CN104452763A - 溢流面砼采用轨道埋入式拉模施工方法 - Google Patents
溢流面砼采用轨道埋入式拉模施工方法 Download PDFInfo
- Publication number
- CN104452763A CN104452763A CN201410619536.1A CN201410619536A CN104452763A CN 104452763 A CN104452763 A CN 104452763A CN 201410619536 A CN201410619536 A CN 201410619536A CN 104452763 A CN104452763 A CN 104452763A
- Authority
- CN
- China
- Prior art keywords
- die
- concrete
- track
- walking
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Road Paving Machines (AREA)
- Road Paving Structures (AREA)
Abstract
本发明提供了一种用于水利水电工程建设领域中的溢流面砼采用轨道埋入式拉模施工方法,包括:(1)、配制两套拉模行走装置;(2)、轨道架设:根据工程要求,将轨道上表面控制在砼结构线以下至少5 cm,在轨道下表面与溢流面面层钢筋网焊接固定轨道;(3)、安装拉模行走装置及拉模;(5)、拉模行走:采用卷扬机或手拉葫芦或液压装置,通过牵引拉模行走装置前耳板带动拉模体移动;(6)、抹面收光。本发明架设方法简单、安全可靠,外观更漂亮,施工效率高,本发明不仅适用于溢流面施工,也可用于其它砼底板施工。
Description
技术领域:
本发明属水利水电工程建筑技术领域,特别涉及的是一种大坝溢流面砼采用轨道埋入式拉模施工方法。
背景技术:
在大坝溢流面砼采用拉模施工中,目前有轨拉模施工方法中拉模行走轨道均是架设于砼面以上,轨道架设高度高,支撑轨道所投入的材料及人工费都较高,轨道稳定性难以保证,极易造成拉模体跑模、脱模,引发质量安全事故。溢流面施工后,轨道须进行拆除,拆除轨道后的砼表面须修补预埋锥孔等表面缺陷,影响砼外观质量。
发明内容:
本发明的目的是针对以往溢流面拉模施工过后须拆除轨道并且须处理表面预埋锥孔这一问题,提供了一种使砼表面可以一次成型,施工效率高,外观漂亮,溢流面轨道埋入式拉模施工方法。
本发明的目的是这样来实现的:
本发明溢流面砼采用轨道埋入式拉模施工方法,包括以下步骤:
(1)、配制两套拉模行走装置:每套拉模行走装置中有行走大梁、安装在行走大梁下腹板前端或中部的可使行走大梁在轨道上稳定行走的行走轮、反扣轮,拉模行走大梁后部上腹板上有与拉模体耳板铰接的上耳板,拉模行走大梁前端有作为牵引点的前耳板;
(2)、轨道架设:根据工程要求,将轨道上表面控制在砼结构线以下至少5 cm,在轨道下表面与溢流面面层钢筋网焊接固定轨道;
(3)、安装拉模行走装置及拉模:首仓尚未浇筑砼时,拉模体前端与拉模行走装置上的上耳板穿销连接,拉模体后端设置临时支撑防止模板下沉,等首仓砼浇筑完毕可以起滑后,拉模体后端便可依靠已浇筑的砼作为支撑;
(5)、拉模行走:采用卷扬机或手拉葫芦或液压装置,通过牵引拉模行走装置前耳板带动拉模体移动;
(6)、抹面收光:操作人员站在抹面平台上对刚出模的砼进行抹面收光,直至浇筑到设计高程。
本发明提供了一种拉模在轨道上行走的同时,将拉模体面板以下的轨道埋入砼中的方法。
本发明有益效果是:
(1)轨道位于结构面以下,可以依靠溢流面面层钢筋网架设,架设方法简单、安全可靠;
(2)砼一次成形,较以往不用拆除轨道并不用处理拆除轨道后所留下的砼表面缺陷,外观更漂亮,施工效率更高;
(3)本发明方法不仅适用于溢流面施工,也可用于其它砼底板施工。
附图说明:
图1为本发明施工侧视图。
图2为发明施工正视图。
具体实施方式:
参见图1、图2,本实施例溢流面砼采用轨道埋入式拉模施工方法,包括以下步骤:
(1)、配制两套拉模行走装置:每套拉模行走装置中有行走大梁1、安装在行走大梁下腹板的前端或中部的行走轮2、反扣轮3。行走大梁后部上腹板上有与拉模体7耳板铰接的上耳板4。行走大梁前端有作为牵引点的前耳板5;
(2)、轨道架设:根据工程要求,将轨道6上表面控制在砼结构线9以下5 cm,在轨道下表面与溢流面面层钢筋网8焊接固定轨道;
(3)、安装拉模行走装置及拉模:首仓尚未浇筑砼时,拉模体7前端与拉模行走装置上的上耳板4穿销连接。模体后端设置临时支撑11防止拉模板下沉。等首仓砼浇筑完毕可以起滑后,拉模体后端便可依靠已浇筑的砼10作为支撑;
(5)、拉模行走:采用卷扬机或手拉葫芦或液压装置,通过牵引拉模行走装置前耳板5,从而带动拉模体移动;
(6)、抹面收光:操作人员站在抹面平台上对刚出模的砼进行抹面收光,直至浇筑到设计高程。
上述各实施例是对本发明的上述内容作进一步的说明,但不应该将此理解为本发明上述主题的范围仅限于上述实施例。凡基于上述内容所实现的技术均属本发明的范围。
Claims (1)
1.溢流面砼采用轨道埋入式拉模施工方法,包括以下步骤:
(1)、配制两套拉模行走装置:每套拉模行走装置中有行走大梁、安装在行走大梁下腹板前端或中部的可使行走大梁在轨道上稳定行走的行走轮、反扣轮,拉模行走大梁后部上腹板上有与拉模体耳板铰接的上耳板,拉模行走大梁前端有作为牵引点的前耳板;
(2)、轨道架设:根据工程要求,将轨道上表面控制在砼结构线以下至少5 cm,在轨道下表面与溢流面面层钢筋网焊接固定轨道;
(3)、安装拉模行走装置及拉模:首仓尚未浇筑砼时,拉模体前端与拉模行走装置上的上耳板穿销连接,拉模体后端设置临时支撑防止模板下沉,待首仓砼浇筑完毕可以起滑后、拉模体后端便可依靠已浇筑的砼作为支撑;
(4)、拉模行走:采用卷扬机或手拉葫芦或液压装置,通过牵引拉模行走装置前耳板带动拉模体移动;
(5)、抹面收光:操作人员站在抹面平台上对刚出模的砼进行抹面收光,直至浇筑到设计高程。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410619536.1A CN104452763B (zh) | 2014-11-07 | 2014-11-07 | 溢流面砼采用轨道埋入式拉模施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410619536.1A CN104452763B (zh) | 2014-11-07 | 2014-11-07 | 溢流面砼采用轨道埋入式拉模施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104452763A true CN104452763A (zh) | 2015-03-25 |
CN104452763B CN104452763B (zh) | 2016-06-29 |
Family
ID=52899463
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410619536.1A Active CN104452763B (zh) | 2014-11-07 | 2014-11-07 | 溢流面砼采用轨道埋入式拉模施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104452763B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104929131A (zh) * | 2015-07-14 | 2015-09-23 | 葛洲坝集团第一工程有限公司 | 高陡坡轨道牵引式混凝土滑模装置 |
CN105040704A (zh) * | 2015-08-20 | 2015-11-11 | 中国水利水电第十工程局有限公司 | 面板堆石坝砼面板施工全线段面板自动修抹机 |
CN112343015A (zh) * | 2020-09-16 | 2021-02-09 | 中国葛洲坝集团第二工程有限公司 | 泄槽底板砼桁架轨道拉模施工装置 |
CN114991152A (zh) * | 2022-05-27 | 2022-09-02 | 中国水利水电第七工程局有限公司 | 大坝溢流面常态混凝土与碾压混凝土浇筑施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS585595A (ja) * | 1981-06-30 | 1983-01-12 | Shimizu Constr Co Ltd | マスコンクリ−トにおける表面構造 |
CN201390951Y (zh) * | 2009-05-05 | 2010-01-27 | 中国水利水电第八工程局有限公司 | 一种碾压混凝土大坝溢流面的台阶模板 |
CN203639920U (zh) * | 2013-11-28 | 2014-06-11 | 中国水利水电第八工程局有限公司 | 一种混凝土大坝溢流面的无轨滑模 |
-
2014
- 2014-11-07 CN CN201410619536.1A patent/CN104452763B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS585595A (ja) * | 1981-06-30 | 1983-01-12 | Shimizu Constr Co Ltd | マスコンクリ−トにおける表面構造 |
CN201390951Y (zh) * | 2009-05-05 | 2010-01-27 | 中国水利水电第八工程局有限公司 | 一种碾压混凝土大坝溢流面的台阶模板 |
CN203639920U (zh) * | 2013-11-28 | 2014-06-11 | 中国水利水电第八工程局有限公司 | 一种混凝土大坝溢流面的无轨滑模 |
Non-Patent Citations (3)
Title |
---|
刘红岩: "亭子口水电站表孔溢流面拉模设计", 《水力发电》, vol. 38, no. 6, 31 August 2012 (2012-08-31), pages 54 - 56 * |
吴小峰: "景洪电站溢流坝段溢流面拉模施工", 《广东水利水电》, no. 2, 28 February 2009 (2009-02-28), pages 61 - 62 * |
王晓飞: "张河湾水库拦河坝拉模施工溢流面及改进措施", 《中华民居》, no. 1, 31 January 2013 (2013-01-31), pages 278 - 280 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104929131A (zh) * | 2015-07-14 | 2015-09-23 | 葛洲坝集团第一工程有限公司 | 高陡坡轨道牵引式混凝土滑模装置 |
CN104929131B (zh) * | 2015-07-14 | 2017-01-18 | 中国葛洲坝集团第一工程有限公司 | 高陡坡轨道牵引式混凝土滑模装置 |
CN105040704A (zh) * | 2015-08-20 | 2015-11-11 | 中国水利水电第十工程局有限公司 | 面板堆石坝砼面板施工全线段面板自动修抹机 |
CN105040704B (zh) * | 2015-08-20 | 2017-01-25 | 中国水利水电第十工程局有限公司 | 面板堆石坝砼面板施工全线段面板自动修抹机 |
CN112343015A (zh) * | 2020-09-16 | 2021-02-09 | 中国葛洲坝集团第二工程有限公司 | 泄槽底板砼桁架轨道拉模施工装置 |
CN114991152A (zh) * | 2022-05-27 | 2022-09-02 | 中国水利水电第七工程局有限公司 | 大坝溢流面常态混凝土与碾压混凝土浇筑施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104452763B (zh) | 2016-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101372261B1 (ko) | 암거 시공용 박스 폼 구조 | |
CN103195450B (zh) | 液压隧道仰拱作业台车及仰拱施工方法 | |
CN104452763A (zh) | 溢流面砼采用轨道埋入式拉模施工方法 | |
CN203022024U (zh) | 一种管廊现浇施工整体移动式模架 | |
CN104632251A (zh) | 一体浇筑式模板台车和地下通道混凝土浇筑的施工方法 | |
CN112359779B (zh) | 一种斜面混凝土翻模施工集成化装置及其施工工艺 | |
CN103419279A (zh) | T梁模板整体拆除及纵向滑移施工方法 | |
CN104213559B (zh) | 滩涂区梁下支架钢管桩拔出设备的拔出方法 | |
CN203320425U (zh) | 现浇箱梁侧模滑移施工装置 | |
CN207526506U (zh) | 分离式钢模台车 | |
CN103866699A (zh) | 无轨道式行走挂篮 | |
CN106241234B (zh) | 一种用于预制综合管廊的自行式运输拼装车 | |
CN103184878B (zh) | 一种提高隧道加宽段二衬施工效率的方法 | |
CN203515607U (zh) | 隧道加宽断可调式钢模台车 | |
CN202882411U (zh) | 一种造粒塔滑模制造装置 | |
CN205088634U (zh) | 一种边坡截水沟定型模板 | |
CN114875969A (zh) | 一种明挖现浇地下综合管廊移动台模一体化施工工法 | |
CN108005684A (zh) | 分离式钢模台车及其施工方法 | |
CN204370319U (zh) | 道路桥梁裂缝加固装置 | |
CN203947419U (zh) | 一种高速铁路桥梁垫石模板 | |
CN203730015U (zh) | 一种用于高速公路隧道整体衬砌台车的沟槽衬砌成型装置 | |
CN103195232B (zh) | 电梯井的施工平台及利用该施工平台对电梯井施工的方法 | |
CN204021215U (zh) | 一种适用于尾矿库溢洪塔的作业平台 | |
CN205047236U (zh) | 一种隧道电缆沟台车上的开沟脱模装置 | |
CN208870085U (zh) | 一种地铁车站混凝土支撑底模 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 610091 Sichuan Province, Chengdu District of Qingyang City Industrial Development Zone (East) with the road No. 8 Building 10 Applicant after: China Ge Zhou Ba group is second project Co., Ltd. Address before: 610091 Sichuan Province, Chengdu District of Qingyang City Industrial Development Zone (East) with the road No. 8 Building 10 Applicant before: Gezhouba Group No.2 Engineering Co., Ltd. |
|
COR | Change of bibliographic data | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |