CN103061515A - 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法 - Google Patents

混凝土空心砌块填充墙预埋pvc电线管穿管安装方法 Download PDF

Info

Publication number
CN103061515A
CN103061515A CN2012105915563A CN201210591556A CN103061515A CN 103061515 A CN103061515 A CN 103061515A CN 2012105915563 A CN2012105915563 A CN 2012105915563A CN 201210591556 A CN201210591556 A CN 201210591556A CN 103061515 A CN103061515 A CN 103061515A
Authority
CN
China
Prior art keywords
wall
spool
line box
building
hollow block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012105915563A
Other languages
English (en)
Other versions
CN103061515B (zh
Inventor
张培林
马建国
马勇
杨佳
谢磊
高展
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SCEGC NO.3 CONSTRUCTION ENGINEERING GROUP Co.,Ltd.
Original Assignee
SHANXI THIRD ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANXI THIRD ENGINEERING Co Ltd filed Critical SHANXI THIRD ENGINEERING Co Ltd
Priority to CN201210591556.3A priority Critical patent/CN103061515B/zh
Publication of CN103061515A publication Critical patent/CN103061515A/zh
Application granted granted Critical
Publication of CN103061515B publication Critical patent/CN103061515B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,该方法利用空心砌块的空腔特性和PVC线管的柔韧性,使得PVC电线管一次性隐蔽在空心砌块墙内,配电箱安装采用先墙体预留洞后安装箱体的方法,线盒安装采用先在墙体上开孔后安装线盒的方式。本发明的目的在于利用砌体结构特点及合理的施工工序,保证墙体结构的完整性,提高线管、箱/盒安装的效率及质量。

