CN103850262B - Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile - Google Patents

Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile Download PDF

Info

Publication number
CN103850262B
CN103850262B CN201210497647.0A CN201210497647A CN103850262B CN 103850262 B CN103850262 B CN 103850262B CN 201210497647 A CN201210497647 A CN 201210497647A CN 103850262 B CN103850262 B CN 103850262B
Authority
CN
China
Prior art keywords
pile
collection
stopping method
concrete pile
place concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210497647.0A
Other languages
Chinese (zh)
Other versions
CN103850262A (en
Inventor
许海岩
谢非
李修岩
许利捷
苏亚鹏
肖策
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201210497647.0A priority Critical patent/CN103850262B/en
Publication of CN103850262A publication Critical patent/CN103850262A/en
Application granted granted Critical
Publication of CN103850262B publication Critical patent/CN103850262B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to Deep Foundation Pit Supporting Project, particularly relate to the water-stopping method of deep foundation pit support.Drain water-stopping method between a kind of Punching Borehole Cast-in-place Concrete Pile campshed support pile, it includes: in Excavation Process, before extension bar-mat reinforcement spray sets facing concrete, collection arm is embedded between bored concrete pile, it is connected with standpipe by joint, along with the excavation of foundation pit degree of depth connects downwards, finally bottom foundation ditch, guide to cheat end collecting main through facing concrete, after unified collection, use water pump to be discharged to outside foundation ditch.The present invention can realize sealing without water-stop curtain, reduces construction cost and cycle.

Description

Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile
Technical field
The present invention relates to Deep Foundation Pit Supporting Project, particularly relate to the water-stopping method of deep foundation pit support.
Background technology
Deep Foundation Pit Supporting Project, through the campshed support pattern frequently with bored concrete pile form, uses high pressure outstanding spray stake between campshed Carry out waterproof between piles.But at some deep & thick silt regions or the sludge region of fill block stone throwing or when having into rock demand, frequently with Punching Borehole Cast-in-place Concrete Pile technique is constructed, and Punching Borehole Cast-in-place Concrete Pile easily causes the phenomenon such as collapse hole, reaming, causes waterproof between piles curtain to be difficult to Implement, need to use change fill out or draw hole after carry out mixing pile or high-pressure rotary jet grouting pile water-stopping method, such construction cost is high, long in time limit, Excavation Process also needs to secondary sealing, affects construction operation.
Summary of the invention
Present invention seek to address that drawbacks described above, it is provided that drain water-stopping method between a kind of Punching Borehole Cast-in-place Concrete Pile campshed support pile.This Invent and can realize sealing without water-stop curtain, reduce construction cost and cycle.
For solving the problems referred to above, drain water-stopping method between a kind of Punching Borehole Cast-in-place Concrete Pile campshed support pile, it includes: open at foundation ditch During digging, before extension bar-mat reinforcement spray sets facing concrete, collection arm is embedded between bored concrete pile, by joint with standpipe even Connect, along with the excavation of foundation pit degree of depth connects downwards, finally guide to cheat end collecting main through facing concrete bottom foundation ditch, Water pump is used to be discharged to outside foundation ditch after unified collection.
Drain water-stopping method between described Punching Borehole Cast-in-place Concrete Pile campshed support pile, it is characterised in that described collection branch pipe wall It is provided with collection hole, body parcel filter membrane, and is bundled fixing by rope or iron wire.
Present invention process is simple, strong operability, simple installation.Reduce the engineering cost of water-stop curtain, effectively improve Working environment in foundation ditch, it is ensured that deep pit monitor, improves work efficiency, has higher using value.
Accompanying drawing explanation
The present invention is further illustrated below in conjunction with the accompanying drawings:
Fig. 1 is schematic diagram of the present invention;
Fig. 2 is elevation of the present invention;
Fig. 3 is described arm schematic diagram.
Detailed description of the invention
Please see Figure 1 and Fig. 2, drain water-stopping method between one Punching Borehole Cast-in-place Concrete Pile campshed support pile of the present invention, it includes: at base In the digging process of hole, before extension bar-mat reinforcement spray sets facing concrete 8, the collection arm 1 of this drainage system is embedded in bored concrete pile 5 Between, it is connected with standpipe 3 by joint 2, along with the excavation of foundation pit degree of depth connects downwards, finally mixes through mask bottom foundation ditch Solidifying soil guides to cheat end collecting main 4, uses the catch pit 9 that water pump is discharged in foundation ditch after unified collection.
Drain water-stopping method between described Punching Borehole Cast-in-place Concrete Pile campshed support pile, described collection branch pipe wall is provided with collection hole 10, body parcel filter membrane 6, and bundled fixing (seeing Fig. 3) by rope or iron wire 7.
Embodiment:
Collecting arm 1 uses the pvc of φ 32 to manage, and tube wall is provided with the filter membranes 6 such as the collection hole of φ 5, body parcel geotextiles, adopts It is fixed colligation with nylon rope or iron wire 7.
Punching Borehole Cast-in-place Concrete Pile campshed has been implemented, and before excavation of foundation pit, buries collection arm 1 underground, use PVC reducing between drilled pile Joint 2 is connected with φ 50PVC standpipe 3, along with the degree of depth of excavation of foundation pit, by the collecting main 4 of 0.5m-0.75m segmentation Yu φ 75 Connect, collect the infiltration between campshed, by arranging catch pit water pump in excavation face, water is discharged to outside foundation ditch, it is ensured that opening of foundation ditch Dig environment.
Every section bury underground after arm and riser, along with the intensification of cutting depth, use linked network spray between stake to set concrete and enter Row is fixing.
Collecting arm, standpipe and the diameter of collecting main and material can different according to the water yield between campshed from stake vertical Straight degree, selects different diameters and material to make.

Claims (2)

1. drain water-stopping method between a Punching Borehole Cast-in-place Concrete Pile campshed support pile, it is characterised in that it uses to include collection Pipe and the drainage system of standpipe, in Excavation Process, before extension bar-mat reinforcement spray sets facing concrete, by the collection of drainage system Arm is embedded between bored concrete pile, is connected with standpipe by joint, along with the excavation of foundation pit degree of depth connects downwards, finally at foundation ditch End collecting main is guided to cheat through facing concrete in bottom, uses water pump to be discharged to outside foundation ditch after unified collection.
Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile the most according to claim 1, it is characterised in that described receipts Collection branch pipe wall is provided with collection hole, body parcel filter membrane, and is bundled fixing by rope or iron wire.
CN201210497647.0A 2012-11-29 2012-11-29 Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile Active CN103850262B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210497647.0A CN103850262B (en) 2012-11-29 2012-11-29 Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210497647.0A CN103850262B (en) 2012-11-29 2012-11-29 Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile

Publications (2)

Publication Number Publication Date
CN103850262A CN103850262A (en) 2014-06-11
CN103850262B true CN103850262B (en) 2016-12-21

Family

ID=50858375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210497647.0A Active CN103850262B (en) 2012-11-29 2012-11-29 Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile

Country Status (1)

Country Link
CN (1) CN103850262B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107780436B (en) * 2017-09-26 2019-05-07 湖南大学 Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08189030A (en) * 1995-01-10 1996-07-23 Tenox Corp Method for constructing self-supporting earth-retaining wall
KR20020067083A (en) * 2001-02-15 2002-08-22 (주)스틸엔콘크리트 The method of obstructing water and The pile of obstructing water by using the concrete pile construct having the grout space
CN202194148U (en) * 2011-07-15 2012-04-18 深圳市鸿荣轩建设工程有限公司 Waterproof curtain
CN102425179A (en) * 2011-11-28 2012-04-25 长沙理工大学 Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes
CN102776891A (en) * 2012-08-03 2012-11-14 天津二十冶建设有限公司 Method for processing underground supporting structure leakage of foundation with rock block layer in soft soil

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08189030A (en) * 1995-01-10 1996-07-23 Tenox Corp Method for constructing self-supporting earth-retaining wall
KR20020067083A (en) * 2001-02-15 2002-08-22 (주)스틸엔콘크리트 The method of obstructing water and The pile of obstructing water by using the concrete pile construct having the grout space
CN202194148U (en) * 2011-07-15 2012-04-18 深圳市鸿荣轩建设工程有限公司 Waterproof curtain
CN102425179A (en) * 2011-11-28 2012-04-25 长沙理工大学 Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes
CN102776891A (en) * 2012-08-03 2012-11-14 天津二十冶建设有限公司 Method for processing underground supporting structure leakage of foundation with rock block layer in soft soil

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
探讨旋挖钻机在复杂地质条件下支护桩钻孔工艺及堵漏;范红兵;《四川建材》;20111008(第05期);第74-75页 *

Also Published As

Publication number Publication date
CN103850262A (en) 2014-06-11

Similar Documents

Publication Publication Date Title
CN100480475C (en) Controllable one-well lamina precipitation construction method
CN100501011C (en) Hole drilling mudjack pile construction method
CN105822347B (en) A kind of tunnel siphon drainge system and its method of construction
CN102286984A (en) Water-stop curtain and construction method thereof
CN102383437B (en) Well point positioned pumping tubular well and well point positioned pumping method
CN109024706A (en) A kind of foundation pit waterproof curtain breakthrough inside method for blocking
CN107489158A (en) A kind of spiral-digging pore stirs the construction method of water spray soil occlusion curtain pile
CN109371980B (en) Deep foundation pit enclosure construction method combining spray anchor reverse construction and punched pile
CN104746519A (en) Obstacle clearing construction method
CN202194149U (en) Water-proof curtain
CN105804107A (en) High-pressure-jetting and anti-seepage treatment method for triple tube of joint of underground diaphragm wall
CN113279421A (en) Vacuum dewatering process for deep foundation pit
CN216342131U (en) Shield tunnel invades limit stake and handles reinforced structure
CN208733655U (en) A kind of high water level dewatering construction structure
JP4074313B2 (en) Structure of steel sheet pile for water flow and water retaining wall, and its construction method.
KR20140096731A (en) Underground water drainage system of excavated ground and pipeline construction method using the same
CN103850262B (en) Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile
CN107700508A (en) A kind of shaped steel stirs the construction method of water spray soil curtain support pile
CN102434718A (en) Method for reinforcing originating end of push bench
CN104831735A (en) Water stop support structure integrating piles and screens as well as construction method and construction device thereof
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN205314117U (en) Foundation structure that draw water is carried out with centrifugal pump
CN105586978A (en) Construction method of soil replacement stir waterproof curtain based on gravels
CN105064384B (en) Vacuum tube well precipitation system
JP4376760B2 (en) Groundwater absorption device and groundwater absorption method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant