CN103938869A - Ms砌块后砌筑墙体内线管、线盒的施工方法 - Google Patents

Ms砌块后砌筑墙体内线管、线盒的施工方法 Download PDF

Info

Publication number
CN103938869A
CN103938869A CN201410199758.2A CN201410199758A CN103938869A CN 103938869 A CN103938869 A CN 103938869A CN 201410199758 A CN201410199758 A CN 201410199758A CN 103938869 A CN103938869 A CN 103938869A
Authority
CN
China
Prior art keywords
line box
line
building block
building
spool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410199758.2A
Other languages
English (en)
Other versions
CN103938869B (zh
Inventor
孙明福
郜磊
周宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP filed Critical 1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
Priority to CN201410199758.2A priority Critical patent/CN103938869B/zh
Publication of CN103938869A publication Critical patent/CN103938869A/zh
Application granted granted Critical
Publication of CN103938869B publication Critical patent/CN103938869B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种MS砌块后砌筑墙体内线管、线盒的施工方法。其步骤是:确定线管的预留位置,进行放线标注;按照线管位置进行MS砌块排砖;将线管接长至将要预留的线盒位置;砌筑MS砌块至将要预留的线盒位置标高;根据线盒位置及尺寸在砌块上留线盒孔;砌筑带有线盒孔的砌块;利用砌块碎块填充线盒所在位置空心砌块;空心砌块内浇注混凝土;用专用砂浆抹实线盒周边。本发明的优点是:根治了在后砌墙体上剔凿进行预留、预埋专业线管、线盒遗留下的诸多问题,与砌筑过程同步完成专业线管及线盒的预埋工作,一次成活,无需后期剔凿,减少了工作量,缩短了工期,提高了线盒位置的准确性,保证了施工质量,降低了施工成本。

Description

MS砌块后砌筑墙体内线管、线盒的施工方法
技术领域
本发明涉及后砌墙体上的专业线管和线盒的施工方法,具体是一种MS砌块后砌筑墙体内线管、线盒的施工方法。
背景技术
通常后砌墙体上的专业线管和线盒,必须在后砌墙体砌筑完成以后,按照图纸位置进行专业的线管剔凿,剔凿完成后进行线管、线盒敷设、固定,然后对开槽位置进行砂浆填补,最终填补至与墙面平,在墙面抹灰时还要在该位置增设一层网格布,防止后期开裂,存在质量隐患且增加施工成本。
发明内容
本发明针对以往线管预埋的缺陷,为有效避免后期切割砌块以放置专业线管而导致的增加工作量、不美观、且容易开裂等问题,提供一种采用空心砌块(MS)局部灌注混凝土的方法对预留线管、线盒进行固定,保证施工质量、提高施工速度、降低施工成本的MS砌块后砌筑墙体内线管、线盒的施工方法。
本发明解决上述技术问题采用的技术方案是:
一种MS砌块后砌筑墙体内线管、线盒的施工方法,包括以下步骤:
a.确定线管的预留位置,进行放线标注;
b.按照线管位置进行MS砌块排砖;
c.将线管接长至将要预留的线盒位置;
d.砌筑MS砌块至将要预留的线盒位置标高;
e.根据线盒位置及尺寸在砌块上留线盒孔;
f.砌筑带有线盒孔的砌块;
g.利用砌块碎块填充线盒所在位置空心砌块;
h.空心砌块内浇注混凝土;
i.用专用砂浆抹实线盒周边。
采用上述技术方案的本发明,与现有技术相比,其优点是:
根治了在后砌墙体上剔凿进行预留、预埋专业线管、线盒遗留下的诸多问题,与砌筑过程同步完成专业线管及线盒的预埋工作,一次成活,无需后期剔凿,减少了工作量,缩短了工期,提高了线盒位置的准确性,保证了施工质量,降低了施工成本。
作为优选,本发明更进一步的技术方案是:
所述步骤b中,在MS砌块排砖时,砌块实心处要避开线管、线盒预留位置。
所述步骤e中,在砌块上切线盒孔时,切洞尺寸超出线盒尺寸不大于5mm。
所述步骤g中,在空心砌块内填碎块时,选用的碎块尺寸要保证缝隙不大于25 mm。
所述步骤h中,在灌注混凝土时,对线盒进行临时固定和调整位置。
附图说明
图1是本发明实施例施工构造外观图。
图2是本发明实施例施工构造剖视图。
图中:1-线管,2-混凝土,3-线盒,4-MS砌块,5-砌块碎块。
具体实施方式
下面结合实施例对本发明作进一步说明,目的仅在于更好的理解本发明内容。因此,所举之例并非限制本发明的保护范围。
参见附图,本实施例所述的MS砌块后砌筑墙体内线管、线盒的施工方法,按以下步骤进行:
①确定线管1的预留位置,进行放线标注。
地面清理干净后,依据施工图中线管的位置、尺寸,在地面上进行放线标注。
②按照线管1位置进行MS砌块4排砖。
按照线管1位置,对MS砌块4进行排砖,排砖时必须保证线管1位于MS砌块4的空心部分,便于施工。
③将线管1接长至将要预留的线盒3位置。
随着MS砌块4的砌筑,线管1按照线盒3位置接长,直至将要预留的线盒3位置。
④砌筑MS砌块4至将要预留的线盒3位置标高。
依据MS砌筑4规则砌筑砌块,待砌筑至线盒3标高时,线盒3所在的位置停止砌筑。
⑤根据线盒3位置及尺寸在MS砌块4上留线盒孔。
依据施工图所标注的线盒3位置及尺寸,在MS砌块4上切割、留设线盒孔,开孔尺寸要大于线盒3尺寸不超过5mm。
⑥砌筑带有线盒孔的砌块。
将预先切割好线盒孔的砌块,按照MS砌筑方式砌筑,并将线盒3放在切割孔内,线盒3出墙面控制在5-7 mm。
⑦利用砌块碎块5填充线盒3所在位置空心砌块。
在线盒3所在的砌块空心内,借助下层砌块,用砌块碎块将线盒3固定于切割好的孔洞之中,且用砌块碎块5填实该砌块下部,以为下一步填实混凝土做好“模板”的准备。
⑧空心砌块内浇注混凝土2。
空心砌块下部“模板”填实后,缝隙不大于25mm,开始浇筑C20细石混凝土2,并且要用钢筋棍插倒密实混凝土2,使之与砌块粘接成为整体,浇筑混凝土2时应随时观察线盒3位置,如有偏位及时调整。
⑨专用砂浆抹实线盒3周边。
当MS砌块4内部用细石混凝土2灌实后,再用MS砌块4专用粘接砂浆将砌块外部线盒3周边的空隙抹实。

Claims (5)

1.一种MS砌块后砌筑墙体内线管、线盒的施工方法,其特征在于,包括以下步骤:
a.确定线管的预留位置,进行放线标注;
b.按照线管位置进行MS砌块排砖;
c.将线管接长至将要预留的线盒位置;
d.砌筑MS砌块至将要预留的线盒位置标高;
e.根据线盒位置及尺寸在砌块上留线盒孔;
f.砌筑带有线盒孔的砌块;
g.利用砌块碎块填充线盒所在位置空心砌块;
h.空心砌块内浇注混凝土;
i.用专用砂浆抹实线盒周边。
2.如权利要求1所述的MS砌块后砌筑墙体内线管、线盒的施工方法,其特征在于,所述步骤b中,在MS砌块排砖时,砌块实心处避开线管、线盒预留位置。
3.如权利要求1所述的MS砌块后砌筑墙体内线管、线盒的施工方法,其特征在于,所述步骤e中,在砌块上切线盒孔时,切洞尺寸超出线盒尺寸不大于5mm。
4.如权利要求1所述的MS砌块后砌筑墙体内线管、线盒的施工方法,其特征在于,所述步骤g中,在空心砌块内填碎块时,选用的碎块尺寸保证缝隙不大于25 mm。
5.如权利要求1所述的MS砌块后砌筑墙体内线管、线盒的施工方法,其特征在于,所述步骤h中,在灌注混凝土时,对线盒进行临时固定和调整位置。
CN201410199758.2A 2014-05-13 2014-05-13 Ms砌块后砌筑墙体内线管、线盒的施工方法 Active CN103938869B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410199758.2A CN103938869B (zh) 2014-05-13 2014-05-13 Ms砌块后砌筑墙体内线管、线盒的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410199758.2A CN103938869B (zh) 2014-05-13 2014-05-13 Ms砌块后砌筑墙体内线管、线盒的施工方法

Publications (2)

Publication Number Publication Date
CN103938869A true CN103938869A (zh) 2014-07-23
CN103938869B CN103938869B (zh) 2016-04-27

Family

ID=51186719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410199758.2A Active CN103938869B (zh) 2014-05-13 2014-05-13 Ms砌块后砌筑墙体内线管、线盒的施工方法

Country Status (1)

Country Link
CN (1) CN103938869B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196148A (zh) * 2014-09-15 2014-12-10 京鑫建设集团有限公司 一种空心砌块填充墙施工工艺及预设管线
CN104989099A (zh) * 2015-05-22 2015-10-21 重庆一建建设集团有限公司 预埋线盒施工方法
CN107859332A (zh) * 2017-11-23 2018-03-30 中国二十二冶集团有限公司 预制配电箱线管预埋的施工方法
CN110397188A (zh) * 2019-07-30 2019-11-01 中信国安建工集团有限公司 一种抗裂砌体墙及施工方法
CN110792200A (zh) * 2019-09-25 2020-02-14 江苏兴厦建设工程集团有限公司 一种无需后期剔打的砌体施工方法及其包管结构
CN110863587A (zh) * 2019-12-02 2020-03-06 中国建筑第四工程局有限公司 一种线管安装砌体免开槽施工方法及结构
CN113463827A (zh) * 2021-07-14 2021-10-01 中冶京诚工程技术有限公司 一种连锁砌块墙体线盒固定构造及其施工方法
CN114580070A (zh) * 2022-04-21 2022-06-03 中建二局第四建筑工程有限公司 基于bim技术的砌体墙线盒免开洞预制化安装方法
CN115162607A (zh) * 2022-09-08 2022-10-11 中铁建设集团有限公司 一种砌筑配管组件及其同步施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2535473Y (zh) * 2002-02-22 2003-02-12 杨先礼 一种新型的型体砖
CN2786229Y (zh) * 2005-03-01 2006-06-07 张水明 带线槽的墙体砌块
CN201943244U (zh) * 2010-12-30 2011-08-24 湖南高岭建设集团股份有限公司 建筑用空心砌块
CN102561580A (zh) * 2010-12-30 2012-07-11 湖南高岭建设集团股份有限公司 建筑用空心砌块
CN202745259U (zh) * 2012-08-22 2013-02-20 中国建筑第六工程局有限公司 空心砌块电管后拉槽结构
CN103061515A (zh) * 2012-12-29 2013-04-24 陕西省第三建筑工程公司 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法
CN203420403U (zh) * 2013-07-13 2014-02-05 陕西华山建设有限公司 一种基于线盒与线管安装预制砌块的填充墙砌筑结构
CN103758272A (zh) * 2014-01-08 2014-04-30 永生建设集团有限公司 蒸压加气混凝土砌块墙体内置管线预埋施工方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2535473Y (zh) * 2002-02-22 2003-02-12 杨先礼 一种新型的型体砖
CN2786229Y (zh) * 2005-03-01 2006-06-07 张水明 带线槽的墙体砌块
CN201943244U (zh) * 2010-12-30 2011-08-24 湖南高岭建设集团股份有限公司 建筑用空心砌块
CN102561580A (zh) * 2010-12-30 2012-07-11 湖南高岭建设集团股份有限公司 建筑用空心砌块
CN202745259U (zh) * 2012-08-22 2013-02-20 中国建筑第六工程局有限公司 空心砌块电管后拉槽结构
CN103061515A (zh) * 2012-12-29 2013-04-24 陕西省第三建筑工程公司 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法
CN203420403U (zh) * 2013-07-13 2014-02-05 陕西华山建设有限公司 一种基于线盒与线管安装预制砌块的填充墙砌筑结构
CN103758272A (zh) * 2014-01-08 2014-04-30 永生建设集团有限公司 蒸压加气混凝土砌块墙体内置管线预埋施工方法

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196148A (zh) * 2014-09-15 2014-12-10 京鑫建设集团有限公司 一种空心砌块填充墙施工工艺及预设管线
CN104989099A (zh) * 2015-05-22 2015-10-21 重庆一建建设集团有限公司 预埋线盒施工方法
CN107859332A (zh) * 2017-11-23 2018-03-30 中国二十二冶集团有限公司 预制配电箱线管预埋的施工方法
CN110397188A (zh) * 2019-07-30 2019-11-01 中信国安建工集团有限公司 一种抗裂砌体墙及施工方法
CN110397188B (zh) * 2019-07-30 2024-05-14 中信国安建工集团有限公司 一种抗裂砌体墙及施工方法
CN110792200A (zh) * 2019-09-25 2020-02-14 江苏兴厦建设工程集团有限公司 一种无需后期剔打的砌体施工方法及其包管结构
CN110863587A (zh) * 2019-12-02 2020-03-06 中国建筑第四工程局有限公司 一种线管安装砌体免开槽施工方法及结构
CN113463827A (zh) * 2021-07-14 2021-10-01 中冶京诚工程技术有限公司 一种连锁砌块墙体线盒固定构造及其施工方法
CN114580070A (zh) * 2022-04-21 2022-06-03 中建二局第四建筑工程有限公司 基于bim技术的砌体墙线盒免开洞预制化安装方法
CN115162607A (zh) * 2022-09-08 2022-10-11 中铁建设集团有限公司 一种砌筑配管组件及其同步施工方法

Also Published As

Publication number Publication date
CN103938869B (zh) 2016-04-27

Similar Documents

Publication Publication Date Title
CN103938869B (zh) Ms砌块后砌筑墙体内线管、线盒的施工方法
CN103321436B (zh) 建筑砖砌体上线盒预安装施工方法及其预安装支架
CN106320706A (zh) 一种砌筑墙体线管线槽线盒暗埋的施工方法
CN103266767B (zh) 混凝土结构与填充墙间裂缝防治施工工法
CN103410332B (zh) 一种混凝土空心砌块加筋墙施工工艺
CN103758272B (zh) 蒸压加气混凝土砌块墙体内置管线预埋施工方法
CN109853832A (zh) 一种填充墙砌筑与电气预埋线管同步施工的施工方法
CN103469806A (zh) 一种预制砼基础承台侧模替代砖胎模的施工方法
CN110512892B (zh) 既有古城墙修复施工方法
CN105019651B (zh) 空心砖填充墙成排线盒高效安装施工工法
CN104343239A (zh) 加气混凝土填充墙打孔暗敷设电气穿线管施工工艺
CN106812219A (zh) 填充墙顶部塞缝施工方法
CN110792200A (zh) 一种无需后期剔打的砌体施工方法及其包管结构
EA201700452A1 (ru) Способ строительства твердого дорожного покрытия для осуществления естественного пополнения грунтовых вод
CN106553263A (zh) 一种用于室内试验隧道明洞模型预制与边坡模型成洞的施工方法
CN104404857B (zh) 一种透水型铺砖地面及施工方法
CN104499611A (zh) 一种新型灌孔后抹浆快速施工墙体及其施工方法
CN104810744A (zh) 一种墙体管线自由预埋施工方法
CN104890434A (zh) 一种塑石景观制作方法
CN107916789A (zh) 一种混凝土空心砌块墙体穿管嵌盒的方法
CN105155794A (zh) 一种石膏加气砖墙面的石材湿挂方法及其结构
CN205677235U (zh) 一种应用在卫生间的预制反坎施工构造
CN204651834U (zh) 一种砖墙中电气管线的预埋结构
CN104763158B (zh) 榫接式轻集料连锁砌块施工方法
CN106193120A (zh) 地下室悬挑底板逆作结构及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240820

Address after: 064000 happiness Road 16, Fengrun District, Hebei, Tangshan City

Patentee after: China MCC22 Group Corp.,Ltd.

Country or region after: China

Address before: 064000 9 communities, Fengrun District, Tangshan City, Hebei Province

Patentee before: The 1st Construction Corp., Ltd. of 22MCC Group

Country or region before: China