CN102330436B - 一种用于半岩土层超深圆形旋流池的组合支护结构及方法 - Google Patents

一种用于半岩土层超深圆形旋流池的组合支护结构及方法 Download PDF

Info

Publication number
CN102330436B
CN102330436B CN201110186245.4A CN201110186245A CN102330436B CN 102330436 B CN102330436 B CN 102330436B CN 201110186245 A CN201110186245 A CN 201110186245A CN 102330436 B CN102330436 B CN 102330436B
Authority
CN
China
Prior art keywords
soil layer
rock
ring beam
pond
anchor pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110186245.4A
Other languages
English (en)
Other versions
CN102330436A (zh
Inventor
张凤勇
吴彦俊
王龙
黄治松
赵建立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
CMTCC Shanghai Shisanye Construction Co Ltd
MCC Tiangong Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMTCC Shanghai Shisanye Construction Co Ltd, MCC Tiangong Construction Co Ltd filed Critical CMTCC Shanghai Shisanye Construction Co Ltd
Priority to CN201110186245.4A priority Critical patent/CN102330436B/zh
Publication of CN102330436A publication Critical patent/CN102330436A/zh
Application granted granted Critical
Publication of CN102330436B publication Critical patent/CN102330436B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本发明涉及一种用于半岩土层超深圆形旋流池的组合支护结构及方法,所述的组合支护方法为,在软土层中,沿着圆形旋流池周边,等间距设置人工挖孔桩,并将人工挖孔桩锚固在岩土层中;在人工挖孔桩的上部设置冠梁,随着基坑挖深,在人工挖孔桩的中部内侧设置若干道中间环梁,同时在中间环梁之间设置钢筋网喷射混凝土;在进入岩土层时,在人工挖孔桩的底部设置底部环梁,同时在每个桩间土之间设置钢筋混凝土锚杆;在进入岩土层后,边开挖边等距离设置钢筋混凝土锚杆,同时设置钢筋网喷射混凝土;根据所述的支护方法形成一种组合支护结构。本发明充分发挥地质条件和围护构件的力学性能,用较低的成本解决了在狭小区域进行超深圆形水池施工的难题。

Description

一种用于半岩土层超深圆形旋流池的组合支护结构及方法
方法领域
本发明属于大型地下圆形旋流池的施工装置方法领域,特别是涉及一种用于半岩土层超深圆形旋流池的组合支护结构及方法。
背景方法
一般在半岩土层(上层为土,下层为岩)施工大型地下圆形旋流池,可采用地下连续墙或排桩支护。然而针对场地比较狭小的地区大型设备难以进入施工,针对土层较硬地区沉桩过程困难效率低下会提高施工成本。
发明内容
本发明所要解决的方法问题是提供一种用于半岩土层超深圆形旋流池的组合支护结构及方法,以解决在狭小区域进行超深圆形水池施工的难题。
本发明解决其方法问题所采用的方法方案是:提供一种用于半岩土层超深圆形旋流池的组合支护方法,包括以下步骤:
(1)在软土层中,沿着圆形旋流池周边,等间距设置人工挖孔桩,并将人工挖孔桩锚固在岩土层中;
(2)在人工挖孔桩的上部设置冠梁,随着基坑挖深,在人工挖孔桩的中部内侧设置若干道中间环梁,同时在中间环梁之间设置第一钢筋网喷射混凝土;重复步骤(1)和(2),直至完成软土层的土方开挖,完成内部支护;
(3)在进入岩土层时,在人工挖孔桩的底部设置底部环梁,并在每个桩间土之间设置第一锚杆,第一锚杆的一端拉在底部环梁上,另一端固定在软土层中;
(4)在进入岩土层后,按照一定间距,边开挖边设置第二锚杆,钢筋网连接在第二锚杆上,同时设置第二钢筋网喷射混凝土;重复步骤(3)和(4),直至完成旋流池支护。
所述的人工挖孔桩为钢筋混凝土圆柱体。
所述的冠梁、中间环梁和底部环梁为矩形截面钢筋混凝土梁。
所述的第一钢筋网喷射混凝土和第二钢筋网喷射混凝土为钢筋混凝土曲面板。
所述的第一锚杆和第二锚杆为钢筋混凝土杆件。
所述的冠梁、中间环梁和底部环梁,等间距设置拉筋,所述的拉筋焊接锚固在人工挖孔桩上。
所述的旋流池周边设置砖砌挡土墙和排水沟。
所述的基坑侧壁有泄水管。
所述的旋流池完成支护后,在基坑底部及时浇筑混凝土垫层。
本发明提供一种用于半岩土层超深圆形旋流池的组合支护支护结构,所述的支护结构包括软土层、岩土层和圆形旋流池;所述的圆形旋流池上部为在软土层中的支护结构,所述的支护结构为,沿着圆形旋流池周边,等间距设置有人工挖孔桩,人工挖孔桩锚固在岩土层中,在人工挖孔桩的上部设置有冠梁,中部内侧设置有若干道中间环梁,底部设置有底部环梁,在所述的中间环梁之间设置有第一钢筋网喷射混凝土,在每个桩间土之间设置有第一锚杆,所述的第一锚杆的一端拉在底部环梁上,另一端固定在软土层中;所述的圆形旋流池下部为在岩土层中的支护结构,所述的支护结构为,沿着圆形旋流池内壁等距离地设置有第二锚杆,和第二钢筋网喷射混凝土,钢筋网连接在第二锚杆上。
有益效果
本发明涉及一种用于半岩土层超深圆形旋流池的组合支护结构及方法,应用于上部为软土下部为岩石的层的基坑支护,可以充分发挥地质条件和围护构件的性能,适用于场地比较狭小或土层较硬的地区,用较低的成本解决了在狭小区域进行超深圆形水池施工的难题,该施工工艺构造简单,制作容易,安装方便,针对性强,便于推广。
附图说明
图1为人工挖孔桩布置示意图。
图2为半岩土层超深圆形旋流池组合支护工艺示意图。
图3为钢筋混凝土环梁拉锚示意图。
图4为地下水泄水管安装示意图。
具体实施方式
下面结合具体实施例,进一步阐述本发明。应理解,这些实施例仅用于说明本发明而不用于限制本发明的范围。此外应理解,在阅读了本发明讲授的内容之后,本领域方法人员可以对本发明作各种改动或修改,这些等价形式同样落于本申请所附权利要求书所限定的范围。
实施例1
如图1-4所示,本发明提供一种用于半岩土层超深圆形旋流池的组合支护方法,包括以下步骤:
(1)在软土层A中,沿着圆形旋流池周边,按照等间距设置人工挖孔桩1,并将人工挖孔桩1锚固在岩土层B中,人工挖孔桩1为钢筋混凝土圆柱体土桩,形成挡土墙用于基坑支护;
(2)在人工挖孔桩1的上部设置冠梁2,随着基坑挖深,在人工挖孔桩1的中部内侧设置若干道中间环梁3,同时在中间环梁3之间设置第一钢筋网喷射混凝土4,形成钢筋混凝土曲面板,防止桩间土脱落;重复步骤(1)和(2),直至完成软土层A的土方开挖,完成内部支护;
(3)在进入岩土层B时,在人工挖孔桩1的底部设置底部环梁5,并在每个桩间土之间设置第一锚杆6,第一锚杆6的一端拉在底部环梁5上,另一端固定在软土层A中,用于提高人工挖孔桩1的锚固强度;
(4)在进入岩土层B后,按照一定间距,边开挖边设置第二锚杆7,钢筋网连接在第二锚杆7上,同时设置第二钢筋网喷射混凝土8;重复步骤(3)和(4),直至完成旋流池支护。
所述的冠梁2、中间环梁3和底部环梁5为矩形截面钢筋混凝土梁;所述的第一锚杆6和第二锚杆7为钢筋混凝土杆件;所述的冠梁2、中间环梁3和底部环梁5,按照一定间距设置拉筋,所述的拉筋焊接锚固在人工挖孔桩1上。为防止地面水流入旋流池,旋流池周边设置砖砌挡土墙10和排水沟11,及时将地表水隔断并引走;根据土层中地下水的分布情况,可在基坑侧壁适当设置泄水管12,以降低地下水压力;待旋流池完成支护后,在基坑底部及时浇筑混凝土垫层13。
人工挖孔桩1、中间环梁3、第一锚杆6和第二锚杆7的数量、尺寸、材料等级和间距等,要根据不同地质情况,通过理论计算确定。
本发明提供一种用于半岩土层超深圆形旋流池的组合支护结构,所述的支护结构包括软土层A、岩土层B和圆形旋流池;所述的圆形旋流池上部为在软土层中的支护结构,所述的支护结构为,沿着圆形旋流池周边,等间距设置有人工挖孔桩1,人工挖孔桩1锚固在岩土层B中,在人工挖孔桩1的上部设置有冠梁2,中部内侧设置有若干道中间环梁3,底部设置有底部环梁5,在所述的中间环梁3之间设置有第一钢筋网喷射混凝土4,在每个桩间土之间设置有第一锚杆6,所述的第一锚杆6的一端拉在底部环梁5上,另一端固定在软土层A中;所述的圆形旋流池下部为在岩土层B中的支护结构,所述的支护结构为,沿着圆形旋流池内壁等距离地设置有第二锚杆7,和第二钢筋网喷射混凝土8,钢筋网连接在第二锚杆7上。

Claims (8)

1.一种用于半岩土层超深圆形旋流池的组合支护方法,其特征在于,所述的旋流池周边设置砖砌挡土墙(10)和排水沟(11),所述的基坑侧壁有泄水管(12),包括以下步骤: 
(1)在软土层(A)中,沿着圆形旋流池周边,等间距设置人工挖孔桩(1),并将人工挖孔桩(1)锚固在岩土层(B)中; 
(2)在人工挖孔桩(1)的上部设置冠梁(2),随着基坑挖深,在人工挖孔桩(1)的中部内侧设置若干道中间环梁(3),同时在中间环梁(3)之间设置第一钢筋网喷射混凝土(4);重复步骤(1)和(2),直至完成软土层(A)的土方开挖,完成内部支护; 
(3)在进入岩土层(B)时,在人工挖孔桩(1)的底部设置底部环梁(5),并在每个桩间土之间设置第一锚杆(6),第一锚杆(6)的一端拉在底部环梁(5)上,另一端固定在软土层(A)中; 
(4)在进入岩土层(B)后,边开挖边等距离地设置第二锚杆(7),钢筋网连接在第二锚杆(7)上,同时设置第二钢筋网喷射混凝土(8);重复步骤(3)和(4),直至完成旋流池支护。 
2.根据权利要求1所述的一种用于半岩土层超深圆形旋流池的组合支护方法,其特征在于,所述的人工挖孔桩(1)为钢筋混凝土圆柱体。 
3.根据权利要求1所述的一种用于半岩土层超深圆形旋流池的组合支护方法,其特征在于,所述的冠梁(2)、中间环梁(3)和底部环梁(5)为矩形截面钢筋混凝土梁。 
4.根据权利要求1所述的一种用于半岩土层超深圆形旋流池的组合支护结构及方法,其特征在于,所述的第一钢筋网喷射混凝土(4)和第二钢筋网喷射混凝土(8)为钢筋混凝土曲面板。 
5.根据权利要求1所述的一种用于半岩土层超深圆形旋流池的组合支护方法,其特征在于,所述的第一锚杆(6)和第二锚杆(7)为钢筋混凝土杆件。 
6.根据权利要求1所述的一种用于半岩土层超深圆形旋流池的组合支护方法,其特征在于,所述的冠梁(2)、中间环梁(3)和底部环梁(5)上,等间距设置拉筋,所述的拉筋焊接锚固在人工挖孔桩(1)上。 
7.根据权利要求1所述的一种用于半岩土层超深圆形旋流池的组合支护方法,其特征在于,所述的旋流池完成支护后,在基坑底部及时浇筑混凝土垫层(13)。 
8.根据权利要求1所述的一种用于半岩土层超深圆形旋流池的组合支护方法所形成的一种组合支护结构,其特征在于,所述的支护结构包括软土层(A)、岩土层(B)和圆形旋 流池;所述的圆形旋流池上部为在软土层中的支护结构,所述的支护结构为,沿着圆形旋流池周边,等间距设置有人工挖孔桩(1),人工挖孔桩(1)锚固在岩土层(B)中,在人工挖孔桩(1)的上部设置有冠梁(2),中部内侧设置有若干道中间环梁(3),底部设置有底部环梁(5),在所述的中间环梁(3)之间设置有第一钢筋网喷射混凝土(4),在每个桩间土之间设置有第一锚杆(6),所述的第一锚杆(6)的一端拉在底部环梁(5)上,另一端固定在软土层(A)中;所述的圆形旋流池下部为在岩土层(B)中的支护结构,所述的支护结构为,沿着圆形旋流池内壁等距离地设置有第二锚杆(7),和第二钢筋网喷射混凝土(8),钢筋网连接在第二锚杆(7)上。 
CN201110186245.4A 2011-07-05 2011-07-05 一种用于半岩土层超深圆形旋流池的组合支护结构及方法 Active CN102330436B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110186245.4A CN102330436B (zh) 2011-07-05 2011-07-05 一种用于半岩土层超深圆形旋流池的组合支护结构及方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110186245.4A CN102330436B (zh) 2011-07-05 2011-07-05 一种用于半岩土层超深圆形旋流池的组合支护结构及方法

Publications (2)

Publication Number Publication Date
CN102330436A CN102330436A (zh) 2012-01-25
CN102330436B true CN102330436B (zh) 2014-06-04

Family

ID=45482382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110186245.4A Active CN102330436B (zh) 2011-07-05 2011-07-05 一种用于半岩土层超深圆形旋流池的组合支护结构及方法

Country Status (1)

Country Link
CN (1) CN102330436B (zh)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102605801A (zh) * 2012-03-15 2012-07-25 中冶天工上海十三冶建设有限公司 一种地下圆形水池悬挂半逆作施工方法
CN103615252B (zh) * 2013-11-25 2015-09-09 中铁十八局集团有限公司 地铁盾构井单层主体结构的施工工艺
CN104631878B (zh) * 2015-01-09 2016-09-07 中国十九冶集团有限公司 铝业铸造机井施工方法
CN107476335B (zh) * 2017-08-10 2023-08-22 中国电建集团贵阳勘测设计研究院有限公司 一种用于岩体管廊结构
CN112609732A (zh) * 2020-12-02 2021-04-06 中国十九冶集团有限公司 一种旋流井施工方法
CN112627199A (zh) * 2020-12-02 2021-04-09 中国十九冶集团有限公司 一种旋流井基坑支护施工方法
CN115059096A (zh) * 2022-03-30 2022-09-16 上海二十冶建设有限公司 一种页岩地质紧邻既有厂房的旋流池施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1131221A (zh) * 1995-12-29 1996-09-18 曾宪明 基坑边坡平锚喷网支护方法
CN1399039A (zh) * 2002-09-03 2003-02-26 贾金青 一种用于支护基坑侧壁的无根护壁桩及其施工方法
JP2004293281A (ja) * 2003-02-05 2004-10-21 Ohbayashi Corp 永久アンカーが施工された壁構造の構築方法、永久アンカーが施工された壁構造
CN101126241A (zh) * 2006-08-15 2008-02-20 吴忠诚 疏排桩-土钉墙组合支护方法
CN101250878A (zh) * 2008-03-11 2008-08-27 青建集团股份公司 一种用无嵌固端桩锚结合锚板墙的深基坑支护方法
CN101280564A (zh) * 2008-06-06 2008-10-08 北京建工集团有限责任公司 基坑桩锚护壁混凝土腰梁结构及其施工方法
CN201347559Y (zh) * 2009-01-08 2009-11-18 广州市设计院 一种吊脚桩基坑支护体系结构
CN102002952A (zh) * 2009-09-03 2011-04-06 中国二十冶集团有限公司 土岩结合地域的旋流池基坑防护施工方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1131221A (zh) * 1995-12-29 1996-09-18 曾宪明 基坑边坡平锚喷网支护方法
CN1399039A (zh) * 2002-09-03 2003-02-26 贾金青 一种用于支护基坑侧壁的无根护壁桩及其施工方法
JP2004293281A (ja) * 2003-02-05 2004-10-21 Ohbayashi Corp 永久アンカーが施工された壁構造の構築方法、永久アンカーが施工された壁構造
CN101126241A (zh) * 2006-08-15 2008-02-20 吴忠诚 疏排桩-土钉墙组合支护方法
CN101250878A (zh) * 2008-03-11 2008-08-27 青建集团股份公司 一种用无嵌固端桩锚结合锚板墙的深基坑支护方法
CN101280564A (zh) * 2008-06-06 2008-10-08 北京建工集团有限责任公司 基坑桩锚护壁混凝土腰梁结构及其施工方法
CN201347559Y (zh) * 2009-01-08 2009-11-18 广州市设计院 一种吊脚桩基坑支护体系结构
CN102002952A (zh) * 2009-09-03 2011-04-06 中国二十冶集团有限公司 土岩结合地域的旋流池基坑防护施工方法

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
半逆作法施工技术在旋流沉淀池工程中的应用;黎明中;《土工基础》;20031231(第04期);第9页第1章第1段-第11页第6章第3段及图1 *
张如俊.深基坑支护的设计与施工.《市政技术》.2006,(第01期),第50-51页.
张绍波等.组合支护方式在大连地区深基坑支护中的应用.《探矿工程(岩土钻掘工程)》.2011,(第03期),第61-63页.
深基坑"半逆作法"施工实践;钟卫斌;《岩土力学》;20040331(第03期);第495第1章第1段-498页第4.4节末段 *
深基坑支护的设计与施工;张如俊;《市政技术》;20060131(第01期);第50页第1章第1段-第51页第4章第2段 *
组合支护方式在大连地区深基坑支护中的应用;张绍波等;《探矿工程(岩土钻掘工程)》;20110331(第03期);第61第1章第1段-第63页 *
钟卫斌.深基坑"半逆作法"施工实践.《岩土力学》.2004,(第03期),第495-499页.
黎明中.半逆作法施工技术在旋流沉淀池工程中的应用.《土工基础》.2003,(第04期),第9-12页.

Also Published As

Publication number Publication date
CN102330436A (zh) 2012-01-25

Similar Documents

Publication Publication Date Title
CN102330436B (zh) 一种用于半岩土层超深圆形旋流池的组合支护结构及方法
CN102518135B (zh) 水平旋喷土锚和灌注桩复合基坑支护施工工法
CN202969392U (zh) 复杂地质深基坑联合支护
CN103526770A (zh) 一种高防渗抗浮桩筏结构及施工方法
CN103452120B (zh) 一种用于基坑支护的高强预应力管桩的桩顶冠梁结构及其施工方法
CN202689031U (zh) 深基坑支护挡墙
CN102605773B (zh) 注浆成型扩底钻孔灌注桩的施工方法及其挤扩装置
CN100510281C (zh) 超大直径、超埋深度调蓄池的半逆作施工方法
CN106013171A (zh) 一种深基坑侧壁的半刚性半柔性支护结构和方法
CN103590408A (zh) 一种双排桩梁竖锚新型支护体系及其施工方法
CN109457709A (zh) 一种双排桩结合大角度锚索的支护结构及施工方法
CN204825928U (zh) 一种基坑支护
CN104131566B (zh) 一种地下室无水平支撑基坑的施工方法
CN211200426U (zh) 一种微型钢管桩挡墙抗滑支挡结构
CN203594041U (zh) 一种高防渗抗浮桩筏结构
CN102220764B (zh) 深基坑支护体系的施工方法
CN207176700U (zh) 一种复杂环境下的密排灌注桩内支撑基坑永久支护结构
CN103243721A (zh) 软弱地质条件下高层建筑筏板基础及核心筒开挖施工方法
CN203729309U (zh) 组合双排桩联合竖向预应力锚杆支护体系
CN110805049B (zh) 一种山体边坡超厚度喷锚永久支护结构的施工方法
CN101793027A (zh) 一种桩心注浆静压锚杆桩
CN101793032A (zh) 一种小场地深基坑施工方法
CN206337566U (zh) 基坑竖向预应力锚杆支撑结构
CN110512613B (zh) 一种红砂岩层隔水喷锚支护方法及其隔水装置
CN201635072U (zh) 一种桩心注浆静压锚杆桩成桩装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee after: MCC TIANGONG CONSTRUCTION Co.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee before: MCC TIANGONG CONSTRUCTION Co.,Ltd.

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee after: MCC TIANGONG CONSTRUCTION Co.,Ltd.

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201900, Room 403, room 1325, Mudanjiang Road, Shanghai, Baoshan District,

Co-patentee before: MCC TIANGONG CONSTRUCTION Co.,Ltd.

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190703

Address after: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Co-patentee after: CHINA MCC20 GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Co-patentee before: MCC TIANGONG CONSTRUCTION Co.,Ltd.

Patentee before: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.