CN104213713A - Method for mounting self-heat-insulation light-weight interior wallboards and shear wallboards simultaneously - Google Patents

Method for mounting self-heat-insulation light-weight interior wallboards and shear wallboards simultaneously Download PDF

Info

Publication number
CN104213713A
CN104213713A CN201410379758.0A CN201410379758A CN104213713A CN 104213713 A CN104213713 A CN 104213713A CN 201410379758 A CN201410379758 A CN 201410379758A CN 104213713 A CN104213713 A CN 104213713A
Authority
CN
China
Prior art keywords
self
wall panel
insulating light
light inner
heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410379758.0A
Other languages
Chinese (zh)
Other versions
CN104213713B (en
Inventor
钱元弟
雷团结
王孝平
黄维军
周杨
李亚辉
王慧
陈贺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maanshan MCC 17 Engineering Science and Technology Co Ltd
Original Assignee
Maanshan MCC 17 Engineering Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maanshan MCC 17 Engineering Science and Technology Co Ltd filed Critical Maanshan MCC 17 Engineering Science and Technology Co Ltd
Priority to CN201410379758.0A priority Critical patent/CN104213713B/en
Publication of CN104213713A publication Critical patent/CN104213713A/en
Application granted granted Critical
Publication of CN104213713B publication Critical patent/CN104213713B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a method for mounting self-heat-insulation light-weight interior wallboards and shear wallboards simultaneously, and belongs to the technical field of building construction. According to the method, the shear wallboards are mounted while the self-heat-insulation light-weight interior wallboards are mounted. The method mainly comprises the following steps: firstly, hoisting the self-heat-insulation light-weight interior wallboards, and determining the height and the cutting position of each self-heat-insulation light-weight interior wallboard according to the floor height so as to cut the self-heat-insulation light-weight interior wallboards; secondly, setting up a simple beam, and then mounting the self-heat-insulation light-weight interior wallboards; thirdly, correcting the wall surface flatness of each self-heat-insulation light-weight interior wallboard; finally, filling special adhesive mortar between the self-heat-insulation light-weight interior wallboards and floors, connecting the self-heat-insulation light-weight interior wallboards with an upper beam plate, performing mortar closing, laying glass fiber nets among the self-heat-insulation light-weight interior wallboards, and plastering the adhesive mortar. The method has the technical characteristics of high work efficiency, firmness in mounting and the like.

Description

A kind of method that self-insulating light inner wall panel and shear wall slab are installed simultaneously
Technical field
The invention belongs to technical field of building construction, be specifically related to a kind of method that self-insulating light inner wall panel and shear wall slab are installed simultaneously.
Background technology
The installation of existing self-insulating light inner wall panel is all after agent structure is built up, install again and fill inner wall panel, mounting process is relatively complicated, install loaded down with trivial details, between wallboard or between wallboard and agent structure, be connected firmly not, safety can not be guaranteed, and work efficiency is low, in the situation that installing space is narrow especially, installation effectiveness is lower.
Summary of the invention
The present invention is directed to the technical problem existing in existing self-insulating light inner wall panel mounting technique, a kind of method that provides self-insulating light inner wall panel and shear wall slab simultaneously to install.
The method that a kind of self-insulating light inner wall panel provided by the present invention and shear wall slab are installed simultaneously, the method is when shear wall slab is installed, to carry out the installation of self-insulating light inner wall panel, its concrete steps are as follows:
(1) lifting of self-insulating light inner wall panel: utilize shear wall installation lifting appliance to carry out self-insulating light inner wall panel and vertically allocate and transport, 10 standard self-insulating light inner wall panels of each lifting, the binding of employing Special belt, self-insulating light inner wall panel lower end stress point cushioning rubber is fast, and protection self-insulating light inner wall panel is not subject to local failure;
(2) adopt infrared ray gradienter to carry out unwrapping wire, determine self-insulating light inner wall panel height and cutting position according to floor height, carry out the cutting process of self-insulating light inner wall panel;
(3) build simple and easy beam: first hole at bottom floor, by expansion bolt, H shape steel tube is fixed on floor, H shape steel tube bottom is welded with chassis, chassis is provided with 3 holes, and H shape steel tube upper end is welded with top bar, and top bar is provided with 2 holes, then angle steel is fixed on the top bar of H shape steel tube by screw, then the Adjustable bracing bar that will stretch is fixed on angle steel, is screwed connection strap and angle steel, completes simple and easy beam and builds;
(4) self-insulating light inner wall panel is installed: hold up first self-insulating light inner wall panel, below first self-insulating light inner wall panel, squeeze into 4 timber wedge location levellings, timber wedge makes to hold out against between first self-insulating light inner wall panel and angle steel, first self-insulating light inner wall panel lower end side installed right angle code, fix by ail gun nailing, then smear special adhesive mortar at tongue-and-groove place; Then second self-insulating light inner wall panel holded up, tenon is aimed to tongue-and-groove and slowly squeeze out mortar, locate levellings and right angle code is installed with 4 timber wedges again, repeat to install always, until whole self-insulating light inner wall panel installs, then proofread and correct the degree of plainness for wall surface of self-insulating light inner wall panel, finally between self-insulating light inner wall panel and floor, tamp special adhesive mortar;
(5) connect self-insulating light inner wall panel and top beam slab: the top of self-insulating light inner wall panel is far from the reserved certain distance of top beam slab, after the installation of self-insulating light inner wall panel, top beam slab starts construction, the reserved bar dowel in beam slab lower end is aimed at self-insulating light inner wall panel upper end preformed hole, lift, then place block rubber on self-insulating light inner wall panel top, self-insulating light inner wall panel and beam slab are held out against, then remove simple and easy beam, between self-insulating light inner wall panel top and beam slab, tamp special adhesive mortar, comprise self-insulating light inner wall panel preformed hole, finally carry out mortar closing in, between self-insulating light inner wall panel, lay glass fiber net, smear adhesive mortar,
(6) after self-insulating light inner wall panel installs, 24h is interiorly must not collide, must not carry out next process, should take safeguard procedures to self-insulating light inner wall panel partition wall, in 7 days, must not bear any lateral action power, the material that construction ladder, engineering are used must not support, push up presses or leans on self-insulating light inner wall panel, after 3 days, self-insulating light inner wall panel bottom connects mortar strength and reaches 5MPa and withdraw from timber wedge when above, with tamping in the cavity that connection mortar leaves timber wedge.
The inventive method have work efficiency fast, the technical characterstics such as firm are installed.
Brief description of the drawings
Fig. 1: be that self-insulating light inner wall panel is installed main TV structure schematic diagram;
Fig. 2: be that self-insulating light inner wall panel is installed left TV structure schematic diagram;
Fig. 3: be that self-insulating light inner wall panel is installed plan structure schematic diagram;
Fig. 4: be vertical support shelf structure schematic diagram;
Fig. 5: be self-insulating light inner wall panel installation fitting structural representation.
Detailed description of the invention
The method that a kind of self-insulating light inner wall panel provided by the present invention and shear wall slab are installed simultaneously, the method concrete steps are:
Preparation of construction → self-insulating light inner wall panel lifts → locates that unwrapping wire → (steel pipe is fixed on lower floor's platform to build simple and easy beam, on steel pipe, be supported with angle steel, flexible Adjustable bracing bar is fixed again on angle steel in side, steel pipe support place) → first self-insulating light inner wall panel installation, squeeze into timber wedge levelling below ... repeat to install all wallboard → schools of self-insulating light inner wall panel plate → tamp in all self-insulating light inner wall panels lower end mortar → top beam slab and start construction, the reserved bar dowel in beam slab lower end is aimed at preformed hole lift → self-insulating light inner wall panel top, self-insulating light inner wall panel upper end and is placed the simple and easy beam of block rubber → remove → tamp the closing in of mortar (comprising self-insulating light inner wall panel preformed hole) → mortar (to spread glass fiber net between self-insulating light inner wall panel between self-insulating light inner wall panel upper end and top beam slab, smear adhesive mortar) complete → directly finishing of → wall body.
1, preparation of construction:
(1) material is prepared: dry self-insulating light inner wall panel and supporting door plate, glass fiber mesh or 0.8 thick gauze wire cloth.
(2) construction tool: angle steel, steel pipe (or H shaped steel), screw, nut, U-shaped card article, infrared level gauge, with the crow bar of horizontal angle bar, electric saw and plastering plate, putty knife, plaster ground, timber wedge, expansion bolt etc.;
(3) operation is prepared: after lower floor's platform construction completes, sheet material and other material are possessed to Qi Dengyong, according to drawing requirement, unwrapping wire on floor, marks the partition wall position line, door position etc.Installed surface bonded part is cleaned out.It is whole that projection picks chipping.Prepare special adhesive mortar stand-by.
2, self-insulating light inner wall panel lifting: utilize shear wall installation lifting appliance to carry out self-insulating light inner wall panel and vertically allocate and transport; 10 standard self-insulating light inner wall panels of each lifting; the binding of employing Special belt; lower end self-insulating light inner wall panel stress point cushioning rubber is fast, and protection self-insulating light inner wall panel is not subject to local failure.Use flat bogie to carry out floor levels transport.
3, adopt infrared ray gradienter to carry out unwrapping wire, determine wallboard height and cutting position according to floor height, carry out the cutting of self-insulating light inner wall panel.
4, simple and easy beam is built: the boring of first bottom floor, by expansion bolt, steel pipe (H shaped steel) is fixed on floor and (bottom steel pipe, is welded with chassis, on chassis, there are 3 holes, upper end is welded with top bar, top bar has 2 holes), then angle steel is fixed on the top bar of steel pipe by screw, then flexible Adjustable bracing bar is fixed again on angle steel in side, steel pipe support place, be screwed connection strap and angle steel upper end, simple and easy like this beam has been built, and can carry out the installation of self-insulating light inner wall panel.
5, self-insulating light inner wall panel is installed:
First self-insulating light inner wall panel holded up, squeeze into 4 timber wedge location levellings (timber wedge makes to hold out against between self-insulating light inner wall panel and angle steel) below, self-insulating light inner wall panel lower end side is installed right angle code (fixing by ail gun nailing), then smears special adhesive mortar at tongue-and-groove place; Second self-insulating light inner wall panel holded up, tenon is aimed to tongue-and-groove and slowly squeeze out mortar, again 4 timber wedges are located to levellings and right angle code is installed, repeat to install always, until whole self-insulating light inner wall panel installs, then proofread and correct the degree of plainness for wall surface of self-insulating light inner wall panel, finally between self-insulating light inner wall panel and floor, tamp special adhesive mortar.
6, self-insulating light inner wall panel is connected with top beam slab: self-insulating light inner wall panel top is far from the reserved certain distance of top beam slab, after the installation of self-insulating light inner wall panel, top beam slab starts construction, the reserved bar dowel in beam slab lower end is aimed at self-insulating light inner wall panel upper end preformed hole and is lifted, then place block rubber on self-insulating light inner wall panel top, self-insulating light inner wall panel and beam slab are held out against, then remove simple and easy beam, between self-insulating light inner wall panel top and beam slab, tamp special adhesive mortar (comprising self-insulating light inner wall panel preformed hole), finally carry out mortar closing in and (between self-insulating light inner wall panel, spread glass fiber net, smear adhesive mortar).
7,, after self-insulating light inner wall panel installs, 24h is interiorly must not collide, must not carry out next process.Should take safeguard procedures to wallboard partition wall, must not bear any lateral action power in 7d, the material that construction ladder, engineering are used etc. must not support, push up presses or leans on body of wall.After 3d, self-insulating light inner wall panel bottom connects mortar strength and reaches 5MPa and withdraw from timber wedge when above, tamps with the cavity that connection mortar leaves timber wedge, and part self-insulating light inner wall panel can be coated putty.

Claims (1)

1. the method that self-insulating light inner wall panel and shear wall slab are installed simultaneously, the method is when shear wall slab is installed, to carry out the installation of self-insulating light inner wall panel, the method concrete steps are as follows:
(1) lifting of self-insulating light inner wall panel: utilize shear wall installation lifting appliance to carry out self-insulating light inner wall panel and vertically allocate and transport, 10 standard self-insulating light inner wall panels of each lifting, the binding of employing Special belt, in the lower end of described self-insulating light inner wall panel, stress point cushioning rubber is fast;
(2) adopt infrared ray gradienter to carry out unwrapping wire, determine from described heat-insulating light inner wall panel height and cutting position according to floor height, described self-insulating light inner wall panel is carried out to cutting process;
(3) build simple and easy beam: first hole at bottom floor, by expansion bolt, H shape steel tube is fixed on floor, described H shape steel tube bottom is welded with chassis, described chassis is provided with 3 holes, and described H shape steel tube upper end is welded with top bar, and described top bar is provided with 2 holes, then by screw, angle steel is fixed on the bar of described top, then the Adjustable bracing bar that will stretch is fixed on described angle steel, is screwed connection strap and described angle steel, completes simple and easy beam and builds;
(4) self-insulating light inner wall panel is installed: hold up first self-insulating light inner wall panel, below described first self-insulating light inner wall panel, squeeze into 4 timber wedge location levellings, timber wedge makes to hold out against between described first self-insulating light inner wall panel and angle steel, described first self-insulating light inner wall panel lower end side installed right angle code, fix by ail gun nailing, then smear special adhesive mortar at tongue-and-groove place; Then second self-insulating light inner wall panel holded up, tenon is aimed to tongue-and-groove and slowly squeeze out mortar, locate levellings and right angle code is installed with 4 timber wedges again, repeat to install always, until whole self-insulating light inner wall panel installs, then proofread and correct the degree of plainness for wall surface of described self-insulating light inner wall panel, finally between described self-insulating light inner wall panel and floor, tamp special adhesive mortar;
(5) connect described self-insulating light inner wall panel and top beam slab: the top of described self-insulating light inner wall panel is far from the reserved certain distance of top beam slab, after the installation of described self-insulating light inner wall panel, top beam slab starts construction, the reserved bar dowel in beam slab lower end is aimed at described self-insulating light inner wall panel upper end preformed hole, lift, then place block rubber on described self-insulating light inner wall panel top, described self-insulating light inner wall panel and beam slab are held out against, then remove simple and easy beam, between described self-insulating light inner wall panel top and beam slab, tamp special adhesive mortar, comprise preformed hole special adhesive mortar in described self-insulating light inner wall panel upper end is tamped, finally carry out mortar closing in, between described self-insulating light inner wall panel, lay glass fiber net, smear adhesive mortar,
(6) after described self-insulating light inner wall panel installs, 24h is interiorly must not collide, must not carry out next process, should take safeguard procedures to described self-insulating light inner wall panel partition wall, in 7 days, must not bear any lateral action power, the material that construction ladder, engineering are used must not support, push up presses or leans on self-insulating light inner wall panel, after 3 days, described self-insulating light inner wall panel bottom connects mortar strength and reaches 5MPa and withdraw from timber wedge when above, with tamping in the cavity that connection mortar leaves timber wedge.
CN201410379758.0A 2014-08-05 2014-08-05 A kind of method that self-insulating light inner wall panel and shear wall slab are installed simultaneously Active CN104213713B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410379758.0A CN104213713B (en) 2014-08-05 2014-08-05 A kind of method that self-insulating light inner wall panel and shear wall slab are installed simultaneously

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410379758.0A CN104213713B (en) 2014-08-05 2014-08-05 A kind of method that self-insulating light inner wall panel and shear wall slab are installed simultaneously

Publications (2)

Publication Number Publication Date
CN104213713A true CN104213713A (en) 2014-12-17
CN104213713B CN104213713B (en) 2016-04-06

Family

ID=52095594

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410379758.0A Active CN104213713B (en) 2014-08-05 2014-08-05 A kind of method that self-insulating light inner wall panel and shear wall slab are installed simultaneously

Country Status (1)

Country Link
CN (1) CN104213713B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268837A (en) * 2017-08-07 2017-10-20 北京天基新材料股份有限公司 A kind of swollen stone walling plate of assembled and combinations thereof installation method
CN107461209A (en) * 2017-07-31 2017-12-12 中国建筑第六工程局有限公司 The construction method of mid-board top reserved steel bar in a kind of Tunnel Engineering

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58218558A (en) * 1982-06-15 1983-12-19 ナショナル住宅産業株式会社 Construction of wall panel
JP2002356854A (en) * 2001-06-01 2002-12-13 Itogumi Construction Co Ltd Method for building concrete wall using floor slab of building
CN102251699A (en) * 2011-05-13 2011-11-23 北京华美科博科技发展有限公司 Residential building system with cast-in-situ beam columns and prefabricated sandwich concrete wall panels and construction method
CN102505862A (en) * 2011-11-03 2012-06-20 中山建华墙体材料有限公司 Installing process of lightweight internal partition wallboards
CN102777045A (en) * 2012-08-09 2012-11-14 龙信建设集团有限公司 Construction method for assembling light energy-saving composite wallboards on separation wall
CN103216107A (en) * 2013-04-23 2013-07-24 东莞市彩丽建筑维护技术有限公司 Method for installing concrete light board wall and jacking and fixing device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58218558A (en) * 1982-06-15 1983-12-19 ナショナル住宅産業株式会社 Construction of wall panel
JP2002356854A (en) * 2001-06-01 2002-12-13 Itogumi Construction Co Ltd Method for building concrete wall using floor slab of building
CN102251699A (en) * 2011-05-13 2011-11-23 北京华美科博科技发展有限公司 Residential building system with cast-in-situ beam columns and prefabricated sandwich concrete wall panels and construction method
CN102505862A (en) * 2011-11-03 2012-06-20 中山建华墙体材料有限公司 Installing process of lightweight internal partition wallboards
CN102777045A (en) * 2012-08-09 2012-11-14 龙信建设集团有限公司 Construction method for assembling light energy-saving composite wallboards on separation wall
CN103216107A (en) * 2013-04-23 2013-07-24 东莞市彩丽建筑维护技术有限公司 Method for installing concrete light board wall and jacking and fixing device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107461209A (en) * 2017-07-31 2017-12-12 中国建筑第六工程局有限公司 The construction method of mid-board top reserved steel bar in a kind of Tunnel Engineering
CN107268837A (en) * 2017-08-07 2017-10-20 北京天基新材料股份有限公司 A kind of swollen stone walling plate of assembled and combinations thereof installation method

Also Published As

Publication number Publication date
CN104213713B (en) 2016-04-06

Similar Documents

Publication Publication Date Title
CN104878766A (en) Long side slope protection concrete continuous rapid pouring and form-drawing system and construction method
CN103741846A (en) Construction method for concrete shear wall
CN103835505A (en) Outer wall compound heat preservation board construction method
CN111576890A (en) Construction method of assembled ALC partition wall
CN104213713B (en) A kind of method that self-insulating light inner wall panel and shear wall slab are installed simultaneously
CN111576680A (en) Method for mounting light steel concrete combined external wall panel
CN103074949A (en) Construction method for environment-friendly light energy-saving wallboard
CN104499614A (en) Wall heat-preservation integration point hanging system and mounting method thereof
CN107747367A (en) A kind of autoclaved lightweight sand aerated concrete(AAC)Sheet material construction method
CN204418434U (en) A kind of outer wall heat insulating device
CN204690763U (en) Long side slope protection concrete continuous fast pouring drawing-die system
US20100037538A1 (en) Temporary adjustable support brace
CN101886470B (en) Construction method of exposed concrete ribbed beams
KR102089751B1 (en) Assembly type wall and floor structure of ocher room
CN215331591U (en) Integral hoisting operation device for composite insulation board
CN102251671B (en) Exterior heat insulation on-site construction process of exterior wall based on foaming cement material
CN204876399U (en) Collection hoist and mount are positioned integrative prefabricated staircase
CN111576681A (en) FS composite heat-preservation construction integrated technology construction process
CN104453252A (en) Method for mounting and constructing sand aerated inner partition wall board
CN211666280U (en) Assembled building wallboard bottom cementer
CN205046709U (en) Prefabricated partition wall component of light gauge steel sand air entrainment board
CN111206737A (en) Wall connecting piece of plug-in type low-carbon heat-preservation energy-saving plate
CN110259035A (en) A kind of floor leveling system
CN220644715U (en) Install masonry structure of hanging blue brick dry wall
CN218323344U (en) Evaporate and press quick connecting device of lightweight concrete slab inner partition wall and roof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant