CN107780436B - Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment - Google Patents

Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment Download PDF

Info

Publication number
CN107780436B
CN107780436B CN201710884507.1A CN201710884507A CN107780436B CN 107780436 B CN107780436 B CN 107780436B CN 201710884507 A CN201710884507 A CN 201710884507A CN 107780436 B CN107780436 B CN 107780436B
Authority
CN
China
Prior art keywords
drainage arrangement
interlayer
tgxg
connector
interlayer drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710884507.1A
Other languages
Chinese (zh)
Other versions
CN107780436A (en
Inventor
杜运兴
刘倍宏
周芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CN201710884507.1A priority Critical patent/CN107780436B/en
Publication of CN107780436A publication Critical patent/CN107780436A/en
Application granted granted Critical
Publication of CN107780436B publication Critical patent/CN107780436B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)
  • Retaining Walls (AREA)

Abstract

The present invention discloses a kind of Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment, which mainly includes dregs filler, TGXG, precast concrete facade panel, interlayer drainage arrangement, drainpipe;To guarantee that TGXG to the restraint performance of dregs filler, is laid with interlayer drainage arrangement on geogrids layer top, water is pooled in drainpipe unified discharge, can effectively reduce the pore water pressure of filler by interlayer drainage arrangement;The reinforced earth bulkhead consolidation rate is fast, mechanics quality stable, construction time are short, at low cost, be conducive to environmental protection, realizes the recycling of building waste to greatest extent.

Description

Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment
Technical field
The invention belongs to reinforced earth technology field, in particular to a kind of Geogrid Reinforced Earth Retaining Wall based on architecture sediment Structure and its construction method.
Background technique
Currently, with the acceleration of urbanization process, construction industry is also fast-developing simultaneously, the construction of road, foundation pit excavation, The quantity for the architecture sediment that the construction etc. of subway generates every year is especially huge.Due to containing more cohesive soil in architecture sediment, It will lead to discharging consolidation difficulty, so it can neither be used for recycled aggregate, regeneration filler can not be used for.The processing of dregs at present Mode is essentially filled and is stacked, to can cause great harm to environment and will increase subsequent processing cost.2015 Landslide accident occurs for the red col dregs receiving field in December, Shenzhen light new district, causes more people's injures and deaths, direct economic loss reaches 8.81 hundred million yuan, the main reason for current accident occurs: being on the one hand because architecture sediment accumulate it is excessively high, be on the other hand then because For the water in architecture sediment is not discharged quickly.
At present for architecture sediment still without good processing method, a large amount of stack is easy to generate disaster, therefore, Solve architecture sediment Quick drainage, solidification problem is the key that architecture sediment recycling.
Summary of the invention
The present invention is an approach of architecture sediment recycling, mainly solves the problems, such as the discharging consolidation of architecture sediment, is realized Architecture sediment is used for the technology of filler.A kind of Geogrid Reinforced Earth Retaining Wall knot based on architecture sediment has been invented on this basis Structure and its construction method.Accelerate dregs consolidation by being laid with interlayer drainage arrangement on TGXG top, it will be in architecture sediment Water is collected in drainpipe by interlayer drainage arrangement and is discharged, and constraint of the reinforcement material to the soil body is improved, and solves architecture sediment money The problem of source.
The present invention relates to a kind of Geogrid Reinforced Earth Retaining Wall structure and its construction method based on architecture sediment, it is main By architecture sediment filler, TGXG, precast concrete facade panel, vertical drainage pipe, horizontal drain pipe, interlayer drainage arrangement, row Ditch, reinforced earth bulkhead strip footing, sand-gravel cushion, connector composition.
Preferably, the interlayer drainage arrangement described in, including geomembrane, drain bar, long fine geotextiles, reinforced mesh, Be characterized in that, geomembrane package reinforced mesh is located at bottom, and drain bar is located at middle part, and top is then long fibre geotextiles, with company The interface for connecing device, is closed using pitch, and interlayer drainage arrangement is pre-buried by reinforced mesh and precast concrete facade panel Part is welded and fixed.
Preferably, the interlayer drainage arrangement described in is located at TGXG top 5cm between 15cm, according to the gradient 2% -5% is laid with, and is connected between interlayer drainage arrangement and vertical drainage pipe by connector, connector and vertical drainage pipe it Between by sleeve connection, one end of interlayer drainage arrangement is placed in connector, and the ply stacking angle of connector and interlayer drain Device is consistent, and vertical drainage pipe and horizontal drain pipe pass through sleeve connection.
Draining mechanism of the invention is summarized as follows:
Architecture sediment filler cannot be used for the main reason for reinforced earth filler: due to containing a large amount of viscosity in architecture sediment Soil causes discharging consolidation difficult, influences whether the interface friction performance between reinforcement material and architecture sediment filler.In order to solve The technical problem, the present invention place interlayer drainage arrangement, vertical drainage pipe, horizontal drain pipe in reinforced earth bulkhead.Interlayer row Water installations are made of geomembrane, drain bar, long fine geotextiles, reinforced mesh, wherein long fibre geotextiles are located at top layer, are mainly The loss of the filler particles in drainage procedure is prevented, geomembrane package reinforced mesh is located at bottom, primarily to reduction layer Between drainage arrangement deformation quantity in compacting process, the water energy in dregs filler is smoothly discharged enough, accelerates the consolidation of filler.Interlayer Drainage arrangement is placed on TGXG top 5cm between 15cm, is laid with according to the gradient 2% -5%, and utilizes connector Interlayer drainage arrangement and vertical drainage pipe are connected as an entirety, the water that interlayer drainage arrangement is collected passes through connector stream Enter in vertical drainage pipe, then gutter is flowed by horizontal drain pipe, to realize the discharging consolidation process of architecture sediment filler.
Detailed description of the invention
Fig. 1 is that reinforced earth bulkhead backfills schematic diagram;
Fig. 2 is connector detail drawing;
Fig. 3 is vertical drainage pipe detail drawing;
Fig. 4 is interlayer drainage arrangement detail drawing;
Fig. 5 is the connection top view of interlayer drainage arrangement and vertical drainage plate;
Fig. 6 is the connection front view of interlayer drainage arrangement and vertical drainage plate;
Fig. 7 is the connection detail drawing of precast concrete facade panel and interlayer drainage arrangement;
Fig. 8 is connector A-A sectional view;
In figure: 1-architecture sediment filler, 2-TGXG, 3-precast concrete facade panels, 4-vertical drainage pipes, 5- Horizontal drain pipe, 6-interlayer drainage arrangements, 7-gutters, 8-reinforced earth bulkhead strip footings, 9-sand-gravel cushions, 10- Connector, 11-12-drain bars of geomembrane, 13-long fine geotextiles, 14-reinforced mesh, 15-sleeves, 16-foundation soils, 17-built-in fittings.
Specific embodiment
With reference to embodiment and attached drawing, the present invention is described in further detail:
One, earth's surface sundries is removed, ground excavation is carried out, substrate is subjected to grinding compacting, on the ground after smooth compacting It is laid with sand-gravel cushion (9), sand-gravel cushion (9) should be more than 1m or more on the outside of reinforced earth bulkhead strip footing (9), and should The position of reserved steel bar concrete continuous footing (8) and gutter (7) is poured at the position reserved on sand-gravel cushion (9) Build reinforced concrete strip foundation (8) and gutter (7).
Two, horizontal drain pipe (5) and first layer vertical drainage pipe (4) are installed on sand-gravel cushion (9), utilize sleeve (15) first layer vertical drainage pipe (4) and horizontal drain pipe (5) are connected into an entirety.
Three, it fills architecture sediment filler (1), is compacted architecture sediment filler (1), and adjust horizontal drain pipe (5) and first The position of layer vertical drainage pipe (4) is laid with TGXG (2) until first layer TGXG (2) paving location, in distance soil The partial size of used architecture sediment filler (1) is no more than 15cm within work grid (2) surface 5cm.
Four, within the top 5cm to 15cm of TGXG (2), interlayer drainage arrangement is laid with according to the gradient 2% -5% (6), one end of interlayer drainage arrangement (6) is placed in connector (10), the paving of connector (10) and interlayer drainage arrangement (6) Set direction is consistent, in the interface of interlayer drainage arrangement (6) and connector (10), is closed using pitch, connector (10) Got up with vertical drainage pipe (4) by sleeve connection, then install precast concrete facade panel (3), by TGXG (2) with it is prefabricated Concrete slab (3) is connected using pitman, while interlayer drainage arrangement (6) being mixed by reinforced mesh (14) with prefabricated The built-in fitting (17) of solidifying soil panel (3) is welded and fixed.It repeats the above steps until retaining wall fills specified altitude assignment.

Claims (2)

1. a kind of Geogrid Reinforced Earth Retaining Wall based on architecture sediment, comprising: architecture sediment filler (1), TGXG (2), Precast concrete facade panel (3), vertical drainage pipe (4), horizontal drain pipe (5), interlayer drainage arrangement (6), gutter (7), reinforcement Native barricade strip footing (8), sand-gravel cushion (9), connector (10);It is characterized in that, the interlayer drainage arrangement (6) described in it It include: geomembrane (11), drain bar (12), long fine geotextiles (13), reinforced mesh (14), wherein geomembrane (11) wraps up reinforcing bar Mesh sheet (14) is located at bottom, and drain bar (12) is located at middle part, and top is then long fine geotextiles (13), in interlayer drainage arrangement (6) It with the interface of connector (10), is closed using pitch, interlayer drainage arrangement (6) passes through reinforced mesh (14) and prefabricated mixed The built-in fitting (17) of solidifying soil panel (3) is welded and fixed;Interlayer drainage arrangement (6) be located at TGXG (2) top 5cm to 15cm it Between, and having certain slope laying, range of grade 2% -5% is high outside and low outside, and along wall length direction etc. in same layer Spacing distribution, connect between interlayer drainage arrangement (6) and vertical drainage pipe (4) by connector (10), connector (10) with erect It is connected to sleeve (15) are passed through between drainpipe (4), one end of interlayer drainage arrangement (6) is placed in connector (10), and even It is consistent with the laying direction of interlayer drainage arrangement (6) to connect device (10), vertical drainage pipe (4) and horizontal drain pipe (5) pass through sleeve (15) it connects.
2. a kind of construction method of reinforced earth bulkhead as described in claim 1, it is characterised in that: excavation pit first is laid with Sand-gravel cushion (9) is simultaneously compacted, and the position of reserved reinforced earth bulkhead strip footing (8) and gutter (7), in sand-gravel cushion (9) reinforced earth bulkhead strip footing (8) and gutter (7) are poured at the position reserved on, installation horizontal drain pipe (5), the One layer of vertical drainage pipe (4), fills architecture sediment filler (1), is compacted architecture sediment filler (1), until first layer TGXG Paving location is laid with TGXG (2), in TGXG (2) top 5cm between 15cm, is laid with according to the gradient 2% -5% Interlayer drainage arrangement (6) is connect with vertical drainage pipe (4) by connector (10) by interlayer drainage arrangement (6), and then installation is pre- TGXG (2) is connect by concrete slab (3) processed with precast concrete facade panel (3), and will be in interlayer drainage arrangement (6) Reinforced mesh (14) and precast concrete facade panel (3) built-in fitting (17) weld, repeat the above steps until retaining wall fill To specified altitude assignment.
CN201710884507.1A 2017-09-26 2017-09-26 Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment Expired - Fee Related CN107780436B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710884507.1A CN107780436B (en) 2017-09-26 2017-09-26 Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710884507.1A CN107780436B (en) 2017-09-26 2017-09-26 Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment

Publications (2)

Publication Number Publication Date
CN107780436A CN107780436A (en) 2018-03-09
CN107780436B true CN107780436B (en) 2019-05-07

Family

ID=61433779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710884507.1A Expired - Fee Related CN107780436B (en) 2017-09-26 2017-09-26 Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment

Country Status (1)

Country Link
CN (1) CN107780436B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547306A (en) * 2018-03-12 2018-09-18 江苏建筑职业技术学院 A kind of building waste block stone does the construction method of bank protection
CN110374133A (en) * 2019-06-20 2019-10-25 浙江大学 It is a kind of to wrap up in face earth-retaining wall construction method suitable for sand soil
CN110424449B (en) * 2019-07-16 2021-06-15 河海大学 Microorganism control method for long-term stability of reinforced retaining wall

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6663323B1 (en) * 2002-11-18 2003-12-16 Mark A. Boys Retaining wall block and drainage system
CN202202339U (en) * 2011-08-25 2012-04-25 中国电力工程顾问集团西南电力设计院 Geogrid reinforced soil retaining wall of concrete module
CN103850262B (en) * 2012-11-29 2016-12-21 中国二十冶集团有限公司 Drain water-stopping method between Punching Borehole Cast-in-place Concrete Pile campshed support pile
CN105714759B (en) * 2016-03-09 2018-04-20 广东安元矿业勘察设计有限公司 The row that liquefaction collapse is taken precautions against in urban dregs blends reinforcement means
CN105970909B (en) * 2016-06-01 2018-06-15 上海建研地基基础工程有限公司 Well point plastic strip vacuum preloading seepage consolidation joint precipitating, pre-pressing dynamic consolidation method

Also Published As

Publication number Publication date
CN107780436A (en) 2018-03-09

Similar Documents

Publication Publication Date Title
CN104480963B (en) The constructional method of a kind of precast module type panel geo-grid reinforced tailing sand barricade
CN106522037B (en) Side broad way based structures based on existing railway roadbed and its construction method
CN107780436B (en) Geogrid Reinforced Earth Retaining Wall and construction method based on architecture sediment
CN203393530U (en) Anti-floating lightweight high-fill embankment structure
CN204370473U (en) Precast module type panel Fill Reinforced With Geogrids CHARACTERISTICS OF TAILINGS SAND barricade
US11952728B2 (en) Road structure reconstructed from large-scale independent underground garage and construction method thereof
CN204570720U (en) A kind of widening of subgrade culvert foundation
CN106836034B (en) High-fill cover plate culvert flexible load shedding system and construction method
CN219410355U (en) Flexible side-width structure of high-fill embankment of existing railway
CN103572680A (en) Road roadbed filling construction method of coal mine gob
CN209603112U (en) Shallow karst cave processing structure that buries
CN117127642A (en) Fluidized solidified soil bearing platform structure and manufacturing method
CN212128696U (en) Road bridge links up mixed light dirt road bed structure of section bubble
CN215165533U (en) Anchoring structure for side slope of solid waste landfill
CN108677999A (en) A kind of Muddy Bottoms packeted soil barrier wall structure and construction method
CN211113579U (en) Heavy-load ground foundation structure for seepage-proofing area of soft foundation
CN210458817U (en) Prevent road settlement's foundation structure
CN209482302U (en) Sanitary filling field laying assembled anchor structure
CN113700111A (en) Construction method of rainwater permeation, drainage and reuse integrated system
CN111979983A (en) Sand geological water retaining dam solidified by using construction waste
CN215051733U (en) Construction access road structure in deep soft soil area
CN110593242A (en) Heavy-load ground foundation structure of seepage-proofing area of soft foundation and processing method thereof
CN112030870B (en) Building rubbish reinforcing river levee under sandy soil geology
CN215165696U (en) Tunnel portal side slope supporting structure
CN217869782U (en) Concrete permeates water with pouring basic unit's structure that permeates water

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190507