CN104343111A - 一种利用节点桩加固厚沙土层的复合地基 - Google Patents
一种利用节点桩加固厚沙土层的复合地基 Download PDFInfo
- Publication number
- CN104343111A CN104343111A CN201410509330.3A CN201410509330A CN104343111A CN 104343111 A CN104343111 A CN 104343111A CN 201410509330 A CN201410509330 A CN 201410509330A CN 104343111 A CN104343111 A CN 104343111A
- Authority
- CN
- China
- Prior art keywords
- node
- pile
- soil layer
- stake
- sandy soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/48—Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及一种利用节点桩加固厚沙土层的复合地基,其特征在于包括由厚沙土层(1)、节点桩(2)、节点预成装置(7)组成;所述节点桩(2)为混凝土结构插入厚沙土层(1)中,该节点桩(2)由桩节点(4)和桩柱(3)组成,节点预成装置(7)是由加长管(6)和水喷头(5)组成;所述节点预成装置(7)位于节点桩(2)的内部。通过节点桩的桩节点可加大桩体与厚沙土层的接触面积,同时桩节点的横向椭圆球体可有效的阻止桩体下沉,增大了单根桩体加固土体的面积,从而可减少桩体布设的密度,由此降低桩体的数量,节约了成本,缩短了工期。
Description
技术领域
本发明专利涉及一种利用节点桩加固厚沙土层的复合地基。
背景技术
众所周知,在我国西北地区的青藏高原分布有广阔的冻土面积,黄土高原、内蒙古高原、东北平原、山东的菏泽和黄河古道等地区均覆盖有厚厚的表土层,有的表土层厚度甚至超过一千米之距。随着我国城镇化进程的不断推进,高层建筑和工程建设数量迅猛增加,对地基的要求也更加的严格,特别是在厚砂土层地区建设大型工程,对地基的承载的要求更加不言而喻。
目前,对于地基的软弱土层地基的处治采用排水固接后开挖,现在又新兴起利用透水性混凝土结合排水井的方法对软弱土层地基进行加固。但是面对极厚沙土层地基的软弱,易沉降,施工后地基持续发生沉降的问题不能有效解决,仅仅依靠加大桩基的密度和深度,这种方法虽然能够起到预期的效果,但是其施工工期长,经济投入大,因此,需要一种新的地基处理方式既能达到厚沙土层地基沉降的要求,又能节约成本,缩短工期。
发明内容
本发明专利的目的在于提供一种利用节点桩加固厚沙土层的复合地基,其特征在于包括由厚沙土层(1)、节点桩(2)、节点预成装置(7)组成;
所述节点桩(2)为混凝土结构插入厚沙土层(1)中,该节点桩(2)由桩节点(4)和桩柱(3)组成,节点预成装置(7)是由加长管(6)和水喷头(5)组成;
所述节点预成装置(7)位于节点桩(2)的内部。
所述节点桩(2)在厚沙土层(1)中布置方式为矩形布置或三角形布置,相邻两桩心间距3.5~5m。
所述桩柱(3)直径不小于60cm,桩节点(4)呈椭球形,桩节点(4)的长轴长约1.5~2.5倍的桩柱(3)直径,短轴长与桩柱(3)直径相当,所述桩节点(4)在桩柱(3)上间隔设置,上下间距为4.9~5.1m。
所述水喷头(5)是由10~15cm的圆管组成,水喷头(5)杆长4.9~5.1m,水喷头(5)的出水端与杆径垂直,水喷头(5)的进水端设有法兰盘(8)。
所述加长管(6),其管径规格与水喷头(5)一样,加长管(6)的长度也为4.9~5.1m,同时加长管(6)的进水端和出水端设有法兰盘(8)。
有益效果:
本发明专利的有益效果是:通过节点桩的桩节点可加大桩体与厚沙土层的接触面积,同时桩节点的横向椭圆球体可有效的阻止桩体下沉,增大了单根桩体加固土体的面积,从而可减少桩体布设的密度,由此降低桩体的数量,节约了成本,缩短了工期。
本发明专利的使用方法是:首先确定地基处理的桩位点,然后利用打桩机进行桩孔的施作,桩孔到达设计深度后进行桩节点的预成。桩节点的预成采用水利冲孔法,将特定长度的加长管和水喷头构成的节点预成装置放入桩孔内,将进水端与水泵相连,利用水泵向节点预成装置压水,使形成的高压水从水喷头喷出,对桩孔壁进行水力冲孔,冲孔过程保持出水孔匀速水平旋转,由此形成椭球形的桩节点空间,随后利用抽水泵将桩底的淤泥和水一并排出到地表,再进行下一个桩节点的预成。完成整个桩节点预成后,将搅拌好的混凝土灌入桩孔内,待其凝固,那么节点桩即可形成。
附图说明
图1 节点桩加固厚沙土层地基方法示意图;
图2 桩位点的矩形布置图;
图3 桩位点的三角形布置图;
图4 节点预成装置示意图;
图5 桩节点预成示意图.
具体实施方式
下面结合具体实施例,进一步阐述本发明。
一种利用节点桩加固厚沙土层的复合地基,其特征在于包括由厚沙土层(1)、节点桩(2)、节点预成装置(7)组成;
所述节点桩(2)为混凝土结构插入厚沙土层(1)中,该节点桩(2)由桩节点(4)和桩柱(3)组成,节点预成装置(7)是由加长管(6)和水喷头(5)组成;
所述节点预成装置(7)位于节点桩(2)的内部。
所述节点桩(2)在厚沙土层(1)中布置方式为矩形布置或三角形布置,相邻两桩心间距3.5~5m。
所述桩柱(3)直径不小于60cm,桩节点(4)呈椭球形,桩节点(4)的长轴长约1.5-2.5倍的桩柱(3)直径,短轴长与桩柱(3)直径相当,所述桩节点(4)在桩柱(3)上间隔设置,上下间距为4.9-5.1m。
所述水喷头(5)是由10~15cm的圆管组成,水喷头(5)杆长4.9~5.1m,水喷头(5)的出水端与杆径垂直,水喷头(5)的进水端设有法兰盘(8)。
所述加长管(6),其管径规格与水喷头(5)一样,加长管(6)的长度也为4.9~5.1m,同时加长管(6)的进水端和出水端设有法兰盘(8)。
本发明专利的使用方法是:首先确定地基处理的桩位点(9),然后利用打桩机进行桩孔的施作,桩孔到达设计深度后进行桩节点(4)的预成。桩节点(4)的预成采用水利冲孔法,将特定长度的加长管(6)和水喷头(5)构成的节点预成装置(7)放入桩孔内,将进水端与水泵相连,利用水泵向节点预成装置(7)压水,使形成的高压水从水喷头(5)喷出,对桩孔壁进行水力冲孔,冲孔过程保持出水孔匀速水平旋转,由此形成椭球形的桩节点(4)空间,随后利用抽水泵将桩底的淤泥和水一并排出到地表,再进行下一个桩节点(4)的预成。完成整个桩节点(4)预成后,将搅拌好的混凝土灌入桩孔内,待其凝固,那么节点桩(2)即可形成。
应理解,这些实施例仅用于说明本发明而不用于限制本发明的范围。此外应理解,在阅读了本发明讲授的内容之后,本领域技术人员可以对本发明作各种改动或修改,这些等价形式同样落于本申请所附权利要求书所限定的范围。
Claims (5)
1.一种利用节点桩加固厚沙土层的复合地基,其特征在于包括由厚沙土层(1)、节点桩(2)、节点预成装置(7)组成;
所述节点桩(2)为混凝土结构插入厚沙土层(1)中,该节点桩(2)由桩节点(4)和桩柱(3)组成,节点预成装置(7)是由加长管(6)和水喷头(5)组成;
所述节点预成装置(7)位于节点桩(2)的内部。
2.如权利要求1所述的一种利用节点桩加固厚沙土层的复合地基,其特征在于所述节点桩(2)在厚沙土层(1)中布置方式为矩形布置或三角形布置,相邻两桩心间距3.5~5m。
3.如权利要求1所述的一种利用节点桩加固厚沙土层的复合地基,其特征在于所述桩柱(3)直径不小于60cm,桩节点(4)呈椭球形,桩节点(4)的长轴长约1.5~2.5倍的桩柱(3)直径,短轴长与桩柱(3)直径相当,所述桩节点(4)在桩柱(3)上间隔设置,上下间距为4.9~5.1m。
4.如权利要求1所述的一种利用节点桩加固厚沙土层的复合地基,其特征在于所述水喷头(5)是由10~15cm的圆管组成,水喷头(5)杆长4.9~5.1m,水喷头(5)的出水端与杆径垂直,水喷头(5)的进水端设有法兰盘(8)。
5.如权利要求1所述的一种利用节点桩加固厚沙土层的复合地基,其特征在于所述加长管(6),其管径规格与水喷头(5)一样,加长管(6)的长度也为4.9~5.1m,同时加长管(6)的进水端和出水端设有法兰盘(8)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410509330.3A CN104343111A (zh) | 2014-09-28 | 2014-09-28 | 一种利用节点桩加固厚沙土层的复合地基 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410509330.3A CN104343111A (zh) | 2014-09-28 | 2014-09-28 | 一种利用节点桩加固厚沙土层的复合地基 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104343111A true CN104343111A (zh) | 2015-02-11 |
Family
ID=52499519
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410509330.3A Pending CN104343111A (zh) | 2014-09-28 | 2014-09-28 | 一种利用节点桩加固厚沙土层的复合地基 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104343111A (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105157264A (zh) * | 2015-09-15 | 2015-12-16 | 戚荣生 | 一种在沙漠地区收集太阳热能的装置 |
CN105157250A (zh) * | 2015-09-15 | 2015-12-16 | 戚荣生 | 一种在沙漠中收集太阳热能的装置 |
CN105157263A (zh) * | 2015-09-15 | 2015-12-16 | 戚荣生 | 一种收集利用沙漠表层太阳热能的装置 |
CN105180468A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 一种收集沙漠表层太阳热能的装置 |
CN105180469A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 一种在沙漠地区接收太阳热能的装置 |
CN105180471A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 沙漠地区太阳热能收集利用装置 |
CN105180487A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 一种收集沙漠表层热量的装置 |
CN106836176A (zh) * | 2017-04-11 | 2017-06-13 | 水利部交通运输部国家能源局南京水利科学研究院 | 利用抽真空技术加固沙性土并改良其工程特性的方法 |
CN114960625A (zh) * | 2021-02-28 | 2022-08-30 | 江西基业科技集团有限公司 | 多段扩径混凝土灌注桩的施工方法 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1391011A (zh) * | 2002-07-19 | 2003-01-15 | 王景军 | 钻孔高压喷射扩孔压灌混凝土异型桩成桩方法及所用装置 |
CN1844588A (zh) * | 2006-03-15 | 2006-10-11 | 中国矿业大学 | 塌陷区插筋高压旋喷扩盘桩成型方法 |
CN201056690Y (zh) * | 2007-03-13 | 2008-05-07 | 黑龙江农垦建工有限公司 | 一种挤扩灌注桩 |
JP2011174252A (ja) * | 2010-02-23 | 2011-09-08 | Takenaka Komuten Co Ltd | 多段拡径杭及び構造物 |
CN102409660A (zh) * | 2011-09-19 | 2012-04-11 | 苏州予力再生建材有限公司 | 多节扩大头散粒材料桩复合地基予力工法 |
JP5095944B2 (ja) * | 2006-01-27 | 2012-12-12 | 株式会社竹中工務店 | 多段拡径場所打ちコンクリート杭の製造方法、及び多段拡径場所打ちコンクリート杭の評価方法 |
CN202899121U (zh) * | 2012-04-09 | 2013-04-24 | 浙江大学城市学院 | 粘结力增强式刚柔组合桩 |
CN103711123A (zh) * | 2013-12-17 | 2014-04-09 | 上海岩土工程勘察设计研究院有限公司 | 竹节式砂浆桩及其施工方法 |
CN203808056U (zh) * | 2014-03-18 | 2014-09-03 | 齐迎春 | 多节钻扩灌注桩 |
-
2014
- 2014-09-28 CN CN201410509330.3A patent/CN104343111A/zh active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1391011A (zh) * | 2002-07-19 | 2003-01-15 | 王景军 | 钻孔高压喷射扩孔压灌混凝土异型桩成桩方法及所用装置 |
JP5095944B2 (ja) * | 2006-01-27 | 2012-12-12 | 株式会社竹中工務店 | 多段拡径場所打ちコンクリート杭の製造方法、及び多段拡径場所打ちコンクリート杭の評価方法 |
CN1844588A (zh) * | 2006-03-15 | 2006-10-11 | 中国矿业大学 | 塌陷区插筋高压旋喷扩盘桩成型方法 |
CN201056690Y (zh) * | 2007-03-13 | 2008-05-07 | 黑龙江农垦建工有限公司 | 一种挤扩灌注桩 |
JP2011174252A (ja) * | 2010-02-23 | 2011-09-08 | Takenaka Komuten Co Ltd | 多段拡径杭及び構造物 |
CN102409660A (zh) * | 2011-09-19 | 2012-04-11 | 苏州予力再生建材有限公司 | 多节扩大头散粒材料桩复合地基予力工法 |
CN202899121U (zh) * | 2012-04-09 | 2013-04-24 | 浙江大学城市学院 | 粘结力增强式刚柔组合桩 |
CN103711123A (zh) * | 2013-12-17 | 2014-04-09 | 上海岩土工程勘察设计研究院有限公司 | 竹节式砂浆桩及其施工方法 |
CN203808056U (zh) * | 2014-03-18 | 2014-09-03 | 齐迎春 | 多节钻扩灌注桩 |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105157264A (zh) * | 2015-09-15 | 2015-12-16 | 戚荣生 | 一种在沙漠地区收集太阳热能的装置 |
CN105157250A (zh) * | 2015-09-15 | 2015-12-16 | 戚荣生 | 一种在沙漠中收集太阳热能的装置 |
CN105157263A (zh) * | 2015-09-15 | 2015-12-16 | 戚荣生 | 一种收集利用沙漠表层太阳热能的装置 |
CN105180468A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 一种收集沙漠表层太阳热能的装置 |
CN105180469A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 一种在沙漠地区接收太阳热能的装置 |
CN105180471A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 沙漠地区太阳热能收集利用装置 |
CN105180487A (zh) * | 2015-09-15 | 2015-12-23 | 戚荣生 | 一种收集沙漠表层热量的装置 |
CN106836176A (zh) * | 2017-04-11 | 2017-06-13 | 水利部交通运输部国家能源局南京水利科学研究院 | 利用抽真空技术加固沙性土并改良其工程特性的方法 |
CN114960625A (zh) * | 2021-02-28 | 2022-08-30 | 江西基业科技集团有限公司 | 多段扩径混凝土灌注桩的施工方法 |
CN114960625B (zh) * | 2021-02-28 | 2023-12-15 | 江西基业科技集团有限公司 | 多段扩径混凝土灌注桩的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104343111A (zh) | 一种利用节点桩加固厚沙土层的复合地基 | |
CN103993611B (zh) | 一种深层旋喷水泥土板与锚杆组合抗浮桩筏结构的施工方法 | |
CN102926390B (zh) | 黄土边坡浅层加固及表层固结的方法 | |
CN106013171A (zh) | 一种深基坑侧壁的半刚性半柔性支护结构和方法 | |
CN103924602A (zh) | 深厚软土基坑施工方法 | |
CN107299650B (zh) | 一种远距离沉井排土纠偏方法 | |
CN104775440A (zh) | 一种井筒式地下车库深基坑支护结构 | |
CN105780719A (zh) | 现役驳坎护岸墙加高施工方法 | |
CN102330436B (zh) | 一种用于半岩土层超深圆形旋流池的组合支护结构及方法 | |
CN111364532B (zh) | 一种基于浆液控制的既有桩基加固方法 | |
CN202323865U (zh) | 一种新型护岸组合结构 | |
CN205954638U (zh) | 一种深基坑侧壁的半刚性半柔性支护结构 | |
CN206204967U (zh) | 一种双排灌注桩围堰 | |
CN108797578A (zh) | 带分级扩大头的碎石注浆桩及其施工方法 | |
CN104131566B (zh) | 一种地下室无水平支撑基坑的施工方法 | |
CN102995647B (zh) | 一种桩孔注浆隔渗的地下水控制方法 | |
CN203866852U (zh) | 一种深层旋喷水泥土板与锚杆组合抗浮桩筏结构 | |
CN204551430U (zh) | 一种用于软土地基上的预埋花管注浆加固装置 | |
CN207176700U (zh) | 一种复杂环境下的密排灌注桩内支撑基坑永久支护结构 | |
CN103243721A (zh) | 软弱地质条件下高层建筑筏板基础及核心筒开挖施工方法 | |
CN101338567B (zh) | 旋喷沉井法配合半逆作法施工地下建筑物的施工方法 | |
CN106869153A (zh) | 一种井点降水快速处理软地基的方法 | |
CN104005416A (zh) | 一种用于高陡边坡素填土反压条件下大直径孔桩塌孔的处理方法 | |
CN204238239U (zh) | 桩基础锚索预应力高挡墙结构 | |
CN207846429U (zh) | 一种高地下水位、高基岩出露面的基坑支护体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150211 |
|
RJ01 | Rejection of invention patent application after publication |