CN107780436B - Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment - Google Patents
Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment Download PDFInfo
- Publication number
- CN107780436B CN107780436B CN201710884507.1A CN201710884507A CN107780436B CN 107780436 B CN107780436 B CN 107780436B CN 201710884507 A CN201710884507 A CN 201710884507A CN 107780436 B CN107780436 B CN 107780436B
- Authority
- CN
- China
- Prior art keywords
- drainage arrangement
- interlayer
- tgxg
- connector
- interlayer drainage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000013049 sediment Substances 0.000 title claims abstract description 31
- 238000010276 construction Methods 0.000 title claims abstract description 11
- 239000011229 interlayer Substances 0.000 claims abstract description 38
- 239000000945 filler Substances 0.000 claims abstract description 20
- 239000010410 layer Substances 0.000 claims abstract description 10
- 239000011178 precast concrete Substances 0.000 claims abstract description 9
- 239000004746 geotextile Substances 0.000 claims description 7
- 239000002689 soil Substances 0.000 claims description 7
- 238000009412 basement excavation Methods 0.000 claims description 3
- 239000004567 concrete Substances 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 238000007596 consolidation process Methods 0.000 abstract description 7
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 7
- 238000004064 recycling Methods 0.000 abstract description 3
- -1 TGXG Substances 0.000 abstract description 2
- 230000007613 environmental effect Effects 0.000 abstract 1
- 239000011148 porous material Substances 0.000 abstract 1
- 239000002699 waste material Substances 0.000 abstract 1
- 238000007599 discharging Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 239000000835 fiber Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000001133 acceleration Effects 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 230000034994 death Effects 0.000 description 1
- 231100000517 death Toxicity 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000012279 drainage procedure Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 230000008929 regeneration Effects 0.000 description 1
- 238000011069 regeneration method Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0225—Retaining or protecting walls comprising retention means in the backfill
- E02D29/0241—Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
- Retaining Walls (AREA)
Abstract
The present invention discloses a kind of Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment, which mainly includes dregs filler, TGXG, precast concrete facade panel, interlayer drainage arrangement, drainpipe;To guarantee that TGXG to the restraint performance of dregs filler, is laid with interlayer drainage arrangement on geogrids layer top, water is pooled in drainpipe unified discharge, can effectively reduce the pore water pressure of filler by interlayer drainage arrangement;The reinforced earth bulkhead consolidation rate is fast, mechanics quality stable, construction time are short, at low cost, be conducive to environmental protection, realizes the recycling of building waste to greatest extent.
Description
Technical field
The invention belongs to reinforced earth technology field, in particular to a kind of Geogrid Reinforced Earth Retaining Wall based on architecture sediment
Structure and its construction method.
Background technique
Currently, with the acceleration of urbanization process, construction industry is also fast-developing simultaneously, the construction of road, foundation pit excavation,
The quantity for the architecture sediment that the construction etc. of subway generates every year is especially huge.Due to containing more cohesive soil in architecture sediment,
It will lead to discharging consolidation difficulty, so it can neither be used for recycled aggregate, regeneration filler can not be used for.The processing of dregs at present
Mode is essentially filled and is stacked, to can cause great harm to environment and will increase subsequent processing cost.2015
Landslide accident occurs for the red col dregs receiving field in December, Shenzhen light new district, causes more people's injures and deaths, direct economic loss reaches
8.81 hundred million yuan, the main reason for current accident occurs: being on the one hand because architecture sediment accumulate it is excessively high, be on the other hand then because
For the water in architecture sediment is not discharged quickly.
At present for architecture sediment still without good processing method, a large amount of stack is easy to generate disaster, therefore,
Solve architecture sediment Quick drainage, solidification problem is the key that architecture sediment recycling.
Summary of the invention
The present invention is an approach of architecture sediment recycling, mainly solves the problems, such as the discharging consolidation of architecture sediment, is realized
Architecture sediment is used for the technology of filler.A kind of Geogrid Reinforced Earth Retaining Wall knot based on architecture sediment has been invented on this basis
Structure and its construction method.Accelerate dregs consolidation by being laid with interlayer drainage arrangement on TGXG top, it will be in architecture sediment
Water is collected in drainpipe by interlayer drainage arrangement and is discharged, and constraint of the reinforcement material to the soil body is improved, and solves architecture sediment money
The problem of source.
The present invention relates to a kind of Geogrid Reinforced Earth Retaining Wall structure and its construction method based on architecture sediment, it is main
By architecture sediment filler, TGXG, precast concrete facade panel, vertical drainage pipe, horizontal drain pipe, interlayer drainage arrangement, row
Ditch, reinforced earth bulkhead strip footing, sand-gravel cushion, connector composition.
Preferably, the interlayer drainage arrangement described in, including geomembrane, drain bar, long fine geotextiles, reinforced mesh,
Be characterized in that, geomembrane package reinforced mesh is located at bottom, and drain bar is located at middle part, and top is then long fibre geotextiles, with company
The interface for connecing device, is closed using pitch, and interlayer drainage arrangement is pre-buried by reinforced mesh and precast concrete facade panel
Part is welded and fixed.
Preferably, the interlayer drainage arrangement described in is located at TGXG top 5cm between 15cm, according to the gradient
2% -5% is laid with, and is connected between interlayer drainage arrangement and vertical drainage pipe by connector, connector and vertical drainage pipe it
Between by sleeve connection, one end of interlayer drainage arrangement is placed in connector, and the ply stacking angle of connector and interlayer drain
Device is consistent, and vertical drainage pipe and horizontal drain pipe pass through sleeve connection.
Draining mechanism of the invention is summarized as follows:
Architecture sediment filler cannot be used for the main reason for reinforced earth filler: due to containing a large amount of viscosity in architecture sediment
Soil causes discharging consolidation difficult, influences whether the interface friction performance between reinforcement material and architecture sediment filler.In order to solve
The technical problem, the present invention place interlayer drainage arrangement, vertical drainage pipe, horizontal drain pipe in reinforced earth bulkhead.Interlayer row
Water installations are made of geomembrane, drain bar, long fine geotextiles, reinforced mesh, wherein long fibre geotextiles are located at top layer, are mainly
The loss of the filler particles in drainage procedure is prevented, geomembrane package reinforced mesh is located at bottom, primarily to reduction layer
Between drainage arrangement deformation quantity in compacting process, the water energy in dregs filler is smoothly discharged enough, accelerates the consolidation of filler.Interlayer
Drainage arrangement is placed on TGXG top 5cm between 15cm, is laid with according to the gradient 2% -5%, and utilizes connector
Interlayer drainage arrangement and vertical drainage pipe are connected as an entirety, the water that interlayer drainage arrangement is collected passes through connector stream
Enter in vertical drainage pipe, then gutter is flowed by horizontal drain pipe, to realize the discharging consolidation process of architecture sediment filler.
Detailed description of the invention
Fig. 1 is that reinforced earth bulkhead backfills schematic diagram;
Fig. 2 is connector detail drawing;
Fig. 3 is vertical drainage pipe detail drawing;
Fig. 4 is interlayer drainage arrangement detail drawing;
Fig. 5 is the connection top view of interlayer drainage arrangement and vertical drainage plate;
Fig. 6 is the connection front view of interlayer drainage arrangement and vertical drainage plate;
Fig. 7 is the connection detail drawing of precast concrete facade panel and interlayer drainage arrangement;
Fig. 8 is connector A-A sectional view;
In figure: 1-architecture sediment filler, 2-TGXG, 3-precast concrete facade panels, 4-vertical drainage pipes, 5-
Horizontal drain pipe, 6-interlayer drainage arrangements, 7-gutters, 8-reinforced earth bulkhead strip footings, 9-sand-gravel cushions, 10-
Connector, 11-12-drain bars of geomembrane, 13-long fine geotextiles, 14-reinforced mesh, 15-sleeves, 16-foundation soils,
17-built-in fittings.
Specific embodiment
With reference to embodiment and attached drawing, the present invention is described in further detail:
One, earth's surface sundries is removed, ground excavation is carried out, substrate is subjected to grinding compacting, on the ground after smooth compacting
It is laid with sand-gravel cushion (9), sand-gravel cushion (9) should be more than 1m or more on the outside of reinforced earth bulkhead strip footing (9), and should
The position of reserved steel bar concrete continuous footing (8) and gutter (7) is poured at the position reserved on sand-gravel cushion (9)
Build reinforced concrete strip foundation (8) and gutter (7).
Two, horizontal drain pipe (5) and first layer vertical drainage pipe (4) are installed on sand-gravel cushion (9), utilize sleeve
(15) first layer vertical drainage pipe (4) and horizontal drain pipe (5) are connected into an entirety.
Three, it fills architecture sediment filler (1), is compacted architecture sediment filler (1), and adjust horizontal drain pipe (5) and first
The position of layer vertical drainage pipe (4) is laid with TGXG (2) until first layer TGXG (2) paving location, in distance soil
The partial size of used architecture sediment filler (1) is no more than 15cm within work grid (2) surface 5cm.
Four, within the top 5cm to 15cm of TGXG (2), interlayer drainage arrangement is laid with according to the gradient 2% -5%
(6), one end of interlayer drainage arrangement (6) is placed in connector (10), the paving of connector (10) and interlayer drainage arrangement (6)
Set direction is consistent, in the interface of interlayer drainage arrangement (6) and connector (10), is closed using pitch, connector (10)
Got up with vertical drainage pipe (4) by sleeve connection, then install precast concrete facade panel (3), by TGXG (2) with it is prefabricated
Concrete slab (3) is connected using pitman, while interlayer drainage arrangement (6) being mixed by reinforced mesh (14) with prefabricated
The built-in fitting (17) of solidifying soil panel (3) is welded and fixed.It repeats the above steps until retaining wall fills specified altitude assignment.
Claims (2)
1. a kind of Geogrid Reinforced Earth Retaining Wall based on architecture sediment, comprising: architecture sediment filler (1), TGXG (2),
Precast concrete facade panel (3), vertical drainage pipe (4), horizontal drain pipe (5), interlayer drainage arrangement (6), gutter (7), reinforcement
Native barricade strip footing (8), sand-gravel cushion (9), connector (10);It is characterized in that, the interlayer drainage arrangement (6) described in it
It include: geomembrane (11), drain bar (12), long fine geotextiles (13), reinforced mesh (14), wherein geomembrane (11) wraps up reinforcing bar
Mesh sheet (14) is located at bottom, and drain bar (12) is located at middle part, and top is then long fine geotextiles (13), in interlayer drainage arrangement (6)
It with the interface of connector (10), is closed using pitch, interlayer drainage arrangement (6) passes through reinforced mesh (14) and prefabricated mixed
The built-in fitting (17) of solidifying soil panel (3) is welded and fixed;Interlayer drainage arrangement (6) be located at TGXG (2) top 5cm to 15cm it
Between, and having certain slope laying, range of grade 2% -5% is high outside and low outside, and along wall length direction etc. in same layer
Spacing distribution, connect between interlayer drainage arrangement (6) and vertical drainage pipe (4) by connector (10), connector (10) with erect
It is connected to sleeve (15) are passed through between drainpipe (4), one end of interlayer drainage arrangement (6) is placed in connector (10), and even
It is consistent with the laying direction of interlayer drainage arrangement (6) to connect device (10), vertical drainage pipe (4) and horizontal drain pipe (5) pass through sleeve
(15) it connects.
2. a kind of construction method of reinforced earth bulkhead as described in claim 1, it is characterised in that: excavation pit first is laid with
Sand-gravel cushion (9) is simultaneously compacted, and the position of reserved reinforced earth bulkhead strip footing (8) and gutter (7), in sand-gravel cushion
(9) reinforced earth bulkhead strip footing (8) and gutter (7) are poured at the position reserved on, installation horizontal drain pipe (5), the
One layer of vertical drainage pipe (4), fills architecture sediment filler (1), is compacted architecture sediment filler (1), until first layer TGXG
Paving location is laid with TGXG (2), in TGXG (2) top 5cm between 15cm, is laid with according to the gradient 2% -5%
Interlayer drainage arrangement (6) is connect with vertical drainage pipe (4) by connector (10) by interlayer drainage arrangement (6), and then installation is pre-
TGXG (2) is connect by concrete slab (3) processed with precast concrete facade panel (3), and will be in interlayer drainage arrangement (6)
Reinforced mesh (14) and precast concrete facade panel (3) built-in fitting (17) weld, repeat the above steps until retaining wall fill
To specified altitude assignment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710884507.1A CN107780436B (en) | 2017-09-26 | 2017-09-26 | Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710884507.1A CN107780436B (en) | 2017-09-26 | 2017-09-26 | Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107780436A CN107780436A (en) | 2018-03-09 |
CN107780436B true CN107780436B (en) | 2019-05-07 |
Family
ID=61433779
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710884507.1A Expired - Fee Related CN107780436B (en) | 2017-09-26 | 2017-09-26 | Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107780436B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108547306A (en) * | 2018-03-12 | 2018-09-18 | 江苏建筑职业技术学院 | A kind of building waste block stone does the construction method of bank protection |
CN110374133A (en) * | 2019-06-20 | 2019-10-25 | 浙江大学 | It is a kind of to wrap up in face earth-retaining wall construction method suitable for sand soil |
CN110424449B (en) * | 2019-07-16 | 2021-06-15 | 河海大学 | Microorganism control method for long-term stability of reinforced retaining wall |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6663323B1 (en) * | 2002-11-18 | 2003-12-16 | Mark A. Boys | Retaining wall block and drainage system |
CN202202339U (en) * | 2011-08-25 | 2012-04-25 | 中国电力工程顾问集团西南电力设计院 | Geogrid reinforced soil retaining wall of concrete module |
CN103850262B (en) * | 2012-11-29 | 2016-12-21 | 中国二十冶集团有限公司 | Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile |
CN105714759B (en) * | 2016-03-09 | 2018-04-20 | 广东安元矿业勘察设计有限公司 | The row that liquefaction collapse is taken precautions against in urban dregs blends reinforcement means |
CN105970909B (en) * | 2016-06-01 | 2018-06-15 | 上海建研地基基础工程有限公司 | Well point plastic strip vacuum preloading seepage consolidation joint precipitating, pre-pressing dynamic consolidation method |
-
2017
- 2017-09-26 CN CN201710884507.1A patent/CN107780436B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN107780436A (en) | 2018-03-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104480963B (en) | The constructional method of a kind of precast module type panel geo-grid reinforced tailing sand barricade | |
CN106522037B (en) | Side broad way based structures based on existing railway roadbed and its construction method | |
CN107780436B (en) | Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment | |
CN203393530U (en) | Anti-floating lightweight high-fill embankment structure | |
CN204370473U (en) | Precast module type panel Fill Reinforced With Geogrids CHARACTERISTICS OF TAILINGS SAND barricade | |
US11952728B2 (en) | Road structure reconstructed from large-scale independent underground garage and construction method thereof | |
CN204570720U (en) | A kind of widening of subgrade culvert foundation | |
CN106836034B (en) | High-fill cover plate culvert flexible load shedding system and construction method | |
CN219410355U (en) | Flexible side-width structure of high-fill embankment of existing railway | |
CN110805049B (en) | Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure | |
CN209603112U (en) | Shallow karst cave processing structure that buries | |
CN117127642A (en) | Fluidized solidified soil bearing platform structure and manufacturing method | |
CN212128696U (en) | Road bridge links up mixed light dirt road bed structure of section bubble | |
CN215165533U (en) | Anchoring structure for side slope of solid waste landfill | |
CN108677999A (en) | A kind of Muddy Bottoms packeted soil barrier wall structure and construction method | |
CN211113579U (en) | Heavy-load ground foundation structure for seepage-proofing area of soft foundation | |
CN210458817U (en) | Prevent road settlement's foundation structure | |
CN209482302U (en) | Sanitary filling field laying assembled anchor structure | |
CN113700111A (en) | Construction method of rainwater permeation, drainage and reuse integrated system | |
CN111979983A (en) | Sand geological water retaining dam solidified by using construction waste | |
CN215051733U (en) | Construction access road structure in deep soft soil area | |
CN110593242A (en) | Heavy-load ground foundation structure of seepage-proofing area of soft foundation and processing method thereof | |
CN112030870B (en) | Building rubbish reinforcing river levee under sandy soil geology | |
CN215165696U (en) | Tunnel portal side slope supporting structure | |
CN217869782U (en) | Concrete permeates water with pouring basic unit's structure that permeates water |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190507 |