CN103452558A - Cutting method for sublevel caving mining - Google Patents

Cutting method for sublevel caving mining Download PDF

Info

Publication number
CN103452558A
CN103452558A CN2013103968255A CN201310396825A CN103452558A CN 103452558 A CN103452558 A CN 103452558A CN 2013103968255 A CN2013103968255 A CN 2013103968255A CN 201310396825 A CN201310396825 A CN 201310396825A CN 103452558 A CN103452558 A CN 103452558A
Authority
CN
China
Prior art keywords
row
medium
cutting
length
blasting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103968255A
Other languages
Chinese (zh)
Other versions
CN103452558B (en
Inventor
宫国慧
田迎春
陈继宏
齐双飞
马东
郭海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Angang Group Mining Co Ltd
Original Assignee
Angang Group Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Angang Group Mining Co Ltd filed Critical Angang Group Mining Co Ltd
Priority to CN201310396825.5A priority Critical patent/CN103452558B/en
Publication of CN103452558A publication Critical patent/CN103452558A/en
Application granted granted Critical
Publication of CN103452558B publication Critical patent/CN103452558B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a cutting method for sublevel caving mining. The upward excavation is performed in a cutting roadway. The cutting method is characterized by comprising the following steps: (a), uniformly forming two rows of large-aperture medium-length holes in parallel in a position in which a cutting well is about to be dug according to the design height of the cutting well, uniformly forming two rows of blasting medium-length holes along the cutting roadway side of each row of large-aperture medium-length holes in parallel, performing millisecond blasting on the two rows of blasting medium-length holes, uniformly forming a third row of blasting medium-length holes behind the second row of blasting medium-length holes in parallel, and performing secondary blasting, wherein the large-aperture diameter of each large-aperture medium-length hole is 120mm to 200mm, a hole-edge interval is 100mm to 150mm, the aperture of each blasting medium-length hole is 55mm to 75mm, and a hole interval in the third row of blasting medium-length holes and the row distance between the second row of blasting medium-length holes and the third row of blasting medium-length holes are 500mm to 600mm; (b), uniformly forming blasting medium-length holes in sequence row by row in parallel behind the third row of holes, and performing one-row blasting one time or two-row millisecond blasting one time, wherein the hole interval and the row distance are 800mm to 1,200mm.

Description

A kind of cutting method of sublevel caving method mining
Technical field
The present invention relates to a kind of cutting method of sublevel caving method mining.
Background technology
Sublevel caving is that the metal mine underground mining is generally applied a kind of method, the stoping operation of this mining methods all carries out in stope drift active workings, the cutting tunnel is substantially perpendicular to stope drift active workings, the cutting well has been done in cutting end, tunnel, usings the cutting well as the scope of freedom, in the cutting tunnel, cut medium-length hole blasting, pull out and just arrange the medium-length hole blasting free space, just just arranging medium-length hole blasting, carry out stoping operation.
Its cutting is to carry out in the cutting tunnel in each substoping nugget, and its cutting method is:
The one, (common law is used the overhead driller rock drilling exactly, with timber, sets up platform, carries out the driling explosion construction, drives design height first to do the cutting well in the both ends or one end in cutting tunnel by common law;
The 2nd, from cutting well position, by distance and array pitch at the bottom of less hole, on carrying out by row in the cutting lane, to fan shaped medium length hole, construct;
The 3rd, take and cut well as the scope of freedom, start to carry out each row or two row's cutting fan shaped round blastings from cutting well position.
Form cutting room by above three steps.
The problem that this cutting technique exists is:
The one, need to manually do the cutting well, cutting well height is generally all in the 15-25m left and right, has that work high above the ground, blasting fume are poisoning, wall caving roof fall an etc. potential safety hazard, drives constructional difficulties, long in time limit.The aperture explosive payload of fan shaped medium length hole is concentrated, and powder charge is not easy to control, and easily occurs bulk after explosion, and after explosion, lower cinder notch is subject to lateral openingly to affect greatlyr, sometimes is not easy lower slag.
Summary of the invention
For overcoming the shortcoming of above-mentioned prior art, the technical problem to be solved in the present invention is to provide a kind of cutting method of sublevel caving method mining, does not drive specially the cutting well, does not make fan-shaped cutting construction, all by the parallel hole explosion, realizes the method for cutting.
For achieving the above object, the present invention is achieved by following technical proposals:
The cutting method of a kind of sublevel caving method mining is upwards drived in the cutting tunnel, it is characterized in that comprising the steps: that a will do cutting well position, by the cutting well design height two row large aperture medium-length holes that evenly are arranged in parallel; Its large aperture diameter is 120-200mm, and limit, hole spacing is 100-150mm; Every row large aperture medium-length hole along the cutting tunnel side two explosive broken medium-length holes that evenly are arranged in parallel, its aperture is 55-75mm; Two explosive broken medium-length holes are carried out to short-delay blasting; The 3rd explosive broken medium-length hole that evenly is arranged in parallel after second row explosion medium-length hole, pitch of holes and and second row explosion medium-length hole between array pitch be 500-600mm, carry out explosion for the second time; B after the 3rd round, the explosion medium-length hole that evenly is arranged in parallel by row successively, pitch-row and array pitch are 800-1200mm, explosive broken or once two row's short-delay blastings.
It is the scope of freedom that the parallel medium-length hole in large aperture is take in the present invention, has solved the safety problem that artificial construction's courtyard brings, and has saved manpower and materials simultaneously, with parallel medium depth holes millisecond blasting, strengthens crushing effect, forms cutting well free space.The hole explosion of the even cloth of parallel medium-length hole, guaranteed breaking size, reduces the human and material resources consumption of secondary blasting, reduced labour intensity, improved production efficiency.
The accompanying drawing explanation
Fig. 1 is the cutting method floor map of sublevel caving method mining.
Fig. 2 is explosion on line mode schematic diagram.
Wherein, the 1st, large aperture medium-length hole, the 2nd, explosion medium-length hole, the 3rd, cutting well position, the 4th, cutting tunnel, 1' are that the first row explosion medium-length hole section of detonating is other, 2' is that the second row explosion medium-length hole section of detonating is other, 3' is that the 3rd explosive broken medium-length hole section of detonating is other.
The specific embodiment
Below in conjunction with accompanying drawing, the invention will be further described:
As shown in Figure 1, a kind of cutting method of sublevel caving method mining, in cutting tunnel 4, upwards drive, the formation of a cutting well free space: do cutting well position 3, selecting diameter is the 120-200mm drill bit, is evenly arranged 1 liang of row of large aperture medium-length hole by cutting well design height is parallel, as the explosion scope of freedom, the diameter of each large aperture medium-length hole 1 is 120-200mm, and limit, hole spacing is 100-150mm; Two row large aperture medium-length holes 1 along the cutting tunnel 4 sides two explosive broken medium-length holes 2 that evenly are arranged in parallel, carry out short-delay blasting, two round millisecond times are less than or equal to 25ms, guarantee that the entity between each large aperture medium-length hole 1 can be fully broken, after going out only by quick-fried fallen slag, just form " cutting well " free space; For improving " cutting well " effect, rear the 3rd explosive broken medium-length hole 2 that evenly is arranged in parallel of second row explosion medium-length hole 2, it is 500-600mm that pitch of holes reaches with second row explosion medium-length hole 2 array pitch, the 3rd explosive broken medium-length hole 2 is carried out to explosion for the second time, further enlarge the scope of " cutting well " free space, and the increase compensating space in blasting, guaranteed normally carrying out of follow-up explosion medium-length hole 2 explosions.
Wherein, the height of large aperture medium-length hole 1 and explosion medium-length hole 2, according to producing the actual needs design, be generally 12-30m.One row large aperture medium-length hole 1 number is 8-10,16-20 altogether of two row.
After the 3rd explosive broken medium-length hole 2, the explosion medium-length hole 2 that evenly is arranged in parallel successively, and pitch-row and array pitch 800-1200mm; One explosive broken or once two row's short-delay blastings, guaranteed demolition effect, thereby guaranteed cutting effect.
The blasting method of this cutting method as shown in Figure 2, in explosion on line figure, first row explosion medium-length hole 2 links together and carries out short-delay blasting with second row explosion medium-length hole 2, the other 1' of the first row explosion medium-length hole section of detonating and the other 2' time delay of the second row explosion medium-length hole section of detonating differ and are less than or equal to 25ms, wherein the other 1' time delay of the first row explosion medium-length hole section of detonating is less than the other 2' of the second row explosion medium-length hole section of detonating, therefore the first explosion of the first round, explosion after the second round, explosion is slagged tap after formation " cutting well ", again to the other 3' of the 3rd explosive broken medium-length hole section of the detonating operation of being detonated, further brush large " cutting well " space.Afterwards, parallel explosion medium-length hole 2 in cutting tunnel 4 is carried out to bursting work: onepull one row or once two row's short-delay blastings, slagging tap in explosion limit, limit, has guaranteed the driling explosion effect, makes cutting everything goes well with your work to finish.

Claims (2)

1. the cutting method of sublevel caving method mining is upwards drived in the cutting tunnel, it is characterized in that comprising the steps: that a will do cutting well position, by the cutting well design height two row large aperture medium-length holes that evenly are arranged in parallel; Its large aperture diameter is 120-200mm, and limit, hole spacing is 100-150mm; Every row large aperture medium-length hole along the cutting tunnel side two explosive broken medium-length holes that evenly are arranged in parallel, its aperture is 55-75mm; Two explosive broken medium-length holes are carried out to short-delay blasting; The 3rd explosive broken medium-length hole that evenly is arranged in parallel after second row explosion medium-length hole, pitch of holes and and second row explosion medium-length hole between array pitch be 500-600mm, carry out explosion for the second time; B after the 3rd round, the explosion medium-length hole that evenly is arranged in parallel by row successively, pitch-row and array pitch are 800-1200mm, explosive broken or once two row's short-delay blastings.
2. the cutting method that sublevel caving method according to claim 1 is dug up mine, it is characterized in that: described short-delay blasting millisecond time is less than 25ms.
CN201310396825.5A 2013-09-04 2013-09-04 A kind of cutting method of sublevel caving method mining Active CN103452558B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310396825.5A CN103452558B (en) 2013-09-04 2013-09-04 A kind of cutting method of sublevel caving method mining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310396825.5A CN103452558B (en) 2013-09-04 2013-09-04 A kind of cutting method of sublevel caving method mining

Publications (2)

Publication Number Publication Date
CN103452558A true CN103452558A (en) 2013-12-18
CN103452558B CN103452558B (en) 2015-08-05

Family

ID=49735341

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310396825.5A Active CN103452558B (en) 2013-09-04 2013-09-04 A kind of cutting method of sublevel caving method mining

Country Status (1)

Country Link
CN (1) CN103452558B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110530219A (en) * 2019-09-06 2019-12-03 中钢集团马鞍山矿山研究院有限公司 A kind of control blasting method reducing loss and dilution
CN110823034A (en) * 2019-11-25 2020-02-21 中交路桥建设有限公司 Soft rock foundation blasting method capable of controlling mass percentage after blasting

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4043596A (en) * 1975-08-11 1977-08-23 Occidental Oil Shale, Inc. Forming shale oil recovery retort by blasting into slot-shaped columner void
SU1136527A1 (en) * 1983-08-11 1992-01-07 Государственный Макеевский Научно-Исследовательский Институт По Безопасности Работ В Горной Промышленности Electric hydraulic installation for well breaking down of rock
RU2055303C1 (en) * 1993-05-21 1996-02-27 Московский государственный горный университет Process of blast breaking of rocks with stratified texture in stripping
RU2290597C2 (en) * 2004-06-25 2006-12-27 Геннадий Буржалиевич Алиев Method for conducting of drilling and blasting operations
CN102518438A (en) * 2012-01-06 2012-06-27 中南大学 Roof regeneration medium-length hole ore blast backfill mining method
CN102748029A (en) * 2012-07-05 2012-10-24 北京矿冶研究总院 Sectional mining method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4043596A (en) * 1975-08-11 1977-08-23 Occidental Oil Shale, Inc. Forming shale oil recovery retort by blasting into slot-shaped columner void
SU1136527A1 (en) * 1983-08-11 1992-01-07 Государственный Макеевский Научно-Исследовательский Институт По Безопасности Работ В Горной Промышленности Electric hydraulic installation for well breaking down of rock
RU2055303C1 (en) * 1993-05-21 1996-02-27 Московский государственный горный университет Process of blast breaking of rocks with stratified texture in stripping
RU2290597C2 (en) * 2004-06-25 2006-12-27 Геннадий Буржалиевич Алиев Method for conducting of drilling and blasting operations
CN102518438A (en) * 2012-01-06 2012-06-27 中南大学 Roof regeneration medium-length hole ore blast backfill mining method
CN102748029A (en) * 2012-07-05 2012-10-24 北京矿冶研究总院 Sectional mining method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
不明: ""分段崩落采矿法的应用_续二"", 《有色矿山》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110530219A (en) * 2019-09-06 2019-12-03 中钢集团马鞍山矿山研究院有限公司 A kind of control blasting method reducing loss and dilution
CN110823034A (en) * 2019-11-25 2020-02-21 中交路桥建设有限公司 Soft rock foundation blasting method capable of controlling mass percentage after blasting

Also Published As

Publication number Publication date
CN103452558B (en) 2015-08-05

Similar Documents

Publication Publication Date Title
CN102778182B (en) Beside-roadway topping pressure relief method of roadway driving along gob of small coal pillar influenced by dynamic pressure
CN107829742B (en) Caving-filling-open stope-caving mining method
CN102182461A (en) Efficient mining method for thick metal ore body in slanting
CN103790588B (en) A kind of gently inclined orebody is from slipping mining methods
CN105952450B (en) A kind of new method of the double stope collaboration exploitations in underground mine underground
CN105178961B (en) A kind of roomy stope borehole drilling stage open stope afterwards filling mining method
CN102953732A (en) Room-and-pillar major-diameter longhole inverted-step-like segmented lateral caving subsequent filling mining method
CN106223956B (en) Medium-length hole courtyard mining afterwards filling method
CN104989404A (en) Diagonal ore-break-down medium-length hole mining method for steeply-inclined thin vein ore body
CN103244180B (en) Gob-side entry driving surrounding rock control method using remaining small pillars
CN105626073B (en) A kind of mining methods for reserving cutting groove based on the method for mining by the way of filling
CN101285384B (en) Large diameter, deep borehole and non undercutting mining method
CN102720500A (en) Mechanized underground mining method for sharply inclined thin ore body
CN111058847B (en) Continuous large-aperture deep hole blasting mechanized mining method for thick and large ore body
CN108590649A (en) A kind of broken narrow vein medium-length hole recovery method of low-angle dip
CN105673014A (en) Method for controlling rock burst of hard roof jump mining working face
CN110145311A (en) Thick or thick phosphorus ore body underground mining method in a kind of low-angle dip
CN102337893B (en) Method for processing suspension top by medium-deep hole blasting on upper and lower shoes
CN108625855B (en) Mining method under filling body
CN104594903A (en) Ore breaking method for whole-section high combination rock drilling blasting
CN105370280B (en) A kind of double-deck thin jade ore deposit nondestructive blasting mining methods of underground low-angle dip
CN103437766A (en) In-situ fragmentation mining method
CN101893415A (en) Blasting method by arch roof control and smooth-surface pillar control
CN105298493B (en) Underground low-angle dip lamelliform jade ore deposit nondestructive blasting mining methods
CN105863727A (en) Method for treating pillar goaf

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 114001 Anshan District, Liaoning, No. 219 Road, No. 39, Tiedong

Patentee after: Anshan Iron and Steel Group Mining Co., Ltd.

Address before: 114001 Anshan District, Liaoning, No. 219 Road, No. 39, Tiedong

Patentee before: Anshan Iron & Steel Group Mining Co., Ltd.