CN104420485B - Underground space leaking type water stopping method for utility tunnel - Google Patents

Underground space leaking type water stopping method for utility tunnel Download PDF

Info

Publication number
CN104420485B
CN104420485B CN201310365833.3A CN201310365833A CN104420485B CN 104420485 B CN104420485 B CN 104420485B CN 201310365833 A CN201310365833 A CN 201310365833A CN 104420485 B CN104420485 B CN 104420485B
Authority
CN
China
Prior art keywords
waterstop
top surface
water
underground space
trench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310365833.3A
Other languages
Chinese (zh)
Other versions
CN104420485A (en
Inventor
王瑜
张志敏
王洪伟
张磊
何义常
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201310365833.3A priority Critical patent/CN104420485B/en
Publication of CN104420485A publication Critical patent/CN104420485A/en
Application granted granted Critical
Publication of CN104420485B publication Critical patent/CN104420485B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures

Abstract

The invention relates to an underground space leaking type water stopping method for a utility tunnel. The method comprises the steps of 1, excavating a trench; 2, mounting water stops and internal supports; and 3, mounting decorative plates; when excavating the trench, water accumulated in a pipe trench is removed, then steams are respectively cut in the bottom surface, sidewalls and the top surface of a pipe trench from two edges of a deformation joint by a cutting machine, and finally concrete between the two seams is excavated to remove, so as to form the trench; another trench excavating mode is that the salient part on the top surface of the pipe trench in a differential settlement section is cut off, and then a concave groove is formed with the assisting of angle steel which is fixed in the part through bolts; when mounting the water stops and the internal supports, the water stops are mounted from top to bottom by sections, that is, the water stops are positioned on the top surface firstly, the sidewalls are secondly, and the bottom surface is thirdly; after the water stops are mounted in place, the internal supports for supporting and extruding are timely mounted into the concave grooves in the water stops by sections; when being mounted, the decorative plates are arranged on the top surface and the sidewalls of the pipe trench, sections of the decorative plates are groove-shaped, and two sides are fixed by the position, wherein a circular hole is drilled in one side, and a long hole is drilled in the other side. The underground space leaking type water stopping method for the utility tunnel is simple and effective, a few investments are needed, and the popularization and application prospect is great.

Description

The water-stopping method of integrated pipe canal underground space seepage
Technical field
The present invention relates to a kind of water-stopping method of underground space seepage, specifically integrated pipe canal underground space seepage Water-stopping method.
Background technology
With the construction of urban infrastructure and perfect, increasing urban road is concentrated in the form of integrated pipe canal Arrangement pipeline, but exist with the difference of geological condition along the line because integrated pipe canal is linearly arranged, after road comes into operation, In the presence of vehicular load, integrated pipe canal more or less occurs some sedimentations or lateral displacement, especially through soft Ji Chu The roadbed of reason, its settlement after construction and relative settlement become apparent from, and the persistent period is longer, and serious even causes integrated pipe canal Movement joint rubber fastening band tears leak, Given this situation, in order to avoid secondary excavation is keeped in repair in leak stopping, affects road, and one As take the method that blocked inside pipe trench to process.For tiny leakage point, blocked using chemical grouting putty(Such as PU Grouting leak-stopping glue), comparatively easily, but, settle not yet stability region, the more serious integrated pipe canal of leak for being located in There is the situation of tear in rubber fastening band, then block more difficult.
The content of the invention
It is contemplated that overcoming the defect of prior art, there is provided a kind of water-stopping method of integrated pipe canal underground space seepage, Method is simple, effective, and input cost is low, it is easy to which general constructing operation personnel grasp, and relatively have wide popularizing application prospect.
In order to solve above-mentioned technical problem, what the present invention was realized in:
A kind of water-stopping method of integrated pipe canal underground space seepage, it is characterised in that:It comprises the steps:
Step one:Fluting;
Adjacent two sections of pipe trench movement joint leak:Pipe trench hydrops are excluded first, on movement joint both sides with cutting machine successively in pipe Ditch bottom surface, side wall, top surface joint-cutting, afterwards by the concrete chisel removal between two seams, form groove, and channel bottom is repaiied chisel, is polished flat It is whole;Pipe trench corner is using artificial fluting, and groove width is more than mechanical slotting width, afterwards, floating with cement mortar;When adjacent two Section pipe trench has differential settlement and dislocation simultaneously when, by a raised area excision part for settling section pipe trench top surface, Ran Hou The pipe trench top surface of movement joint another side arranges angle steel, and reinforcing plate is provided with angle steel, makes the top surface of angle steel high-rise and the raised area Top surface is high-rise consistent;
Step 2:Lay waterstop and internal stay support;
Waterstop is provided with a groove, and width and the sealing bandwidth of the groove are adapted, and waterstop is along integrated pipe canal inwall Surrounding ring is laid, and its length is consistent with inwall girth, and the reserved lap of splice;Waterstop width requirement is adapted with groove;
Waterstop adopts cold-adhered mode bonding, needs bonding plane polishing machine to be polished into inclined-plane waterstop before bonding, and Keep bonding plane clean, bonded joint is arranged on the bottom surface of integrated pipe canal, the position of neighbouring hydrops ditch;
Waterstop is laid from top to bottom, carries out paragraph by paragraph, i.e., first top surface, then side wall, rear bottom surface;
It is piecewise in time that internal stay support is laid in the groove of waterstop after waterstop is in place, internal stay support is passed through during placement Support squeeze, first waterstop is fixed temporarily, after waterstop all it is in place install after, then fasten the support of internal stay support paragraph by paragraph and squeeze only Water band;
Step 3:Mounting decoration panel;
Decoration panel adopts prefabricated reinforced concrete aisle cover plate or steel grating located at pipe trench top surface and side wall, pipe trench bottom surface, Decoration panel is made using corrosion resistant plate, and its section configuration is grooved, and decoration panel both sides drilling, a sidetracking circular hole, opposite side is being justified Hole correspondence position bores elongated hole, during installation, is screwed.
The water-stopping method of described integrated pipe canal underground space seepage, it is characterised in that:Lancing location in the step one It is 10cm each away from movement joint both sides.
The water-stopping method of described integrated pipe canal underground space seepage, it is characterised in that:The width of groove in the step one Spend for 20cm.
The water-stopping method of described integrated pipe canal underground space seepage, it is characterised in that:Pipe trench bottom surface in the step one Using slab cutter joint-cutting, side wall and top surface adopt hand-held concrete cutting machine joint-cutting, and joint-cutting depth is 3cm.
The water-stopping method of described integrated pipe canal underground space seepage, it is characterised in that:The lap of splice in the step 2 For 20cm.
The water-stopping method of described integrated pipe canal underground space seepage, it is characterised in that:Internal stay in the step 2 Frame includes the screw rod of about two supports being oppositely arranged and connecting bracket, and the support includes a cross bar, cross bar top At least one pair of diagonal brace group is provided with, two diagonal brace its one ends of each pair diagonal brace group are connected respectively with cross bar;The other end prolongs upwards respectively Intersecting direction extends, by a nut connection between the end;Connected by screw rod between the nut of two supports.
The water-stopping method of described integrated pipe canal underground space seepage, it is characterised in that:The cross bar is provided with three pairs tiltedly Support group, the within angle between the diagonal brace and cross bar is 60 °, the screw rod two ends reverse screw thread each other.
The invention has the beneficial effects as follows:Process is simple, it is easy to operate, it is easy to which that general staff grasps;Implement inside pipe trench, Avoid carrying out road secondary excavation, affect road;Implementation cost is low, and effect is directly perceived, can implement many in same leakage point Secondary closure.
Description of the drawings
Below in conjunction with the accompanying drawings the present invention is described in further detail with embodiment:
Fig. 1 is the structural representation slotted after waterstop tear of the present invention.
Fig. 2 is pipe trench sedimentation of the present invention and the structural representation for misplacing and slotting after waterstop tear.
Fig. 3 is structural representation of the present invention through the external labeling type rubber fastening band of processing.
Fig. 4 is the structural representation of waterstop of the present invention and internal stay mount.
Fig. 5 is the structural representation of waterstop and internal stay mount under pipe trench sedimentation of the present invention and misalignment.
Fig. 6 is the structural representation of decoration panel.
Fig. 7 is the side view of Fig. 6.
Fig. 8 is the structural representation of internal stay support.
Specific embodiment
A kind of water-stopping method of integrated pipe canal underground space seepage, it comprises the steps:
Step one:Fluting;
As shown in Figure 1:Adjacent two sections of pipe trench movement joint leak, former waterstop 2 tears:First exclude pipe trench hydrops, away from With cutting machine successively in pipe trench bottom surface, side wall, top surface joint-cutting at each 10cm in movement joint both sides, afterwards by the concrete between two seams Cut, form the wide grooves 1 of about 20cm, channel bottom is repaiied chisel, polished flat;Cut using slab cutter pipe trench bottom surface Seam, side wall and top surface adopt hand-held concrete cutting machine joint-cutting, and joint-cutting depth is 3cm;Opened using artificial fluting pipe trench corner Well width is more than mechanical slotting width, afterwards, floating with cement mortar;When adjacent two sections of pipe trench exist simultaneously differential settlement and During dislocation, as shown in Figure 2:After fluting, the raised area of the pipe trench top surface of settling section is cut off, then pass through bolt at the position An angle steel 3 is fixed, reinforcing plate 4 is provided with angle steel, the groove of internal stay mount is easy in formation;
Step 2:Lay waterstop and internal stay support;
Rubber fastening band 5 used typically adopts flat board rubber strip, and the external labeling type rubber water-proof through processing may also be employed Band replaces, as shown in Figure 3:External labeling type rubber fastening band through processing is provided with a groove 6, width and the sealing bandwidth of the groove Degree is adapted, and sealing tape thickness is generally 5-6mm, and waterstop is along the laying of integrated pipe canal inwall surrounding ring, its length and inwall Girth is consistent, and the lap of splice of reserved 20cm;Waterstop width requirement is adapted with groove;
As shown in Figure 4,5:Waterstop adopts cold-adhered mode bonding, adhesive glue to adopt and meet country and the relevant matter of industry The rubber fastening band High-strength adhesive that amount is required, is connected in the form of overlap joint, needs bonding plane to grind waterstop before bonding Ray machine is polished into inclined-plane, and keeps bonding plane clean, and bonded joint is arranged on the bottom surface of integrated pipe canal, the position of neighbouring hydrops ditch Put;
Waterstop is laid from top to bottom, carries out paragraph by paragraph, i.e., first top surface, then side wall, rear bottom surface;
It is piecewise in time that internal stay support 7 is laid in the groove of waterstop after waterstop is in place, internal stay support is passed through during placement Support squeeze, first waterstop is fixed temporarily, after waterstop all it is in place install after, then fasten the support of internal stay support paragraph by paragraph and squeeze only Water band;
Step 3:Mounting decoration panel;
As shown in Figure 6,7:Decoration panel 8 adopts prefabricated reinforced concrete aisle located at pipe trench top surface and side wall, pipe trench bottom surface Cover plate or steel grating, decoration panel is made using corrosion resistant plate, and its section configuration is grooved, and decoration panel both sides drilling a, sidetracking is justified Hole 9, opposite side bores elongated hole 10 in circular hole correspondence position, during installation, is screwed.
As shown in Figure 8:The internal stay support includes the screw rod of about two supports being oppositely arranged and connecting bracket, institute Support is stated including a cross bar 11, cross bar top is provided with least one pair of diagonal brace group, two its one ends of diagonal brace 12 of each pair diagonal brace group It is connected with cross bar respectively;The other end prolongs upwards respectively intersecting direction and extends, and is connected by a nut 13 between the end;Two Connected by screw rod 14 between the nut of frame;The cross bar is provided with three pairs of diagonal brace groups, the inner clip between the diagonal brace and cross bar Angle is 60 °, the screw rod two ends reverse screw thread each other.

Claims (7)

1. a kind of water-stopping method of integrated pipe canal underground space seepage, it is characterised in that:It comprises the steps:
Step one:Fluting;
Adjacent two sections of pipe trench movement joint leak:Pipe trench hydrops are excluded first, on movement joint both sides with cutting machine successively at pipe trench bottom Face, side wall, top surface joint-cutting, afterwards by the concrete chisel removal between two seams, form groove, and channel bottom is repaiied chisel, polished flat;Pipe Ditch corner is using artificial fluting, and groove width is more than mechanical slotting width, afterwards, floating with cement mortar;When adjacent two sections pipes Ditch has differential settlement and dislocation simultaneously when, by a raised area excision part for settling section pipe trench top surface, then in deformation The pipe trench top surface of seam another side arranges angle steel, and reinforcing plate is provided with angle steel;Make the high-rise top surface with the raised area of top surface of angle steel It is high-rise consistent;
Step 2:Lay waterstop and internal stay support;
Waterstop is provided with a groove, and width and the sealing bandwidth of the groove are adapted, and waterstop is along integrated pipe canal inwall surrounding Ring is laid, and its length is consistent with inwall girth, and the reserved lap of splice;Waterstop width requirement is adapted with groove;
Waterstop adopts cold-adhered mode bonding, needs bonding plane polishing machine to be polished into inclined-plane waterstop before bonding, and keeps Bonding plane is clean, and bonded joint is arranged on the bottom surface of integrated pipe canal, the position of neighbouring hydrops ditch;
Waterstop is laid from top to bottom, carries out paragraph by paragraph, i.e., first top surface, then side wall, rear bottom surface;
It is piecewise in time that internal stay support is laid in the groove of waterstop after waterstop is in place, by the support of internal stay support during placement Squeeze, first temporarily fix waterstop, after waterstop all it is in place install after, then fasten the support of internal stay support paragraph by paragraph and squeeze sealing Band;
Step 3:Mounting decoration panel;
, located at pipe trench top surface and side wall, pipe trench bottom surface is using prefabricated reinforced concrete aisle cover plate or steel grating, facing for decoration panel Plate is made using corrosion resistant plate, and its section configuration is grooved, and decoration panel both sides drill, a sidetracking circular hole, and opposite side is in circular hole pair Answer position to bore elongated hole, during installation, be screwed.
2. the water-stopping method of integrated pipe canal underground space seepage according to claim 1, it is characterised in that:The step one Middle lancing location is 10cm each away from movement joint both sides.
3. the water-stopping method of integrated pipe canal underground space seepage according to claim 1, it is characterised in that:The step one The width of middle groove is 20cm.
4. the water-stopping method of integrated pipe canal underground space seepage according to claim 1, it is characterised in that:The step one Middle pipe trench bottom surface adopts slab cutter joint-cutting, side wall and top surface to adopt hand-held concrete cutting machine joint-cutting, joint-cutting Depth is 3cm.
5. the water-stopping method of integrated pipe canal underground space seepage according to claim 1, it is characterised in that:The step 2 The middle lap of splice is 20cm.
6. the water-stopping method of integrated pipe canal underground space seepage according to claim 1, it is characterised in that:The step 2 In internal stay support include the screw rod of about two supports being oppositely arranged and connecting bracket, the support includes a horizontal stroke Bar, cross bar top is provided with least one pair of diagonal brace group, and two diagonal brace its one ends of each pair diagonal brace group are connected respectively with cross bar;The other end Prolong intersecting direction upwards respectively to extend, by a nut connection between the end;Connected by screw rod between the nut of two supports Connect.
7. the water-stopping method of integrated pipe canal underground space seepage according to claim 6, it is characterised in that:On the cross bar It is provided with three pairs of diagonal brace groups, the within angle between the diagonal brace and cross bar is 60 °, the screw rod two ends reverse screw thread each other.
CN201310365833.3A 2013-08-21 2013-08-21 Underground space leaking type water stopping method for utility tunnel Active CN104420485B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310365833.3A CN104420485B (en) 2013-08-21 2013-08-21 Underground space leaking type water stopping method for utility tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310365833.3A CN104420485B (en) 2013-08-21 2013-08-21 Underground space leaking type water stopping method for utility tunnel

Publications (2)

Publication Number Publication Date
CN104420485A CN104420485A (en) 2015-03-18
CN104420485B true CN104420485B (en) 2017-04-19

Family

ID=52970547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310365833.3A Active CN104420485B (en) 2013-08-21 2013-08-21 Underground space leaking type water stopping method for utility tunnel

Country Status (1)

Country Link
CN (1) CN104420485B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108729475A (en) * 2017-04-25 2018-11-02 中国二十冶集团有限公司 Underground structure multi-layer combined type expansion joint waterproof construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1982541A (en) * 2005-12-14 2007-06-20 李应芝 Underground channel of hydroelectric station and cavity group waterproofing and leakage-stopping construction
CN103184747A (en) * 2013-02-26 2013-07-03 上海隧道工程股份有限公司 Method and structure for leakage seepage prevention construction for two-walls-in-one structure of deep-underground engineering
CN203034492U (en) * 2012-12-10 2013-07-03 河北省电力勘测设计研究院 Reinforced concrete pipe ditch deformation seam

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3889113B2 (en) * 1997-05-12 2007-03-07 大成建設株式会社 Construction method of solidified water wall
JPH11229418A (en) * 1998-02-10 1999-08-24 Kubota Corp Underground water recharge method in earth-retaining wall composed of steel pipe column row

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1982541A (en) * 2005-12-14 2007-06-20 李应芝 Underground channel of hydroelectric station and cavity group waterproofing and leakage-stopping construction
CN203034492U (en) * 2012-12-10 2013-07-03 河北省电力勘测设计研究院 Reinforced concrete pipe ditch deformation seam
CN103184747A (en) * 2013-02-26 2013-07-03 上海隧道工程股份有限公司 Method and structure for leakage seepage prevention construction for two-walls-in-one structure of deep-underground engineering

Also Published As

Publication number Publication date
CN104420485A (en) 2015-03-18

Similar Documents

Publication Publication Date Title
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
CN110878700B (en) Tunnel waterproof structure and construction method thereof
CN103821180B (en) The two water-stopping structure of a kind of concrete extension joint
CN103114863A (en) Tunnel secondary lining back arch grouting pipe reserving system
CN107524174B (en) Continuous wall I-shaped steel joint with water swelling water stop strip
CN109751080A (en) The supporting construction and construction method with guarded drainage function suitable for water rich strata
CN102561405A (en) Opening treatment method for pipe-roofing continuous perforation
CN101532386B (en) Method and device for underpinning antifriction separator for shallow underground space construction
CN104420485B (en) Underground space leaking type water stopping method for utility tunnel
CN103205986A (en) Concrete raft foundation construction-joint grouting device and construction method
CN105756102A (en) Waterproof structure and process of integrated underground diaphragm wall and basement exterior wall
CN202401561U (en) Multifunctional environment-friendly movable water channel
CN102425228A (en) Multifunctional environment-friendly movable water tank
CN210797919U (en) Waterproof structure of wall deformation joint
CN111188648A (en) Tunnel water-proof and drainage system and construction method thereof
CN1362573A (en) Construction mode with full cross-section tunneller
CN212336350U (en) Deformation joint waterproof structure
CN204419202U (en) A kind of tunnel slot repair structure
CN211446883U (en) Underground continuous wall antiseep connection structure
CN205077393U (en) Seamless expansion joint structure
CN107151954A (en) A kind of type unballasted track bed plates of CRTS III drop supercharging fills curing means and fills the method for supporting
CN210562300U (en) Waterproof structure at joint of station main body and auxiliary channel
CN103774620B (en) The vertical water-stopping structure fixture in a kind of concrete work shrinkage joint
CN113931665A (en) Loose soil layer tunnel waterproof construction method
CN111749280A (en) Deformation joint waterproof structure and method

Legal Events

Date Code Title Description