CN102383437B - Well point positioned pumping tubular well and well point positioned pumping method - Google Patents
Well point positioned pumping tubular well and well point positioned pumping method Download PDFInfo
- Publication number
- CN102383437B CN102383437B CN201110224948.1A CN201110224948A CN102383437B CN 102383437 B CN102383437 B CN 102383437B CN 201110224948 A CN201110224948 A CN 201110224948A CN 102383437 B CN102383437 B CN 102383437B
- Authority
- CN
- China
- Prior art keywords
- water
- well
- well section
- foundation pit
- sand
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000005086 pumping Methods 0.000 title claims abstract description 40
- 238000000034 method Methods 0.000 title abstract description 33
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 137
- 238000001556 precipitation Methods 0.000 claims abstract description 21
- 239000004568 cement Substances 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 8
- 239000004576 sand Substances 0.000 claims description 7
- 239000002002 slurry Substances 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 claims description 2
- 239000011083 cement mortar Substances 0.000 claims description 2
- 239000010959 steel Substances 0.000 claims description 2
- 230000000694 effects Effects 0.000 abstract description 3
- 239000003673 groundwater Substances 0.000 description 31
- 239000002689 soil Substances 0.000 description 12
- 238000010276 construction Methods 0.000 description 8
- 238000009412 basement excavation Methods 0.000 description 5
- 238000001035 drying Methods 0.000 description 5
- 239000011362 coarse particle Substances 0.000 description 4
- 239000010419 fine particle Substances 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 239000002245 particle Substances 0.000 description 3
- 230000035699 permeability Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000005855 radiation Effects 0.000 description 1
- 238000002791 soaking Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Sewage (AREA)
Abstract
Description
技术领域 technical field
本发明属于管井排水领域,尤其涉及一种井点定位抽水管井及井点定位抽水法。The invention belongs to the field of tube well drainage, and in particular relates to a well point positioning pumping tube well and a well point positioning pumping method.
背景技术 Background technique
无论是高层建筑基础还是地下建筑,当位于地下水位以下时,一般都需要降低地下水位,以保证施工的便利与安全。基坑降水通过抽排方式,在一定时间内降低基坑范围内地下水的水位,以保证基坑开挖的施工环境,同时为基坑底板与边坡的稳定提供有力保障。从地下水控制方式来说,基坑地下水控制方法有两大类:止水法和降水法。止水法,即通过有效手段,在基坑周围形成止水帷幕,将地下水止于基坑外,如防渗垂直帷幕、地下连续墙等;降水法是将基坑范围内地下水降低,如明沟排水法、井点降水法等。目前,在基坑工程中被广泛采用的是降水法。降水方法有垂直井点法、自渗井法、辐射井法,及其组合方法。Whether it is a high-rise building foundation or an underground building, when it is below the groundwater level, it is generally necessary to lower the groundwater level to ensure the convenience and safety of construction. Foundation pit dewatering reduces the groundwater level within the scope of the foundation pit within a certain period of time through pumping and drainage, so as to ensure the construction environment of the foundation pit excavation, and at the same time provide a strong guarantee for the stability of the foundation pit floor and slope. In terms of groundwater control methods, there are two types of groundwater control methods for foundation pits: water stop method and precipitation method. The water-stop method is to form a water-stop curtain around the foundation pit through effective means to stop the groundwater outside the foundation pit, such as anti-seepage vertical curtains, underground continuous walls, etc.; the precipitation method is to reduce the groundwater within the foundation pit, such as open ditch Drainage method, well point precipitation method, etc. At present, the precipitation method is widely used in foundation pit engineering. Precipitation methods include vertical well point method, self-seepage well method, radiation well method, and their combination methods.
在这些常规垂直井点降水中,时常可遇到一种特殊现象,即垂直井内水一抽即无,一停又有,开挖时仍有水。人们把这种现象叫做“疏不干”现象。从理论上讲,“疏不干”存在于如图1所示的情况中,即,无论垂直降水井点如何布置,抽水强度如何大,含水层底界面处总存在一定量的地下水,致使基坑内部分地段处于理论浸润线之下,也即基坑范围内的地下水位无法都降至基坑下0.5m。In the precipitation of these conventional vertical well points, a special phenomenon can often be encountered, that is, there is no water in the vertical well when it is pumped, and there is water when it stops, and there is still water during excavation. This phenomenon is called "sparseness". Theoretically speaking, "sparse but not dry" exists in the situation shown in Figure 1, that is, no matter how the vertical precipitation wells are arranged and how strong the pumping intensity is, there will always be a certain amount of groundwater at the bottom interface of the aquifer, resulting in Part of the pit is below the theoretical soaking line, that is, the groundwater level within the pit cannot be lowered to 0.5m below the pit.
“疏不干”现象使得含水层内仍存在着地下水,基坑开挖时残留水沿着基坑侧壁流入基坑内,使得基坑作业面泥泞,工人施工困难,影响施工进度;侧壁渗水还会使边坡支护失效。坑外水携带细小颗粒向基坑内渗流,土颗粒随着水流移动,就产生了流砂现象。当土层中的土颗粒大小差别较大,缺少某种粒径时,细颗粒将随水流在粗颗粒间隙中移动,形成一个连续的通道,即管涌现象。流砂、管涌现象使得土层被掏空,造成地面不均匀沉降,甚至导致基坑滑移、坍塌等工程事故,造成人力物力的损失。The phenomenon of "draining and not drying" makes groundwater still exist in the aquifer. When the foundation pit is excavated, the residual water flows into the foundation pit along the side wall of the foundation pit, making the working surface of the foundation pit muddy, making it difficult for workers to construct, and affecting the construction progress; water seepage from the side wall It will also render the slope support ineffective. The water outside the pit seeps into the foundation pit with fine particles, and the soil particles move with the water flow, which produces the quicksand phenomenon. When the size of the soil particles in the soil layer is quite different and there is a lack of a certain particle size, the fine particles will move with the water flow in the gaps between the coarse particles to form a continuous channel, that is, the piping phenomenon. The phenomena of quicksand and piping make the soil layer hollowed out, resulting in uneven ground settlement, and even engineering accidents such as foundation pit slippage and collapse, resulting in loss of manpower and material resources.
当建筑场地存在多个地下含水层时,由于降落漏斗的客观存在,井点降水的管井埋深均须远远大于基坑的深度,通长的滤水管长度很大,即管井进水段很长,导致基坑降水过程中不仅抽排了基坑降水深度范围内的水,而且也抽取了基坑降水深度以下独立含水层(可以是多个)的水资源。然而,基坑降水深度以下独立含水层(可以是多个)中的地下水对基坑工程影响几乎不存在。同时,由于管井的存在使管井深度范围内的多层独立含水层的地下水贯通了。众所周知,上部含水层中地下水与大气相通,受人类活动影响大,多已受污染,而且越往上含水层中地下水受污染相对越重。上部受污染的地下水在其重力作用下将沿管井进入到下部含水层中,使下部原本很纯洁的地下水也不同程度地受到污染。因此,目前基坑降水的做法既造成了资源的浪费,又增加了工程成本,更严重的是污染了下部优质的地下水资源。When there are multiple underground aquifers on the construction site, due to the objective existence of the down funnel, the burial depth of the tube well for dewatering at the well point must be much greater than the depth of the foundation pit, and the length of the long filter pipe is very long, that is, the water inlet section of the tube well is very long. Long, resulting in the process of foundation pit dewatering not only pumping and draining water within the range of foundation pit dewatering depth, but also extracting water resources from independent aquifers (which can be multiple) below the foundation pit dewatering depth. However, the impact of groundwater in independent aquifers (which can be multiple) below the precipitation depth of the foundation pit on the foundation pit engineering is almost non-existent. At the same time, due to the existence of the tube well, the groundwater in the multi-layer independent aquifer within the depth range of the tube well is penetrated. As we all know, the groundwater in the upper aquifer communicates with the atmosphere, and is greatly affected by human activities, and most of them have been polluted, and the pollution of the groundwater in the upper aquifer is relatively heavier. The polluted groundwater in the upper part will enter the lower aquifer along the tube well under its gravity, so that the originally pure groundwater in the lower part will also be polluted to varying degrees. Therefore, the current method of dewatering foundation pits has not only caused a waste of resources, but also increased the cost of the project, and more seriously, polluted the high-quality groundwater resources in the lower part.
发明内容 Contents of the invention
本发明的目的在于提供一种井点定位抽水管井,旨在解决(1)基坑垂直井点降水“疏不干”问题,即,常规垂直井点降水中,垂直井内水一抽即无,一停又有,开挖时仍有水,使基坑作业面泥泞,工人施工困难,影响施工进度,基坑侧壁渗水还会使边坡支护失效,产生流砂现象,土中细颗粒随水流在粗颗粒间隙中移动,使得土层被掏空,造成地面不均匀沉降,甚至导致基坑滑移、坍塌,造成人力物力损失的问题。(2)基坑降水深度以下独立含水层中水资源的保护问题。The object of the present invention is to provide a well point positioning pumping pipe well, aiming to solve (1) the problem of "drainage and non-drying" of the vertical well point dewatering of foundation pits, that is, in the conventional vertical well point dewatering, the water in the vertical well will disappear as soon as it is pumped, Once stopped, there will still be water during excavation, which will make the working surface of the foundation pit muddy, making it difficult for workers to construct, which will affect the construction progress. The water flow moves in the gaps of coarse particles, which makes the soil layer hollowed out, causing uneven ground settlement, and even causing the foundation pit to slip and collapse, resulting in the loss of manpower and material resources. (2) The protection of water resources in the independent aquifer below the precipitation depth of the foundation pit.
本发明的目的在于提供一种井点定位抽水管井,该管井包括无砂管井段、储水管井段:The object of the present invention is to provide a well point positioning pumping tube well, which includes a sand-free tube well section and a water storage tube well section:
位于基坑降水深度以下的首个隔水层某位置以上,用于集聚基坑降水深度范围内的含水层中水源的无砂管井段;Above a certain position of the first water-resisting layer below the dewatering depth of the foundation pit, it is a sand-free well section used to accumulate water sources in the aquifer within the dewatering depth of the foundation pit;
位于所述的基坑降水深度以下的首个隔水层某位置以下,与所述无砂管井段相连接,用于储存所述基坑降水深度范围内的含水层中水源的储水管井段。A water storage tube well section that is connected to the sand-free tube well section and is used to store water in the aquifer within the scope of the foundation pit dewatering depth. .
本发明的另一目的在于提供一种井点定位抽水方法,该方法包括:Another object of the present invention is to provide a well point location pumping method, the method comprising:
一种井点定位抽水方法,该方法包括:A well point positioning pumping method, the method comprising:
按地下水位面至储水管井段顶端之间的土层综合渗透系数、含水层厚度和降深确定井间距;The well spacing is determined according to the comprehensive permeability coefficient of the soil layer between the groundwater table and the top of the well section of the water storage pipe, the thickness of the aquifer and the drawdown;
基坑降水深度以下首个隔水层某位置往上采用无砂管井段;The first aquifer below the dewatering depth of the foundation pit is used to use a sand-free well section upwards from a certain position;
基坑降水深度以下首个隔水层某位置往下采用储水管井段;The water storage pipe well section is used downwards at a certain position of the first water-resisting layer below the dewatering depth of the foundation pit;
利用抽水设备定水位抽取储水管井段储存的水源。The water source stored in the well section of the water storage pipe is pumped by using the water pumping equipment to fix the water level.
本发明通过采用无砂管井段、储水管井段组成的降水管井,有效地集聚了基坑降水深度范围内含水层中的水源,利用抽水设备定水位抽取储水管井段储存的水源,解决了垂直井内水一抽即无,一停又有,开挖时仍有水,使基坑作业面泥泞,工人施工困难,影响施工进度,基坑侧壁渗水使边坡支护失效,产生流砂现象,土中细颗粒随水流在粗颗粒间隙中移动,使得土层被掏空,造成地面不均匀沉降,甚至导致基坑滑移、坍塌,造成人力物力损失问题。同时解决了不多抽水、抽降水不污染基坑降水深度以下的独立含水层中地下水源以及“疏不干”条件下的“疏不干”的难题。采用定水位自动抽水方法,将使抽水总时间大为缩短,大大降低基坑工程成本。在目前水资源日益匮乏、水环境与水资源日益受到重视的今天,具有明显的社会效益与经济效益。The present invention effectively gathers the water source in the aquifer within the range of the foundation pit dewatering depth by adopting the downwater tube well composed of the sand-free tube well section and the water storage tube well section, and uses the pumping equipment to fix the water level to extract the water source stored in the water storage tube well section, solving the problem of Once the water in the vertical well is pumped, there will be no water, and once it is stopped, there will still be water during excavation, which will make the working surface of the foundation pit muddy, making it difficult for workers to construct, which will affect the construction progress. Phenomenon, the fine particles in the soil move with the water flow in the gap between the coarse particles, causing the soil layer to be hollowed out, causing uneven ground settlement, and even causing the foundation pit to slip and collapse, resulting in the loss of manpower and material resources. At the same time, it solves the problem of "draining and not drying" under the condition of "not dredging and not drying" under the condition of not pumping much water and pumping precipitation without polluting the groundwater source in the independent aquifer below the precipitation depth of the foundation pit. Adopting the method of automatic water pumping at fixed water level will greatly shorten the total time of pumping water and greatly reduce the cost of foundation pit engineering. Today, when water resources are increasingly scarce and water environment and water resources are increasingly valued, it has obvious social and economic benefits.
附图说明 Description of drawings
图1是现有技术提供的“疏不干”含水层的结构示意图;Fig. 1 is the structural representation of " dredge not dry " aquifer that prior art provides;
图2是本发明提供的井点定位抽水管井的剖面结构示意图;Fig. 2 is the schematic cross-sectional structure diagram of the well point positioning pumping tube well provided by the present invention;
图3是本发明提供的井点定位抽水方法的流程图。Fig. 3 is a flow chart of the well point positioning pumping method provided by the present invention.
图中:1、无砂管井段;2、储水管井段;3、上部含水层;4、下部含水层;5、基坑;6、隔水层。In the figure: 1. Well section without sand tube; 2. Well section with water storage tube; 3. Upper aquifer; 4. Lower aquifer; 5. Foundation pit; 6. Water-resisting layer.
具体实施方式 Detailed ways
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
图2示出了本发明实施例提供的井点定位抽水管井的结构示意图。为了便于说明,仅仅示出了与本发明实施例相关的部分。Fig. 2 shows a schematic structural diagram of a well point positioning pumping tube well provided by an embodiment of the present invention. For ease of description, only parts related to the embodiments of the present invention are shown.
该管井包括:The tube well includes:
位于基坑以下的首个隔水层6的某位置以上,用于集聚基坑5降水深度范围内的上部含水层3中水源的无砂管井段1;Located above a certain position of the first water-resisting layer 6 below the foundation pit, the sand-free tube well section 1 is used to accumulate water source in the upper aquifer 3 within the depth range of the foundation pit 5;
位于基坑以下的首个隔水层6的某位置以下,与无砂管井段1相连接,用于储存上部含水层3中水源的储水管井段2。Below a certain position of the first water-resisting layer 6 below the foundation pit, it is connected with the sand-free tube well section 1 and is used for storing the water storage tube well section 2 of the water source in the upper aquifer 3 .
在本发明实施例中,储水管井段2为无砂管井段或钢管井段或实壁水泥管井段,当选用无砂管时,其外侧必须涂抹有水泥浆层。In the embodiment of the present invention, the well section 2 of the water storage pipe is a sand-free pipe well section or a steel pipe well section or a solid-wall cement pipe well section. When a sand-free pipe is selected, the outer side must be coated with a cement slurry layer.
此外,在本发明实施例中,还可以采用预制双壁管,或可称组合壁管(薄水泥砂浆实壁外层和无砂管内层两种组合而成的储水管)。双壁管在剖面上就是双层圆环,外层不透水,很薄,而内层相对很厚,可以透水,但整个这种组合双层壁管不透水。本发明专利所述的外侧涂有水泥浆层的无砂管实际上也属于这种双层壁管结构,只是其外层水泥浆层更薄,外层壁制作方法不同。当水压很大时,采用这种预制的双壁管会更好。In addition, in the embodiment of the present invention, prefabricated double-wall pipes can also be used, or composite wall pipes (a water storage pipe composed of a thin cement mortar solid wall outer layer and a sand-free inner pipe layer). The double-wall pipe is a double-layer ring in section. The outer layer is impermeable and very thin, while the inner layer is relatively thick and can be water-permeable, but the entire double-wall pipe of this combination is impermeable. The sand-free pipe coated with a cement slurry layer on the outside described in the patent of the present invention actually also belongs to this double-wall pipe structure, but the outer layer of cement slurry layer is thinner and the outer wall is made in a different way. When the water pressure is high, it is better to use this kind of prefabricated double wall pipe.
在本发明实施例中,储水管井段2外侧填充有止水材料层。In the embodiment of the present invention, the outer side of the well section 2 of the water storage pipe is filled with a water-stop material layer.
在本发明实施例中,储水管井段的管节连接处设有止水圈垫。基坑降水深度以下首个隔水层某位置的确定需考虑其下含水层水压的影响,应确保该含水层水不突涌通过无砂管井段进入储水管井段内。In the embodiment of the present invention, a water stop gasket is provided at the connection of the pipe joints of the well section of the water storage pipe. The determination of the position of the first aquifer below the dewatering depth of the foundation pit needs to consider the influence of the water pressure of the aquifer below it, and it should be ensured that the water in the aquifer does not rush into the water storage tube well section through the sand-free well section.
在本发明实施例中,基坑降水深度以下首个隔水层某位置的确定标准是:In the embodiment of the present invention, the criteria for determining a certain position of the first water-resisting layer below the foundation pit precipitation depth are:
根据含水层水压的大小,该位置确保含水层水不突涌通过无砂管井段进入储水管井段内。According to the size of the water pressure of the aquifer, this position ensures that the water in the aquifer does not rush into the well section of the water storage tube through the well section without sand tube.
图3示出了本发明实施例提供的井点定位抽水方法的实现流程。Fig. 3 shows the implementation flow of the well point positioning pumping method provided by the embodiment of the present invention.
一种井点定位抽水方法,该方法包括:A well point positioning pumping method, the method comprising:
在步骤S301中,按地下水位面至储水管井段顶端之间的土层(或含水层)的综合渗透系数、含水层厚度和降深确定井间距;In step S301, the well spacing is determined according to the comprehensive permeability coefficient, aquifer thickness and drawdown of the soil layer (or aquifer) between the groundwater table and the top of the well section of the water storage pipe;
在步骤S302中,基坑降水深度以下的首个隔水层6的某位置往上采用无砂管井段1;In step S302, a sand-free well section 1 is used upwards at a certain position of the first water-resisting layer 6 below the dewatering depth of the foundation pit;
在步骤S303中,基坑降水深度以下的首个隔水层6的某位置往下采用储水管井段2;In step S303, the water storage pipe well section 2 is used downward at a certain position of the first water-resisting layer 6 below the dewatering depth of the foundation pit;
在步骤S304中,利用抽水设备定水位抽取储水管井段2储存的水源。In step S304, the water source stored in the well section 2 of the water storage pipe is extracted by using the water pumping equipment to fix the water level.
在本发明实施例中,储水管井段2为外侧涂抹有水泥浆层的无砂管井段。In the embodiment of the present invention, the water storage tube well section 2 is a sand-free tube well section coated with a cement slurry layer on the outside.
在本发明实施例中,储水管井段2外侧采用止水材料层填充。In the embodiment of the present invention, the outside of the well section 2 of the water storage pipe is filled with a water-stop material layer.
在本发明实施例中,基坑降水深度以下的首个隔水层某位置通过确保该含水层水不渗流不突涌(通过无砂管井段)进入储水管井段内的原则确定;In the embodiment of the present invention, a certain position of the first aquifer below the dewatering depth of the foundation pit is determined by the principle of ensuring that the water in the aquifer does not seep and surge (through the well section without sand tube) into the well section of the water storage pipe;
在本发明实施例中,储水管井段是由多节储水管连接而成,管节连接处设有止水圈垫;In the embodiment of the present invention, the well section of the water storage pipe is formed by connecting multiple sections of water storage pipes, and a water stop gasket is provided at the junction of the pipe sections;
在本发明实施例中,无砂管井段1的外侧采用级配砂填充。In the embodiment of the present invention, the outside of the sand-free tube well section 1 is filled with graded sand.
在本发明实施例中,利用抽水设备定水位抽取储水管井段2储存的水源的实现方法为:In the embodiment of the present invention, the implementation method of using the pumping equipment to fix the water level to extract the water source stored in the well section 2 of the water storage pipe is as follows:
可采用简易自动控制装置自动控制抽水泵的工作状态,实现抽水泵定水位抽取储水管井段2储存的水源。A simple automatic control device can be used to automatically control the working state of the water pump, so that the water source stored in the well section 2 of the water storage pipe can be extracted by the water pump at a fixed water level.
下面结合附图及具体实施例对本发明的应用原理作进一步描述。The application principle of the present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
井点定位抽水方法,即按地下水位面至储水管井段顶端之间的土层(或含水层)的综合渗透系数、含水层厚度和降深确定井间距,在基坑降水深度以下的首个隔水层6的某位置往上采用无砂管井段1(又称砾石滤水管),往下则采用储水管井段2,组合成降水管井。无砂管井段1外侧采用级配砂填充,地下水通过级配砂、无砂管进入到管井内。储水管井段2可采用外侧涂抹水泥浆层的无砂管井段,其外侧采用止水材料填充,阻止了下部含水层4的水进入降水管井内,这段管井实际上就变为储水库,储存上部含水层3中并渗入到降水管井内的水。这段储水管井段2的长度设计主要依据水量的多少和抽水设备的抽水能力,以能保证在一次抽水后不透水井管段内有一定的储存地下水空间为基准。Well point positioning pumping method, that is, the well spacing is determined according to the comprehensive permeability coefficient, aquifer thickness and drawdown of the soil layer (or aquifer) between the groundwater table and the top of the water storage pipe well section. A certain position of the aquifer 6 adopts a sand-free tube well section 1 (also known as a gravel filter pipe) upwards, and a water storage tube well section 2 is used downward to form a downwater tube well. The outside of the sand-free tube well section 1 is filled with graded sand, and the groundwater enters the tube well through the graded sand and the sand-free tube. The water storage tube well section 2 can be a sand-free tube well section coated with a cement slurry layer on the outside, and its outside is filled with water-stopping materials to prevent the water in the lower aquifer 4 from entering the downfall tube well. This section of the tube well actually becomes a water storage reservoir. Water stored in the upper aquifer 3 and infiltrated into the downcomer wells. The length design of this section of water storage pipe well section 2 is mainly based on the amount of water and the pumping capacity of the pumping equipment, so as to ensure that there is a certain storage groundwater space in the impermeable well pipe section after a pumping.
因为“疏不干”条件下,后期水流量有限,一抽即无,不抽又有,主要是一停泵,泵管中的水回流所致。假如回流的水基本上占据了储存水管段的空间,则管井外的地下水无法再进入到管井内,基坑的地下水位就无法进一步下降,因此无法疏排基坑降水深度范围内的地下水。如果储水管井段2段过短,扣除停泵水回流占据的空间后,剩余的空间(称为有效空间)不多,则要停启泵频繁,既费电又耗损抽水设备,降水效果差;如果储水管井段2段过长,有效空间变大了,停启泵时间间隔也大,对抽水有利,但因降水管井加深将带来管井成本增大,深孔成孔困难,以及费用的增大。所以,要合理设计储水管井段2段的长度。Because under the condition of "draining and not drying", the water flow in the later period is limited, and there will be no water when it is pumped, and there will be water when it is not pumped. This is mainly caused by the water in the pump pipe returning when the pump is stopped. If the returned water basically occupies the space of the storage pipe section, the groundwater outside the tube well can no longer enter the tube well, and the groundwater level of the foundation pit cannot be further reduced, so the groundwater within the depth of the foundation pit cannot be drained. If the second section of the well section of the water storage pipe is too short, the remaining space (called the effective space) is not much after deducting the space occupied by the backflow of the pumped water, and the pump must be stopped and started frequently, which consumes electricity and pumping equipment, and the precipitation effect is poor. ; If the second section of the water storage tube well section is too long, the effective space becomes larger, and the time interval between stopping and starting the pump is also large, which is beneficial to pumping water, but the deepening of the downwater tube well will increase the cost of the tube well, make it difficult to form a deep hole, and cost increase. Therefore, the length of the second section of the water storage pipe well section should be reasonably designed.
本发明实施例通过采用无砂管井段1、储水管井段2组成的降水管井,有效地集聚了基坑5所在的上部含水层3中水源,利用抽水设备(抽水泵)定水位抽取储水管井段2储存的水源,解决了垂直井内水一抽即无,一停又有,开挖时仍有水,使基坑5作业面泥泞,工人施工困难,影响施工进度,基坑5侧壁渗水使边坡支护失效,产生流砂现象,土中细颗粒随水流在粗颗粒间隙中移动,使得土层被掏空,造成地面不均匀沉降,导致基坑5滑移、坍塌,造成人力物力损失问题。同时只抽取对基坑工程有影响的地下水,大大缩短了抽水总时间,降低了工程成本,而且由于上部含水层中地下水与基坑以下独立含水层中地下水相隔离,受污染的上部含水层地下水不会对下部地下水质造成污染。这在目前水资源日益匮乏、水环境与水资源日益受到重视的今天,具有明显的社会效益与经济效益。In the embodiment of the present invention, the water source in the upper aquifer 3 where the foundation pit 5 is located is effectively collected by using a downwater tube well composed of a sand-free tube well section 1 and a water storage tube well section 2, and the water storage pipe is extracted by using a pumping device (pump) to fix the water level. The water source stored in the well section 2 solves the problem that the water in the vertical well disappears when it is pumped, and there is still water when it is stopped, and there is still water during excavation, which makes the working surface of the foundation pit 5 muddy, and the construction is difficult for workers, which affects the construction progress. The side wall of the foundation pit 5 Water seepage makes the slope support invalid, resulting in quicksand phenomenon, and the fine particles in the soil move with the water flow in the gaps between the coarse particles, which makes the soil layer hollowed out, resulting in uneven ground settlement, resulting in the foundation pit 5 slipping and collapsing, resulting in loss of manpower and material resources question. At the same time, only the groundwater that has an impact on the foundation pit project is extracted, which greatly shortens the total pumping time and reduces the project cost, and because the groundwater in the upper aquifer is isolated from the groundwater in the independent aquifer below the foundation pit, the groundwater in the upper aquifer that is polluted It will not pollute the lower groundwater quality. This has obvious social and economic benefits in today's day when water resources are increasingly scarce and water environment and water resources are increasingly valued.
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention should be included in the protection of the present invention. within range.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110224948.1A CN102383437B (en) | 2011-08-08 | 2011-08-08 | Well point positioned pumping tubular well and well point positioned pumping method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110224948.1A CN102383437B (en) | 2011-08-08 | 2011-08-08 | Well point positioned pumping tubular well and well point positioned pumping method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102383437A CN102383437A (en) | 2012-03-21 |
| CN102383437B true CN102383437B (en) | 2015-05-20 |
Family
ID=45823238
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201110224948.1A Expired - Fee Related CN102383437B (en) | 2011-08-08 | 2011-08-08 | Well point positioned pumping tubular well and well point positioned pumping method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102383437B (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104005418A (en) * | 2014-06-17 | 2014-08-27 | 中铁城建集团第二工程有限公司 | Method for rapidly treating underground piping |
| CN105804104B (en) * | 2015-03-13 | 2017-08-15 | 河北建设集团卓诚路桥工程有限公司 | A kind of construction method of well-points dewatering |
| CN105735330B (en) * | 2015-03-13 | 2017-11-14 | 苏建林 | A kind of construction method of well-points dewatering |
| CN104831742B (en) * | 2015-04-15 | 2016-08-24 | 中国建筑第八工程局有限公司 | The Method on Dewatering of Foundation Pit that adjacent two layers low pressure water layer is not cut off by water barrier |
| CN105780793B (en) * | 2016-04-06 | 2017-07-04 | 中建交通建设集团有限公司 | A kind of high artesian stratum Foundation Pit Pouring emergency processing method |
| CN110847200B (en) * | 2019-11-14 | 2024-02-06 | 河南理工大学 | Dewatering and draining structure and dewatering and draining method for horizontal sand well of annular foundation pit |
| CN111719573A (en) * | 2020-06-23 | 2020-09-29 | 上海长凯岩土工程有限公司 | Foundation ditch emergency precipitation gas monitoring integral installation structure in huge thick rich water aquifer |
| CN114876411B (en) * | 2022-05-06 | 2023-10-24 | 陕西省水工环地质调查中心 | Anti-floating decompression layout mechanism and layout method for underground engineering curtain radiation well |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3338909B2 (en) * | 1994-01-19 | 2002-10-28 | 清水建設株式会社 | Layered pumping well |
| JP3567411B2 (en) * | 1997-03-19 | 2004-09-22 | 清水建設株式会社 | Pumping equipment |
| CN100480475C (en) * | 2007-06-04 | 2009-04-22 | 上海地矿工程勘察有限公司 | Controllable one-well lamina precipitation construction method |
| CN100516380C (en) * | 2007-06-07 | 2009-07-22 | 上海交通大学 | Method for lowering water by combining phreatic water in footing groove with artesian aquifer - well stratifications |
| CN101363228A (en) * | 2008-05-23 | 2009-02-11 | 上海广联建设发展有限公司 | Tube well for simultaneously dewatering and decompressing and technology thereof |
-
2011
- 2011-08-08 CN CN201110224948.1A patent/CN102383437B/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| CN102383437A (en) | 2012-03-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102383437B (en) | Well point positioned pumping tubular well and well point positioned pumping method | |
| CN102418347B (en) | Drainage construction method for blind drain and sump wells in deep foundation pit | |
| CN103046565B (en) | Draining method for ultra-deep batholith deep foundation pit | |
| CN103510528A (en) | Blind trench water discharging structure used for underground structure up-floating prevention | |
| CN205152968U (en) | Precipitation tubular well structure | |
| CN104480974A (en) | Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond | |
| CN114718101B (en) | A seepage cut-off structure of a tailings pond with a seepage cut-off wall and a precipitation well and a construction method thereof | |
| CN103088836A (en) | Sedimentation control method for pumping water and performing reinjection in well casing simultaneously | |
| CN102535488A (en) | Waterproof construction method and system for bottom plate of high-water-level basement | |
| CN105625445A (en) | Foundation pit dewatering method in coastal sandy soil region | |
| CN111827328A (en) | Subway deep foundation pit well point dewatering system and construction method thereof | |
| CN201567582U (en) | A water-saving device for foundation pit dewatering | |
| CN206368379U (en) | A kind of systems stabilisation of buried pond anti-floating | |
| CN109577380B (en) | Construction method for basement bottom plate water seepage under karst landform condition | |
| CN105484277A (en) | Component for tubular well precipitation construction in elevator foundation pit or sump and construction method | |
| CN112554215B (en) | Double-sleeve artesian deep well precipitation construction method and structure for muddy silty clay with silty soil geology | |
| CN205205844U (en) | Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit | |
| CN107794954A (en) | A kind of anti-floating sluicing pressure relief | |
| CN204551510U (en) | A kind of filled-up ground catchments pressure reduction well drop and drainage structure | |
| CN115992525A (en) | Precipitation structure and precipitation method of deep foundation pit penetrating through pebble mudstone interface | |
| CN202440826U (en) | Waterproof system for high-water level basement foundation slabs | |
| CN205444216U (en) | Depth well foundation pit dewatering system on compound stratum of large -scale foundation ditch | |
| CN204298837U (en) | Bright, dark drainage system | |
| CN105714771B (en) | Construction method of manual hole digging pile | |
| CN210712967U (en) | Impervious anti structure that floats of basement |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150520 Termination date: 20200808 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |