CN103866985A - Butt joint method and device for construction elevator and creeping formwork frame body - Google Patents

Butt joint method and device for construction elevator and creeping formwork frame body Download PDF

Info

Publication number
CN103866985A
CN103866985A CN201210551041.0A CN201210551041A CN103866985A CN 103866985 A CN103866985 A CN 103866985A CN 201210551041 A CN201210551041 A CN 201210551041A CN 103866985 A CN103866985 A CN 103866985A
Authority
CN
China
Prior art keywords
creeping formwork
construction elevator
support body
frame body
formwork support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210551041.0A
Other languages
Chinese (zh)
Inventor
袁茂生
李晓阳
谢翔
梁超
明睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN201210551041.0A priority Critical patent/CN103866985A/en
Publication of CN103866985A publication Critical patent/CN103866985A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a butt joint method and device for a construction elevator and a creeping formwork frame body. In the method, an elongated attached wall is adopted; the construction elevator is outwards moved out of the creeping formwork frame body; the protective fence or the protective screening of the creeping formwork frame body is provided with a safety door in butt joint with the construction elevator; construction personnel are transported to the position level with the creeping formwork frame body by the construction elevator; the construction personnel enter the creeping formwork frame body through the safety door. According to the invention, the construction elevator is outwards moved to be out of the creeping formwork frame body, so that the construction elevator and the creeping formwork frame body can be directly subjected to butt joint; meanwhile, the outer side of the creeping formwork frame body is provided with an openable steel protective door used for the construction personnel to enter and leave the creeping formwork. According to the method disclosed by the invention, the construction personnel can be safely and quickly transported to the creeping formwork frame body. The method has the advantages of simpleness in manufacture and low construction price, other measures do not need to be adopted after the creeping formwork is climbed, and the method is a feasible procedure.

Description

A kind of construction elevator and creeping formwork support body docking calculation and device
Technical field
the present invention relates to a kind of construction elevator and creeping formwork support body docking calculation and device, belong to building operations personnel vertical transport technical field.
Background technology
along with expanding economy, the super highrise building in each city is more and more, and in the time of construction of super highrise building, choice for use creeping formwork is constructed conventionally.Creeping formwork be a kind of wall-attached from climbing system, by hydraulic jack, guide rail and climbing frame are replaced jacking and are realized the structural system of creeping formwork pier stud concrete construction.But the constructor on creeping formwork need to adopt construction elevator to be transported on creeping formwork support body.
the distance that creeping formwork support body stretches out exterior wall has conventionally exceeded the effective length of construction elevator sustaining wall, so current construction elevator cage is generally arranged on creeping formwork support body below, after construction elevator is transported to constructor creeping formwork support body below, again by one independently climbing type transition steel platform be connected with creeping formwork support body, constructor climbs up creeping formwork support body by climbing type transition steel platform, because this stand alone type transition steel platform stable is poor, security risk is large, and creeping formwork one deck that often climbs, this transition steel platform also needs to climb once, thereby safety management difficulty and expense are increased.
Summary of the invention
the object of the invention is to, a kind of construction elevator and creeping formwork support body docking calculation and device are provided.Abolish current climbing type transition steel platform, make constructor directly enter creeping formwork support body by construction elevator, to guarantee constructor's safety.And reduce safety management difficulty and expense.To overcome the deficiencies in the prior art.
technical scheme of the present invention:
a kind of construction elevator and creeping formwork support body docking calculation, the method is to adopt extended type attached wall, and construction elevator is outwards shifted out outside creeping formwork support body; And arrange and dock safety door with construction elevator on the protective guard of creeping formwork body frame or protective screening; By construction elevator, constructor is transported to and creeping formwork support body flush position, constructor enters creeping formwork support body by safety door.
in preceding method, described safety door adopts unidirectional opening the door; On creeping formwork support body, cannot open, can only open from cage one side, to guarantee the safety of constructor on creeping formwork support body.
the construction elevator and the creeping formwork support body docking facilities that form according to preceding method, comprise creeping formwork and construction elevator, and construction elevator comprises vertical support frame, and vertical support frame is connected with building through attached wall, and vertical support frame is provided with cage; Creeping formwork is provided with creeping formwork support body; Described attached wall is extended type attached wall, and cage is positioned at outside the upright projection at creeping formwork support body edge; The external side of climbing form frame is provided with protective screening, and protective screening is provided with safety door.
in aforementioned means, described safety door is to open the door in outside.
in aforementioned means, described safety door is welded with steel pipe and gauze wire cloth.
compared with prior art, the present invention outwards moves to construction elevator outside creeping formwork support body, construction elevator energy and creeping formwork are directly docked, pass in and out creeping formwork at the openable safety steel door of climbing form frame body arranged outside for constructor simultaneously, safe and efficient constructor being transported on creeping formwork support body of method energy of the present invention, make simple, low cost, and creeping formwork also need not take other measure after climbing, be a kind of more feasible way.
Brief description of the drawings
fig. 1 is structural representation of the present invention.
being labeled as in figure: 1-vertical support frame, 2-attached wall, 3-building, 4-cage, 5-creeping formwork support body, 6-safety door, 7-creeping formwork.
Detailed description of the invention
below in conjunction with accompanying drawing, the present invention is described in further detail, but not as any limitation of the invention.
a kind of construction elevator and creeping formwork support body docking calculation, as shown in Figure 1.The method is to adopt extended type attached wall, and construction elevator is outwards shifted out outside creeping formwork support body; And arrange and dock safety door with construction elevator on the protective guard of creeping formwork body frame or protective screening; By construction elevator, constructor is transported to and creeping formwork support body flush position, constructor enters creeping formwork support body by safety door.Safety door adopts unidirectional opening the door; On creeping formwork support body, cannot open, can only open from cage one side, to guarantee the safety of constructor on creeping formwork support body.
the construction elevator and the creeping formwork support body docking facilities that form according to preceding method, as shown in Figure 1, comprise creeping formwork 7 and construction elevator, and construction elevator comprises vertical support frame 1, and vertical support frame 1 is connected with building 3 through attached wall 2, and vertical support frame 1 is provided with cage 4; Creeping formwork 7 is provided with creeping formwork support body 5; Described attached wall 2 is extended type attached wall, and cage 4 is positioned at outside the upright projection at creeping formwork support body 5 edges; Creeping formwork support body 5 outsides are provided with protective screening, and protective screening is provided with safety door 6.Safety door 6 is for opening the door in outside.Safety door 6 use steel pipes and gauze wire cloth are welded.
the present invention adopts extended type attached wall, extended type attached wall can be ordered to professional elevator company, construction elevator is outwards shifted out to climbing form frame external, construction elevator energy and creeping formwork are directly docked, and on support body, stay and establish steel security door outside creeping formwork, in order to ensure constructor's safety, safety door can only be opened from cage one side.Make its safety protective door when docking with construction elevator, the creeping formwork up and down of constructability personal security.Take this way can safe and efficient constructor being transported on creeping formwork support body, make simple, low cost, and creeping formwork also need not take other measure after climbing, be a kind of more feasible way.

Claims (5)

1. construction elevator and a creeping formwork support body docking calculation, is characterized in that: the method is to adopt extended type attached wall, and construction elevator is outwards shifted out outside creeping formwork support body; And arrange and dock safety door with construction elevator on the protective guard of creeping formwork body frame or protective screening; By construction elevator, constructor is transported to and creeping formwork support body flush position, constructor enters creeping formwork support body by safety door.
2. method according to claim 1, is characterized in that: aforementioned safety door adopts unidirectional opening the door; On creeping formwork support body, cannot open, can only open from cage one side, to guarantee the safety of constructor on creeping formwork support body.
3. the construction elevator and the creeping formwork support body docking facilities that form according to method described in claim 1 or 2, comprise creeping formwork (7) and construction elevator, construction elevator comprises vertical support frame (1), vertical support frame (1) is connected with building (3) through attached wall (2), and vertical support frame (1) is provided with cage (4); Creeping formwork (7) is provided with creeping formwork support body (5); It is characterized in that: described attached wall (2) is extended type attached wall, and cage (4) is positioned at outside the upright projection at creeping formwork support body (5) edge; Creeping formwork support body (5) outside is provided with protective screening, and protective screening is provided with safety door (6).
4. install according to claim 3, it is characterized in that: aforementioned safety door (6) is for opening the door in outside.
5. install according to claim 4, it is characterized in that: aforementioned safety door (6) steel pipe and gauze wire cloth are welded.
CN201210551041.0A 2012-12-18 2012-12-18 Butt joint method and device for construction elevator and creeping formwork frame body Pending CN103866985A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210551041.0A CN103866985A (en) 2012-12-18 2012-12-18 Butt joint method and device for construction elevator and creeping formwork frame body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210551041.0A CN103866985A (en) 2012-12-18 2012-12-18 Butt joint method and device for construction elevator and creeping formwork frame body

Publications (1)

Publication Number Publication Date
CN103866985A true CN103866985A (en) 2014-06-18

Family

ID=50905964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210551041.0A Pending CN103866985A (en) 2012-12-18 2012-12-18 Butt joint method and device for construction elevator and creeping formwork frame body

Country Status (1)

Country Link
CN (1) CN103866985A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605152A (en) * 2017-07-28 2018-01-19 中建四局第建筑工程有限公司 The combination unit and its application method of a kind of construction elevator and creeping formwork support body
WO2020052291A1 (en) * 2018-09-13 2020-03-19 上海建工集团股份有限公司 Construction elevator wall-attaching frame mounting platform attached to steel platform formwork and method therefor
CN111395183A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for electric bridge type scaffold platform for double-column pier construction
CN111395184A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for constructing high pier with gradually-changed section by using electric bridge type scaffold platform
CN111395185A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for applying electric bridge type scaffold platform to construction of equal-section high pier

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05148909A (en) * 1991-11-29 1993-06-15 Kajima Corp Multilayer preceding contruction method for building body
JPH09317183A (en) * 1996-05-28 1997-12-09 Sato Kogyo Co Ltd Construction method of building
CN201305994Y (en) * 2008-09-25 2009-09-09 中建三局建设工程股份有限公司 Automatic plate turnover mechanism for floor passage of construction elevator
CN202017335U (en) * 2011-04-18 2011-10-26 南通一建集团有限公司 Hydraulic mutual-climbing type lifting scaffold

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05148909A (en) * 1991-11-29 1993-06-15 Kajima Corp Multilayer preceding contruction method for building body
JPH09317183A (en) * 1996-05-28 1997-12-09 Sato Kogyo Co Ltd Construction method of building
CN201305994Y (en) * 2008-09-25 2009-09-09 中建三局建设工程股份有限公司 Automatic plate turnover mechanism for floor passage of construction elevator
CN202017335U (en) * 2011-04-18 2011-10-26 南通一建集团有限公司 Hydraulic mutual-climbing type lifting scaffold

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张松等: "广州珠江城核心筒施工关键技术研究", 《建筑施工》, vol. 33, no. 10, 31 October 2011 (2011-10-31), pages 880 - 883 *
朱重建等: "整体升降脚手架与垂直运输施工机械的工作协调性", 《江苏建筑》, no. 3, 30 June 1998 (1998-06-30), pages 33 - 36 *
马茂忠: "建筑施工升降机的使用与维护浅见", 《建筑安全》, no. 9, 30 September 2012 (2012-09-30), pages 51 - 53 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605152A (en) * 2017-07-28 2018-01-19 中建四局第建筑工程有限公司 The combination unit and its application method of a kind of construction elevator and creeping formwork support body
WO2020052291A1 (en) * 2018-09-13 2020-03-19 上海建工集团股份有限公司 Construction elevator wall-attaching frame mounting platform attached to steel platform formwork and method therefor
CN111395183A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for electric bridge type scaffold platform for double-column pier construction
CN111395184A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for constructing high pier with gradually-changed section by using electric bridge type scaffold platform
CN111395185A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for applying electric bridge type scaffold platform to construction of equal-section high pier

Similar Documents

Publication Publication Date Title
CN103866985A (en) Butt joint method and device for construction elevator and creeping formwork frame body
CN205077885U (en) Building core section of thick bamboo hydraulic pressure intelligence protection platform that climbs
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN204782031U (en) Interior climbing tower hangs entrance to a cave from promoting safety protection platform
CN103422668A (en) Construction method of super-thick large-slope shear wall and hydraulic self-jacking inclined creeping framework thereof
CN203855895U (en) Mobile jib operation platform for constructing and overhauling bridges
CN104060541B (en) A kind of little Hanging Basket and construction technology for installing intercepting drain thereof of sliding
CN103912128B (en) The construction method of high-altitude disjunctor steel truss
CN103174283B (en) Mobile operation platform
CN105952133A (en) Suspended large-span reinforced concrete structure construction steel platform and construction method
CN203361634U (en) Device for butt-jointing construction elevator and climbing formwork
CN203173644U (en) Multifunctional lifting shaft working platform system
CN204626930U (en) A kind of integrated form crane operating platform
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN211689948U (en) Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge
CN203547125U (en) Column type overall steel platform hydraulic creeping formwork
CN202913679U (en) Double-function construction operation protection derrick in elevator shaft way
CN205894715U (en) Light steel structure is semi -automatic under enclosed construction constructs from hoisting machine that climbs
CN201649607U (en) Overhung-type outer wall scaffold
CN201401000Y (en) Special hanging basket for installing noise barrier roof boards
CN211775606U (en) Regularization assembled that can have enough to meet need climbs frame and goes up people's passageway
CN210655915U (en) Connecting device for climbing frame and tower crane
CN204038917U (en) Dismountable external hanging service platform
CN203769402U (en) Steel pipe tower safety climbing and treading device
CN202988663U (en) Return hook suspension mechanism

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140618