CN203034492U - Reinforced concrete pipe ditch deformation seam - Google Patents
Reinforced concrete pipe ditch deformation seam Download PDFInfo
- Publication number
- CN203034492U CN203034492U CN 201220673056 CN201220673056U CN203034492U CN 203034492 U CN203034492 U CN 203034492U CN 201220673056 CN201220673056 CN 201220673056 CN 201220673056 U CN201220673056 U CN 201220673056U CN 203034492 U CN203034492 U CN 203034492U
- Authority
- CN
- China
- Prior art keywords
- joint
- seam
- concrete pipe
- fastening band
- rubber fastening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Abstract
The utility model discloses a reinforced concrete pipe ditch deformation seam, belonging to the field of construction engineering. The deformation seam includes a rubber water seal belt pre-embedded in the middle part of the wall thickness of a reinforced concrete pipe ditch along a construction seam, seam filling plates are arranged on and under the rubber water seal belt in the construction seam, embedded seam sealing materials for proofing water leakage are arranged between the seam filling plate on the rubber water seal belt and the upstream face, anti-shearing steel bars vertical to the construction seam are penetrated through the seam filling plate under the rubber water seal belt, a grease layer is painted on the surfaces of one ends of the anti-shearing steel bars, and the anti-shearing steel bars are symmetrically arranged by taking the construction seam as the center line. The reinforced concrete pipe ditch deformation seam provided is simple and convenient, has good adjusting, telescoping, and settlement effects, and is safe and reliable in use performance.
Description
Technical field
The utility model relates to the deformation joint in the building engineering field, and concrete is the deformation joint of a kind of steam power station steel concrete pipe trench.
Background technology
The cast-in-situ steel reinforced concrete raceway groove of steam power station and other building engineering fields regular meeting under the extraneous factor effect produces distortion, causes cracking even destruction.Deformation joint is the build joint of reserving at this situation, and build joint can be divided into three kinds at shrinkage joint, settlement joint, aseismic joint, but shrinkage joint, settlement joint, aseismic joint often three sew up one in practical engineering application, the unified deformation joint that is called.
Deformation joint uses very general in the pipe of firepower electrical plant, ditch, because the pipe trench of steam power station is mainly used in make up water, recirculated water, draining etc., is water system important in the power plant, so pipe trench just seems very high to the requirement of deformation joint.
The cast-in-situ steel reinforced concrete raceway groove of steam power station is general to be designed according to " steam power station water conservancy project design specifications " (DL/T 5339-2006).The 8.3.16 bar regulation of " steam power station water conservancy project design specifications ": the spacing at cast-in-situ steel reinforced concrete raceway groove shrinkage joint, should be according to local temperature condition, foundation property, channel material, cross dimensions, earthing height, factor such as job practices and construction seasons is determined, is generally adopted 20m ~ 30m.When take measures through the demonstration after, the shrinkage joint spacing can increase.In addition, the 8.3.19 bar of " steam power station water conservancy project design specifications " is further stipulated: cast-in-situ steel reinforced concrete pipe, ditch should arrange flexible interface or settlement joint at two kinds of foundation soil intersections that may produce differential settlement or the two ends by railway, highway, dykes and dams and other fixed buildings.
The shrinkage joint of cast-in-situ steel reinforced concrete pipe, ditch and flexible interface comprise the build joint of reservation and the rubber fastening band that arranges in build joint, rubber fastening band is complied with the direction setting of build joint, and be in the medium position of pipe trench wall thickness, there are some assistants the both sides of rubber fastening band, assistant is cast in the steel concrete of pipe trench of build joint both sides, plays fixedly rubber fastening band.The joint filling board of build joint is filled up in the upper and lower surface setting of rubber fastening band in the build joint, in addition, for preventing that pipe trench from leaking at the build joint place, filleting sealing material is set in the build joint between joint filling board and the upstream face again, close the whole piece build joint, eliminate the influence to pipe trench such as flexible of uneven settlement of foundation and pipe trench with the structure of this shrinkage joint and flexible interface.
At pipe trench bottom foundation soil relatively evenly or under the little situation of pipe trench upper load difference, adopt the above-mentioned deformation joint substantially can engineering demands, but change greatly or under the pipe trench upper load difference situation greatly at pipe trench bottom foundation soil, the rubber fastening band that common plastic deformation seam place arranges is because the effect of shearing, be torn the situation of leaking easily.If deformation joint leaks, not only can cause the waste of valuable water resource, also may cause Power Plant completely not send out owing to the deficiency of the water yield, cause compressor emergency shutdown what is more, produce bigger economic loss and social influence.
The utility model content
It is simple and convenient that the utility model technical issues that need to address provide a kind of construction, can effectively regulate the differential settlement of the flexible and ground of pipe trench, avoid the deformation joint rubber fastening band by drawing crack, a kind of steel concrete pipe trench deformation joint of causing raceway groove to leak.
For solving the problems of the technologies described above, the technical scheme that the utility model adopts is:
A kind of steel concrete pipe trench deformation joint, comprise the rubber fastening band that is embedded in concrete reinforced pipe ditch wall thickness middle part along build joint, top and the following joint filling board that all arranges of rubber fastening band in the build joint, arrange between joint filling board above the rubber fastening band and the upstream face and prevent the filleting sealing material that leaks, the joint filling board below the described rubber fastening band is equipped with the shear reinforcement perpendicular to build joint.
Further improvement of the utility model is: the external coating of described shear reinforcement one end has oil layer.
Further improvement of the utility model is: described shear reinforcement line centered by build joint is symmetrical arranged.
Further improvement of the utility model is: the diameter of described shear reinforcement is 20mm, and length is 800mm.
Because the technological progress of having adopted technique scheme, the utility model to obtain is:
Steel concrete pipe trench deformation joint of the present utility model is applied to the steel concrete pipe trench of steam power station and other building engineering fields, not only construction is very simple and convenient, and can regulate the differential settlement of the flexible and ground of pipe trench effectively, thereby guaranteed the integrality of pipe trench, avoided deformation joint to be caused the leak generation of situation of pipe trench because of rubber fastening band by drawing crack.
The utility model is provided with shear reinforcement between rubber fastening band and back side; deformation joint since the shearing that the sedimentation of ground causes all born by shear reinforcement; shear reinforcement has good supporting role to rubber fastening band; effectively protected rubber fastening band; avoid the fracture of rubber fastening band and the integrality of pipe trench, and then avoided the leak generation of situation of pipe trench.In addition, shear reinforcement is arranged on away from upstream face, near the position of back side, can slow down infiltration to the corrosion of shear reinforcement, prolongs the application life of shear reinforcement.
The external coating oil layer of shear reinforcement one end makes this section shear reinforcement that the amount of movement of horizontal direction be arranged in concrete, not only satisfied the flexible requirement of steel concrete pipe trench, and the flexible effect of adjusting is remarkable, and functional performance is safe and reliable.
The utility model has only been set up shear reinforcement in original deformation joint, it is comparatively simple and convenient to construct.
Description of drawings
Fig. 1 is structural representation of the present utility model.
Wherein, 1, filleting sealing material, 2, rubber fastening band, 3, shear reinforcement, 4, joint filling board, 7, steel concrete, 8, upstream face, 9, back side.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is described in further details:
A kind of steel concrete pipe trench deformation joint, as shown in Figure 1, the rubber fastening band 2 that comprises the build joint of reservation and arrange in build joint, rubber fastening band 2 are embedded in the medium position of pipe trench wall thickness along the build joint direction.There are some assistants the both sides of rubber fastening band 2, and the assistant of both sides is cast in respectively in the steel concrete 7 of deformation joint both sides, plays fixedly rubber fastening band.Top and the following joint filling board 4 that all arranges of the rubber fastening band 2 in the build joint, joint filling board 4 is used for filling up build joint.For preventing that pipe trench from leaking at the build joint place, filleting sealing material 1 is set between the joint filling board on rubber fastening band 24 and the upstream face 8 again, be used for closing the whole piece build joint.Joint filling board 4 below the rubber fastening band 2 is equipped with shear reinforcement 3, and as shown in Figure 1, shear reinforcement 3 is perpendicular to build joint, and line is symmetrical arranged centered by build joint.Between rubber fastening band 2 and back side 9, along the build joint direction some shear reinforcements 3 are set at interval.Regulate flexible effect for increasing, the external coating of shear reinforcement 3 one ends has oil layer.The position of the diameter of shear reinforcement 3, length, setting and spacing can design according to actual conditions.In the present embodiment, the width of build joint is 30mm, and the diameter of shear reinforcement 3 is 20mm, and length is 800mm, and spacing is 300mm, is arranged on apart from back side 100mm place.
Claims (4)
1. steel concrete pipe trench deformation joint, comprise the rubber fastening band (2) that is embedded in concrete reinforced pipe ditch wall thickness middle part along build joint, top and the following joint filling board (4) that all arranges of rubber fastening band (2) in the build joint, arrange between joint filling board (4) above the rubber fastening band (2) and the upstream face (8) and prevent that the filleting that leaks from sealing material (1), it is characterized in that: the joint filling board (4) below the described rubber fastening band (2) is equipped with the shear reinforcement (3) perpendicular to build joint.
2. a kind of steel concrete pipe trench deformation joint according to claim 1, it is characterized in that: the external coating of described shear reinforcement (3) one ends has oil layer.
3. a kind of steel concrete pipe trench deformation joint according to claim 1 and 2, it is characterized in that: described shear reinforcement (3) line centered by build joint is symmetrical arranged.
4. a kind of steel concrete pipe trench deformation joint according to claim 1 and 2, it is characterized in that: the diameter of described shear reinforcement (3) is 20mm, length is 800mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220673056 CN203034492U (en) | 2012-12-10 | 2012-12-10 | Reinforced concrete pipe ditch deformation seam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220673056 CN203034492U (en) | 2012-12-10 | 2012-12-10 | Reinforced concrete pipe ditch deformation seam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203034492U true CN203034492U (en) | 2013-07-03 |
Family
ID=48686627
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220673056 Expired - Lifetime CN203034492U (en) | 2012-12-10 | 2012-12-10 | Reinforced concrete pipe ditch deformation seam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203034492U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104420485A (en) * | 2013-08-21 | 2015-03-18 | 中国二十冶集团有限公司 | Underground space leaking type water stopping method for utility tunnel |
CN105735078A (en) * | 2016-03-10 | 2016-07-06 | 长沙理工大学 | Double-layer continuous reinforced concrete pavement structure suitable for pluvial region |
CN105780625A (en) * | 2016-03-10 | 2016-07-20 | 长沙理工大学 | Double-layer reinforced concrete pavement structure suitable for pluvial region urban road |
CN107035007A (en) * | 2017-05-22 | 2017-08-11 | 中国能源建设集团广东省电力设计研究院有限公司 | Expanded joint structure and its construction technology |
CN114232681A (en) * | 2021-12-30 | 2022-03-25 | 中国二十冶集团有限公司 | Utility tunnel expansion joint structure |
-
2012
- 2012-12-10 CN CN 201220673056 patent/CN203034492U/en not_active Expired - Lifetime
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104420485A (en) * | 2013-08-21 | 2015-03-18 | 中国二十冶集团有限公司 | Underground space leaking type water stopping method for utility tunnel |
CN104420485B (en) * | 2013-08-21 | 2017-04-19 | 中国二十冶集团有限公司 | Underground space leaking type water stopping method for utility tunnel |
CN105735078A (en) * | 2016-03-10 | 2016-07-06 | 长沙理工大学 | Double-layer continuous reinforced concrete pavement structure suitable for pluvial region |
CN105780625A (en) * | 2016-03-10 | 2016-07-20 | 长沙理工大学 | Double-layer reinforced concrete pavement structure suitable for pluvial region urban road |
CN105735078B (en) * | 2016-03-10 | 2017-10-13 | 长沙理工大学 | A kind of double layer continuous reinforced concrete pavement structure suitable for area of heavy rainfull |
CN107035007A (en) * | 2017-05-22 | 2017-08-11 | 中国能源建设集团广东省电力设计研究院有限公司 | Expanded joint structure and its construction technology |
CN114232681A (en) * | 2021-12-30 | 2022-03-25 | 中国二十冶集团有限公司 | Utility tunnel expansion joint structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203034492U (en) | Reinforced concrete pipe ditch deformation seam | |
CN202689046U (en) | Closed advanced water sealing post-cast strip | |
CN201176640Y (en) | Grouting type expansion steel edge water-stop meet with water | |
CN203498799U (en) | Prefabricated hollow pipe pile water-facing envelop enclosure | |
CN204753627U (en) | Prefabricated comprehensive piping lane | |
CN104790435A (en) | Post-subsidence pouring belt advancing waterstop impermeable concrete structure and construction technology thereof | |
CN102367735B (en) | Back-to-back waterstop installation equipment for tunnel construction joint | |
CN206432677U (en) | A kind of tunnel all standing formula cable duct | |
CN103806412A (en) | Water leakage repair structure for water pool expansion joint | |
CN204662506U (en) | A kind of cable communication well | |
CN106088758B (en) | A kind of bilayer assembled underground granary | |
CN206035052U (en) | Prefabricated caulking strips's in area circular underground granary of outer steel plated assembled | |
CN206035045U (en) | Prefabricated assembled underground granary of endocyst plastics | |
CN204691255U (en) | Diaphragm wall | |
CN204690730U (en) | Diaphragm wall skeleton | |
CN204343251U (en) | Horizontal connection structure between a kind of concrete cut and concrete structure | |
CN203668975U (en) | Sedimentation post-cast strip advancing water stopping anti-permeability concrete structure | |
CN203741782U (en) | Multi-section face plate structure of high concrete faced rockfill dam | |
CN202451974U (en) | Anti-floating structure of buried pipeline | |
CN207092031U (en) | A kind of dam | |
CN206035046U (en) | Inside and outside prefabricated assembled underground granary of plastics echelonment that all wraps | |
CN206941658U (en) | The double water sealing structures of concrete extension joint | |
CN206189971U (en) | Circular underground granary of prefabricated assembled of outer steel plated | |
CN206035044U (en) | Prefabricated assembled underground granary of plastic cover echelonment | |
CN206053490U (en) | A kind of stepped prefabricated assembled rectangular underground granary of interior encased steel plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 050031 No. 6 Jianhua Street, Shijiazhuang City, Hebei Province Patentee after: POWERCHINA HEBEI ELECTRIC POWER ENGINEERING Co.,Ltd. Address before: 050031 No. 6 Jianhua Street, Shijiazhuang City, Hebei Province Patentee before: HEBEI ELECTRIC POWER DESIGN & Research Institute |
|
CP01 | Change in the name or title of a patent holder | ||
CX01 | Expiry of patent term |
Granted publication date: 20130703 |
|
CX01 | Expiry of patent term |