CN103920600A - 大型浮选机转子离线组装方法 - Google Patents
大型浮选机转子离线组装方法 Download PDFInfo
- Publication number
- CN103920600A CN103920600A CN201410182830.0A CN201410182830A CN103920600A CN 103920600 A CN103920600 A CN 103920600A CN 201410182830 A CN201410182830 A CN 201410182830A CN 103920600 A CN103920600 A CN 103920600A
- Authority
- CN
- China
- Prior art keywords
- rotor
- column
- line
- assembling
- flotation machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Manufacture Of Motors, Generators (AREA)
Abstract
本发明涉及一种大型浮选机转子离线组装方法,其组装方法步骤为:⑴制作专用支撑装置;⑵大型浮选机转子组装;⑶将浮选机筒体安装在厂房内设备安装场地上;⑷组装后的转子及支架整体存放和运输,到达厂房内设备安装场地后,将转子与支架联接螺栓松开,利用吊耳将转子吊装到浮选机筒体上,大型浮选机转子组装完毕。本发明将提前离线组装的转子在厂房内设备安装场地进行在线安装。因离线组装与在线安装不在同一工作面上,占用安装现场的作业面少,使施工机具、人力等资源得到充分利用,提高了转子在线安装的施工效率,缩短了浮选设备的总体安装工期,同时减少了交叉、高空、受限空间作业,降低施工的安全风险。
Description
技术领域
本发明属于浮选设备安装领域,尤其是一种大型浮选机转子离线组装方法。
背景技术
浮选机是选矿厂的主体设备之一,由于大型选矿厂浮选机的数量较多,结构相同,具有散件多、现场安装工作量大、安装工期长的特点。如何提高浮选机的安装效率,确保工程质量和施工进度,是选矿厂浮选机安装的关键环节和关键工序,尤其是大型浮选机转子的安装。
发明内容
本发明的目的在于克服现有技术的不足,提供一种大型浮选机转子离线组装方法,该组装方法科学合理,在保证工程质量的前提下,极大地提高了安装作业效率和工程进度,缩短设备安装工期,降低施工成本。
本发明解决其技术问题是通过以下技术方案实现的:
一种大型浮选机转子离线组装方法,其组装方法步骤为:
⑴、制作专用支撑装置:包括四根立柱、两根底梁、四根主斜撑,四根立柱设置在矩形的四角,在长向的两根立柱之间下部分别设置底梁,在短向的两根立柱之间设置主斜撑,每根立柱分别由底部立柱以及加长立柱构成,底部立柱与加长立柱之间通过连接螺栓固装,底部立柱与底梁之间安装有底部加固斜撑,加长立柱与底梁之间安装有加长斜撑,在加长立柱的上端设置有转子支撑面,底部立柱与底梁之间通过连接板安装底部加固斜撑,加长立柱与底梁之间通过连接板安装有加长斜撑;
⑵、大型浮选机转子组装:将转子下部构件泡沫溢流槽、散流器罩、散流器、星形转子、开口轴环提前放到支撑装置内,以便在转子上部构件吊装后方便组装,将转子上部构件吊装到转子组装支撑装置上,将转子轴和轴承座组装后从上方吊入转子上部构件内,在转子轴上方放框式水平,将转子轴找垂直,依次安装星形转子、转子散流器、散流器罩、开口轴环、传动电机、主动皮带轮、从动皮带轮、传动三角带,并确保各三角带张力保持一致;三角带防掉罩;
⑶、将浮选机筒体安装在厂房内设备安装场地上;
⑷、组装后的转子及支架整体存放和运输,到达厂房内设备安装场地后,将转子与支架联接螺栓松开,利用吊耳将转子吊装到浮选机筒体上,大型浮选机转子组装完毕。
本发明的优点和有益效果为:
本发明将提前离线组装的转子在厂房内设备安装场地进行在线安装。因离线组装与在线安装不在同一工作面上,占用安装现场的作业面少,使施工机具、人力等资源得到充分利用,提高了转子在线安装的施工效率,缩短了浮选设备的总体安装工期,同时减少了交叉、高空、受限空间作业,降低施工的安全风险。
附图说明
图1为本发明的专用支撑装置结构示意图;
图2为图1的左视图;
图3为本发明的大型浮选机转子组装示意图。
具体实施方式
下面通过具体实施例对本发明作进一步详述,以下实施例只是描述性的,不是限定性的,不能以此限定本发明的保护范围。
一种大型浮选机转子离线组装方法,其组装方法步骤为:
⑴、制作专用支撑装置:包括四根立柱、两根底梁5、四根主斜撑,四根立柱设置在矩形的四角,在长向的两根立柱之间下部分别设置底梁,在短向的两根立柱之间设置主斜撑9、10,每根立柱分别由底部立柱1以及加长立柱2构成,底部立柱与加长立柱之间通过连接螺栓8固装,底部立柱与底梁之间安装有底部加固斜撑6,加长立柱与底梁之间安装有加长斜撑7,在加长立柱的上端设置有转子支撑面3,底部立柱与底梁之间通过连接板4安装底部加固斜撑,加长立柱与底梁之间通过连接板安装有加长斜撑;
⑵、大型浮选机转子组装:将转子下部构件泡沫溢流槽12、散流器罩13、散流器14、星形转子15、开口轴环16提前放到支撑装置17内,以便在转子上部构件18吊装后方便组装,将转子上部构件吊装到转子组装支撑装置上,将转子轴20和轴承座19组装后从上方吊入转子上部构件内,在转子轴上方放框式水平,将转子轴找垂直,依次安装星形转子15、转子散流器14、散流器罩13、开口轴环16、传动电机11、主动皮带轮24、从动皮带轮21、传动三角带23,并确保各三角带张力保持一致;三角带防掉罩25;
⑶、将浮选机筒体安装在厂房内设备安装场地上;
⑷、组装后的转子及支架整体存放和运输,到达厂房内设备安装场地后,将转子与支架联接螺栓松开,利用吊耳22将转子吊装到浮选机筒体上,大型浮选机转子组装完毕。
浮选机一般是成排成列布置的,一台浮选机与相邻浮选机之间均有相应的定位要求。应采用系统定位的措施,以确保浮选机整体排列定位准确。每列浮选机有若干个,可组成一个完整的浮选流程。因此,每列浮选机都可以作为一个整体单元来进行安装和调整。为减少累积误差,浮选机调整定位时应从中间往两头进行。筒体安装时的调整定位,还要严格确认其他连接装置的定位尺寸和相对位置,以确保整套浮选机顺利安装完成。安装应从每排筒体的进料端开始,卸料端结束。逐级且依次进行安装。吊装筒体之前,筒体内部构件(包括耐磨板、活动底板、引流管、垂直挡板、开口轴环、径向流水槽)应全部安装完毕,起重吊装作业周围场地必须进行清理,筒体吊装应前检查所有吊具和索具,合格后方可使用。吊装筒体时,为了防止筒体在吊装过程中的变形,应设计、使用专用吊具进行吊装,吊装过程中要保持筒体水平,防止筒体倾斜碰撞地面,基础或其它物体,直到筒体缓慢、平稳地落在设备基础上。
将提前离线组装的转子在厂房内设备安装场地进行在线安装。转子在线安装时要严格保证转子轴的垂直度,浮选筒内作业照明灯须使用24V安全电压。因离线组装与在线安装不在同一工作面上,占用安装现场的作业面少,使施工机具、人力等资源得到充分利用,提高了转子在线安装的施工效率,缩短了浮选设备的总体安装工期,同时减少了交叉、高空、受限空间作业,降低施工的安全风险。
使用专用支撑装置,在浮选设备安装场地之外进行设备转子的离线组装,转子离线组装时要保证转子的组装质量,提高了转子组装的施工效率。由于转子组装占用的时间较多,又不需要在浮选筒体内部进行组装,减少了大量的受限空间内作业,使本来在筒体安装后的工序提前同时进行,转子离线组装与在线安装工序也可同时进行、并相互协调,总体上加快了施工进度,改善了劳动环境,使施工现场的资源配置更加优化、顺畅。根据浮选机转子的离线组装与在线安装的进度安排,制作和使用多套转子组装支架,以满足组装、运输的要求。
Claims (1)
1.一种大型浮选机转子离线组装方法,其特征在于:该组装方法步骤为:
⑴、制作专用支撑装置:包括四根立柱、两根底梁、四根主斜撑,四根立柱设置在矩形的四角,在长向的两根立柱之间下部分别设置底梁,在短向的两根立柱之间设置主斜撑,每根立柱分别由底部立柱以及加长立柱构成,底部立柱与加长立柱之间通过连接螺栓固装,底部立柱与底梁之间安装有底部加固斜撑,加长立柱与底梁之间安装有加长斜撑,在加长立柱的上端设置有转子支撑面,底部立柱与底梁之间通过连接板安装底部加固斜撑,加长立柱与底梁之间通过连接板安装有加长斜撑;
⑵、大型浮选机转子组装:将转子下部构件泡沫溢流槽、散流器罩、散流器、星形转子、开口轴环提前放到支撑装置内,以便在转子上部构件吊装后方便组装,将转子上部构件吊装到转子组装支撑装置上,将转子轴和轴承座组装后从上方吊入转子上部构件内,在转子轴上方放框式水平,将转子轴找垂直,依次安装星形转子、转子散流器、散流器罩、开口轴环、传动电机、主动皮带轮、从动皮带轮、传动三角带,并确保各三角带张力保持一致;三角带防掉罩;
⑶、将浮选机筒体安装在厂房内设备安装场地上;
⑷、组装后的转子及支架整体存放和运输,到达厂房内设备安装场地后,将转子与支架联接螺栓松开,利用吊耳将转子吊装到浮选机筒体上,大型浮选机转子组装完毕。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410182830.0A CN103920600B (zh) | 2014-04-30 | 2014-04-30 | 大型浮选机转子离线组装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410182830.0A CN103920600B (zh) | 2014-04-30 | 2014-04-30 | 大型浮选机转子离线组装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103920600A true CN103920600A (zh) | 2014-07-16 |
CN103920600B CN103920600B (zh) | 2016-08-17 |
Family
ID=51139132
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410182830.0A Active CN103920600B (zh) | 2014-04-30 | 2014-04-30 | 大型浮选机转子离线组装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103920600B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108772203A (zh) * | 2018-07-01 | 2018-11-09 | 张大伟 | 一种锡矿矿厂选矿用浮选机 |
CN109046793A (zh) * | 2018-07-03 | 2018-12-21 | 安徽理工大学 | 一种矿物浮选系统 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2770789Y (zh) * | 2005-02-06 | 2006-04-12 | 王连华 | 浮选机的叶轮和定子的组合构造 |
US20070289912A1 (en) * | 2004-03-12 | 2007-12-20 | Noram Engineering And Constructors Ltd. | Circular clarifier apparatus and method |
WO2008062097A1 (en) * | 2006-11-22 | 2008-05-29 | Outotec Oyj | Rotor for a flotation machine, method for forming same, and method for maintenance of same |
CN202366793U (zh) * | 2011-08-21 | 2012-08-08 | 唐海仁 | 完全模拟生产流程浮选试验设备组 |
CN203484236U (zh) * | 2013-09-25 | 2014-03-19 | 瓮福(集团)有限责任公司 | 一种改进的浮选机转子装置 |
-
2014
- 2014-04-30 CN CN201410182830.0A patent/CN103920600B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070289912A1 (en) * | 2004-03-12 | 2007-12-20 | Noram Engineering And Constructors Ltd. | Circular clarifier apparatus and method |
CN2770789Y (zh) * | 2005-02-06 | 2006-04-12 | 王连华 | 浮选机的叶轮和定子的组合构造 |
WO2008062097A1 (en) * | 2006-11-22 | 2008-05-29 | Outotec Oyj | Rotor for a flotation machine, method for forming same, and method for maintenance of same |
CN202366793U (zh) * | 2011-08-21 | 2012-08-08 | 唐海仁 | 完全模拟生产流程浮选试验设备组 |
CN203484236U (zh) * | 2013-09-25 | 2014-03-19 | 瓮福(集团)有限责任公司 | 一种改进的浮选机转子装置 |
Non-Patent Citations (1)
Title |
---|
母小波: "大型浮选机安装施工控制方法及调整技巧", 《山西科技》, vol. 29, no. 2, 20 March 2014 (2014-03-20), pages 37 - 39 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108772203A (zh) * | 2018-07-01 | 2018-11-09 | 张大伟 | 一种锡矿矿厂选矿用浮选机 |
CN109046793A (zh) * | 2018-07-03 | 2018-12-21 | 安徽理工大学 | 一种矿物浮选系统 |
Also Published As
Publication number | Publication date |
---|---|
CN103920600B (zh) | 2016-08-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101748799B (zh) | 烟囱钢筋混凝土筒壁液压提升翻模施工方法 | |
CN101284628B (zh) | 大吨位压力机架的吊装方法 | |
CN103920600A (zh) | 大型浮选机转子离线组装方法 | |
CN103669882A (zh) | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 | |
CN111058609A (zh) | 一种施工与防护一体化便携式操作平台及方法 | |
CN107792774B (zh) | 一种多根钢平台次梁整体吊装方法及吊装工具 | |
CN205602927U (zh) | 一体式曳引机及导向轮固定装置 | |
CN209192912U (zh) | 一种发电机检修移位装置 | |
CN115199023A (zh) | 一种吊篮的防坠保护装置 | |
CN208684271U (zh) | 一种大型水轮发电机定子线棒吊装装置 | |
CN103982359A (zh) | 一种水轮机与发电机轴机快速铰孔连接的方法 | |
CN110410277B (zh) | 一种风力发电机塔架及其安装方法 | |
CN207177305U (zh) | 预制梁张拉千斤顶悬吊门架 | |
CN207143731U (zh) | 一种桥梁护栏设备安装简易吊篮 | |
CN102951554B (zh) | 用于高炉炉顶吊车梁系统整体吊装的连接件及其使用方法 | |
CN201704035U (zh) | 大型煤气柜柜顶提升装置 | |
CN110697575A (zh) | 一种大型设备吊装精准就位装置、就位系统及就位方法 | |
CN203887509U (zh) | 大型浮选机转子离线组装支撑装置 | |
CN204024009U (zh) | 一种风力发电预制混凝土塔架拼装操作平台 | |
CN203213561U (zh) | 一种安装作业平台 | |
CN220058752U (zh) | 水电站活动导叶吊装作业平台 | |
CN203654768U (zh) | 一种井装组合式布料装置 | |
CN214942232U (zh) | 一种新型的可移动悬挑操作平台 | |
CN212375718U (zh) | 一种墩身钢筋整体连接固定模具 | |
CN214616851U (zh) | 一种水轮机检修排架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |