN201410738939.8A priority Critical patent/CN104495205A/en
Publication of CN104495205A publication Critical patent/CN104495205A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G37/00Combinations of mechanical conveyors of the same kind, or of different kinds, of interest apart from their application in particular machines or use in particular manufacturing processes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G47/00Article or material-handling devices associated with conveyors; Methods employing such devices
    • B65G47/52Devices for transferring articles or materials between conveyors i.e. discharging or feeding devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Structure Of Belt Conveyors (AREA)

Abstract

The invention discloses a two-working procedure assembling production line of an air compressor component. A workpiece is transported through a first annular conveyer belt and a second annular conveyer belt; a first assembling platform is arranged between the two annular conveyer belts to assemble the workpiece on the first annular conveyer belt; after the assembling is completed, the assembled workpiece is transferred to the second annular conveyer belt; the workpiece on the second annular conveyer belt is assembled by the second assembling platform; after the assembling is completed, the assembled workpiece is placed on a discharging conveyer belt to be output. According to the invention, the space of a workshop can be well utilized, operators can assemble workpieces relatively conveniently, and unlike a stream line which is too fast or too slow speed is very fast or very slow, the two-working procedure assembling production line can automatically adjust the assembling time; moreover, first turnover plates and second turnover plates are arranged at four corners for enabling operators to go into and outof the two-working procedure assembling production line, so that the assembling production line is quite humanized without affecting the conveying speed; the heights of the first annular conveyer belt, the first assembling platform, the second annular conveyer belt and the second assembling platform are reduced in sequence, so that operators can operate relatively conveniently.

Description

A kind of Air compressor parts two-step assembling line
Technical field
The present invention relates to the assembling field of Air compressor, particularly relate to a kind of Air compressor parts two-step assembling line.
Background technology
It is main body in the dynamo-electric bleed air source device of nucleus equipment of pneumatic system that air compressor is just to provide source of the gas power, it be the mechanical energy of former dynamic (normally electrical motor) is converted to gaseous tension can device, be compressed-air actuated pressure generator.Be assembled by multiple accessory in automobile air compressor production process, my company's productive output is large, the parts of a lot of Air compressor need be assembled simultaneously, the mode of conveyor line is adopted to assemble, conveyor line is generally strip shape, need very large space to supply assembling, and there is no so large space assembly line aborning now, therefore solve the problem and just seem very necessary.
Summary of the invention
The invention provides a kind of Air compressor parts two-step assembling line, adopt two annular conveyer belt place work pieces, between two annular conveyer belts and the inside arranges and turns the assembling of allotment of labor's station, solves produced problem in background technology.
For solving the problem, the invention provides a kind of Air compressor parts two-step assembling line, include the first annular conveyer belt and the second annular conveyer belt that entirety is rectangle, described second annular conveyer belt is arranged on the inner side being close to the first annular conveyer belt inside the first annular conveyer belt; Accompany at least 10 the first assembly supports between described first annular conveyer belt and the second annular conveyer belt, the inner side of the second annular conveyer belt is provided with at least 8 the second assembly supports; The outside on the short both sides of described first annular conveyer belt is connected with material loading conveyer belt; The four corners of described first annular conveyer belt is the first flap, and the four corners of the second annular conveyer belt is the second flap, and people that the first flap and the second flap are withdrawn a confession comes in and goes out.
Further improvement is: in described second annular conveyer belt, ground is provided with at least two blanking conveyer belts perpendicular on the direction on the both sides of the second annular transport belt length between the second assembly support, and two blanking conveyer belts pass from the bottom of the first annular conveyer belt and the second annular conveyer belt and are jointly connected with total conveyer belt.
Further improvement is: the surface of described first annular conveyer belt and the second annular conveyer belt tilts to be convenient to workpiece of taking all to the inside.
Further improvement is: the height of described first annular conveyer belt is higher than the height of the first assembly support, and the height of the first assembly support is higher than the height of the second annular conveyer belt, and the height of the second annular conveyer belt is higher than the height of the second assembly support.
Beneficial effect of the present invention: the present invention is by arranging the first annular conveyer belt and the second annular transport brings transporting work pieces, between two annular conveyer belts, arrange the first assembly support assemble the workpiece on the first annular conveyer belt, assemble the workpiece transfer that assembles on the second annular conveyer belt, then the second assembly support assembles the workpiece on the second annular conveyer belt, be placed on after assembling on blanking conveyer belt and export, the space in workshop can well be utilized like this, workman can assemble by convenient carrying out, without the need to extremely to catch up with as conveyor line or very slowly full, the time of assembling can be regulated voluntarily, and arrange the first flap and the second flap confession workman discrepancy in corner, very hommization does not affect travelling speed, and the height of the first annular conveyer belt, the first assembly support, the second annular conveyer belt and the second assembly support reduces successively, operative can be facilitated more smoothly like this, enhance productivity, structure of the present invention is simple to operation, efficiently can assemble Air compressor by fast speed, make use of the space in workshop greatly, improve production efficiency, make production hommization more, is applicable in production.
Accompanying drawing explanation
Fig. 1 is birds-eye view of the present invention.
Fig. 2 is side half of the present invention partial schematic diagram.
Wherein: 1-first annular conveyer belt, 2-second annular conveyer belt, 3-first assembly support, 4-second assembly support, 5-material loading conveyer belt, 6-first flap, 7-second flap, 8-blanking conveyer belt, the total conveyer belt of 9-.
Detailed description of the invention
In order to deepen the understanding of the present invention, below in conjunction with embodiment, the invention will be further described, and this embodiment only for explaining the present invention, does not form limiting the scope of the present invention.
As illustrated in fig. 1 and 2, the present embodiment provides a kind of Air compressor parts two-step assembling line, include the first annular conveyer belt 1 and the second annular conveyer belt 2 that entirety is rectangle, described second annular conveyer belt 2 is arranged on the inner side being close to the first annular conveyer belt 1 inside the first annular conveyer belt 1; The inner side accompanying 12 the first assembly support 3, second annular conveyer belts 2 between described first annular conveyer belt 1 and the second annular conveyer belt 2 is provided with 10 the second assembly supports 4; The outside on the short both sides of described first annular conveyer belt 1 is connected with material loading conveyer belt 5; People that the four corners of described first annular conveyer belt 1 to be the four corners of the first flap 6, second annular conveyer belt 2 be the second flap 7, first flap 6 and the second flap 7 are withdrawn a confession comes in and goes out; In described second annular conveyer belt 2, ground passes jointly be connected with total conveyer belt 9 perpendicular to the direction on the long both sides of the second annular conveyer belt 2 being provided with the bottom of at least two blanking conveyer belts 8, two blanking conveyer belts 8 from the first annular conveyer belt 1 and the second annular conveyer belt 2 between the second assembly support 4; The surface of described first annular conveyer belt 1 and the second annular conveyer belt 2 tilts to be convenient to workpiece of taking all to the inside; The height of described first annular conveyer belt 1 is higher than the height of the first assembly support 3, and the height of the first assembly support 3 is higher than the height of the second annular conveyer belt 2, and the height of the second annular conveyer belt 2 is higher than the height of the second assembly support 4.
By arranging the first annular conveyer belt 1 and the second annular conveyer belt 2 carrys out transporting work pieces, between two annular conveyer belts, arrange the first assembly support 3 assemble the workpiece on the first annular conveyer belt 1, assemble the workpiece transfer that assembles on the second annular conveyer belt 2, then the second assembly support 4 assembles the workpiece on the second annular conveyer belt 2, be placed on after assembling on blanking conveyer belt 8 and export, the space in workshop can well be utilized like this, workman can assemble by convenient carrying out, without the need to extremely to catch up with as conveyor line or very slowly full, the time of assembling can be regulated voluntarily, and arrange the first flap 6 and the second flap 7 confession workman discrepancy in corner, very hommization does not affect travelling speed, and the height of the first annular conveyer belt 1, first assembly support 3, second annular conveyer belt 2 and the second assembly support 4 reduces successively, can facilitate operative more smoothly like this, enhance productivity.
The present embodiment structure is simple to operation, efficiently can assemble Air compressor by fast speed, make use of the space in workshop greatly, improve production efficiency, make production hommization more, is applicable in production.

Claims (4)

1. an Air compressor parts two-step assembling line, include the first annular conveyer belt (1) and the second annular conveyer belt (2) that entirety is rectangle, it is characterized in that: described second annular conveyer belt (2) is arranged on the inner side that the first annular conveyer belt (1) is close in the first annular conveyer belt (1) the inside; Accompany at least 10 the first assembly supports (3) between described first annular conveyer belt (1) and the second annular conveyer belt (2), the inner side of the second annular conveyer belt (2) is provided with at least 8 the second assembly supports (4); The outside on the short both sides of described first annular conveyer belt (1) is connected with material loading conveyer belt (5); The four corners of described first annular conveyer belt (1) is the first flap (6), and the four corners of the second annular conveyer belt (2) is the second flap (7), and people that the first flap (6) and the second flap (7) are withdrawn a confession comes in and goes out.
2. a kind of Air compressor parts two-step assembling line as claimed in claim 1, it is characterized in that: the direction interior ground of described second annular conveyer belt (2) being positioned at both sides long perpendicular to the second annular conveyer belt (2) between the second assembly support (4) is provided with at least two blanking conveyer belts (8), two blanking conveyer belts (8) pass from the bottom of the first annular conveyer belt (1) and the second annular conveyer belt (2) and are jointly connected with total conveyer belt (9).
3. a kind of Air compressor parts two-step assembling line as claimed in claim 1, is characterized in that: the surface of described first annular conveyer belt (1) and the second annular conveyer belt (2) tilts to be convenient to workpiece of taking all to the inside.
4. a kind of Air compressor parts two-step assembling line as claimed in claim 1, it is characterized in that: the height of described first annular conveyer belt (1) is higher than the height of the first assembly support (3), the height of the first assembly support (3) is higher than the height of the second annular conveyer belt (2), and the height of the second annular conveyer belt (2) is higher than the height of the second assembly support (4).
CN201410738939.8A 2014-12-08 2014-12-08 Two-working procedure assembling production line of air compressor component Pending CN104495205A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410738939.8A CN104495205A (en) 2014-12-08 2014-12-08 Two-working procedure assembling production line of air compressor component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410738939.8A CN104495205A (en) 2014-12-08 2014-12-08 Two-working procedure assembling production line of air compressor component

Publications (1)

Publication Number Publication Date
CN104495205A true CN104495205A (en) 2015-04-08

Family

ID=52936688

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410738939.8A Pending CN104495205A (en) 2014-12-08 2014-12-08 Two-working procedure assembling production line of air compressor component

Country Status (1)

Country Link
CN (1) CN104495205A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110641943A (en) * 2019-10-21 2020-01-03 远大可建科技有限公司 Pipe body conveying line and conveying method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2662581A1 (en) * 1990-06-01 1991-12-06 Soviba Installation for recovering and transferring products, particularly in a slaughterhouse line
JPH0819576B2 (en) * 1991-08-27 1996-02-28 株式会社石川製作所 Bobbin transfer device for spinning machine etc.
CN2529173Y (en) * 2002-03-20 2003-01-01 张恕修 Automatic continuous vacuum freeze drying device
JP2009214261A (en) * 2008-03-12 2009-09-24 Honda Motor Co Ltd Assembling system
CN201334240Y (en) * 2008-11-28 2009-10-28 山东新华医疗器械股份有限公司 Sterilizer assembly line
CN204341838U (en) * 2014-12-08 2015-05-20 芜湖福马汽车零部件有限公司 A kind of Air compressor parts two-step assembling line

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2662581A1 (en) * 1990-06-01 1991-12-06 Soviba Installation for recovering and transferring products, particularly in a slaughterhouse line
JPH0819576B2 (en) * 1991-08-27 1996-02-28 株式会社石川製作所 Bobbin transfer device for spinning machine etc.
CN2529173Y (en) * 2002-03-20 2003-01-01 张恕修 Automatic continuous vacuum freeze drying device
JP2009214261A (en) * 2008-03-12 2009-09-24 Honda Motor Co Ltd Assembling system
CN201334240Y (en) * 2008-11-28 2009-10-28 山东新华医疗器械股份有限公司 Sterilizer assembly line
CN204341838U (en) * 2014-12-08 2015-05-20 芜湖福马汽车零部件有限公司 A kind of Air compressor parts two-step assembling line

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110641943A (en) * 2019-10-21 2020-01-03 远大可建科技有限公司 Pipe body conveying line and conveying method thereof
CN110641943B (en) * 2019-10-21 2021-06-15 远大可建科技有限公司 Pipe body conveying line and conveying method thereof

Similar Documents

Publication Publication Date Title
US9815104B2 (en) Uncoiling, blanking and forming method
CN203901281U (en) Automatic feeding and discharging mechanical hand
CN104444305A (en) Sorting type conveying device
CN106584128A (en) Automatic assembly production line of spool
CN105268872A (en) Automatic sorting oil-immersion pick-up/delivery manipulator of hydraulic drawing press
CN104175194A (en) Tapered roller bearing inner and outer ring automatic grinding production line and method thereof
CN204896737U (en) Automobile parts coating line with pusher
CN203033456U (en) Stacking device for large aluminum profiles
CN204341838U (en) A kind of Air compressor parts two-step assembling line
CN104495205A (en) Two-working procedure assembling production line of air compressor component
CN203774991U (en) Armature automatic production line
CN106505803A (en) A kind of micromotor automatic assembly equipment
CN104037997B (en) A kind of full-automatic stator coil reshaping machine
CN104064624B (en) Full-automatic battery side machining production line
CN206500627U (en) A kind of powder metallurgy knockout machine
CN206185139U (en) Dust exhaust device
CN203667463U (en) High-efficiency assembly production line
CN206047412U (en) A kind of production line for the full-automatic welding of bicycle brandreth tripod
CN203993447U (en) Taper roll bearing Internal and external cycle automatic grinding production line
CN207827371U (en) A kind of Transmission Towers tower material arrangement sorting equipment
CN107539739A (en) A kind of vehicle glass gluing bound edge production line
CN104229382A (en) Pre-assembling conveying device for automobile lamp
CN207267358U (en) A kind of aerial transport system for tire production line
CN204161934U (en) A kind of automobile lamp pre-assy conveyer
CN206624379U (en) Lift release unit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150408

RJ01 Rejection of invention patent application after publication