A kind of structure improving corridor ceiling height and method Download PDFInfo
- Publication number
- CN104405071B CN104405071B CN201410659723.2A CN201410659723A CN104405071B CN 104405071 B CN104405071 B CN 104405071B CN 201410659723 A CN201410659723 A CN 201410659723A CN 104405071 B CN104405071 B CN 104405071B
- Authority
- CN
- China
- Prior art keywords
- suspension
- support
- furred ceiling
- corridor
- pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The invention provides a kind of structure improving corridor ceiling height and method, this structure includes being lifted on secondary beam or floor roof along longitudinally disposed pipeline furred ceiling combination suspension and support, forceful electric power wire casing and the air conditioner cold water of girder for return pipe, pipeline furred ceiling combination suspension and support;Air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe;Forceful electric power wire casing is lifted on the lower section of floor roof, forceful electric power wire casing is in addition to having the lower concave part for crossing described secondary beam in the place through secondary beam, arrange in remainder space between the bottom surface at the bottom surface of described secondary beam and described floor roof, so that the furred ceiling absolute altitude in corridor significantly improves.Pipeline suspension and support and furred ceiling suspension and support are united two into one and combine suspension and support into pipeline furred ceiling by the application, this pipeline furred ceiling combination suspension and support undertakes the effect supporting air conditioner cold water for return pipe, Os Draconis and furred ceiling simultaneously, thus eliminate main joist in original furred ceiling suspension and support, raise furred ceiling further.
Description
Technical field
The present invention relates to the technical field of auxiliary equipment of building structure, particularly to improving corridor ceiling height
Structure and method.
Background technology
At present, traditional in the furred ceiling of civil buildings corridor electromechanical pipeline and decorative ceiling use respective to hang
Frame.Needing to carry out decoration construction after described dynamo-electric construction, construction is likely to occur collision each other,
Particularly narrow space region, therefore has to reduce furred ceiling absolute altitude.
Refer to Fig. 1, the independent pipeline suspension and support 2 that air conditioner cold water uses for return pipe 1, decorative ceiling
3 are also adopted by independent furred ceiling suspension and support 4.Fig. 1 shows two groups of air conditioner cold waters for return pipes 3 respectively by
Respective pipeline suspension and support supports 2.Described pipeline suspension and support 2 includes the end respectively with described furred ceiling suspension and support 4
Seat and suspension rod, the lower end of described suspension rod is connected to described base.Described air conditioner cold water is the most straight for return pipe 1
Connect on the base being arranged at described pipeline suspension and support 2.Refer to Fig. 2 and incorporated by reference to refering to Fig. 1, described in hang
Base in topmast suspension bracket 4 includes main joist 4.2 and false keel 4.3, described main joist 4.2 and described secondary dragon
Bone 4.3 intersecting vertical is arranged, and the lower end of suspension rod 4.1 is connected on described main joist 4.2.For air-conditioning cold
Water arranges pipeline suspension and support 2 for return pipe 1, arranges furred ceiling suspension and support 4 again in the lower section of pipeline suspension and support 2,
Not only working procedure is loaded down with trivial details, wastes material, and because occurs that two bases cause furred ceiling 3 absolute altitude to reduce.
Further, existing electromechanical pipeline is when arrangement, and forceful electric power wire casing 5 uses the mode that Fang Ping under beam walks,
Namely forceful electric power wire casing 5 is located in the same horizontal plane arrangement.Owing to the location comparison of forceful electric power wire casing 5 is low, and
Air conditioner cold water have to be arranged on the lower section of forceful electric power wire casing for return pipe 1, causes furred ceiling 3 absolute altitude seriously to drop.
Summary of the invention
For solving the problem that in prior art, corridor space narrow and small furred ceiling absolute altitude is too low, the present invention provides one to carry
The structure of high corridor ceiling height and method, make full use of the space between beam and floor roof and arrange forceful electric power line
Groove, thus significantly improve air conditioner cold water accordingly and supply return pipe and the absolute altitude of furred ceiling, and by by existing pipe
Line suspension and support and decorative ceiling suspension and support unite two into one and combine suspension and support into pipeline furred ceiling, can compress suspension and support institute
Take up room, further lifting corridor furred ceiling absolute altitude.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of structure improving corridor ceiling height, including the longitudinally disposed pipeline furred ceiling combination along girder
Suspension and support, forceful electric power wire casing and air conditioner cold water are for return pipe, and described pipeline furred ceiling combination suspension and support is lifted on secondary
On beam or floor roof;Described air conditioner cold water is directly arranged at the combination of described pipeline furred ceiling for return pipe and hangs
On frame;Described forceful electric power wire casing is lifted on the lower section of floor roof, and described forceful electric power wire casing is except through secondary beam
Place has beyond the lower concave part for crossing described secondary beam, remainder be positioned at the bottom surface of described secondary beam with
Arrange in space between the bottom surface of described floor roof.
Preferably, described lower concave part includes two outer transverse slot portion, an intermediate lateral groove portion and two oblique slot portions,
Described two outer transverse parts are connected to the two ends in described intermediate lateral groove portion respectively through described two oblique slot portions.
Preferably, described pipeline furred ceiling combination suspension and support includes base and suspension rod, and described suspension rod is along the described end
The longitudinally spaced of seat is arranged on described base, and the upper end of described suspension rod is respectively fixedly connected with in corresponding secondary beam
On, described air conditioner cold water is directly arranged on described base for return pipe.
Preferably, arrange between described suspension rod strengthen connecting rod, the upper end of described suspension rod by steel plate with
On the side surface of the secondary beam that bolt is fixed on correspondence.
Preferably, the transverse ends of described base is upwards dug.
Preferably, described base includes transverse bar and the longitudinal rod that square crossing arranges, and described transverse bar is with vertical
Square steel is used to bar.
In the above-mentioned structure improving corridor ceiling height, also include the secondary dragon for arranging decorative ceiling
Bone, described false keel is arranged on described base.
The invention also discloses a kind of method improving corridor ceiling height, use and improve corridor as above
The structure of ceiling height, comprises the steps:
Step one, lifting forceful electric power wire casing is on described floor roof;
Step 2, arranges air conditioner cold water on pipeline furred ceiling combination suspension and support and supplies return pipe, and by pipeline furred ceiling
Combination suspension and support is lifted on described floor roof or secondary beam.
Effect of the invention is that: the structure of the raising corridor ceiling height that the present invention provides and method, this knot
Structure, including longitudinally disposed pipeline furred ceiling combination suspension and support, forceful electric power wire casing and the air conditioner cold water along girder
For return pipe, described pipeline furred ceiling combination suspension and support is lifted on secondary beam or floor roof;Described air-conditioning cold
Water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe;Described forceful electric power wire casing is lifted on floor
The lower section of top board, described forceful electric power wire casing is except having for crossing under described secondary beam in the place through secondary beam
Beyond recess, remainder space between the bottom surface at the bottom surface of described secondary beam and described floor roof
Interior arrangement.Middle forceful electric power wire casing is entirely located in side's walking under beam, due to described in the present invention
Being predominantly located in the space between beam and floor roof of forceful electric power wire casing, so that air conditioner cold water supplies
Return pipe is raised accordingly, and then pipeline furred ceiling combination suspension and support is raised, and finally makes the furred ceiling mark in corridor
Height significantly improves, and about can improve furred ceiling absolute altitude 340 millimeters.Additionally, the combination of described pipeline furred ceiling is hung
Frame and forceful electric power wire casing can use serial pre-fabrication, can effectively save construction material, shorten the engineering time.
Additionally, due in compared to existing technology, the side that pipeline suspension and support and furred ceiling suspension and support are independently arranged
Method, pipeline suspension and support and furred ceiling suspension and support are united two into one and combine suspension and support, this pipe into pipeline furred ceiling by the application
Line furred ceiling combination suspension and support undertakes the effect supporting air conditioner cold water for return pipe, Os Draconis and furred ceiling simultaneously, thus
Eliminate the setting of main joist in original furred ceiling suspension and support, saved vertical direction spatial, suspension and support institute can be compressed
Take up room so that the absolute altitude of furred ceiling raises 45 millimeter.And by by pipeline suspension and support and decoration
Furred ceiling suspension and support unites two into one, and arranges so that suspension and support is unified in corridor, simplifies construction technology.
