CN206972266U - A kind of tunnel arch heavy in section junction steel plate structure with ribbing - Google Patents

A kind of tunnel arch heavy in section junction steel plate structure with ribbing Download PDF

Info

Publication number
CN206972266U
CN206972266U CN201720572809.0U CN201720572809U CN206972266U CN 206972266 U CN206972266 U CN 206972266U CN 201720572809 U CN201720572809 U CN 201720572809U CN 206972266 U CN206972266 U CN 206972266U
Authority
CN
China
Prior art keywords
steel plate
heavy
section
section steel
bow member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720572809.0U
Other languages
Chinese (zh)
Inventor
李行利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN201720572809.0U priority Critical patent/CN206972266U/en
Application granted granted Critical
Publication of CN206972266U publication Critical patent/CN206972266U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of tunnel arch heavy in section junction steel plate structure with ribbing, adjacent two section bow members(1)Tip side is respectively arranged with heavy in section steel plate(3)Or any of which section bow member(1)Tip side is provided with heavy in section steel plate(3)Another section bow member(1)Tip side is provided with generic connectivity steel plate(4), two heavy in section steel plates(3)Between or heavy in section steel plate(3)With generic connectivity steel plate(4)Between pass through connecting bolt(5)It is connected, heavy in section steel plate(3)Length is not less than bow member(1)The 1/2 of spacing, and heavy in section steel plate(3)Stretch out bow member(1)The length of the left and right sides is consistent.Heavy in section steel plate(3)Plate face compared with it is long, lifting surface area is big, so as to effectively constrain bow member(1)Sinking.

Description

A kind of tunnel arch heavy in section junction steel plate structure with ribbing
Technical field
A kind of tunnel junction steel plate is the utility model is related to, more specifically to a kind of tunnel arch heavy in section company with ribbing Steel plate structure is connect, belongs to tunnel steelframe technical field of construction.
Background technology
Preliminary bracing is to ensure adjoining rock stability and the important means of control deformation after tunnel excavation, therefore in work progress The quality and effect of preliminary bracing are must assure that, to ensure construction safety and reduce surrouding rock deformation.At present, generally using grille arch The primary structure of frame and shaped steel arch as Tunnel;Because the factors such as tunnel excavation method, installation operation influence, tunnel Road bow member needs segmented making, and junction steel plate is generally set in every section termination and is connected by screw bolts;Therefore bow member joint is The weak link of total, ensure that its connection effect tool is of great significance.
In weak surrounding rock, because basal plane bearing capacity is weak, there is problems with existing tunnel arch joint:First, it is common Junction steel plate stress surface is narrow, and uncontrollable bow member arch springing sinks, and then easily causes Vault settlement, cracking.2nd, got out of a predicament or an embarrassing situation in excavation Afterwards, bow member arch springing is hanging, and first branch bow member easily produces moderate finite deformation because stress is mutated, or even has the risk of unstability.3rd, bow member encircles For pin by the easy run-off the straight of lateral pressure, generic connectivity steel plate resistivity is weak, or even gross distortion or warpage therewith, causes up and down It can not be connected by screw bolts between adjacent steelframe section at step, and have to use and be welded to connect, on the one hand, influence bow member It is overall smoother, it is unfavorable for stress, still further aspect, may causes gap be present between bow member joint, weaken bow member joint Intensity.
The content of the invention
The purpose of this utility model is easily to produce because stress is mutated for bow member existing for existing tunnel arch joint Raw moderate finite deformation, the problems such as bow member joint intensity is smaller, there is provided a kind of tunnel arch heavy in section junction steel plate structure with ribbing.
To achieve the above object, technical solution of the present utility model is:A kind of tunnel arch heavy in section connection with ribbing Steel plate structure, adjacent two section bow member tip sides are respectively arranged with heavy in section steel plate or any of which section bow member tip side is set It is equipped with another section bow member tip side of heavy in section steel plate and is provided with generic connectivity steel plate, between described two heavy in section steel plates, Or be connected between heavy in section steel plate and generic connectivity steel plate by connecting bolt, described heavy in section steel plate length is not less than The 1/2 of bow member spacing, and the length that heavy in section steel plate is stretched out at left and right sides of bow member is consistent.
The bow member tip side both sides for being provided with heavy in section steel plate are welded with along between web center line and heavy in section steel plate center line Straight triangular stall board.
Described straight triangular stall board inclination angle is 45~60 degree, and straight two right angle edge lengths of triangular stall board are not less than heavy in section The 1/3 of steel plate length, the straight right-angle side of triangular stall board one and wire bonding in bow member web, straight another right-angle side of triangular stall board are cut with big Wire bonding in the steel plate of face.
Forward direction is provided with pre-embedded bolt on the inside of described heavy in section steel plate, and one end sealing is stamped in described pre-embedded bolt termination PVC sleeve pipes.
Compared with prior art, the beneficial effects of the utility model are:
1st, two section bow member tip sides adjacent in the utility model are respectively arranged with heavy in section steel plate or any of which section Bow member tip side is provided with another section bow member tip side of heavy in section steel plate and is provided with generic connectivity steel plate;Heavy in section steel plate with it is existing Generic connectivity steel plate compare, its plate face compared with it is long, lifting surface area is big, so as to effectively constrain the sinking of bow member.
2nd, the bow member tip side both sides of heavy in section steel plate are provided with the utility model along web center line and heavy in section steel plate Straight triangular stall board is welded between center line;Reinforced by straight triangular stall board, it is tight can to prevent that the lower heavy in section steel plate of external force effect from occurring Deform again, bow member of being got out of a predicament or an embarrassing situation in influenceing docking;And heavy in section steel plate combines with straight triangular stall board, the bending resistance of bow member can be effectively improved Ability, so as to increase the stability of first branch bow member.
3rd, forward direction is provided with pre-embedded bolt on the inside of the steel plate of heavy in section in the utility model, and one end envelope is stamped in pre-embedded bolt termination The PVC sleeve pipes of mouth;By the positive setting pre-embedded bolt on the inside of the steel plate of bow member heavy in section and the form of PVC casing protections is utilized, The close of bow member connection up and down is ensured, it is firm.
Brief description of the drawings
Fig. 1 is that the section bow member tip side of the utility model two sets heavy in section steel plate and generic connectivity steel plate structure schematic diagram.
Fig. 2 is Fig. 1 side views.
Fig. 3 is that the section bow member tip side of the utility model two sets two pieces of heavy in section steel plate structure schematic diagrames respectively.
Fig. 4 is the utility model generic connectivity steel plate top view.
Fig. 5 is the utility model heavy in section steel plate top view.
In figure, bow member 1, triangular stall board 2, heavy in section steel plate 3, generic connectivity steel plate 4, connecting bolt 5, PVC sleeve pipes 6, in advance Bury bolt 7, nut 8, bolt hole 9, the bow member edge of a wing 10, bow member web 11.
Embodiment
The utility model is described in further detail below in conjunction with brief description of the drawings and embodiment.
Referring to Fig. 1 to Fig. 5, a kind of tunnel arch heavy in section junction steel plate structure with ribbing, the adjacent two section tip sides of bow member 1 It is respectively arranged with heavy in section steel plate 3 or the tip side of any of which section bow member 1 is provided with another section bow member 1 of heavy in section steel plate 3 and connect Head end is provided with generic connectivity steel plate 4;Adjacent two section bow members 1 herein suitable for up/down steps or bow member 2 of getting out of a predicament or an embarrassing situation apply Work.Pass through connecting bolt between described two heavy in section steel plates 3 or between heavy in section steel plate 3 and generic connectivity steel plate 4 5 are connected, and bolt hole sets corresponding with generic connectivity steel plate 4;And the described length of heavy in section steel plate 3 is not less than the spacing of bow member 1 1/2, and heavy in section steel plate 3 stretch out the left and right sides of bow member 1 length it is consistent;The spacing of bow member 1 herein refers to adjacent two Pin Distance between bow member 1.I.e. it changes the generic connectivity steel plate 4 that the arch springing two of tunnel arch 1 is saved between the tip side of bow member 1 into two pieces big Section steel plate 3 or one block of heavy in section steel plate and one block of generic connectivity steel plate 4, the specific size combination bow member 1 of the heavy in section steel plate 3 Model, the spacing of bow member 1, construction environment etc. consider.
Referring to Fig. 1 to Fig. 5, the tip side both sides of bow member 1 of heavy in section steel plate 3 are provided with along web center line and heavy in section steel plate Straight triangular stall board 2 is welded between 3 center lines.Straight triangular stall board 2 can be formed using generic connectivity steel plate 4 to cutting.Further, institute The inclination angle of straight triangular stall board 2 stated is 45~60 degree, and straight 2 two right angle edge lengths of triangular stall board are grown not less than heavy in section steel plate 3 The 1/3 of degree, the straight right-angle side of triangular stall board 2 one and wire bonding, straight 2 another right-angle side of triangular stall board and heavy in section in the web of bow member 1 Wire bonding in steel plate 3;The inclination angle of straight triangular stall board 2 herein is the α angles in Fig. 1.
Referring to Fig. 2, the described inner side forward direction of heavy in section steel plate 3 is provided with pre-embedded bolt 7, the described termination of pre-embedded bolt 7 It is stamped the PVC sleeve pipes 6 of an end closure.The described hot melt of PVC sleeve pipes 6 is fixed, and prevents the foreign matters such as gunite concrete from invading.
The construction method of this kind of tunnel arch heavy in section junction steel plate structure with ribbing, comprises the following steps:
Step 1: process outside the venue:According to design drawing, satisfactory bow member 1, heavy in section steel plate 3 and straight three are produced Angle side bracket 2, and it is firm three is welded each other, in heavy in section, the inner side of steel plate 3 is positive sets pre-embedded bolt 7, and in pre-buried spiral shell The PVC sleeve pipes 6 of a side seal mouth on the termination point casing of bolt 7, fix the hot melt of PVC sleeve pipes 6.
Step 2: upper section bow member 1 is installed:Substrate void slag is cleaned out, it is smooth in place, make the accurate positioning of bow member 1, fixation It is firm, and wrapped the arch springing heavy in section steel plate 3 of bow member 1 with non-woven fabrics, prevent the foreign matters such as gunite concrete from invading.
Step 3: lower section bow member 1 docks:Non-woven fabrics in removal step two, and the end face of heavy in section steel plate 3 is cleared up and done Only, expose inner side pre-embedded bolt 7;Between the heavy in section steel plate 3 of two section bow members 1 or heavy in section steel plate 3 and generic connectivity steel Bolt hole docking between plate 4 is accurate, and the connecting bolt 5 in outside is reversely installed, and the connecting bolt 5 in outside refers to herein Connecting bolt 5 away from country rock side;All connecting bolts 5 are fastened again.
Above content is to combine specific preferred embodiment further detailed description of the utility model, it is impossible to Assert that specific implementation of the present utility model is confined to these explanations.For the ordinary skill of the utility model art For personnel, without departing from the concept of the premise utility, some simple deduction or replace, said structure can also be made The scope of protection of the utility model should be all considered as belonging to.

Claims (4)

  1. A kind of 1. tunnel arch heavy in section junction steel plate structure with ribbing, it is characterised in that:Two adjacent section bow members(1)Tip side point Heavy in section steel plate is not provided with(3)Or any of which section bow member(1)Tip side is provided with heavy in section steel plate(3)Another section arch Frame(1)Tip side is provided with generic connectivity steel plate(4), described two heavy in section steel plates(3)Between or heavy in section steel plate (3)With generic connectivity steel plate(4)Between pass through connecting bolt(5)It is connected, described heavy in section steel plate(3)Length is not less than arch Frame(1)The 1/2 of spacing, and heavy in section steel plate(3)Stretch out bow member(1)The length of the left and right sides is consistent.
  2. A kind of 2. tunnel arch heavy in section junction steel plate structure with ribbing according to claim 1, it is characterised in that:It is provided with Heavy in section steel plate(3)Bow member(1)Tip side both sides are along web center line and heavy in section steel plate(3)Straight triangle is welded between center line Floor(2).
  3. A kind of 3. tunnel arch heavy in section junction steel plate structure with ribbing according to claim 2, it is characterised in that:Described Straight triangular stall board(2)Inclination angle is 45~60 degree, straight triangular stall board(2)Two right angle edge lengths are not less than heavy in section steel plate(3) The 1/3 of length, straight triangular stall board(2)One right-angle side and bow member(1)Wire bonding in web, straight triangular stall board(2)Another right-angle side With heavy in section steel plate(3)Middle wire bonding.
  4. A kind of 4. tunnel arch heavy in section junction steel plate structure with ribbing according to claim 1, it is characterised in that:Described Heavy in section steel plate(3)Inner side forward direction is provided with pre-embedded bolt(7), described pre-embedded bolt(7)It is stamped the PVC of one end sealing in termination Sleeve pipe(6).
CN201720572809.0U 2017-05-22 2017-05-22 A kind of tunnel arch heavy in section junction steel plate structure with ribbing Active CN206972266U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720572809.0U CN206972266U (en) 2017-05-22 2017-05-22 A kind of tunnel arch heavy in section junction steel plate structure with ribbing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720572809.0U CN206972266U (en) 2017-05-22 2017-05-22 A kind of tunnel arch heavy in section junction steel plate structure with ribbing

Publications (1)

Publication Number Publication Date
CN206972266U true CN206972266U (en) 2018-02-06

Family

ID=61410915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720572809.0U Active CN206972266U (en) 2017-05-22 2017-05-22 A kind of tunnel arch heavy in section junction steel plate structure with ribbing

Country Status (1)

Country Link
CN (1) CN206972266U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108612323A (en) * 2018-05-22 2018-10-02 江苏省交通工程集团有限公司 A kind of I-steel steelframe junction steel plate auxiliary locator and its construction method
CN114135322A (en) * 2021-11-22 2022-03-04 中铁十六局集团第三工程有限公司 Reinforcing method for preventing steel frame from being twisted in large-deformation tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108612323A (en) * 2018-05-22 2018-10-02 江苏省交通工程集团有限公司 A kind of I-steel steelframe junction steel plate auxiliary locator and its construction method
CN114135322A (en) * 2021-11-22 2022-03-04 中铁十六局集团第三工程有限公司 Reinforcing method for preventing steel frame from being twisted in large-deformation tunnel

Similar Documents

Publication Publication Date Title
CN108832563A (en) A kind of pre-fabricated electric cables comb and its construction method
CN206972266U (en) A kind of tunnel arch heavy in section junction steel plate structure with ribbing
CN205712137U (en) Foundation pit supporting construction
CN205171549U (en) Piping lane prefab and prefabricated formula utility tunnel
CN103603494A (en) Ultra-thin steel truss inclined wall construction method and formwork structure
CN205858379U (en) A kind of scalable steelframe joint being applicable to serious deformation
CN202925898U (en) Template joint connecting structure
CN208844771U (en) The connected support structure of T plate edge joint position
CN106401617A (en) Steel arch and joint thereof
CN106481347A (en) A kind of anti-internal water pressure composite shield section of jurisdiction
CN106505484A (en) Piping lane cable laying method
CN105781131A (en) Assembled building wall plate mounting support system and construction method thereof
CN111851987A (en) Construction method of attached short-limb I-steel flower basket pull rod knot type cantilever frame
CN207260191U (en) A kind of class rectangle pipe gallery section of jurisdiction connection structure
CN106988224B (en) The arch rib installation system and installation method of bridge
CN206581282U (en) Diaphram wall Ω type milling joints
CN106480906B (en) Feed intake storehouse and the connection structure of standard block tube coupling and the pipe gallery of changes of section
CN107152026B (en) A kind of the mud jacking pipe support and its distribution method of steel-pipe pile
CN211777497U (en) Shield constructs section of jurisdiction hole for hoist built-in fitting position arrangement of reinforcement and improves structure
CN105888700A (en) Telescopic steel frame joint suitable for large tunnel deformation
CN203321537U (en) Self-chinching lining template for tunnel
CN207904877U (en) Surface stuck type multiple wing edge waterstop elbow
CN208690872U (en) A kind of pre-fabricated electric cables comb
CN209179027U (en) Bracing formula pile beam slab props up fender system
CN207194918U (en) A kind of steel frame system for pole Modelling of Tunnel Excavation in Soft Rock

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant