CN103490347B - A kind of cable laying method solving the cable heat expansion amount of stretching - Google Patents

A kind of cable laying method solving the cable heat expansion amount of stretching Download PDF

Info

Publication number
CN103490347B
CN103490347B CN201310391066.3A CN201310391066A CN103490347B CN 103490347 B CN103490347 B CN 103490347B CN 201310391066 A CN201310391066 A CN 201310391066A CN 103490347 B CN103490347 B CN 103490347B
Authority
CN
China
Prior art keywords
cable
underground
pillar
shaft body
cleat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310391066.3A
Other languages
Chinese (zh)
Other versions
CN103490347A (en
Inventor
戚柏林
丁自强
应剑烈
张立平
吴苗森
钱一宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310391066.3A priority Critical patent/CN103490347B/en
Publication of CN103490347A publication Critical patent/CN103490347A/en
Application granted granted Critical
Publication of CN103490347B publication Critical patent/CN103490347B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention discloses a kind of cable laying method solving the cable heat expansion amount of stretching, comprise the steps: 1) cable laying well; 2) installing cables; 3) shutoff underground pillar.The invention provides a kind of cable laying method solving the cable heat expansion amount of stretching; its rational cable arrangements; adopt cable arc change absorbing cable thermal expansion length increment, guarantee that pillar waterproof and snake class animal enter simultaneously, efficiently solve power cable and lay thermal expansion problem down over long distances.

Description

A kind of cable laying method solving the cable heat expansion amount of stretching
Technical field
The present invention and a kind of cable laying method solving the cable heat expansion amount of stretching.
Background technology
At present; China is in urbanization and rapid economic development period; the people improve constantly electricity needs; wish that transmission line and environment are lived integrally harmonious simultaneously; power cable underground laying is the perfect means of urban electricity supply; adopt new technology simultaneously, new technology, construction method is constantly brought forth new ideas, and not only protection of the environment but also the power cable trenchless installation Technique Popularizing economized the land resource application were deeply on both sides of the Changjiang River.
Power cable no-dig technique river crossing is applied, successively successful implementation 250m, 380m, 500m, 680m, crosses over width and constantly breaks through, and along with power cable monomer length increases, power cable thermal expansion length increment problem is also given prominence to gradually.
Summary of the invention
For solving the problem; the object of the present invention is to provide a kind of cable laying method solving the cable heat expansion amount of stretching; its rational cable arrangements; adopt cable arc change absorbing cable thermal expansion length increment; guarantee that pillar waterproof and snake class animal enter simultaneously, efficiently solve power cable and lay thermal expansion problem down over long distances.
The present invention reaches above-mentioned object, and the present invention adopts following technical scheme:
Solve a cable laying method for the cable heat expansion amount of stretching, comprise the steps:
1) cable laying well
First offer cable shaft in underground, then in cable shaft, install fire compartment wall, described fire compartment wall and the two-port of cable shaft are positioned at same straight line; Then at the both sides of fire compartment wall difference installing cables joint, and the both sides of cable joint are separately installed with cable cleat, described cable cleat and fire compartment wall at right angle setting;
2) installing cables
First the import and export of cable shaft misplace vertical being connected with underground pillar respectively, then the cable in the pillar of underground is divided into 2 groups, 2 groups of cables are successively by the import of cable shaft, the outlet of first cable cleat, cable joint, second cable cleat and cable shaft, and described 2 groups of cables lay respectively at the both sides of fire compartment wall; Then every root cable is passed through cable joint, the cable cleat being simultaneously arranged on cable joint two ends is fixed the cable through this cable joint;
3) shutoff underground pillar
Waterproof packing material is installed in the pillar of underground seal between underground pillar and cable, thus completes the provided underground of whole cable.
Described cable shaft comprises the first cable shaft body, the second cable shaft body, the 3rd cable shaft body, the first described cable shaft body, the second cable shaft body are connected with the 3rd cable shaft body entire body, and the width of the first described cable shaft body is greater than the second cable shaft body and the 3rd cable shaft body respectively.
The described cable be arranged between 2 cable cleats is the cable being in pass-through state, and the cable between cable wellhead and cable cleat is the cable being in arc bending shape state.
Described in the pillar of underground install 2 pieces of aluminium alloy clamping plate, between 2 pieces of aluminium alloy clamping plate, then fill waterproof plasticine underground pillar sealed; Described 1 of pillar piece of aluminium alloy clamping plate outer surface and the underground pillar mouth end face of closely descending is positioned at same plane.
Be provided with 3 pieces of anticorrosion fan-shaped iron plates outside described aluminium alloy clamping plate, described anticorrosion fan-shaped iron plate is connected with well body of wall by bolt.
Beneficial effect of the present invention is: the invention provides a kind of cable laying method solving the cable heat expansion amount of stretching; its rational cable arrangements; adopt cable arc change absorbing cable thermal expansion length increment; guarantee that pillar waterproof and snake class animal enter simultaneously, efficiently solve power cable and lay thermal expansion problem down over long distances.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
The left view of Fig. 2 Fig. 1;
Fig. 3 is the structural representation that cable of the present invention occurs when stretching;
Fig. 4 is the amplification view of underground pillar;
Fig. 5 is the structural representation that cable shaft installs fan-shaped iron plate.
Embodiment
Embodiment 1
As shown in Figure 1, the present embodiment provides a kind of cable laying method solving the cable heat expansion amount of stretching, and comprises the steps: the first, cable laying well.First offer cable shaft 1 in underground, then in cable shaft 1, install fire compartment wall 11, described fire compartment wall 11 is positioned at same straight line with the two-port of cable shaft 1; Then at the both sides of fire compartment wall 11 difference installing cables joint 12, and the both sides of cable joint 12 are separately installed with cable cleat 13, described cable cleat 13 and fire compartment wall 11 at right angle setting.Cable shaft 1 comprises the first cable shaft body 14, second cable shaft body 15, the 3rd cable shaft body 16, the first described cable shaft body 14, second cable shaft body 15 is connected with the 3rd cable shaft body 16 entire body, and the width of the first described cable shaft body 14 is greater than the second cable shaft body 15 and the 3rd cable shaft body 16 respectively.
The second, installing cables.First the import and export of cable shaft 1 misplace vertical being connected with underground pillar 3 respectively, then the cable 2 in underground pillar 3 is divided into 2 groups, 2 groups of cables 2 are successively by the import of cable shaft 1, the outlet of first cable cleat 13, cable joint 12, second cable cleat 13 and cable shaft 1, and described 2 groups of cables 2 lay respectively at the both sides of fire compartment wall 11; Then every root cable 2 is passed through cable joint 12, the cable cleat 13 being simultaneously arranged on cable joint 12 two ends is fixed the cable 2 through this cable joint 12.Be arranged on cable 2 between 2 cable cleats 13 for being in the cable 2 of pass-through state, the cable 2 between cable wellhead and cable cleat 13 is for being in the cable 2 of arc bending shape state.
3rd, shutoff underground pillar.Waterproof packing material is installed in underground pillar 3 seal between underground pillar 3 and cable 2.In underground pillar 3,2 pieces of aluminium alloy clamping plate 31 are installed, between 2 pieces of aluminium alloy clamping plate 31, then fill waterproof plasticine 32 pairs of underground pillars 3 seal; Described 1 of pillar 3 piece of aluminium alloy clamping plate 31 outer surface and underground pillar 3 mouthfuls of end faces of closely descending are positioned at same plane.Be provided with 3 pieces of anticorrosion fan-shaped iron plates 33 outside described aluminium alloy clamping plate 31, described anticorrosion fan-shaped iron plate 33 is connected with well body of wall by bolt, thus completes the provided underground of whole cable.
As shown in Figure 1, the import and export of cable shaft 1 misplace vertical being connected with underground pillar 3 respectively.After cable 1 in underground pillar 3 continues straight line, 2 groups of cables 1 turn round respectively and enter the well room of fire compartment wall 11, cable 1 fill on the grade beam of well room cable cleat 13 fixing after, carry out cable joint 12.It is " straight-curved-straight " that cable 1 is exported to cable cleat 13 fixing point floor projection from underground pillar 3, and side projection is dislocation vertical arrangement to three line horizontal registration.
As shown in Figure 2, cable shaft 1 is arranged on the ground end of river crossing and holds with going out.Cable shaft 1 function be cable 2 when laying facility settle, cable joint 12 device; The cable 2 heat expansion amount of stretching absorbs.The import and export of cable shaft 1 misplace vertical being connected with underground pillar 3 respectively.Cable shaft 1 is by concreting.
As shown in Figure 3, when cable 2 is heated generation length increment, cable shaft 1 is imported in the slip that can rub of cable 2 increment size into, underground pillar 3 mouthfuls to grade beam fill in cable cleat 13 fixing point distance, cable 2 produces waveform and bends, cable 2 increment size is larger, and it is larger that waveform bends amplitude, and now cable 2 bending radius still at safe condition.When cable 2 cools retraction, cable 2 waveform bending amplitude reduces, and at waterproof plugging device place, friction slips into underground pillar 3 to cable 2.2 groups of 6 cables 2 are because of staggered, and each own extending space, can not affect respective wave form varies mutually.The transmission of above cable 2 length, slides in the friction of waterproof plugging device place and does not affect waterproof shutoff function.Fix owing to cable 2 grade beam filling cable cleat 13, cable joint 12 position does not affect by tension force, or position is moved.
As shown in Figure 4, after cable 2 shuttles back and forth in underground pillar 3.Waterproof, fire prevention, anti-toy shutoff must be carried out in cable 2 and underground pillar 3 gap.1st piece of aluminium alloy clamping plate 31 are loaded in underground pillar 3 and forms annular with cable 2, at underground pillar 3 and the clearance filled waterproof plasticine 31 of cable 2, then the 2nd piece of aluminium alloy clamping plate 31 are covered, formed on annular aluminium alloy clamping plate 31 and tight a bolt, make aluminium alloy clamping plate 31, waterproof plasticine 32, cable 2 and underground pillar 3, jointly form seal.Finally load onto fan-shaped iron plate 33, be fixed on wall body with expansion bolt.When cable cold and hot flexible time, cable 2 increases and decreases the length slip that can rub and imports cable shaft 1 into, and underground pillar 3 waterproof plugging device does not damage.
As shown in Figure 5, by 6 pieces of aluminium alloy clamping plate 31 and 3 blocks of fan-shaped steel plates 33, waterproof plugging device adds that screw and nut forms a unit, and every 1 underground pillar 3 mouthfuls uses 1 unit.Aluminium alloy clamping plate 31 are cast members, and fan-shaped steel plate 33 is pressing mold steel plates, and all there is preservative treatment on surface.
A kind of cable laying method solving the cable heat expansion amount of stretching described in the present embodiment; its rational cable arrangements; adopt cable arc change absorbing cable thermal expansion length increment; guarantee that pillar waterproof and snake class animal enter simultaneously, efficiently solve power cable and lay thermal expansion problem down over long distances.

Claims (2)

1. solve a cable laying method for the cable heat expansion amount of stretching, it is characterized in that comprising the steps:
1) cable laying well
First offer cable shaft (1) in underground, then in cable shaft (1), install fire compartment wall (11), described fire compartment wall (11) is positioned at same straight line with the two-port of cable shaft (1); Then in the both sides of fire compartment wall (11) difference installing cables joint (12), and the both sides of cable joint (12) are separately installed with cable cleat (13), described cable cleat (13) and fire compartment wall (11) at right angle setting;
2) installing cables
First the import and export of cable shaft (1) misplace vertical being connected with underground pillar (3) respectively, then the cable (2) in underground pillar (3) is divided into 2 groups, 2 groups of cables (2) are successively by the outlet of the import of cable shaft (1), first cable cleat (13), cable joint (12), second cable cleat (13) and cable shaft (1), and described 2 groups of cables (2) lay respectively at the both sides of fire compartment wall (11); Then by every root cable (2) by cable joint (12), the cable cleat (13) being simultaneously arranged on cable joint (12) two ends is fixed the cable (2) through this cable joint (12);
3) shutoff underground pillar
Waterproof packing material is installed in underground pillar (3) seal between underground pillar (3) and cable (2), thus completes the provided underground of whole cable; Described step 1) cable shaft (1) comprises the first cable shaft body (14), the second cable shaft body (15), the 3rd cable shaft body (16); the first described cable shaft body (14), the second cable shaft body (15) are connected with the 3rd cable shaft body (16) entire body, and the width of the first described cable shaft body (14) is greater than the second cable shaft body (15) and the 3rd cable shaft body (16) respectively; Described step 2) be arranged on cable (2) between 2 cable cleats (13) for being in the cable (2) of pass-through state, be positioned at cable (2) between cable wellhead and cable cleat (13) for being in the cable (2) of arc bending shape state; First described step 3) installs 2 pieces of aluminium alloy clamping plate (31) in underground pillar (3), between 2 pieces of aluminium alloy clamping plate (31), then fills waterproof plasticine (32) seal underground pillar (3); Described 1 piece of aluminium alloy clamping plate (31) outer surface of pillar (3) and underground pillar (3) the mouth end face of closely descending is positioned at same plane.
2. a kind of cable laying method solving the cable heat expansion amount of stretching according to claim 1, it is characterized in that: be provided with 3 pieces of anticorrosion fan-shaped iron plates (33) outside described aluminium alloy clamping plate (31), described anticorrosion fan-shaped iron plate (33) is connected with well body of wall by bolt.
CN201310391066.3A 2013-09-02 2013-09-02 A kind of cable laying method solving the cable heat expansion amount of stretching Active CN103490347B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310391066.3A CN103490347B (en) 2013-09-02 2013-09-02 A kind of cable laying method solving the cable heat expansion amount of stretching

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310391066.3A CN103490347B (en) 2013-09-02 2013-09-02 A kind of cable laying method solving the cable heat expansion amount of stretching

Publications (2)

Publication Number Publication Date
CN103490347A CN103490347A (en) 2014-01-01
CN103490347B true CN103490347B (en) 2016-04-06

Family

ID=49830384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310391066.3A Active CN103490347B (en) 2013-09-02 2013-09-02 A kind of cable laying method solving the cable heat expansion amount of stretching

Country Status (1)

Country Link
CN (1) CN103490347B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114917509A (en) * 2022-04-02 2022-08-19 深圳标典新材料有限公司 Application of fire protection system in cable tunnel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08179174A (en) * 1994-12-21 1996-07-12 Hitachi Cable Ltd Connecting joint for tube and wire-like body laying line using the same
CN101383492A (en) * 2008-10-30 2009-03-11 湖北省电力勘测设计院 Cable snake shaped laying method
CN201893535U (en) * 2010-11-22 2011-07-06 宁夏凯晨电气集团有限公司 Sealing device for pipe mouth of cable
CN102623935A (en) * 2012-03-22 2012-08-01 李超 Cable laying method and bracket thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08179174A (en) * 1994-12-21 1996-07-12 Hitachi Cable Ltd Connecting joint for tube and wire-like body laying line using the same
CN101383492A (en) * 2008-10-30 2009-03-11 湖北省电力勘测设计院 Cable snake shaped laying method
CN201893535U (en) * 2010-11-22 2011-07-06 宁夏凯晨电气集团有限公司 Sealing device for pipe mouth of cable
CN102623935A (en) * 2012-03-22 2012-08-01 李超 Cable laying method and bracket thereof

Also Published As

Publication number Publication date
CN103490347A (en) 2014-01-01

Similar Documents

Publication Publication Date Title
CN104818696B (en) The manufacture method of the vertical water sealing structure of hydraulic engineering
CN203684263U (en) General foundation for GIS equipment at transformer station
CN206144184U (en) Construction joint built -in slip casting pipe
CN103151737B (en) Square tube hermetically sealed connector
CN206992626U (en) A kind of assembled cable protecting sleeve
CN103490347B (en) A kind of cable laying method solving the cable heat expansion amount of stretching
CN203808113U (en) Concrete engineering expansion joint vertical water-stop structure
CN203034492U (en) Reinforced concrete pipe ditch deformation seam
CN202474717U (en) Snakelike pavement work well for high-voltage cable
CN102545129A (en) Large-section cable clamp
CN106193279A (en) Agent structure wall prestressed structure and time building method of agent structure wall
CN204793864U (en) Stride provisional overhead line facility of small region muddy ground
CN201904595U (en) Fixture suitable for large cross-section cables
CN207268342U (en) A kind of device for reinforcing the connection of ductile iron pipeline socket joint
CN206529907U (en) A kind of waterstop fixing device suitable for different wall thicknesses
CN111834972A (en) Cable sealing system
CN210920373U (en) Farmland hydraulic engineering construction pipe laying and line fixing device
CN103469766B (en) Method for connecting rigid body and flexible body of dam foundation of reservoir
CN203213428U (en) Connecting device for fixing photovoltaic assembly on corrugated III type color plate metal roof
CN202616685U (en) High strength clamp for three-core cable middle part
CN206673539U (en) A kind of cable laying piping lane
CN213693034U (en) Pre-buried electric conduit coincide connector
CN104674805B (en) A kind of callable prestress anchorage cable
CN104362573A (en) Cable installation tunnel structure
CN219351250U (en) Hydropower installation engineering piping lane mount

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant