CN103953359A CN201410196933.2A CN201410196933A CN103953359A CN 103953359 A CN103953359 A CN 103953359A CN 201410196933 A CN201410196933 A CN 201410196933A CN 103953359 A CN103953359 A CN 103953359A
Authority
CN
China
Prior art keywords
culvert
contained
groove
component
contain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410196933.2A
Other languages
Chinese (zh)
Other versions
CN103953359B (en
Inventor
马海东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian East Horse Concrete Component Co ltd
Original Assignee
DALIAN ZHONGNAN EXTENSION RESOURCES AND ENVIRONMENTAL TECHNOLOGY RESEARCH Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DALIAN ZHONGNAN EXTENSION RESOURCES AND ENVIRONMENTAL TECHNOLOGY RESEARCH Co Ltd filed Critical DALIAN ZHONGNAN EXTENSION RESOURCES AND ENVIRONMENTAL TECHNOLOGY RESEARCH Co Ltd
Priority to CN201410196933.2A priority Critical patent/CN103953359B/en
Publication of CN103953359A publication Critical patent/CN103953359A/en
Application granted granted Critical
Publication of CN103953359B publication Critical patent/CN103953359B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to an underground shield-assembling concrete precast square culvert. The underground shield-assembling concrete precast square culvert is characterized in that a first section of the square culvert (1) is prepared to form a straight port at one end and a bevel notch at the other end; an upper half culvert component (2) and a lower half culvert component (5), which are connected with the bevel notch, are both prepared to U-shaped slots to form a rectangle; an included angle alpha is formed between a long side and a short side ; connecting grooves (11) are formed between the upper half square culvert component (2) and the lower half culvert component (5), adjacent two upper half square culvert components (2), and adjacent lower half culvert components (5); in the connecting grooves (11), connecting plates (8), double-end bolts (10), gaskets (7) and nuts (9) are used to fix each component; both ends of the connecting plates (8) are welded with connecting plate fixing reinforcing steel bars (6); the connecting plate fixing reinforcing steel bars (6) are fixed in a concrete component. The underground shield-assembling concrete precast square culvert can be prepared without ditching or slotting on the ground, so that the pipe gallery construction cost can be saved, and the operation speed is fast.

Description

The assembled concrete prefabricated square culvert of Tunnel Boring
Technical field
The invention belongs to underground prefabricating square culvert, particularly a kind of Urban Underground takes shield machine shield structure tunnel out to make the assembled concrete prefabricated square culvert of land used Tunnel Boring.
Background technology
At present, that the Urban Underground construction of many developed countries of the world has all adopted is advanced, economize on resources, be conducive to create harmonious ecology environment and environmental protection, and the phenomenon of solved repeatedly ditching pipe laying, burying cable occurs; So occurred at embedded underground prefabricating square culvert, formed Urban Underground piping lane.The construction of underground pipe gallery in the past exists that fluting area is large, engineering (earthwork) amount greatly, the deficiencies such as long construction period.So adopt now shield machine, the tunnel that once shield structure goes out to install Fang Han on ground.But existing concrete square is contained, and cannot be transported in tunnel and install, bring technical barrier to advanced technology.
Summary of the invention
The object of the invention is to overcome above-mentioned technical deficiency, provide one can in Fang Han, transport prefabricating square culvert member, the assembled concrete prefabricated square culvert of Tunnel Boring quick for installation in shield structure tunnel.
The technical scheme that technical solution problem of the present invention adopts is: the assembled concrete prefabricated square culvert of a kind of Tunnel Boring, it is characterized in that first segment Fang Han makes one end for straight mouthful, the other end is angle, the upper en culvert member being connected with angle and lower en culvert member are all made the U-shaped groove of parallelogram, the angle of long limit and minor face is α, and the width that upper en is contained member and lower en culvert fresh kidney beans is L; Above the left side of upper en culvert member, be provided with en and contain boss; Be provided with en below and contain groove, above right side, be provided with en and contain groove, be provided with lower en below and contain groove; The lower left that lower en is contained member is provided with lower en culvert boss, is provided with lower en above and contains groove, is provided with lower en and contains boss above right side, is provided with lower en below and contains groove; Upper en contains that member is contained between member with lower en, adjacent two upper ens are contained between members and between adjacent two lower ens culvert members and are equipped with connecting groove; The joint of each concrete component is equipped with the stairstepping socket of boss and groove; In connecting groove, with junction plate, stud, pad and nut, its each member is fixed together; Junction plate two ends are welded with the fixing reinforcing bar of junction plate; The fixing reinforcing bar of junction plate is fixed in concrete component.Upper en contains member and lower en is contained the long limit of member and the angle α=30-80 ° of minor face.Upper en is contained the width L=500--5000mm of member and lower en culvert member.
The invention has the beneficial effects as follows: this invention has solved the technical barrier that adopts shield machine shield formation underground passage of shield machine that square piping lane is installed, and not be used in ground ditching fluting, saves the cost that piping lane is built, and speed is fast.
Brief description of the drawings
Below in conjunction with accompanying drawing, illustrate with embodiment.
Fig. 1 is the assembled concrete prefabricated square culvert front view of Tunnel Boring;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the left side view of Fig. 1;
Fig. 4 is the top view that the upper en in Fig. 1 is contained member;
Fig. 5 is the top view that the lower en in Fig. 1 is contained member;
Fig. 6 is the I place partial enlarged drawing in Fig. 1.
In figure: 1-side is contained; The upper en of 2-is contained member; The upper en of 3-is contained boss; Under 4-, en is contained boss; Under 5-, en is contained member; 6-junction plate is fixed reinforcing bar; 7-pad; 8-junction plate; 9-nut; 10-stud; 11-connecting groove; The upper en of 12-is contained groove; Under 13-, en is contained groove; 14-connecting through hole.
Detailed description of the invention
Embodiment, with reference to accompanying drawing, the assembled concrete prefabricated square culvert of a kind of Tunnel Boring, it is characterized in that it is straight mouthful that one end is made in first segment side's culvert 1, the other end is angle, the upper en culvert member 2 being connected with angle and lower en culvert member 5 are all made the U-shaped groove of parallelogram, and the angle of long limit and minor face is α, and the width that upper en is contained member 2 and lower en culvert member 5 is L; Above the left side of upper en culvert member 2, be provided with en and contain boss 3; Be provided with en below and contain groove 12, above right side, be provided with en and contain groove 12, be provided with lower en below and contain groove 13; The lower left that lower en is contained member 5 is provided with lower en culvert boss 4, is provided with lower en above and contains groove 13, is provided with lower en and contains boss 4 above right side, is provided with lower en below and contains groove 3; Upper en contains member 2 and lower en is contained between member 5, adjacent two upper ens contain between member 2 and adjacent two lower ens are contained between member 5, all there is no connecting groove 11; The joint of each concrete component is equipped with the stairstepping socket of boss and groove; In connecting groove 11, with junction plate 8, stud 10, pad 7 and nut 9, its each member is fixed together; Junction plate 8 two ends are welded with the fixing reinforcing bar 6 of junction plate; The fixing reinforcing bar 6 of junction plate is fixed in concrete component.Upper en contains member 2 and lower en is contained the long limit of member 5 and angle α=50 ° of minor face.Upper en is contained the width L=2000mm of member 2 and lower en culvert member 5.Upper en contains member and 2 times ens culvert member 5 turnings all do not have connecting through hole 14, in connecting through hole 14, puts on steel strand, and stretch-draw is contained together in general side.Four sockets of side's culvert 1 right-hand member angle, upper en culvert member 2 and lower en culvert member 5 are all made the stairstepping socket of boss and groove.
The assembling process of Fang Han is: first first side will be contained to 1(one end for straight mouthful, the other end is angle) install in the underground tunnel of digging, straight mouthful of end will be provided with the well head (vertical or tilt) of the earth rock that lower member excavates out with shield machine, when on transporting, en is contained member 2 or lower en culvert member 5, to first transport lower en and contain member 5, while transporting, plane is downward, upwards, groove is downward for left end boss; Contain 1 angle to connecting with side; On transporting, en is contained when member 2, and by plane upwards, left end boss is downward, and groove upwards, to after getting well, then is fixed connection with stud 10 mutual ladder interface.

Claims (2)

1. the assembled concrete prefabricated square culvert of Tunnel Boring, it is characterized in that first segment Fang Han (1) makes one end for straight mouthful, the other end is angle, the upper en culvert member (2) being connected with angle and lower en culvert member (5) are all made the U-shaped groove of parallelogram, the angle of long limit and minor face is α, and the width that upper en is contained member (2) and lower en culvert member (5) is L; Above the left side of upper en culvert member (2), be provided with en and contain boss (3); Be provided with en below and contain groove (12), above right side, be provided with en and contain groove (13), the lower left that lower en is contained member (5) is provided with lower en culvert boss (4), be provided with lower en above and contain groove (13), above right side, be provided with lower en and contain boss (4), be provided with lower en below and contain groove (13); Upper en contains member (2) and second is contained between member (5), and adjacent two upper ens are contained between member (2), and adjacent two lower ens are contained between member (5) does not all have connecting groove (11); The joint of each concrete component is equipped with the stairstepping socket of boss and groove; In connecting groove (11), with junction plate (8), stud (10), pad (7) and nut (9), its each member is fixed together; Junction plate (8) two ends are welded with the fixing reinforcing bar (6) of junction plate; It is solid that junction plate is fixed reinforcing bar (6) 2.the assembled concrete prefabricated square culvert of Tunnel Boring according to claim 1, is characterized in that en is contained member (2) and lower en is contained the long limit of member (5) and the angle α=30-80 ° of minor face.
2. the assembled concrete prefabricated square culvert of Tunnel Boring according to claim 1, is characterized in that en contains the width L=500-5000mm of member (2) and lower en culvert member (5).
CN201410196933.2A 2014-05-12 2014-05-12 The assembled concrete prefabricated square culvert of Tunnel Boring Active CN103953359B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410196933.2A CN103953359B (en) 2014-05-12 2014-05-12 The assembled concrete prefabricated square culvert of Tunnel Boring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410196933.2A CN103953359B (en) 2014-05-12 2014-05-12 The assembled concrete prefabricated square culvert of Tunnel Boring

Publications (2)

Publication Number Publication Date
CN103953359A true CN103953359A (en) 2014-07-30
CN103953359B CN103953359B (en) 2016-01-20

Family

ID=51330689

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410196933.2A Active CN103953359B (en) 2014-05-12 2014-05-12 The assembled concrete prefabricated square culvert of Tunnel Boring

Country Status (1)

Country Link
CN (1) CN103953359B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104294771A (en) * 2014-09-29 2015-01-21 钟景尧 Square prefabricated reinforced concrete culvert
CN105986825A (en) * 2015-02-06 2016-10-05 大连中南维拓资源与环境技术研究有限公司 Arc-shaped underground shielding assembling concrete prefabricated square culvert
CN109595005A (en) * 2018-11-20 2019-04-09 山东万广建设工程有限公司 The leading type no-dig technique tunnel construction structure of shell and construction method
CN113404091A (en) * 2021-05-28 2021-09-17 内蒙古送变电有限责任公司 Construction method for encapsulating and splicing prefabricated square culvert foundation and cable trench foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020076280A1 (en) * 2000-12-13 2002-06-20 Semotiuk Robert A. Environmentally compatible archway for road building
JP2012001890A (en) * 2010-06-14 2012-01-05 Takenaka Doboku Co Ltd Box culvert device and construction method therefor
CN202108057U (en) * 2011-05-30 2012-01-11 马海东 Up-down assembled concrete precast quadrate culvert
CN202925605U (en) * 2012-12-14 2013-05-08 吉林省天祥建筑材料有限公司 A prefabricated assembly-type square reinforced concrete culvert
CN203822324U (en) * 2014-05-12 2014-09-10 大连中南维拓资源与环境技术研究有限公司 Underground shield assembling prefabricated concrete square box

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20020076280A1 (en) * 2000-12-13 2002-06-20 Semotiuk Robert A. Environmentally compatible archway for road building
JP2012001890A (en) * 2010-06-14 2012-01-05 Takenaka Doboku Co Ltd Box culvert device and construction method therefor
CN202108057U (en) * 2011-05-30 2012-01-11 马海东 Up-down assembled concrete precast quadrate culvert
CN202925605U (en) * 2012-12-14 2013-05-08 吉林省天祥建筑材料有限公司 A prefabricated assembly-type square reinforced concrete culvert
CN203822324U (en) * 2014-05-12 2014-09-10 大连中南维拓资源与环境技术研究有限公司 Underground shield assembling prefabricated concrete square box

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104294771A (en) * 2014-09-29 2015-01-21 钟景尧 Square prefabricated reinforced concrete culvert
CN105986825A (en) * 2015-02-06 2016-10-05 大连中南维拓资源与环境技术研究有限公司 Arc-shaped underground shielding assembling concrete prefabricated square culvert
CN109595005A (en) * 2018-11-20 2019-04-09 山东万广建设工程有限公司 The leading type no-dig technique tunnel construction structure of shell and construction method
CN109595005B (en) * 2018-11-20 2024-04-02 山东万广建设工程有限公司 Shell advance type non-excavation tunnel construction structure and construction method
CN113404091A (en) * 2021-05-28 2021-09-17 内蒙古送变电有限责任公司 Construction method for encapsulating and splicing prefabricated square culvert foundation and cable trench foundation

Also Published As

Publication number Publication date
CN103953359B (en) 2016-01-20

Similar Documents

Publication Publication Date Title
CN202280462U (en) Pipe segment for building subway station through large-diameter shield tunneling expanded excavation
CN205171549U (en) Piping lane prefab and prefabricated formula utility tunnel
CN103953359A (en) Underground shield-assembling concrete precast square culvert
CN205778883U (en) Jacking construction and the connection transfer device of shield-tunneling construction in a kind of tunnel
CN102587959A (en) Method for draining coal seam gas
CN204040062U (en) Prefabricated wedge shape flexible interface assembling piping lane
CN105401593A (en) Assembly type square underground pipe gallery
CN105134214A (en) Method for ventilation-assisting roadway arrangement and surrounding rock stability control in later period of coal mining
CN103291312B (en) The shield machine of three-dimensional slip casting can be realized
CN205955746U (en) Adopt prefabrication of rectangular shield construction to assemble utility tunnel structure
CN102619521B (en) Construction method for vertical shaft bedrock section wall structure
CN203822324U (en) Underground shield assembling prefabricated concrete square box
CN105715273A (en) Arrangement form of lower slice roadways of ultra-thick hard coal
CN206457842U (en) A kind of underground combination and the precast concrete pile for the underground combination
CN202228785U (en) Jack type pipe-jacking head for long transmission pipeline
KR101638478B1 (en) Joint structure for perpendicular hall and horizontal hall
CN206972266U (en) A kind of tunnel arch heavy in section junction steel plate structure with ribbing
CN201671638U (en) Karst tunnel equipped with water stop strip
CN212177148U (en) Symmetrical horseshoe-shaped assembled concrete tunnel
CN209145607U (en) A kind of light-duty intelligent tunneling pin-connected panel integration apparatus
CN202451974U (en) Anti-floating structure of buried pipeline
CN203905024U (en) Internal corner connecting piece of foundation pit supporting system
CN205676941U (en) Electric LHD front bucket door
CN206971233U (en) A kind of supporting construction for deep basal pit
CN205776356U (en) Plug-in Pipe rack

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20140730

Assignee: JIANHUA CONSTRUCTION MATERIALS (CHINA) Co.,Ltd.

Assignor: DALIAN ZHONGNAN EXTENSION RESOURCES AND ENVIRONMENTAL TECHNOLOGY RESEARCH Co.,Ltd.

Contract record no.: X2022980003856

Denomination of invention: Underground shield assembled concrete precast square culvert

Granted publication date: 20160120

License type: Exclusive License

Record date: 20220407

EE01 Entry into force of recordation of patent licensing contract
TR01 Transfer of patent right

Effective date of registration: 20221228

Address after: 116600 dongjiagou Dashu village, Dalian Economic and Technological Development Zone, Liaoning Province

Patentee after: Dalian East horse concrete component Co.,Ltd.

Address before: Shiyuan International 2602, No. 156, Jinma Road, Dalian Development Zone, Liaoning 116600

Patentee before: DALIAN ZHONGNAN EXTENSION RESOURCES AND ENVIRONMENTAL TECHNOLOGY RESEARCH Co.,Ltd.

TR01 Transfer of patent right