CN104179454A - Method for drilling hole across belt conveyor - Google Patents

Method for drilling hole across belt conveyor Download PDF

Info

Publication number
CN104179454A
CN104179454A CN201410325990.6A CN201410325990A CN104179454A CN 104179454 A CN104179454 A CN 104179454A CN 201410325990 A CN201410325990 A CN 201410325990A CN 104179454 A CN104179454 A CN 104179454A
Authority
CN
China
Prior art keywords
fluid pressure
belt conveyor
frame column
pneumatic
hydraulic pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410325990.6A
Other languages
Chinese (zh)
Other versions
CN104179454B (en
Inventor
王卫利
赵娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG HUAKUN GEOLOGICAL ENGINEERING CO., LTD.
Original Assignee
SHANDONG HUAKUN GEOLOGICAL ENGINEERING Co Ltd
Shandong Mining Administration Technology Service Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG HUAKUN GEOLOGICAL ENGINEERING Co Ltd, Shandong Mining Administration Technology Service Group Co Ltd filed Critical SHANDONG HUAKUN GEOLOGICAL ENGINEERING Co Ltd
Priority to CN201410325990.6A priority Critical patent/CN104179454B/en
Publication of CN104179454A publication Critical patent/CN104179454A/en
Application granted granted Critical
Publication of CN104179454B publication Critical patent/CN104179454B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a method for drilling a hole across a belt conveyor. The method comprises the following steps: arranging a crawler type traveling vehicle with a working platform on one side of the belt conveyor of a roadway; mounting a pneumatic hydraulic pump and a pneumatic two-position three-way valve on a hydraulic trestle column type pneumatic drilling machine; connecting a hydraulic pipeline of the pneumatic hydraulic pump with a hydraulic type jacking strut; connecting one outlet of the two-position three-way valve with an air inlet of a drilling machine body, and connecting the other outlet of the two-position three-way valve with the pneumatic hydraulic pump; opening an air source, starting the trestle column type pneumatic drilling machine for drilling, and continuously operating a drilling rod on a construction platform by a constructor until the hole is drilled, so that synchronization of the drilling machine and the belt conveyor is realized, and operation interference is avoided. Due to the fact that the crawler type traveling vehicle stops on one side of the belt conveyor, the constructor drills the hole in the working platform across the belt conveyor to the opposite side, non-interference of the drilling machine and the belt conveyor is realized, coal mine production is not influenced, and the safety of the constructor is guaranteed.

Description

A kind of across conveyor boring method
Technical field
The present invention relates to the drilling equipment for drilling of underground mine use.
Background technology
At present, for the stope with shock hazard, need to be ahead of work plane construction destressing borehole, the generation of endangering and preventing bump to realize release solution.While constructing at present destressing borehole, generally adopt hand-held pneumatic drilling machine, frame column type pneumatic drilling machine or electric hydaulic rig to complete.
When at haulage drift construction drill, owing to being furnished with belt conveyer (abbreviation conveyor) in haulage drift, the limited space of belt conveyer both sides, and rig heaviness and volume are large, cannot construct in tunnel this side of metope, a wherein side that rig can only be placed in to conveyor, rig need be crossed over the metope that conveyor can touch opposite side, thereby causes the situation across belt construction.At conveyor run duration, during across belt construction drill, there is obvious danger; If stop conveyor operation, affect coal production.
Summary of the invention
Based on above problem, for solving a difficult problem of holing across conveyor under existing coal mine, the present invention proposes a kind of across conveyor boring method.
For achieving the above object, method of the present invention is as follows:
The first step, arranges a crawler-type traveling car in conveyor one side in tunnel, arranges a working platform that spans to conveyor top on crawler-type traveling car;
Second step, get a frame column type pneumatic drill, require the trestle of frame column type pneumatic drill to be designed to fluid pressure type jacking pillar, fluid pressure type jacking pillar is arranged on crawler-type traveling car, the rig body of frame column type pneumatic drill is arranged on fluid pressure type jacking pillar by lock sleeve;
The 3rd step is installed air-driven hydraulic pump and pneumatic two position three-way valve on frame column type pneumatic drill; The fluid pressure line of air-driven hydraulic pump and fluid pressure type jacking pillar are connected; One way outlet of two position three-way valve and rig body air intake are connected, and another road and air-driven hydraulic pump are connected;
The 4th step, opens source of the gas, makes fluid pressure type jacking pillar extend and hold out against with back, regulates the orbit inclination angle degree of frame column type pneumatic drill and makes it to be close to bore position;
The 5th step, starting frame column type pneumatic drill can creep into, and constructor continues drilling rod until holed on operation platform; Realized rig and belt conveyer synchronize and without interference work;
The 6th step, after having holed, falls fluid pressure type jacking pillar, controls crawler-type traveling garage and proceeds to next construction location.
Advantage of the present invention is: because crawler-type traveling car is parked in belt conveyer one side, constructor on working platform, stride across conveyor to opposite one sidetracking hole, realize the interference invariably of rig and belt conveyer, do not affected coal production, guaranteed again constructor's safety.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of the embodiment of the present invention.
Marginal data, 1-tunnel; 2-conveyor; 3-crawler-type traveling car; 4-adjusting screw; 5-pneumatic drilling machine body; 6-fluid pressure type jacking pillar; 7-lock sleeve; 8-working platform; 9-guide rail; 10-two position three-way valve; 11-air-driven hydraulic pump; 12-drilling rod.
The specific embodiment
As shown in Figure 1, a kind of across belt boring method, it comprises:
The first step, in tunnel, 1 conveyor 2 one sides are arranged a crawler-type traveling car 3, arrange a working platform 8 that spans to conveyor top on crawler-type traveling car 3;
Second step, get a frame column type pneumatic drill, require the trestle of frame column type pneumatic drill to be designed to fluid pressure type jacking pillar 6, fluid pressure type jacking pillar 6 is arranged on crawler-type traveling car 3, the guide rail of frame column type pneumatic drill 9 is arranged on fluid pressure type jacking pillar 6 by lock sleeve 7;
The 3rd step is installed air-driven hydraulic pump 11 and pneumatic two position three-way valve 10 on frame column type pneumatic drill; The fluid pressure line of air-driven hydraulic pump 11 and fluid pressure type jacking pillar 6 are connected; One way outlet of two position three-way valve 10 and pneumatic drilling machine body 5 air intakes are connected, and another road and air-driven hydraulic pump 11 are connected;
The 4th step, opens source of the gas, makes fluid pressure type jacking pillar 6 extend and hold out against with tunnel 1 top board, regulates track 9 angles of inclination of frame column type pneumatic drill and makes it to be close to bore position;
The 5th step, starting frame column type pneumatic drill can creep into, and constructor continues drilling rod 12 until holed on operation platform 8; Realize rig and belt conveyer synchronize and without interference work;
The 6th step, after having holed, falls fluid pressure type jacking pillar 6, controls crawler-type traveling car 1 and marches to next construction location.

Claims (1)

1. across a conveyor boring method, it is characterized in that,
The first step, arranges a crawler-type traveling car in conveyor one side in tunnel, arranges a working platform that spans to conveyor top on crawler-type traveling car;
Second step, get a frame column type pneumatic drill, require the trestle of frame column type pneumatic drill to be designed to fluid pressure type jacking pillar, fluid pressure type jacking pillar is arranged on crawler-type traveling car, the rig body of frame column type pneumatic drill is arranged on fluid pressure type jacking pillar by lock sleeve;
The 3rd step is installed air-driven hydraulic pump and pneumatic two position three-way valve on frame column type pneumatic drill; The fluid pressure line of air-driven hydraulic pump and fluid pressure type jacking pillar are connected; One way outlet of two position three-way valve and rig body air intake are connected, and another road and air-driven hydraulic pump are connected;
The 4th step, opens source of the gas, makes fluid pressure type jacking pillar extend and hold out against with back, regulates the orbit inclination angle degree of frame column type pneumatic drill and makes it to be close to bore position;
The 5th step, starting frame column type pneumatic drill can creep into, and constructor continues drilling rod until holed on operation platform; Realized rig and belt conveyer synchronize and without interference work;
The 6th step, after having holed, falls fluid pressure type jacking pillar, controls crawler-type traveling garage and proceeds to next construction location.
CN201410325990.6A 2014-07-09 2014-07-09 Method for drilling hole across belt conveyor Active CN104179454B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410325990.6A CN104179454B (en) 2014-07-09 2014-07-09 Method for drilling hole across belt conveyor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410325990.6A CN104179454B (en) 2014-07-09 2014-07-09 Method for drilling hole across belt conveyor

Publications (2)

Publication Number Publication Date
CN104179454A true CN104179454A (en) 2014-12-03
CN104179454B CN104179454B (en) 2017-02-15

Family

ID=51960768

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410325990.6A Active CN104179454B (en) 2014-07-09 2014-07-09 Method for drilling hole across belt conveyor

Country Status (1)

Country Link
CN (1) CN104179454B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201865573U (en) * 2010-11-27 2011-06-15 煤炭科学研究总院西安研究院 Crawler drill for belt-span drilling
CN202165009U (en) * 2011-07-28 2012-03-14 曾昭友 Underground belt-spanning full hydraulic tunnel drilling machine for coal mine
CN102606158A (en) * 2012-03-15 2012-07-25 中国煤矿机械装备有限责任公司 Novel low coal seam coal mine underground mining complete equipment
CN202483437U (en) * 2011-10-14 2012-10-10 青岛达邦钻机有限责任公司 Trestle type pneumatic drilling machine
CN202611589U (en) * 2012-05-29 2012-12-19 平顶山市铁福来机电设备有限公司 Crawler-type belt-crossing wide-angle coal rock drilling device
CN203008780U (en) * 2012-12-21 2013-06-19 四川华蓥山龙滩煤电有限责任公司 Belt-striding shifting device of hydraulic drilling rig
CN103670414A (en) * 2013-11-27 2014-03-26 中煤张家口煤矿机械有限责任公司 Combined coal mechanical blasting mining method
CN203547554U (en) * 2013-10-18 2014-04-16 安徽恒源煤电股份有限公司 Hydraulic mine drilling machine

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201865573U (en) * 2010-11-27 2011-06-15 煤炭科学研究总院西安研究院 Crawler drill for belt-span drilling
CN202165009U (en) * 2011-07-28 2012-03-14 曾昭友 Underground belt-spanning full hydraulic tunnel drilling machine for coal mine
CN202483437U (en) * 2011-10-14 2012-10-10 青岛达邦钻机有限责任公司 Trestle type pneumatic drilling machine
CN102606158A (en) * 2012-03-15 2012-07-25 中国煤矿机械装备有限责任公司 Novel low coal seam coal mine underground mining complete equipment
CN202611589U (en) * 2012-05-29 2012-12-19 平顶山市铁福来机电设备有限公司 Crawler-type belt-crossing wide-angle coal rock drilling device
CN203008780U (en) * 2012-12-21 2013-06-19 四川华蓥山龙滩煤电有限责任公司 Belt-striding shifting device of hydraulic drilling rig
CN203547554U (en) * 2013-10-18 2014-04-16 安徽恒源煤电股份有限公司 Hydraulic mine drilling machine
CN103670414A (en) * 2013-11-27 2014-03-26 中煤张家口煤矿机械有限责任公司 Combined coal mechanical blasting mining method

Also Published As

Publication number Publication date
CN104179454B (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN101832102B (en) Movable two-platform partitioned four-arm hanging wall anchor rod and anchor cable construction drill carriage
CN103883350B (en) The filling coal mining method of adopting is jumped at a kind of interval
CN102134968A (en) Drilling system and drilling equipment
CN104929517B (en) Full-hydraulic drill type pressure relieving equipment with double drill bits and pressure relieving method
CN103899249A (en) Coal mine roadway bottom board anchoring drill carriage
CN108397227A (en) A kind of progressive extinction roadway layout method of tendency
CN105604558B (en) The forward supporting type Unit erriger tunneled suitable for soft rock
CN102434154A (en) Development machine-mounted anchor rod drilling rig
CN110905589A (en) Gas extraction drilling and punching coordination operation system and method
CN106468177A (en) A kind of coal and gas harmonic extraction method
CN107217988B (en) High-pressure hydraulic slotting machine for coal mine driving face
CN206554795U (en) A kind of convertible multi-angle coal mine drilling machine of crawler travel
CN108505999A (en) A kind of high prominent more lane method for arranging of working face of coal seam
CN103075153A (en) Open-air drilling coal cutter
CN101709642B (en) Track-type four-arm rock drilling jumbo
CN206554794U (en) A kind of colliery convertible all-direction borehole rig of crawler travel
CN102080501B (en) Mineral deep hole drilling carriage unit
CN203978276U (en) A kind of tunnel drill borehole machine
CN102606072A (en) 90-degree rotational deep-hole drill rig for coal mines
CN104179454B (en) Method for drilling hole across belt conveyor
CN104564056A (en) Integrated tunneling and exploring machine
CN204081997U (en) A kind of across conveyor drilling equipment
CN103410441A (en) Rotary coal mine underground tunnel drilling rig with small platform
CN202531024U (en) 90-degree rotating deep hole drill carriage for coal mine
CN110552735B (en) Method and system for combined extraction of coal seam gas and gas near goaf

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Wang Weili

Inventor after: Xin Hengqi

Inventor after: Chen Deren

Inventor after: Pang Yuncheng

Inventor after: Wu Zhigang

Inventor after: Liu Yuanyuan

Inventor after: Gong Huagang

Inventor after: Wu Zhenhu

Inventor after: Yang Luzhen

Inventor before: Wang Weili

Inventor before: Zhao Na

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20170116

Address after: The 271413 Shandong Tai''an China Fengzhen Ningyang County Nanshan Industrial Park Shandong Huakun Geological Engineering Co. Ltd.

Applicant after: SHANDONG HUAKUN GEOLOGICAL ENGINEERING CO., LTD.

Address before: 271200 Shandong city of Tai''an province Xintai Xinwen road two new Xinwen Mining Group Shandong Mining Management Technology Services Group Limited

Applicant before: Shandong Mining Administration Technology Service Group Co., Ltd.

Applicant before: SHANDONG HUAKUN GEOLOGICAL ENGINEERING CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant