CN204326340U - A kind of structure improving corridor ceiling height - Google Patents

A kind of structure improving corridor ceiling height Download PDF

Info

Publication number
CN204326340U
CN204326340U CN201420694114.6U CN201420694114U CN204326340U CN 204326340 U CN204326340 U CN 204326340U CN 201420694114 U CN201420694114 U CN 201420694114U CN 204326340 U CN204326340 U CN 204326340U
Authority
CN
China
Prior art keywords
suspension
support
furred ceiling
pipeline
secondary beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420694114.6U
Other languages
Chinese (zh)
Inventor
施志义
袁鹏飞
汪志桃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Installation Engineering Group Co Ltd
Original Assignee
Shanghai Installation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Installation Engineering Group Co Ltd filed Critical Shanghai Installation Engineering Group Co Ltd
Priority to CN201420694114.6U priority Critical patent/CN204326340U/en
Application granted granted Critical
Publication of CN204326340U publication Critical patent/CN204326340U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model provides a kind of structure improving corridor ceiling height, comprise the combination of pipeline furred ceiling suspension and support, forceful electric power wire casing and air conditioner cold water that the longitudinal direction along girder arranges for return pipe, pipeline furred ceiling combination suspension and support is lifted on secondary beam or floor roof; Air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe; Forceful electric power wire casing is lifted on the below of floor roof, forceful electric power wire casing is except having except the lower concave part for crossing described secondary beam in the place through secondary beam, remainder is arranged in the space between the bottom surface of described secondary beam and the bottom surface of described floor roof, thus the furred ceiling absolute altitude in corridor can be made to significantly improve.Pipeline suspension and support and furred ceiling suspension and support unite two into one as pipeline furred ceiling combines suspension and support by the application, this pipeline furred ceiling combination suspension and support is born simultaneously and is supported the effect of air conditioner cold water for return pipe, keel and furred ceiling, thus eliminate main joist in original furred ceiling suspension and support, raise furred ceiling further.

Description

A kind of structure improving corridor ceiling height
Technical field
The utility model relates to the technical field of auxiliary equipment of building structure, particularly improves the structure of corridor ceiling height.
Background technology
At present, in the furred ceiling of civilian construction corridor, traditional electromechanical pipeline and decorative ceiling adopt respective suspension and support.Need to carry out decoration construction after described electromechanics construction, construct each other and likely collide, particularly narrow space region, therefore have to reduce furred ceiling absolute altitude.
Refer to Fig. 1, the independently pipeline suspension and support 2 that air conditioner cold water adopts for return pipe 1, decorative ceiling 3 also adopts independently furred ceiling suspension and support 4.Show two groups of air conditioner cold waters in Fig. 1 and support 2 by respective pipeline suspension and support respectively for return pipe 3.Described pipeline suspension and support 2 comprises base and suspension rod respectively with described furred ceiling suspension and support 4, and the lower end of described suspension rod is connected to described base.Described air conditioner cold water is directly arranged on the base of described pipeline suspension and support 2 respectively for return pipe 1.Refer to Fig. 2 and incorporated by reference to consulting Fig. 1, the base in described furred ceiling suspension and support 4 comprises main joist 4.2 and rider keel 4.3, and described main joist 4.2 is arranged with described rider keel 4.3 intersecting vertical, and the lower end of suspension rod 4.1 is connected on described main joist 4.2.Arrange pipeline suspension and support 2 for air conditioner cold water for return pipe 1, arrange furred ceiling suspension and support 4 again in the below of pipeline suspension and support 2, not only working procedure is loaded down with trivial details, waste material, and because occurs that two bases cause furred ceiling 3 absolute altitude to reduce.
Further, existing electromechanical pipeline is when arranging, and the mode that forceful electric power wire casing 5 adopts Fang Ping under beam to walk, namely forceful electric power wire casing 5 is located in the same horizontal plane arrangement.Because the location comparison of forceful electric power wire casing 5 is low, and air conditioner cold water must be arranged on the below of forceful electric power wire casing for return pipe 1, causes furred ceiling 3 absolute altitude seriously to drop.
Utility model content
For solving the problem that in prior art, corridor space narrow and small furred ceiling absolute altitude is too low, the utility model provides a kind of structure improving corridor ceiling height, make full use of the spatial placement forceful electric power wire casing between beam and floor roof, thus the corresponding absolute altitude significantly improving air conditioner cold water confession return pipe and furred ceiling, and by existing pipeline suspension and support and decorative ceiling suspension and support are united two into one as pipeline furred ceiling combines suspension and support, space shared by suspension and support can be compressed, further lifting corridor furred ceiling absolute altitude.
The utility model solves the technical scheme that its technical problem adopts:
Improve a structure for corridor ceiling height, comprise the combination of pipeline furred ceiling suspension and support, forceful electric power wire casing and air conditioner cold water that the longitudinal direction along girder arranges for return pipe, described pipeline furred ceiling combination suspension and support is lifted on secondary beam or floor roof; Described air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe; Described forceful electric power wire casing is lifted on the below of floor roof, described forceful electric power wire casing is except having except the lower concave part for crossing described secondary beam in the place through secondary beam, and remainder is arranged in the space between the bottom surface of described secondary beam and the bottom surface of described floor roof.
Preferably, described lower concave part comprise two outer transverse slot portion, an intermediate lateral groove portion and with two oblique slot portions, described two outer transverse parts are connected to the two ends in described intermediate lateral groove portion respectively through described two oblique slot portions.
Preferably, described pipeline furred ceiling combination suspension and support comprises base and suspension rod, described suspension rod is arranged on described base along the longitudinal separation of described base, and the upper end of described suspension rod is fixedly connected on corresponding secondary beam respectively, and described air conditioner cold water is directly arranged on described base for return pipe.
Preferably, arrange the connecting rod strengthened between described suspension rod, the upper end of described suspension rod is fixed on the side surface of corresponding secondary beam by steel plate and bolt.
Preferably, the transverse ends of described base is upwards dug.
Preferably, described base comprises transverse bar and the longitudinal rod of square crossing setting, and described transverse bar and longitudinal rod adopt square steel.
In the structure of above-mentioned raising corridor ceiling height, also comprise the rider keel for arranging decorative ceiling, described rider keel is arranged on described base.
Effect of the present utility model is: the structure of the raising corridor ceiling height that the utility model provides, comprise the combination of pipeline furred ceiling suspension and support, forceful electric power wire casing and air conditioner cold water that the longitudinal direction along girder arranges for return pipe, described pipeline furred ceiling combination suspension and support is lifted on secondary beam or floor roof; Described air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe; Described forceful electric power wire casing is lifted on the below of floor roof, described forceful electric power wire casing is except having except the lower concave part for crossing described secondary beam in the place through secondary beam, and remainder is arranged in the space between the bottom surface of described secondary beam and the bottom surface of described floor roof.Middle forceful electric power wire casing is all positioned at side's walking under beam compared to existing technology, due in the space of the major part of described forceful electric power wire casing between beam and floor roof in the utility model, thus air conditioner cold water can be made to raise for return pipe is corresponding, and then pipeline furred ceiling combination suspension and support is raised, finally make the furred ceiling absolute altitude in corridor significantly improve, approximately can improve furred ceiling absolute altitude 340 millimeters.In addition, described pipeline furred ceiling combination suspension and support and forceful electric power wire casing can adopt serial pre-fabrication, effectively can save construction material, shorten the engineering time.
In addition, in compared to existing technology, the method that pipeline suspension and support and furred ceiling suspension and support are independently arranged, pipeline suspension and support and furred ceiling suspension and support unite two into one as pipeline furred ceiling combines suspension and support by the application, this pipeline furred ceiling combination suspension and support is born simultaneously and is supported the effect of air conditioner cold water for return pipe, keel and furred ceiling, thus eliminate the setting of main joist in original furred ceiling suspension and support, save vertical direction spatial, space shared by suspension and support can be compressed, make the absolute altitude of furred ceiling raise 45 millimeter.And by pipeline suspension and support and decorative ceiling suspension and support are united two into one, the unified layout of suspension and support in corridor can be made, simplify construction technology.
In addition, base compared to existing technology in middle suspension and support adopts No. 10 channel-section steels, be highly 100 millimeters, base in the utility model in pipeline furred ceiling combination suspension and support adopts square steel, thus under the prerequisite obtaining identical bearing capacity, the height of square steel can be reduced, thus further save vertical direction spatial, the absolute altitude of furred ceiling is raised further, approximately improves 60 millimeters.
Accompanying drawing explanation
Fig. 1 is existing corridor furred ceiling gut line support arrangement schematic diagram;
Fig. 2 is the structural representation of existing furred ceiling suspension and support;
Fig. 3 is the schematic diagram of the structure of the raising corridor ceiling height of the utility model one embodiment;
Fig. 4 is the side-looking partial schematic sectional view of the structure of the raising corridor ceiling height of the utility model one embodiment.
Fig. 5 is the structural representation of pipeline furred ceiling combination suspension and support in the utility model one embodiment.
In figure: 1-air conditioner cold water is for return pipe, 2-pipeline suspension and support, 3-furred ceiling, 4-furred ceiling suspension and support, 4.1-suspension rod, 4.2-main joist, 4.3-rider keel, 5-forceful electric power wire casing, 5.1-lower concave part, the combination of 6-pipeline furred ceiling suspension and support, 6.1-suspension rod, 6.2-transverse bar, 6.3-longitudinal rod, 6.4-connecting rod, 7-steel plate, 8-bolt, 9-girder, 10-secondary beam, 11-floor roof, 12-floor base plate, 13-wall, 14-fan coil, 15-fire chief, 16-condensate pipe.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, a kind of structure improving corridor ceiling height that the utility model proposes is described in further detail.According to explanation below and claims, advantage of the present utility model and feature will be clearer.Below by cited embodiment by reference to the accompanying drawings, technology contents of the present utility model and feature will be described in detail.Need to illustrate in addition, accompanying drawing all adopts the form that simplifies very much and all uses non-ratio accurately, only in order to object that is convenient, aid illustration the utility model embodiment lucidly.
Refer to Fig. 3 to Fig. 5, present embodiment discloses a kind of structure improving corridor ceiling height, comprise the combination of pipeline furred ceiling suspension and support 6, forceful electric power wire casing 5 and air conditioner cold water that the longitudinal direction (i.e. the bearing of trend of girder 9) along girder 9 arranges for return pipe 1, described pipeline furred ceiling combination suspension and support 6 is lifted on secondary beam 10 or floor roof 11; Described air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support 6 for return pipe 1; Described forceful electric power wire casing 5 is lifted on the below of floor roof 11, described forceful electric power wire casing 5 is except having the lower concave part 5.1 for crossing described secondary beam 10 in the place through secondary beam 10, remainder is being arranged in the horizontal direction in the space between the bottom surface and the bottom surface of described floor roof 11 of described secondary beam 10.Middle forceful electric power wire casing 5 is all positioned at side's walking under beam compared to existing technology, due in the space of the major part of described forceful electric power wire casing 5 between beam and floor roof 11 in the utility model, thus air conditioner cold water can be made to raise for return pipe 1 is corresponding, and then pipeline furred ceiling combination suspension and support 6 is raised, finally make furred ceiling 3 absolute altitude in corridor significantly improve, approximately can improve furred ceiling 3 absolute altitude 340 millimeters.In addition, described pipeline furred ceiling combination suspension and support 6 can adopt serial pre-fabrication with forceful electric power wire casing 5, effectively can save construction material, shorten the engineering time.
Preferably, described lower concave part 5.1 comprise two outer transverse slot portion, an intermediate lateral groove portion and with two oblique slot portions, described two outer transverse parts are connected to the two ends in described intermediate lateral groove portion respectively through described two oblique slot portions.The lower concave part 5.1 of described forceful electric power wire casing 5 can adopt serial pre-fabrication, effectively to save construction material, to shorten the engineering time.
Preferably, described pipeline furred ceiling combination suspension and support 6 comprises base and suspension rod 6.1, described suspension rod 6.1 is arranged on described base along the longitudinal separation of described base, the upper end of described suspension rod 6.1 is fixedly connected on corresponding secondary beam 10 respectively, described air conditioner cold water is directly arranged on described base for return pipe 1, thus without the need to arranging a pipeline suspension and support 2 for return pipe 1 to as prior art often group air conditioner cold water, not only simplify technique, save material, and therefore eliminate the height of a base, the height of the height of a usual base mainly its main joist, approximately can save the vertical height of 45 millimeters.
Preferably, arrange the connecting rod 6.4 strengthened between described suspension rod 6.1, the upper end of described suspension rod 6.1 is fixed on the side surface of corresponding secondary beam 10 by steel plate 7 and bolt 8.The upper end of described suspension rod 6.1 is adopted to be fixed on the mode on the side surface of corresponding secondary beam 10 by steel plate 7 and bolt 8, compare suspension rod 6.1 to be connected with floor top layer, not only can shorten the length of suspension rod 6.1 to save material, and be more convenient to realize being connected between suspension rod 6.1 with fixed buildings (floor roof or secondary beam 10), improve the firmness connected.
Preferably, described base comprises transverse bar 6.2 and the longitudinal rod 6.3 of square crossing setting, and described transverse bar 6.2 adopts square steel with longitudinal rod 6.3.In the present embodiment, described transverse bar 6.2 adopts 40 × 30 square steel, and described longitudinal rod 6.3 adopts 60 × 40 square steel, and above unit is millimeter.
Preferably, the transverse ends of described base is upwards dug.Specifically refer to that the horizontal level of the longitudinal rod 6.3 of the longitudinal both sides of displacement pipeline furred ceiling suspension and support 4 is higher than the longitudinal rod 6.3 in the middle part of displacement, described in each, the two ends of transverse bar 6.2 upwards bend, and so, can expand the space below furred ceiling 3.
In the structure of above-mentioned raising corridor furred ceiling 3 height, also comprise the rider keel for arranging decorative ceiling 3, described rider keel is arranged along the longitudinal direction of described girder, and described rider keel is arranged on described base.By arranging rider keel, can so that install described furred ceiling 3.
The construction method of the structure of raising corridor as above furred ceiling 3 height, mainly comprises the steps:
Step one, lifting forceful electric power wire casing 5 is on described floor roof 11;
Step 2, pipeline furred ceiling combination suspension and support 6 arranges air conditioner cold water for return pipe 1, and is lifted on described floor roof 11 or secondary beam 10 by pipeline furred ceiling combination suspension and support 6.
The structure of the raising corridor ceiling height that the utility model provides, comprise the combination of pipeline furred ceiling suspension and support, forceful electric power wire casing and air conditioner cold water that the longitudinal direction along girder arranges for return pipe, described pipeline furred ceiling combination suspension and support is lifted on secondary beam or floor roof; Described air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe; Described forceful electric power wire casing is lifted on the below of floor roof, described forceful electric power wire casing is except having except the lower concave part for crossing described secondary beam in the place through secondary beam, and remainder is arranged in the space between the bottom surface of described secondary beam and the bottom surface of described floor roof.Middle forceful electric power wire casing is all positioned at side's walking under beam compared to existing technology, due in the space of the major part of described forceful electric power wire casing between beam and floor roof in the utility model, thus air conditioner cold water can be made to raise for return pipe is corresponding, and then pipeline furred ceiling combination suspension and support is raised, finally make the furred ceiling absolute altitude in corridor significantly improve, approximately can improve furred ceiling absolute altitude 340 millimeters.In addition, described pipeline furred ceiling combination suspension and support and forceful electric power wire casing can adopt serial pre-fabrication, effectively can save construction material, shorten the engineering time.
In addition, in compared to existing technology, the method that pipeline suspension and support and furred ceiling suspension and support are independently arranged, pipeline suspension and support and furred ceiling suspension and support unite two into one as pipeline furred ceiling combines suspension and support by the application, this pipeline furred ceiling combination suspension and support is born simultaneously and is supported the effect of air conditioner cold water for return pipe, keel and furred ceiling, thus eliminate the setting of main joist in original furred ceiling suspension and support, save vertical direction spatial, space shared by suspension and support can be compressed, make the absolute altitude of furred ceiling raise 45 millimeter.And by pipeline suspension and support and decorative ceiling suspension and support are united two into one, the unified layout of suspension and support in corridor can be made, simplify construction technology.
In addition, transverse bar in base compared to existing technology in middle suspension and support and longitudinal rod adopt No. 10 channel-section steels, be highly 100 millimeters, transverse bar and the longitudinal rod of the base in the utility model in pipeline furred ceiling combination suspension and support adopt square steel, thus under the prerequisite obtaining identical bearing capacity, the height of square steel can be reduced, thus further save vertical direction spatial, the absolute altitude of furred ceiling is raised further, approximately improves 60 millimeters.
Foregoing description is only the description to the utility model preferred embodiment; any restriction not to the utility model scope; any change that the those of ordinary skill in the utility model field does according to above-mentioned disclosure, modification, all belong to the protection domain of claims.

Claims (7)

1. one kind is improved the structure of corridor ceiling height, it is characterized in that, comprise the combination of pipeline furred ceiling suspension and support, forceful electric power wire casing and air conditioner cold water that the longitudinal direction along girder arranges for return pipe, described pipeline furred ceiling combination suspension and support is lifted on secondary beam or floor roof; Described air conditioner cold water is directly arranged on described pipeline furred ceiling combination suspension and support for return pipe; Described forceful electric power wire casing is lifted on the below of floor roof, described forceful electric power wire casing is except having except the lower concave part for crossing described secondary beam in the place through secondary beam, and remainder is arranged in the space between the bottom surface of described secondary beam and the bottom surface of described floor roof.
2. the structure of raising corridor according to claim 1 ceiling height, it is characterized in that: described lower concave part comprise two outer transverse slot portion, an intermediate lateral groove portion and with two oblique slot portions, described two outer transverse parts are connected to the two ends in described intermediate lateral groove portion respectively through described two oblique slot portions.
3. the structure of raising corridor according to claim 1 ceiling height, it is characterized in that: described pipeline furred ceiling combination suspension and support comprises base and suspension rod, described suspension rod is arranged on described base along the longitudinal separation of described base, the upper end of described suspension rod is fixedly connected on corresponding secondary beam respectively, and described air conditioner cold water is directly arranged on described base for return pipe.
4. the structure of raising corridor according to claim 3 ceiling height, is characterized in that: arrange the connecting rod strengthened between described suspension rod, the upper end of described suspension rod is fixed on the side surface of corresponding secondary beam by steel plate and bolt.
5. the structure of raising corridor according to claim 3 ceiling height, is characterized in that: the transverse ends of described base is upwards dug.
6. the structure of raising corridor according to claim 3 ceiling height, is characterized in that: described base comprises transverse bar and the longitudinal rod of square crossing setting, and described transverse bar and longitudinal rod adopt square steel.
7. the structure of raising corridor according to claim 3 ceiling height, is characterized in that: also comprise the rider keel for arranging decorative ceiling, described rider keel is arranged on described base.
CN201420694114.6U 2014-11-19 2014-11-19 A kind of structure improving corridor ceiling height Withdrawn - After Issue CN204326340U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420694114.6U CN204326340U (en) 2014-11-19 2014-11-19 A kind of structure improving corridor ceiling height

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420694114.6U CN204326340U (en) 2014-11-19 2014-11-19 A kind of structure improving corridor ceiling height

Publications (1)

Publication Number Publication Date
CN204326340U true CN204326340U (en) 2015-05-13

Family

ID=53162714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420694114.6U Withdrawn - After Issue CN204326340U (en) 2014-11-19 2014-11-19 A kind of structure improving corridor ceiling height

Country Status (1)

Country Link
CN (1) CN204326340U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104405071A (en) * 2014-11-19 2015-03-11 上海市安装工程集团有限公司 Structure and method for increasing height of corridor ceiling
WO2019218227A1 (en) * 2018-05-16 2019-11-21 增城市碧桂园物业发展有限公司 Suspended ceiling system having water pipe and low-voltage cable installed therein
WO2019218226A1 (en) * 2018-05-16 2019-11-21 增城市碧桂园物业发展有限公司 Suspended ceiling system having water pipe and high-voltage cable installed therein
WO2019218253A1 (en) * 2018-05-16 2019-11-21 深圳市君盈建筑科技有限公司 Suspended ceiling system having separated water pipe and electrical cable
WO2019218228A1 (en) * 2018-05-16 2019-11-21 增城市碧桂园物业发展有限公司 Suspended ceiling system having high-voltage and low-voltage cables installed therein
CN113684962A (en) * 2021-09-01 2021-11-23 广东爱富兰建设有限公司 Pipeline laying and suspended ceiling integrated construction system for industrial and commercial places

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104405071A (en) * 2014-11-19 2015-03-11 上海市安装工程集团有限公司 Structure and method for increasing height of corridor ceiling
CN104405071B (en) * 2014-11-19 2016-10-12 上海市安装工程集团有限公司 A kind of structure improving corridor ceiling height and method
WO2019218227A1 (en) * 2018-05-16 2019-11-21 增城市碧桂园物业发展有限公司 Suspended ceiling system having water pipe and low-voltage cable installed therein
WO2019218226A1 (en) * 2018-05-16 2019-11-21 增城市碧桂园物业发展有限公司 Suspended ceiling system having water pipe and high-voltage cable installed therein
WO2019218253A1 (en) * 2018-05-16 2019-11-21 深圳市君盈建筑科技有限公司 Suspended ceiling system having separated water pipe and electrical cable
WO2019218228A1 (en) * 2018-05-16 2019-11-21 增城市碧桂园物业发展有限公司 Suspended ceiling system having high-voltage and low-voltage cables installed therein
CN112204203A (en) * 2018-05-16 2021-01-08 增城市碧桂园物业发展有限公司 A ceiling system installed with water pipes and strong electric wires
CN112236569A (en) * 2018-05-16 2021-01-15 增城市碧桂园物业发展有限公司 A ceiling system installed with strong and weak electric wires
CN113684962A (en) * 2021-09-01 2021-11-23 广东爱富兰建设有限公司 Pipeline laying and suspended ceiling integrated construction system for industrial and commercial places

Similar Documents

Publication Publication Date Title
CN104405071A (en) Structure and method for increasing height of corridor ceiling
CN204326340U (en) A kind of structure improving corridor ceiling height
CN205663076U (en) Can reduce steel and concrete composite roof beam of cross -sectional height
CN201144515Y (en) Steel structure high altitude construction platform
CN105908882A (en) Reinforced concrete box-girder with lowerable section height and construction method thereof
CN103291083A (en) Repair method for old wooden tower
CN202390996U (en) Lifting hook for connecting integrated suspended ceiling with keel
CN103603266B (en) Multilayer bridge overhanging isolation structure
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN205035957U (en) Staggered floor roof beam
CN104266166B (en) Boiler bottom supporting construction
CN203891514U (en) Main transformer framework for omitting end support in substation
CN204112782U (en) Novel pseudo-classic is built
CN202672442U (en) Dark-plug open-type keel
CN203770852U (en) Multi-deck integrated pipe frame structure
CN208267371U (en) A kind of mould plate supporting device of large size conversion beam
CN206299900U (en) For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed
CN204023603U (en) A kind of shearing resistance screw communication base station basis
CN203878836U (en) Spliced space truss interlayer floor
CN215670282U (en) A staggered structure of large-surface and wide shear walls in staggered space
CN202544426U (en) Combined adjustable support frame for prefabricated beams and slabs
CN205617565U (en) Upper assembling type steel corbel of thermal power factory structure
CN203867058U (en) Novel U-shaped cross section component
CN203487794U (en) Main assembling jig frame for large-span steel structure roof primary truss
CN204676831U (en) Floor heating layer of concrete constructing structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20150513

Effective date of abandoning: 20161012

C25 Abandonment of patent right or utility model to avoid double patenting