High-tension cable snake laying worker well
Technical field
The utility model relates to a kind of high-tension cable comb and lays Gong Jing.
Background technology
After cable intermediate joint breaks down, need to make joint again behind cutting fault joint and the one section cable in both sides thereof, for this reason, should reserve surplus length in the both sides of cable intermediate joint, prepare against when making joint again and use.
When length adopts comb under the urban road, to lay apart from Voltage Cable Lines Construction at present,, be difficult to reserve surplus length in the cable intermediate joint both sides owing to reasons such as more, that the high-tension cable bending radius is bigger are limited in the urban road.In case the transition joint fault need be equipped with cable and straight coupling again, behind the cable spreading, makes joint again, cause thus that interruption duration is long, difficulty of construction is big and the waste of assets.
Summary of the invention
The utility model is for avoiding above-mentioned existing in prior technology weak point, a kind of high-tension cable snake laying worker well being provided, so that in limited space, reserve surplus length for the making again of failure cable joint.
The utility model adopts following technical scheme for the technical solution problem:
The design feature of the utility model high-tension cable snake laying worker well is: cable adopts snake laying in straight line worker well; Said snake laying is that the length direction along cable laying is provided with suspension geometrical clamp and bottom anchor ear one by one at interval in straight line worker well; With said suspension geometrical clamp cable is suspended on worker's well top board; With said bottom anchor ear cable is fixedly installed on the plate of worker shaft bottom, forms the snake laying of cable.
The utility model is through respectively being provided with the snake laying worker of a place well in cable joint Gong Jing both sides; Make cable in the snake laying worker well make the big radian snake laying of vertical direction; When cable joint breaks down again joint, the snake laying part cut-off in the snake laying worker well can be obtained again the required surplus length of joint.
Compared with present technology, the utility model is reserved surplus length for the making again of failure cable joint in limited space, greatly convenient construction, shortening interruption duration, the waste of minimizing assets.
Description of drawings
Fig. 1 is the utility model structural representation;
Label among the figure: 1 cable; 2 straight line worker wells; 2a worker's well top board; 2b worker shaft bottom plate; 3 suspension geometrical clamps; 4 bottom anchor ears.
Embodiment
Referring to Fig. 1; The structure setting of present embodiment medium and high voltage cable snake laying worker well is: cable 1 adopts snake laying in straight line worker well 2; Snake laying is that the length direction along cable laying is provided with suspension geometrical clamp 3 and bottom anchor ear 4 one by one at interval in straight line worker well 2; By each suspension geometrical clamp 3 cable 1 is suspended on worker's well top board 2a, cable 1 is fixedly installed on the plate 2b of worker shaft bottom, form the big radian snake laying of cable with bottom anchor ear 4.
In the practical implementation, the width of snake laying worker well and highly all close with general worker's well does not need to excavate on a large scale in work progress; In cable joint Gong Jing both sides the one snake laying worker of place well is set respectively, the new cable end of making of can attaching most importance to provides effective surplus length, the investment after can accomplishing reparation behind the cable fault quickly and easily, shortening interruption duration and save fault.
With 220kV double loop cable line is example, and 26 meters long snake laying worker well can provide 2 meters of the surplus length of cable.