Additionally, the base in suspension and support uses No. 10 channel-section steels in compared to existing technology, height is 100 millimeters,
In the present invention, the base in pipeline furred ceiling combination suspension and support uses square steel, thus is obtaining identical bearing capacity
Under premise, it is possible to reduce the height of square steel, thus further save vertical direction spatial so that the absolute altitude of furred ceiling
Raise further, about improve 60 millimeters.
Accompanying drawing explanation
Fig. 1 is that existing corridor furred ceiling gut line supports layout schematic diagram;
Fig. 2 is the structural representation of existing furred ceiling suspension and support;
Fig. 3 is the schematic diagram of the structure improving corridor ceiling height of one embodiment of the invention;
Fig. 4 is the side-looking partial schematic sectional view of the structure improving corridor ceiling height of one embodiment of the invention.
Fig. 5 is the structural representation of pipeline furred ceiling combination suspension and support in one embodiment of the invention.
In figure: 1-air conditioner cold water for return pipe, 2-pipeline suspension and support, 3-furred ceiling, 4-furred ceiling suspension and support, 4.1-suspension rod,
4.2-main joist, 4.3-false keel, 5-forceful electric power wire casing, 5.1-lower concave part, 6-pipeline furred ceiling combination suspension and support,
6.1-suspension rod, 6.2-transverse bar, 6.3-longitudinal rod, 6.4-connecting rod, 7-steel plate, 8-bolt, 9-girder, 10-
Secondary beam, 11-floor roof, 12-floor base plate, 13-wall, 14-fan coil, 15-fire chief, 16-
Condensate pipe.
Detailed description of the invention
A kind of knot the improving corridor ceiling height present invention proposed below in conjunction with the drawings and specific embodiments
Structure and method are described in further detail.According to description below and claims, advantages of the present invention and
Feature will be apparent from.Hereinafter will be combined accompanying drawing by cited embodiment, describe in detail in the technology of the present invention
Hold and feature.Need to additionally illustrate, accompanying drawing all use the form simplified very much and all use non-accurately than
Example, only in order to facilitate, to aid in illustrating lucidly the purpose of the embodiment of the present invention.
Refer to Fig. 3 to Fig. 5, present embodiment discloses a kind of structure improving corridor ceiling height, including
The pipeline furred ceiling combination suspension and support 6 that arranges along the longitudinal direction (i.e. the bearing of trend of girder 9) of girder 9, strong
Wiring duct 5 and air conditioner cold water are lifted on secondary beam 10 for return pipe 1, described pipeline furred ceiling combination suspension and support 6
Or on floor roof 11;Described air conditioner cold water is directly arranged at the combination of described pipeline furred ceiling for return pipe 1
On suspension and support 6;Described forceful electric power wire casing 5 is lifted on the lower section of floor roof 11, and described forceful electric power wire casing 5 removes
Have beyond the lower concave part 5.1 for crossing described secondary beam 10 in the place through secondary beam 10, its remaining part
Point in the space between the bottom surface and the bottom surface of described floor roof 11 of described secondary beam 10 along level side
To arrangement.Middle forceful electric power wire casing 5 is entirely located in side's walking under beam, due to institute in the present invention
State in the space being predominantly located between beam and floor roof 11 of forceful electric power wire casing 5, so that empty
Adjust cold water to raise accordingly for return pipe 1, and then pipeline furred ceiling combination suspension and support 6 is raised, finally make
Furred ceiling 3 absolute altitude in corridor significantly improves, and about can improve furred ceiling 3 absolute altitude 340 millimeters.Additionally, it is described
Pipeline furred ceiling combination suspension and support 6 can use serial pre-fabrication with forceful electric power wire casing 5, can effectively save construction material,
Shorten the engineering time.
Preferably, described lower concave part 5.1 includes two outer transverse slot portion, an intermediate lateral groove portion and two oblique slots
Portion, described two outer transverse parts are connected to the two ends in described intermediate lateral groove portion respectively through described two oblique slot portions.
The lower concave part 5.1 of described forceful electric power wire casing 5 can use serial pre-fabrication, effectively to save construction material, shortening
Engineering time.
Preferably, described pipeline furred ceiling combination suspension and support 6 includes base and suspension rod 6.1, described suspension rod 6.1
Longitudinally spaced along described base is arranged on described base, and the upper end of described suspension rod 6.1 is fixing respectively to be connected
Being connected on the secondary beam 10 of correspondence, described air conditioner cold water is directly arranged on described base for return pipe 1, from
And without arranging a pipeline suspension and support 2, no for return pipe 1 to as prior art often group air conditioner cold water
But simplify technique, saved material, and therefore eliminate the height of a base, at the bottom of usual one
The height of seat is mainly the height of its main joist, about can save the vertical height of 45 millimeters.
Preferably, the connecting rod 6.4 strengthened, the upper end of described suspension rod 6.1 are set between described suspension rod 6.1
It is fixed on the side surface of corresponding secondary beam 10 with bolt 8 by steel plate 7.Use described suspension rod 6.1
Suspension rod, by the way of steel plate 7 is fixed on the side surface of corresponding secondary beam 10 with bolt 8, is compared in upper end
6.1 are connected with floor top layer, not only can shorten the length of suspension rod 6.1 to save material, and more just
It is connected between suspension rod 6.1 with fixed buildings (floor roof or secondary beam 10) in realizing, improves and connect
Firmness.
Preferably, described base includes transverse bar 6.2 and longitudinal rod 6.3, the described horizontal stroke that square crossing arranges
Square steel is used to bar 6.2 and longitudinal rod 6.3.In the present embodiment, described transverse bar 6.2 uses 40 × 30 sides
Steel, described longitudinal rod 6.3 uses 60 × 40 square steel, above unit to be millimeter.
Preferably, the transverse ends of described base is upwards dug.Specifically refer to displacement pipeline furred ceiling suspension and support 4
The horizontal level of the longitudinal rod 6.3 of longitudinal both sides is higher than the longitudinal rod 6.3 in the middle part of displacement, and each is described laterally
The two ends of bar 6.2 are folded upward at, and so, can expand the space below furred ceiling 3.
In the above-mentioned structure improving corridor furred ceiling 3 height, also include the pair for arranging decorative ceiling 3
Os Draconis, described false keel is longitudinally disposed along described girder, and described false keel is arranged on described base.
By arranging false keel, described furred ceiling 3 can be easily installed.
The invention also discloses a kind of method improving corridor furred ceiling 3 height, use as above raising to walk
The structure of corridor furred ceiling 3 height, comprises the steps:
Step one, lifting forceful electric power wire casing 5 is on described floor roof 11;
Step 2, arranges air conditioner cold water on pipeline furred ceiling combination suspension and support 6 and supplies return pipe 1, and by pipeline
Furred ceiling combination suspension and support 6 is lifted on described floor roof 11 or secondary beam 10.
The structure of the raising corridor ceiling height that the present invention provides and method, this structure, including along girder
Longitudinally disposed pipeline furred ceiling combination suspension and support, forceful electric power wire casing and air conditioner cold water are for return pipe, described pipeline
Furred ceiling combination suspension and support is lifted on secondary beam or floor roof;Described air conditioner cold water is directly arranged for return pipe
On described pipeline furred ceiling combination suspension and support;Described forceful electric power wire casing is lifted on the lower section of floor roof, described by force
Wiring duct in addition to there is the lower concave part for crossing described secondary beam in the place through secondary beam, remainder
Arrange in space between the bottom surface at the bottom surface of described secondary beam and described floor roof.Compare existing skill
In art, forceful electric power wire casing is entirely located in side's walking under beam, due to most of position of described forceful electric power wire casing in the present invention
In space between beam and floor roof, so that air conditioner cold water is raised accordingly for return pipe, enter
And pipeline furred ceiling combination suspension and support is raised, finally make the furred ceiling absolute altitude in corridor significantly improve, about may be used
To improve furred ceiling absolute altitude 340 millimeters.Additionally, described pipeline furred ceiling combination suspension and support can be adopted with forceful electric power wire casing
With serial pre-fabrication, can effectively save construction material, shorten the engineering time.
Additionally, due in compared to existing technology, the side that pipeline suspension and support and furred ceiling suspension and support are independently arranged
Method, pipeline suspension and support and furred ceiling suspension and support are united two into one and combine suspension and support, this pipe into pipeline furred ceiling by the application
Line furred ceiling combination suspension and support undertakes the effect supporting air conditioner cold water for return pipe, Os Draconis and furred ceiling simultaneously, thus
Eliminate the setting of main joist in original furred ceiling suspension and support, saved vertical direction spatial, suspension and support institute can be compressed
Take up room so that the absolute altitude of furred ceiling raises 45 millimeter.And by by pipeline suspension and support and decoration
Furred ceiling suspension and support unites two into one, and arranges so that suspension and support is unified in corridor, simplifies construction technology.
Additionally, the transverse bar in the base in suspension and support and longitudinal rod use No. 10 grooves in compared to existing technology
Steel, height is 100 millimeters, the transverse bar of the base during pipeline furred ceiling combines suspension and support in the present invention and longitudinal direction
Bar uses square steel, thus on the premise of obtaining identical bearing capacity, it is possible to reduce the height of square steel, thus
Further save vertical direction spatial so that the absolute altitude of furred ceiling is raised further, about improve 60 millimeters.
Foregoing description is only the description to present pre-ferred embodiments, not any limit to the scope of the invention
Fixed, any change that the those of ordinary skill in field of the present invention does according to the disclosure above content, modification, all belong to
Protection domain in claims.
Claims (8)
1. the structure improving corridor ceiling height, it is characterised in that include that longitudinally disposed pipeline furred ceiling combination suspension and support, forceful electric power wire casing and the air conditioner cold water along girder is lifted on secondary beam or floor roof for return pipe, described pipeline furred ceiling combination suspension and support;Described air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe;Described forceful electric power wire casing is lifted on the lower section of floor roof, described forceful electric power wire casing, in addition to having the lower concave part for crossing described secondary beam in the place through secondary beam, is arranged in remainder space between the bottom surface at the bottom surface of described secondary beam and described floor roof.
The structure of raising corridor the most according to claim 1 ceiling height, it is characterized in that: described lower concave part includes two outer transverse slot portion, an intermediate lateral groove portion and two oblique slot portions, and described two outer transverse slot portion are connected to the two ends in described intermediate lateral groove portion respectively through described two oblique slot portions.
The structure of raising corridor the most according to claim 1 ceiling height, it is characterized in that: described pipeline furred ceiling combination suspension and support includes base and suspension rod, described suspension rod is arranged on described base along the longitudinally spaced of described base, the upper end of described suspension rod is respectively fixedly connected with on corresponding secondary beam, and described air conditioner cold water is directly arranged on described base for return pipe.
The structure of raising corridor the most according to claim 3 ceiling height, it is characterised in that: arranging the connecting rod strengthened between described suspension rod, the upper end of described suspension rod is fixed on the side surface of corresponding secondary beam with bolt by steel plate.
The structure of raising corridor the most according to claim 3 ceiling height, it is characterised in that: the transverse ends of described base is upwards dug.
The structure of raising corridor the most according to claim 3 ceiling height, it is characterised in that: described base includes transverse bar and the longitudinal rod that square crossing arranges, and described transverse bar uses square steel with longitudinal rod.
The structure of raising corridor the most according to claim 3 ceiling height, it is characterised in that: also including the false keel for arranging decorative ceiling, described false keel is arranged on described base.
8. the method improving corridor ceiling height, it is characterised in that use the structure improving corridor ceiling height as described in any one in claim 1-7, comprise the steps:
Step one, lifting forceful electric power wire casing is on described floor roof;
Step 2, arranges air conditioner cold water on pipeline furred ceiling combination suspension and support and supplies return pipe, and be lifted on described floor roof or secondary beam by pipeline furred ceiling combination suspension and support.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410659723.2A CN104405071B (en) | 2014-11-19 | 2014-11-19 | A kind of structure improving corridor ceiling height and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410659723.2A CN104405071B (en) | 2014-11-19 | 2014-11-19 | A kind of structure improving corridor ceiling height and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104405071A CN104405071A (en) | 2015-03-11 |
CN104405071B true CN104405071B (en) | 2016-10-12 |
Family
ID=52642729
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410659723.2A Active CN104405071B (en) | 2014-11-19 | 2014-11-19 | A kind of structure improving corridor ceiling height and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104405071B (en) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107687541A (en) * | 2016-08-05 | 2018-02-13 | 五冶集团上海有限公司 | A kind of pipeline provided with people's row access path shares suspension bracket |
WO2019218200A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having high-voltage cable installed therein |
WO2019218227A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having water pipe and low-voltage cable installed therein |
WO2019218201A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having water pipe installed therein |
WO2019218220A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling |
WO2019218210A1 (en) * | 2018-05-16 | 2019-11-21 | 增城市碧桂园物业发展有限公司 | Suspended ceiling system having water pipe and low-voltage cable installed therein |
CN110499861A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of furred ceiling electricity separation system |
CN112166222A (en) * | 2018-05-16 | 2021-01-01 | 增城市碧桂园物业发展有限公司 | Construction method of suspended ceiling system |
CN110499933A (en) * | 2018-05-16 | 2019-11-26 | 深圳市君盈建筑科技有限公司 | A kind of house that pipeline is separated with main structure |
CN109322435B (en) * | 2018-09-26 | 2023-12-29 | 潘峥毅 | Smallpox system |
CN113566021B (en) * | 2021-06-04 | 2022-12-13 | 中铁电气化局集团北京建筑工程有限公司 | Construction method for suspended-ceiling-free comprehensive pipeline at entrance and exit of subway station |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101886441A (en) * | 2009-05-11 | 2010-11-17 | 金元杰 | Waterproof ceiling with multiple levels |
CN201704839U (en) * | 2010-02-25 | 2011-01-12 | 北新集团建材股份有限公司 | Practical novel ceiling system for corridor passageway |
CN203420399U (en) * | 2013-08-02 | 2014-02-05 | 查子庭 | Suspended ceiling |
CN204326340U (en) * | 2014-11-19 | 2015-05-13 | 上海市安装工程集团有限公司 | A kind of structure improving corridor ceiling height |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101241325B1 (en) * | 2010-12-15 | 2013-03-18 | 대안스틸 주식회사 | Carrying channel with symbol indication part |
-
2014
- 2014-11-19 CN CN201410659723.2A patent/CN104405071B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101886441A (en) * | 2009-05-11 | 2010-11-17 | 金元杰 | Waterproof ceiling with multiple levels |
CN201704839U (en) * | 2010-02-25 | 2011-01-12 | 北新集团建材股份有限公司 | Practical novel ceiling system for corridor passageway |
CN203420399U (en) * | 2013-08-02 | 2014-02-05 | 查子庭 | Suspended ceiling |
CN204326340U (en) * | 2014-11-19 | 2015-05-13 | 上海市安装工程集团有限公司 | A kind of structure improving corridor ceiling height |
Also Published As
Publication number | Publication date |
---|---|
CN104405071A (en) | 2015-03-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104405071B (en) | A kind of structure improving corridor ceiling height and method | |
CN204326340U (en) | A kind of structure improving corridor ceiling height | |
CN205663076U (en) | Can reduce steel and concrete composite roof beam of cross -sectional height | |
CN205875537U (en) | Metal containment system roofing expansion joint resistance to deformation waterproof construction | |
CN106193413A (en) | One hides day rail system and a construction method | |
CN102425099B (en) | Large cantilever wave-purlin combined PC bridge and manufacture method thereof | |
CN203066412U (en) | Installing component of plug-in quickly-installed boards | |
CN109132843B (en) | The installation method of super-section metal bellows in a kind of vertical shaft | |
CN103938755B (en) | The isolation structure of hanging conversion beam and construction method thereof under a kind of hoistway | |
CN203947755U (en) | A kind of large Steel Cantilever trussed construction high-altitude construction first floor steel truss erecting device | |
CN105421638A (en) | Hung interlayer structure and construction method thereof | |
CN112376698A (en) | Corridor construction method | |
CN205802754U (en) | A kind of steel structure hydraulic pressure lift construction auxiliary device | |
CN204781540U (en) | It flower structure | |
CN209114648U (en) | A kind of assembling type outer wall structure | |
CN104499625A (en) | Profiled steel sheet and composite floor | |
CN205000518U (en) | Take combination formula floor board in stair hole | |
CN203808281U (en) | Shock isolation structure for shaft bottom-hung conversion brackets | |
CN205476586U (en) | Power station underground factory building furred ceiling construction platform's interim support system | |
CN108589905A (en) | Lifting construction system and its construction method after truss vestibule entirety | |
CN207671499U (en) | A kind of carriage bracket | |
CN104863315B (en) | A kind of sunshading board | |
CN204266444U (en) | A kind of profiled sheet and composite floor | |
CN205617565U (en) | Upper assembling type steel corbel of thermal power factory structure | |
CN205709390U (en) | A kind of traction machine arrangement of machine-roomless lift |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |