CN103840392B - A kind of concrete bar job platform - Google Patents
A kind of concrete bar job platform Download PDFInfo
- Publication number
- CN103840392B CN103840392B CN201210473886.2A CN201210473886A CN103840392B CN 103840392 B CN103840392 B CN 103840392B CN 201210473886 A CN201210473886 A CN 201210473886A CN 103840392 B CN103840392 B CN 103840392B
- Authority
- CN
- China
- Prior art keywords
- support frame
- concrete
- concrete pole
- platform
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Emergency Lowering Means (AREA)
Abstract
一种砼杆作业平台,用于为输电线路施工人员作业提供安全保障。它包括横梁、平台踏板、支撑架和砼杆抱箍,所述横梁的两端设置平台踏板,横梁的中间部位与支撑架一端固定装配,所述支撑架另一端通过螺栓组件与砼杆抱箍配装。本发明不仅有利于施工人员按施工工艺要求作业,保证了施工质量,使施工时间减少了三分之一,提高了施工效率,而且消除了安全生产方面存在的隐患。
The utility model relates to a concrete pole operation platform, which is used to provide safety guarantee for construction personnel of transmission lines. It includes a beam, a platform pedal, a support frame and a concrete rod hoop. The two ends of the beam are provided with a platform pedal, the middle part of the beam is fixedly assembled with one end of the support frame, and the other end of the support frame is connected to the concrete rod hoop through a bolt assembly. equipped. The invention not only facilitates the construction personnel to operate according to the requirements of the construction technology, ensures the construction quality, reduces the construction time by one-third, improves the construction efficiency, but also eliminates hidden dangers in safe production.
Description
技术领域 technical field
本发明涉及一种电力砼杆作业平台,属于输电线路维修设备技术领域。 The invention relates to an electric concrete pole operation platform, which belongs to the technical field of transmission line maintenance equipment.
背景技术 Background technique
目前,在输电线路建设及检修过程中,施工人员一般通过脚扣在砼杆上完成各种操作,由于砼杆与作业点水平方向距离大,人体与砼杆之间形成很大的倾斜角度,不仅给施工人员作业带来不便,影响施工质量和效率,而且存在着较大的安全隐患;同时,施工人员长时间站在杆塔上感到疲惫需转身或左右脚上下互换时,也极易发生因坠落导致的人身伤亡事故。 At present, in the process of construction and maintenance of transmission lines, construction workers generally complete various operations on the concrete pole by buckling their feet. Due to the large horizontal distance between the concrete pole and the operating point, a large inclination angle is formed between the human body and the concrete pole. It not only brings inconvenience to the construction personnel, affects the construction quality and efficiency, but also has great safety hazards; at the same time, when the construction personnel feel tired standing on the pole tower for a long time and need to turn around or switch their left and right feet up and down, it is also very easy to happen. Personal injury or death due to a fall.
发明内容 Contents of the invention
本发明的目的在于针对现有技术之弊端、提供一种结构简单、性能可靠,能大大减少安全事故发生几率、提高施工质量和效率的砼杆作业平台。 The purpose of the present invention is to provide a concrete pole operation platform with simple structure and reliable performance, which can greatly reduce the probability of safety accidents and improve construction quality and efficiency, aiming at the drawbacks of the prior art.
本发明所述问题是以下述技术方案实现的: Problem described in the present invention is realized with following technical scheme:
一种砼杆作业平台,它包括横梁、平台踏板、支撑架和砼杆抱箍,所述横梁的两端设置平台踏板,横梁的中间部位与支撑架一端固定装配,所述支撑架另一端通过螺栓组件与砼杆抱箍配装。 A concrete rod work platform, which includes a beam, a platform pedal, a support frame and a concrete rod hoop, platform pedals are arranged at both ends of the beam, the middle part of the beam is fixedly assembled with one end of the support frame, and the other end of the support frame passes through The bolt assembly is assembled with the concrete rod hoop.
上述砼杆作业平台,所述平台踏板为方形框架结构,它们固定安装在横梁的两端。 For the above-mentioned concrete pole operation platform, the platform pedals are of a square frame structure, and they are fixedly installed at both ends of the crossbeam.
上述砼杆作业平台,所述支撑架由支撑架横梁、支撑架横撑和支撑架斜撑组成,所述支撑架横梁包括左右对称布置的两部分,所述支撑架横撑安装在左、右纵梁之间,它通过螺栓组件与砼杆抱箍装配,所述支撑架斜撑布置在支撑架横梁左右两侧,它们倾斜安装在支撑架横梁与横梁之间。 For the above-mentioned concrete pole operation platform, the support frame is composed of a support frame beam, a support frame cross brace and a support frame diagonal brace. The support frame beam includes two parts arranged symmetrically on the left and right. Between the longitudinal beams, it is assembled with the concrete rod hoop through the bolt assembly. The support frame diagonal braces are arranged on the left and right sides of the support frame beams, and they are obliquely installed between the support frame beams and the beams.
上述砼杆作业平台,所述砼杆抱箍由通过螺栓组件连接的两部分组成,砼杆抱箍直径与砼杆梢径匹配。 In the above-mentioned concrete pole operation platform, the concrete pole hoop is composed of two parts connected by bolt assemblies, and the diameter of the concrete pole hoop matches the diameter of the concrete pole tip.
上述砼杆作业平台,在横梁的两侧还设有安全挂绳,所述安全挂绳末端设有与砼杆上的耐张横担匹配的挂钩。 The above-mentioned concrete pole operation platform is also provided with a safety hanging rope on both sides of the beam, and the end of the safety hanging rope is provided with a hook matching the tension cross arm on the concrete pole.
本发明适用于10KV、0.4KV新架线路和电网改造中在终端杆、转角杆、T接杆上的作业,它可通过装配不同直径的砼杆抱箍达到与12米杆、10米杆等梢径砼杆匹配的目的。采用本发明后,施工人员可以长时间轻松地站在平台踏板上操作,由于平台踏板与作业点距离缩短,人体与砼杆倾斜角度缩小,不仅有利于施工人员按施工工艺要求作业,保证了施工质量,使施工时间减少了三分之一,提高了施工效率,而且消除了安全生产方面存在的隐患。 The present invention is applicable to work on terminal poles, corner poles, and T poles in 10KV and 0.4KV new lines and power grid transformation. It can achieve the same level as 12m poles, 10m poles, etc. by assembling concrete pole hoops with different diameters. The purpose of matching the tip diameter concrete rod. After adopting the invention, construction workers can easily stand on the platform pedal for a long time to operate, because the distance between the platform pedal and the operating point is shortened, and the inclination angle between the human body and the concrete pole is reduced, which not only facilitates the construction personnel to work according to the construction process requirements, but also ensures the construction Quality reduces the construction time by one-third, improves construction efficiency, and eliminates hidden dangers in production safety.
附图说明 Description of drawings
下面结合附图对本发明作进一步说明。 The present invention will be further described below in conjunction with accompanying drawing.
图1是本发明结构示意图; Fig. 1 is a structural representation of the present invention;
图2是本发明在砼杆上安装示意图。 Fig. 2 is a schematic diagram of the installation of the present invention on a concrete pole.
图中各标号清单为:1、横梁,2、平台踏板,3、安全挂绳,4、挂钩,5、砼杆抱箍,6、支撑架横梁,7、支撑架斜撑,8、支撑架横撑,9、螺栓组件,10、砼杆,11、耐张横担。 The list of labels in the figure is: 1. Beam, 2. Platform pedal, 3. Safety lanyard, 4. Hook, 5. Concrete pole hoop, 6. Support frame beam, 7. Support frame diagonal brace, 8. Support frame Cross brace, 9, bolt assembly, 10, concrete rod, 11, tension cross arm.
具体实施方式 detailed description
参看图 1,并结合具体实施例对本发明进一步说明:本发明包括横梁1、平台踏板2、支撑架和砼杆抱箍5。所述横梁1长1500mm,在其两端设置边长为330mm的方形金属结构平台踏板2,横梁1的中间部位与长500mm的支撑架一端固定装配;所述支撑架由支撑架横梁6、支撑架横撑8和支撑架斜撑7组成,所述支撑架横梁6包括左右对称布置的两部分,所述支撑架横撑8安装在左、右纵梁之间,它通过螺栓组件9与砼杆抱箍5装配,所述支撑架斜撑7布置在支撑架横梁6左右两侧,它们倾斜安装在支撑架横梁6与横梁1之间;所述砼杆抱箍5由通过螺栓组件9连接的两部分组成,砼杆抱箍5直径与砼杆10的梢径匹配,本实施例中设有两套砼杆抱箍5,它们可分别与12米杆、10米杆的砼杆配装;本发明在横梁1的两侧还设有安全挂绳3,所述安全挂绳3的末端设有与砼杆上的耐张横担11匹配的挂钩4。 Referring to Fig. 1, the present invention is further described in conjunction with specific embodiments: the present invention includes a beam 1, a platform pedal 2, a support frame and a concrete pole hoop 5. Described crossbeam 1 is long 1500mm, and the square metal structure platform pedal 2 that side length is 330mm is set at its two ends, and the middle part of crossbeam 1 is fixedly assembled with one end of long 500mm bracing frame; Described bracing frame is supported by bracing frame crossbeam 6, frame cross brace 8 and support frame diagonal brace 7, the support frame cross beam 6 includes two parts symmetrically arranged left and right, the support frame cross brace 8 is installed between the left and right longitudinal beams, and it connects with the concrete through the bolt assembly 9 The rod hoop 5 is assembled, and the support frame diagonal brace 7 is arranged on the left and right sides of the support frame beam 6, and they are obliquely installed between the support frame beam 6 and the beam 1; the concrete rod hoop 5 is connected by a bolt assembly 9 The diameter of the concrete pole hoop 5 matches the tip diameter of the concrete pole 10. In this embodiment, there are two sets of concrete pole hoops 5, which can be equipped with concrete poles of 12 meters and 10 meters respectively. ; The present invention is also provided with a safety lanyard 3 on both sides of the beam 1, and the end of the safety lanyard 3 is provided with a hook 4 that matches the tension cross arm 11 on the concrete pole.
参看图2,本发明使用时通过砼杆抱箍5固定安装在电力砼杆10上,再将两根安全挂绳的挂钩悬挂砼杆上的耐张横担穿钉上,施工人员可以长时间轻松地站在平台踏板2上操作,由于平台踏板2与作业点距离缩短,人体与砼杆10倾斜角度缩小,不仅有利于施工人员按施工工艺要求作业,保证了施工质量,使施工时间减少了三分之一,提高了施工效率,而且消除了安全生产方面存在的隐患。 Referring to Fig. 2, when the present invention is in use, it is fixedly installed on the electric concrete pole 10 through the concrete pole hoop 5, and then the hooks of the two safety lanyards are hung on the tension-resistant cross-arm on the concrete pole, so that the construction personnel can Easily stand on the platform pedal 2 to operate, because the distance between the platform pedal 2 and the operating point is shortened, and the inclination angle between the human body and the concrete pole 10 is reduced, which not only helps the construction personnel to work according to the construction process requirements, but also ensures the construction quality and reduces the construction time One-third, the construction efficiency has been improved, and hidden dangers in production safety have been eliminated.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210473886.2A CN103840392B (en) | 2012-11-21 | 2012-11-21 | A kind of concrete bar job platform |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210473886.2A CN103840392B (en) | 2012-11-21 | 2012-11-21 | A kind of concrete bar job platform |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103840392A CN103840392A (en) | 2014-06-04 |
| CN103840392B true CN103840392B (en) | 2016-12-21 |
Family
ID=50803636
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201210473886.2A Expired - Fee Related CN103840392B (en) | 2012-11-21 | 2012-11-21 | A kind of concrete bar job platform |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103840392B (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104779555A (en) * | 2015-04-22 | 2015-07-15 | 国家电网公司 | Detachable effort-saving stand for 10 KV concrete pole wiring |
| CN104989150B (en) * | 2015-05-21 | 2018-04-20 | 国网青海省电力公司西宁供电公司 | A kind of application method for the operating platform that cable is overhauled on steel pipe pole |
| CN105565220B (en) * | 2015-12-22 | 2018-04-24 | 国家电网公司 | A kind of aerial work platform |
| CN107508535B (en) * | 2017-08-08 | 2023-05-16 | 中国电建集团贵州工程有限公司 | Photovoltaic solar installation aerial work support and system |
| CN108371766A (en) * | 2018-04-16 | 2018-08-07 | 嘉兴市恒光电力建设有限责任公司华创分公司 | Job safety auxiliary device on bar |
| CN109217175A (en) * | 2018-10-25 | 2019-01-15 | 河北晋昌电力工程有限公司 | A kind of stage apparatus |
| CN110265917B (en) * | 2019-06-24 | 2020-10-23 | 绍兴顺泰机械科技有限公司 | Quick patching device of cable |
| CN110445052B (en) * | 2019-07-17 | 2020-09-29 | 贵州电网有限责任公司 | Insulating auxiliary fixtures convenient to distribution lines live working |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202957526U (en) * | 2012-11-21 | 2013-05-29 | 沧州供电公司 | Working platform of concrete pole |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2642577B1 (en) * | 1989-01-27 | 1993-10-08 | Electricite De France | INTERVENTION SUPPORT ON ARMING OF AERIAL ELECTRIC LINE |
| EP0542168B1 (en) * | 1991-11-15 | 1997-02-12 | Alce Garden S.r.l. | Self-propelled vehicle for climbing along pole-shaped elements, such as tree trunks, poles and the like |
| CN2192966Y (en) * | 1994-03-22 | 1995-03-22 | 李宝顺 | Portable working table on pole |
| CN201345514Y (en) * | 2009-01-20 | 2009-11-11 | 重庆市电力公司江北供电局 | Insulated suspender for high-voltage live line work |
| CN102570346B (en) * | 2011-10-12 | 2014-06-11 | 上海置盟电力科技有限公司 | Pole-mounted live-line work platform formed by multifunctional members |
| CN202333624U (en) * | 2011-12-13 | 2012-07-11 | 北京市电力公司 | Hot-line work distance control device |
-
2012
- 2012-11-21 CN CN201210473886.2A patent/CN103840392B/en not_active Expired - Fee Related
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202957526U (en) * | 2012-11-21 | 2013-05-29 | 沧州供电公司 | Working platform of concrete pole |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103840392A (en) | 2014-06-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103840392B (en) | A kind of concrete bar job platform | |
| CN203352051U (en) | Insulation protective umbrella | |
| CN203367865U (en) | Auxiliary bracket for maintaining power transmission line | |
| CN202957526U (en) | Working platform of concrete pole | |
| CN203352053U (en) | Chain-type ladder used for maintenance of straight line tower of power transmission line | |
| CN104906719A (en) | Assembled tower climbing anti-falling device | |
| CN102761077A (en) | Insulating hoisting bracket for strain insulator string of 1000kV extra-high alternating current line | |
| CN203674618U (en) | Dedicated ladder facilitating operation of 220 KV/ 66 KV in-and-out wire | |
| CN203439984U (en) | Handjack for pole | |
| CN205132976U (en) | Auxiliary device is used in introduction of standard festival | |
| CN203569906U (en) | Anti-sliding device of canopy sloping roof without column | |
| CN202840363U (en) | 1000kV UHV AC Line Tension Insulator String Insulation Lifting Bracket | |
| CN203891545U (en) | Reinforcing device for main material of 7727 power transmission tower | |
| CN201424805Y (en) | a support system | |
| CN204266607U (en) | A kind of high-voltage line protective frame | |
| CN103896153A (en) | Zig-zag derrick for replacing disconnecting link | |
| CN204633283U (en) | A kind of built on stilts general cable hook suspension device | |
| CN203769402U (en) | Steel pipe tower safety climbing and treading device | |
| CN203514918U (en) | Concrete pole tower with ladder stand device | |
| CN202997372U (en) | Multipurpose maintenance ladder | |
| CN204511278U (en) | A kind of be exclusively used in transmission line of electricity is housed steel tower on earth potential working cat ladder | |
| CN207377483U (en) | Steel tube tower in electric transmission line aids in climbing tool | |
| CN206864969U (en) | Full-insulation distribute-electricity transformer operating platform | |
| CN205476396U (en) | Steel pipe pole operation platform | |
| CN203794469U (en) | Inversed-v-shaped holding pole for replacing disconnecting link |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C53 | Correction of patent of invention or patent application | ||
| CB02 | Change of applicant information |
Address after: 100761 West Chang'an Avenue, Beijing, No. 86, No. Applicant after: State Grid Corporation of China Applicant after: STATE GRID HEBEI ELECTRIC POWER COMPANY, CANGZHOU BRANCH Applicant after: STATE GRID HEBEI ELECTRIC POWER Co. Address before: 100761 West Chang'an Avenue, Beijing, No. 86, No. Applicant before: State Grid Corporation of China Applicant before: Cangzhou Power Supply Co. Applicant before: Hebei Electric Power Corp. |
|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161221 Termination date: 20211121 |