Description

混凝土空心砌块填充墙预埋PVC电线管穿管安装方法
技术领域
本发明属于建筑墙体电线施工技术领域,涉及一种PVC电线管穿管安装方法,尤其是一种混凝土空心砌块填充墙预埋PVC电线管穿管安装方法。
背景技术
针对混凝土空心砌块填充墙结构及PVC线管的材质,电气配管采用传统工艺施工存在以下缺陷:
①人工费消耗量大。体现在:传统工艺在墙体上开槽进行电气配管施工,会伴随大量的补槽工作量,人工消耗为本发明工艺的2至3倍。
②材料消耗量大。体现在:墙体配管后的补槽工序需要消耗大量的砼。
③能耗大,工效低,综合成本高。体现在:墙体开槽及二次补槽会产生大量建筑垃圾,消耗水电资源,且因施工工序较多,综合成本高,整体工效低。
④墙体质量影响。体现在:由于在墙体上开槽数量偏多,补槽后的砂浆强度不能保证完全达到要求,对墙体结构的稳定性有一定影响和质量隐患。
发明内容
本发明的目的在于克服上述现有技术的缺点,提供一种混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,该方法利用空心砌块的空腔特性和PVC线管的柔韧性,使得PVC电线管一次性隐蔽在空心砌块墙内,配电箱安装采用先墙体预留洞后安装箱体的方式,线盒安装采用先在墙体上开孔后安装线盒的方式。该方法可以做到灵活弯曲及躲避障碍,操作方便,与箱盒连接的线管一端方便弯曲,确保了箱盒安装的准确性。
本发明的目的是通过以下技术方案来解决的:
这种混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,包括以下步骤:
1)首先根据设计图纸要求及空心砌块实际尺寸,绘制出相应位置的墙体排版图,根据排版图定位现浇板中预埋PVC电线管的引出点;
2)由下引上的PVC电线管在墙体砌筑前将其接至一定高度位置,墙体砌筑时,将空心砌块依次套入线管进行砌筑,使得线管一次性隐蔽在空心砌块墙的空腔内,并分段预埋钢筋对线管进行绑扎固定,即随墙体砌筑分段固定;
3)由上引下的PVC电线管在墙体砌筑后,先在所对应线盒所在的墙体剃好安装孔洞,再将PVC线管利用砌块内部空隙路径由上至下进行穿管,线管的固定采用开孔点式填浆法进行固定;
4)墙体砌筑至线盒设计安装位置时,先预留好线盒预留洞,调整好PVC电线管在预留洞中的位置,待墙体砌筑完后,准备进行线盒的安装;
5)线盒安装前,根据地面油漆标记和线盒标高在墙体上进行机械开孔,找出隐蔽在墙体内的电线管,根据线盒设计标高及出墙度修正线管位置进行线盒安装;
6)使进入线盒的管线一管一孔,排列整齐。
进一步的,步骤2)中,利用混凝土空心砌块的空腔特性以及PVC电线管的柔韧性,采用“砖”套“管”、“管”穿“砖”配合施工,即穿管式施工,使得线管穿过砌块空腔而一次性隐蔽在墙体内,穿管方式包括上穿式、下穿式、贯通式三种;
另外,在步骤2)中,每隔50cm分段预埋钢筋对线管进行绑扎固定。
进一步,在步骤3)中,所述开孔点式填浆法具体为:在线管隐蔽处墙体上开适量大小的孔,在孔的下口底部采用廉价的弹性材料进行填充支撑,再填入砂浆对线管进行固定。
本发明具有以下有益效果:
(1)本发明杜绝了在墙体上大量开槽,避免了对墙体结构稳定性的破坏,有效提高了工程质量。
(2)本发明的方法施工操作简便可靠,大大提高了整体施工工效。减少了不必要的人工、材料、水电资源等浪费,综合成本大大降低。
(3)本发明利用PVC电线管柔韧、高弹性的特点,在穿管施工过程中,可以做到灵活弯曲及躲避障碍,操作方便,与箱盒连接的线管一端方便弯曲,确保了箱盒安装的准确性。
附图说明
图1为本发明的混凝土空心砌块结构示意图;
图2为上穿式穿管流程示意图;
图3为下穿式穿管流程示意图;
图4为贯通式穿管流程示意图;
图5为本发明的钢筋绑扎固定法示意图;
图6为本发明的开孔点式填浆法示意图;
具体实施方式
下面结合附图对本发明做进一步详细描述:
本发明的混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,包括以下步骤:
1)首先根据设计图纸要求及空心砌块(如图1所示)实际尺寸,绘制出相应位置的墙体排版图,根据排版图定位现浇板中预埋PVC电线管的引出点;
2)由下引上的PVC电线管在墙体砌筑前将其接至一定高度位置,墙体砌筑时,将空心砌块依次套入线管进行砌筑,使得线管一次性隐蔽在空心砌块墙的空腔内,并分段预埋钢筋对线管进行绑扎固定(如图5),即随墙体砌筑分段固定;在本发明的最佳实施例中,应每隔50cm分段预埋钢筋对线管进行绑扎固定。
利用混凝土空心砌块的空腔特性以及PVC电线管的柔韧性,采用“砖”套“管”、“管”穿“砖”配合施工,即穿管式施工,使得线管穿过砌块空腔而一次性隐蔽在墙体内,穿管方式包括上穿式(如图2)、下穿式(如图3)、贯通式(如图4)三种。
3)由上引下的PVC电线管在墙体砌筑后,先在所对应线盒所在的墙体剃好安装孔洞,再将PVC线管利用砌块内部空隙路径由上至下进行穿管,线管的固定采用开孔点式填浆法进行固定。如图6所示:开孔点式填浆法具体为:在线管隐蔽处墙体上开适量大小的孔,在孔的下口底部采用廉价的弹性材料进行填充支撑,再填入砂浆对线管进行固定。
4)墙体砌筑至线盒设计安装位置时,先预留好线盒预留洞,调整好PVC电线管在预留洞中的位置,待墙体砌筑完后,准备进行线盒的安装;
5)线盒安装前,根据地面油漆标记和线盒标高在墙体上进行机械开孔,找出隐蔽在墙体内的电线管,根据线盒设计标高及出墙度修正线管位置进行线盒安装;
6)使进入线盒的管线一管一孔,排列整齐。

Claims (4)

1.一种混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,其特征在于,包括以下步骤:
1)首先根据设计图纸要求及空心砌块实际尺寸,绘制出相应位置的墙体排版图,根据排版图定位现浇板中预埋PVC电线管的引出点;
2)由下引上的PVC电线管在墙体砌筑前将其接至一定高度位置,墙体砌筑时,将空心砌块依次套入线管进行砌筑,使得线管一次性隐蔽在空心砌块墙的空腔内,并分段预埋钢筋对线管进行绑扎固定,即随墙体砌筑分段固定;
3)由上引下的PVC电线管在墙体砌筑后,先在所对应线盒所在的墙体剃好安装孔洞,再将PVC线管利用砌块内部空隙路径由上至下进行穿管,线管的固定采用开孔点式填浆法进行固定;
4)墙体砌筑至线盒设计安装位置时,先预留好线盒预留洞,调整好PVC电线管在预留洞中的位置,待墙体砌筑完后,准备进行线盒的安装;
5)线盒安装前,根据地面油漆标记和线盒标高在墙体上进行机械开孔,找出隐蔽在墙体内的电线管,根据线盒设计标高及出墙度修正线管位置进行线盒安装;
6)使进入线盒的管线一管一孔,排列整齐。
2.根据权利要求1所述的混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,其特征在于,步骤2)中,利用混凝土空心砌块的空腔特性以及PVC电线管的柔韧性,采用“砖”套“管”、“管”穿“砖”配合施工,即穿管式施工,使得线管穿过砌块空腔而一次性隐蔽在墙体内,穿管方式包括上穿式、下穿式、贯通式三种。
3.根据权利要求1所述的混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,其特征在于,步骤2)中,每隔50cm分段预埋钢筋对线管进行绑扎固定。
4.根据权利要求1所述的混凝土空心砌块填充墙预埋PVC电线管穿管安装方法,其特征在于,步骤3)中,所述开孔点式填浆法具体为:在线管隐蔽处墙体上开适量大小的孔,在孔的下口底部采用廉价的弹性材料进行填充支撑,再填入砂浆对线管进行固定。
CN201210591556.3A 2012-12-29 2012-12-29 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法 Active CN103061515B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210591556.3A CN103061515B (zh) 2012-12-29 2012-12-29 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210591556.3A CN103061515B (zh) 2012-12-29 2012-12-29 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法

Publications (2)

Publication Number Publication Date
CN103061515A true CN103061515A (zh) 2013-04-24
CN103061515B CN103061515B (zh) 2015-10-14

Family

ID=48104377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210591556.3A Active CN103061515B (zh) 2012-12-29 2012-12-29 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法

Country Status (1)

Country Link
CN (1) CN103061515B (zh)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103490354A (zh) * 2013-09-24 2014-01-01 甘肃第七建设集团股份有限公司 预埋电管管孔控制专用模具的使用方法
CN103938869A (zh) * 2014-05-13 2014-07-23 二十二冶集团第一建设有限公司 Ms砌块后砌筑墙体内线管、线盒的施工方法
CN104196148A (zh) * 2014-09-15 2014-12-10 京鑫建设集团有限公司 一种空心砌块填充墙施工工艺及预设管线
CN104453085A (zh) * 2014-10-28 2015-03-25 成都市第四建筑工程公司 一种轻集料混凝土空心隔墙板的线盒安装方法
CN104810744A (zh) * 2014-01-28 2015-07-29 浙江国泰建设集团有限公司 一种墙体管线自由预埋施工方法
CN104806025A (zh) * 2015-05-26 2015-07-29 中建五局蚌埠建筑工程有限公司 砌体工程机电管线与线盒直埋成套施工工艺
CN104989099A (zh) * 2015-05-22 2015-10-21 重庆一建建设集团有限公司 预埋线盒施工方法
CN105019651A (zh) * 2014-04-23 2015-11-04 重庆建工第四建设有限责任公司 空心砖填充墙成排线盒高效安装施工工法
CN106786266A (zh) * 2016-12-13 2017-05-31 上海市建工设计研究院有限公司 预制装配钢结构住宅电缆电线敷设系统及其施工方法
CN107859332A (zh) * 2017-11-23 2018-03-30 中国二十二冶集团有限公司 预制配电箱线管预埋的施工方法
CN107916789A (zh) * 2017-10-27 2018-04-17 江苏南通三建集团股份有限公司 一种混凝土空心砌块墙体穿管嵌盒的方法
CN109853832A (zh) * 2019-01-18 2019-06-07 江苏南通六建建设集团有限公司 一种填充墙砌筑与电气预埋线管同步施工的施工方法
CN110359616A (zh) * 2019-06-24 2019-10-22 中冶天工集团有限公司 一种混凝土或水泥砂浆地坪半圆槽留设方法
CN110863587A (zh) * 2019-12-02 2020-03-06 中国建筑第四工程局有限公司 一种线管安装砌体免开槽施工方法及结构
CN110924692A (zh) * 2019-12-02 2020-03-27 中建三局第三建设工程有限责任公司 砌体管线直埋施工方法
CN112482638A (zh) * 2020-11-20 2021-03-12 临沂城投地产有限公司 一种现浇板管线密集处抗裂措施及施工方法
CN113622510A (zh) * 2020-05-07 2021-11-09 万平华 加气混凝土墙板的安装方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202094560U (zh) * 2011-06-28 2011-12-28 天津天一建设集团有限公司 墙体暗配电管布孔用补洞托盘式固定支架
US20120317913A1 (en) * 2011-06-15 2012-12-20 Esquivel Krisann Grooved Tiles, Grooved Tile Assemblies and Related Methods

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120317913A1 (en) * 2011-06-15 2012-12-20 Esquivel Krisann Grooved Tiles, Grooved Tile Assemblies and Related Methods
CN202094560U (zh) * 2011-06-28 2011-12-28 天津天一建设集团有限公司 墙体暗配电管布孔用补洞托盘式固定支架

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄昌学,李俊: "暗配箱一次到位施工技术", 《电气与自动化仪表安装》 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103490354A (zh) * 2013-09-24 2014-01-01 甘肃第七建设集团股份有限公司 预埋电管管孔控制专用模具的使用方法
CN104810744A (zh) * 2014-01-28 2015-07-29 浙江国泰建设集团有限公司 一种墙体管线自由预埋施工方法
CN105019651B (zh) * 2014-04-23 2017-06-09 重庆建工第四建设有限责任公司 空心砖填充墙成排线盒高效安装施工工法
CN105019651A (zh) * 2014-04-23 2015-11-04 重庆建工第四建设有限责任公司 空心砖填充墙成排线盒高效安装施工工法
CN103938869A (zh) * 2014-05-13 2014-07-23 二十二冶集团第一建设有限公司 Ms砌块后砌筑墙体内线管、线盒的施工方法
CN104196148A (zh) * 2014-09-15 2014-12-10 京鑫建设集团有限公司 一种空心砌块填充墙施工工艺及预设管线
CN104453085A (zh) * 2014-10-28 2015-03-25 成都市第四建筑工程公司 一种轻集料混凝土空心隔墙板的线盒安装方法
CN104989099A (zh) * 2015-05-22 2015-10-21 重庆一建建设集团有限公司 预埋线盒施工方法
CN104806025A (zh) * 2015-05-26 2015-07-29 中建五局蚌埠建筑工程有限公司 砌体工程机电管线与线盒直埋成套施工工艺
CN106786266A (zh) * 2016-12-13 2017-05-31 上海市建工设计研究院有限公司 预制装配钢结构住宅电缆电线敷设系统及其施工方法
CN107916789A (zh) * 2017-10-27 2018-04-17 江苏南通三建集团股份有限公司 一种混凝土空心砌块墙体穿管嵌盒的方法
CN107859332A (zh) * 2017-11-23 2018-03-30 中国二十二冶集团有限公司 预制配电箱线管预埋的施工方法
CN109853832A (zh) * 2019-01-18 2019-06-07 江苏南通六建建设集团有限公司 一种填充墙砌筑与电气预埋线管同步施工的施工方法
CN110359616A (zh) * 2019-06-24 2019-10-22 中冶天工集团有限公司 一种混凝土或水泥砂浆地坪半圆槽留设方法
CN110863587A (zh) * 2019-12-02 2020-03-06 中国建筑第四工程局有限公司 一种线管安装砌体免开槽施工方法及结构
CN110924692A (zh) * 2019-12-02 2020-03-27 中建三局第三建设工程有限责任公司 砌体管线直埋施工方法
CN113622510A (zh) * 2020-05-07 2021-11-09 万平华 加气混凝土墙板的安装方法
CN112482638A (zh) * 2020-11-20 2021-03-12 临沂城投地产有限公司 一种现浇板管线密集处抗裂措施及施工方法

Also Published As

Publication number Publication date
CN103061515B (zh) 2015-10-14

Similar Documents

Publication Publication Date Title
CN103061515B (zh) 混凝土空心砌块填充墙预埋pvc电线管穿管安装方法
CN107401207B (zh) 排水管道的施工方法
CN103321436B (zh) 建筑砖砌体上线盒预安装施工方法及其预安装支架
CN103758272B (zh) 蒸压加气混凝土砌块墙体内置管线预埋施工方法
CN103061504B (zh) 混凝土板管道安装预留洞施工模具及施工方法
CN101247029A (zh) 在墙体上配线管、线盒的施工方法
CN103672181A (zh) 给排水管道套管预埋施工方法
CN103089014A (zh) 一种穿楼板管道的施工方法
CN104806025A (zh) 砌体工程机电管线与线盒直埋成套施工工艺
CN110552370A (zh) 基于逆作法的环形内衬墙整体单边支模施工方法
CN204185845U (zh) 一种防水桩板墙支护结构
CN104500836A (zh) 城市地下管道非开挖快速修补方法
CN101892764B (zh) 一种围墙的建筑方法
CN203096762U (zh) 一种防冻胀地梁
CN103669400A (zh) 预制式排管典型施工方法
CN103046765B (zh) 防空洞加固后继续使用的施工工艺
CN204753783U (zh) 预制砼雨污水检查井装置
CN208918070U (zh) 一种组合式混凝土墙体结构
CN203701145U (zh) 一种地下管网检查井混凝土组件
CN203160693U (zh) 一种可拆卸式止水螺杆
CN105951885B (zh) 一种装配式工井标准节及其在新建工程中的安装方法
CN204387499U (zh) 室内集成装修的水电管网安装装置
CN203452335U (zh) 建筑工程水电安装结构
CN208782449U (zh) 一种电缆排管
CN203729323U (zh) 一种预制混凝土管道基础

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee after: SCEGC NO.3 CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Address before: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee before: SHAANXI CONSTRUCTION ENGINEERING GROUP NO.3 BUILDING ENGINEERING Co.,Ltd.

Address after: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee after: SHAANXI CONSTRUCTION ENGINEERING GROUP NO.3 BUILDING ENGINEERING Co.,Ltd.

Address before: 710054 No. 68 Anton street, Shaanxi, Xi'an

Patentee before: SHAANXI CONSTRUCTION ENGINEERING GROUP THIRD ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder