CN106223956B - Medium-length hole courtyard mining afterwards filling method - Google Patents

Medium-length hole courtyard mining afterwards filling method Download PDF

Info

Publication number
CN106223956B
CN106223956B CN201610717932.7A CN201610717932A CN106223956B CN 106223956 B CN106223956 B CN 106223956B CN 201610717932 A CN201610717932 A CN 201610717932A CN 106223956 B CN106223956 B CN 106223956B
Authority
CN
China
Prior art keywords
courtyard
nugget
boring machine
hole
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610717932.7A
Other languages
Chinese (zh)
Other versions
CN106223956A (en
Inventor
李学锋
程贵海
李朝军
谭定新
曾文俊
黄海斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University
Original Assignee
Guangxi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University filed Critical Guangxi University
Publication of CN106223956A publication Critical patent/CN106223956A/en
Application granted granted Critical
Publication of CN106223956B publication Critical patent/CN106223956B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Abstract

The invention discloses a kind of medium-length hole courtyard mining afterwards filling method, nugget is arranged along orebody trend, and the stage is divided on height hanging down;Nugget both ends arrangement adopts quasi- courtyard, and nugget bottom arranges that flat ore removal structure, nugget top arrange raise boring machine chamber, quasi- courtyard adopted using raise boring machine Drilling;Rock drilling, blasting work platform are promoted using raise boring machine lifting system, down-the-hole drill concentrates rock drilling, blasting in groups, concentrating mining, afterwards filling from courtyard both sides Drilling horizontal parallel or annular medium-length hole blasthole.The method is primarily adapted for use in steeply inclined thin to middle thickness orebody, overcome shrinkage method, sublevel open stope method or upward ut and fill stoping there are the problem of, with adopting, to cut quantities few, stope do mechanization operation degree is high, production efficiency is high, the advantages that production capacity is big, and personnel are not necessarily to enter stope operation, and safety condition is good.

Description

Medium-length hole courtyard mining afterwards filling method
Technical field
The invention belongs to field of mining more particularly to a kind of medium-length hole courtyard mining afterwards filling methods.
Background technology
Steeply dipping narrow deposits often use shrinkage method, sublevel open stope method or overhand cut and fill stoping exploitation to middle thickness orebody.Wherein, Shrinkage method stope exposure area is big, and mechanization degree is low, and labor intensity is big, and operation is dangerous etc.;Sublevel open stoping rule there is It adopts and cuts than big, the deficiencies of stope Ore loss and dilution rates are high;When being exploited according to slicing and filling mining codes, since work cycle is more, The deficiencies of process for stoping is complicated, causes low production efficiency, and labor intensity is big, and mining cost is high, and mine capacity is small.Moreover, Above-mentioned mining methods are required for driving to adopt quasi- courtyard, but it is traditional adopt quasi- upraise method, driving speed is slow, work efficiency is low, peace Full property is poor.
Invention content
The technical problem to be solved in the present invention is to provide a kind of job safety, mechanization degree is high, labor intensity is small, production The medium-length hole courtyard that ability is big, the back production time is short is dug up mine afterwards filling method, and it is relatively regular and to seek survival which is primarily adapted for use in ore body Big, the efficient steeply inclined thin of production capacity power to middle thickness orebody is exploited.
In order to solve the above technical problems, medium-length hole courtyard mining afterwards filling method provided by the invention uses following technical side Case:Nugget is arranged along orebody trend, and the stage is divided on height hanging down;Nugget both ends arrangement adopts quasi- courtyard, nugget bottom cloth horizontalization Bottom ore removal structure, nugget top arrange raise boring machine chamber, quasi- courtyard are adopted using raise boring machine Drilling;It is promoted using raise boring machine System improving rock drilling, blasting work platform;Down-the-hole drill is concentrated from courtyard both sides Drilling horizontal parallel or annular medium-length hole blasthole Rock drilling, blasting in groups, concentrating mining, afterwards filling.
Ore body is steeply inclined thin to middle thickness orebody.
Above-mentioned medium-length hole courtyard mining afterwards filling method, according to the following steps operation carry out:
A) nugget is arranged along orebody trend, is divided into mineral building and ore pillar, ore pillar includes studding and fore-set;
B) it arranges ore removal gallery along orebody trend, the tunnel that undercuts is arranged along ore body bottom, it is flat with dress mine route unicom ore removal Lane and the tunnel that undercuts;Nugget both ends arrangement adopts quasi- courtyard, and nugget top is arranged raise boring machine chamber, adopted using raise boring machine Drilling Quasi- courtyard;
C) after the completion of adopting quasi- courtyard, down-the-hole drill and down-the-hole drill workbench are transferred extremely using raise boring machine lifting system Work surface;Down-the-hole drill deep blasting hole from courtyard both sides Drilling horizontal parallel or annular;
D) in the tunnel Nei Kuo nations that undercut, caunch and to form the pulling end space of 3-6m high after, with raise boring machine lifting system along day Workbench and explosive loader are put to charging work face in underground, load bulk explosive using explosive loader, from bottom to top blasting in groups, root According to it needs to be determined that each explosion number of rows.Ore under explosion is shoveled out from dress mine route, is sent along ore removal gallery by scraper Into neighbouring drop shaft.In order to protect courtyard, away from this section not powder charge of aperture 4m, explosion back court both sides respectively leave the mine of about 3m wide Column.
E) after mineral building back production ore removal, according to adjacent stope situation recycling ore pillar, finally filling method is used to handle goaf.
Step (a) chats block length 40-50m, width are orebody thickness, level interval 50-80m, studding width 6-8m, fore-set thickness Spend 3-6m.
Ore removal gallery is away from ore body lower wall 8-10m, dress mine route spacing 6-8m in step (b).
Blasthole aperture is 50-70mm, hole depth 20-25m, blasthole array pitch 1.0-2.0m, blasthole spacing 0.8- in step (c) 2.5m。
When being exploited using shrinkage method, sublevel open stope method or upward ut and fill stoping for steeply inclined thin to middle thickness orebody Existing deficiency, inventor establish a kind of medium-length hole courtyard mining afterwards filling method, compared with the existing technology, advantage of the invention It is:
<1>The present invention carries out back production with stage overall height, and at nugget both ends, arrangement adopts quasi- courtyard, nugget bottom arrangement it is flat go out Mine structure, raise boring machine chamber is arranged on nugget top, simple in structure, adopts that cut quantities small.
<2>The present invention uses raise boring machine Drilling courtyard, high-quality at well, labor operation condition is good, production safety, machinery Change degree is high;Stoping operation is from courtyard both sides Drilling horizontal parallel or annular medium-length hole blasthole, using explosive loader powder charge, worker It works without entering in stope, labor operation condition is good, production safety, mechanization degree are high.
<3>The present invention uses raise boring machine Drilling courtyard, and Completed advance rate is fast, work efficiency is high;Using medium-length hole ore blast, chisel is concentrated Rock, blasting in groups, scraper ore removal, production capacity is big, and production efficiency is high, at low cost.
Description of the drawings
Fig. 1 is the reference chart using medium-length hole courtyard of the present invention mining afterwards filling method.
Fig. 2 is the cut-away view of the I-I lines in Fig. 1.
In figure:1 ore removal gallery, 2 dress mine routes, 3 courtyard connecting taxiways, 4 adopt quasi- courtyard, and 5 undercut tunnel, 6 raise boring machine caves Room, deep blasting hole in 7 horizontal parallels, 8 workbenches, 9 studdings, 10 raise boring machines, 11 drill bits, 12 lifting systems, 13 fore-sets, 14 is latent Drilling machine, 15 explosive loaders.
Specific implementation mode
The basic principle of medium-length hole courtyard mining afterwards filling method of the present invention
For steeply inclined thin to middle thickness orebody, nugget is arranged along orebody trend, and the stage is divided on height hanging down;Nugget both ends Arrangement adopts quasi- courtyard, and nugget bottom arranges that flat ore removal structure, nugget top arrange raise boring machine chamber;It is bored using raise boring machine Chisel adopts quasi- courtyard;Rock drilling, blasting work platform are promoted using raise boring machine lifting system;Down-the-hole drill is from courtyard both sides Drilling water Average row or annular medium-length hole blasthole, concentrate rock drilling, blasting in groups, concentrating mining, afterwards filling.
The method concrete operation step is as follows:
A) nugget is arranged along orebody trend, is divided into mineral building and ore pillar, ore pillar includes studding 9 and fore-set 13;The long 40- of nugget 50m, width are orebody thickness, level interval 50-80m, 9 width 6-8m of studding, 13 thickness 3-6m of fore-set.
B) tunnel 5 that undercuts is arranged along ore body bottom, with dress along orebody trend arrangement ore removal gallery 1 away from ore body lower wall 8-10m 2 unicom ore removal gallery of mine route and the tunnel that undercuts, dress mine route spacing 6-8m;Nugget both ends arrangement adopts quasi- courtyard 4, nugget top It arranges raise boring machine chamber 6, quasi- courtyard is adopted using 10 Drilling of raise boring machine;Quasi- courtyard 4 is adopted to get in touch with by courtyard with ore removal gallery 1 3 unicom of road;
C) after the completion of adopting quasi- courtyard, the drill bit 11 of raise boring machine 10 is unloaded;It is connected using raise boring machine lifting system 12 Workbench 8, down-the-hole drill 14 are fixed on workbench 8, after the decentralization to rock drilling working face of courtyard 4;Down-the-hole drill is from day Deep blasting hole 7 in well both sides Drilling horizontal parallel (or annular), aperture 50-70mm, hole depth 20-25m, blasthole array pitch 1.0- 2.0m, blasthole spacing 0.8-2.5m;
D) in the 5 Nei Kuo nations of tunnel that undercut, caunch and to form the pulling end space of 3-6m high after, raise boring machine lifting system 12 connects Workbench 8,15 powder charge of explosive loader is fixed on workbench 8, is transferred to charging work face along courtyard, using explosive loader 15 Bulk explosive is loaded, determines each explosion number of rows as needed, blasting in groups, the ore under explosion pass through scraper from bottom to top Machine is shoveled out from dress mine route 2, is sent into neighbouring drop shaft along ore removal gallery 1.;In order to protect courtyard, not away from aperture 4m this section Powder charge, explosion back court both sides respectively leave the ore pillar of 3m wide;
E) it after mineral building back production ore removal, according to adjacent stope situation recycling studding 9 and fore-set 13, finally uses at filling method Manage goaf.

Claims (4)

  1. The afterwards filling method 1. a kind of medium-length hole courtyard is dug up mine, it is characterised in that:Nugget is arranged along orebody trend, is divided on height hanging down For the stage;Nugget both ends arrangement adopts quasi- courtyard, and nugget bottom arranges that flat ore removal structure, nugget top arrange raise boring machine cave Quasi- courtyard is adopted in room using raise boring machine Drilling;Rock drilling, blasting work platform, hidden hole drilling are promoted using raise boring machine lifting system Machine concentrates rock drilling, blasting in groups, concentrating mining, afterwards filling from courtyard both sides Drilling horizontal parallel or annular medium-length hole blasthole; The ore body is steeply inclined thin to middle thickness orebody;The method operates progress according to the following steps:
    A) nugget is arranged along orebody trend, is divided into mineral building and ore pillar, ore pillar includes studding and fore-set;
    B) arrange ore removal gallery along orebody trend, along ore body bottom, arrangement undercuts tunnel, with dress mine route unicom ore removal gallery with Undercut tunnel;Nugget both ends arrangement adopts quasi- courtyard, and nugget top arranges raise boring machine chamber, quasi- day is adopted using raise boring machine Drilling Well;
    C) after the completion of adopting quasi- courtyard, down-the-hole drill and down-the-hole drill workbench are transferred to operation using raise boring machine lifting system Face;Down-the-hole drill deep blasting hole from courtyard both sides Drilling horizontal parallel or annular;Concentration rock drilling, explosive loader powder charge, from bottom to top Blasting in groups, scraper ore removal;
    D) after mineral building back production ore removal, according to adjacent stope situation recycling ore pillar, finally filling method is used to handle goaf.
  2. The afterwards filling method 2. medium-length hole courtyard according to claim 1 is dug up mine, it is characterised in that step (a) chats block length 40-50m, width are orebody thickness, level interval 50-80m, studding width 6-8m, fore-set thickness 3-6m.
  3. The afterwards filling method 3. medium-length hole courtyard according to claim 1 is dug up mine, it is characterised in that ore removal gallery in step (b) Away from ore body lower wall 8-10m, dress mine route spacing 6-8m.
  4. The afterwards filling method 4. medium-length hole courtyard according to claim 1 is dug up mine, it is characterised in that blasthole aperture in step (c) For 50-70mm, hole depth 20-25m, blasthole array pitch 1.0-2.0m, blasthole spacing 0.8-2.5m.
CN201610717932.7A 2016-06-30 2016-08-24 Medium-length hole courtyard mining afterwards filling method Active CN106223956B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610521210 2016-06-30
CN2016105212104 2016-06-30

Publications (2)

Publication Number Publication Date
CN106223956A CN106223956A (en) 2016-12-14
CN106223956B true CN106223956B (en) 2018-08-21

Family

ID=57555424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610717932.7A Active CN106223956B (en) 2016-06-30 2016-08-24 Medium-length hole courtyard mining afterwards filling method

Country Status (1)

Country Link
CN (1) CN106223956B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677780B (en) * 2017-02-21 2018-09-14 中冶北方(大连)工程技术有限公司 Bottom ore removal afterwards filling mining method is cut in a kind of upward and downward stage rock drilling segmentation
CN107448201A (en) * 2017-05-31 2017-12-08 陕西冶金设计研究院有限公司 A kind of steeply inclined thin is to the flat ore removal structure of middle strong vein and method
CN108086979B (en) * 2017-11-27 2019-09-20 西北矿冶研究院 Mining process of vertical deep hole columnar cartridge bag ore breaking stage by using chamber method
CN108590652B (en) * 2018-05-09 2019-05-21 中冶北方(大连)工程技术有限公司 A kind of sublevel caving method without sill pillar dividing a nugget along orebody trend
CN109322683A (en) * 2018-10-24 2019-02-12 临沂会宝岭铁矿有限公司 Underground Large chamber medium-length hole controls blasting construction method
CN110966005A (en) * 2019-11-22 2020-04-07 西北矿冶研究院 Novel medium-length hole ore-breaking stage chamber method
CN111779485A (en) * 2020-07-01 2020-10-16 长沙矿山研究院有限责任公司 Combined hole segmented open stope subsequent filling mining method
CN111963175B (en) * 2020-07-28 2022-06-17 广西大学 Thick ore body mining method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6848748B2 (en) * 2000-09-20 2005-02-01 Dbt Gmbh Mining system with drilling, loading, conveyor, and support
CN101737050A (en) * 2008-11-25 2010-06-16 宝钢集团上海梅山有限公司 Deep hole arranging method in mining
CN103527200A (en) * 2013-10-25 2014-01-22 河北省矾山磷矿有限公司 Sill-pillar-free sublevel rhombus room subsequent filling mining method
CN103615250A (en) * 2013-12-09 2014-03-05 中南大学 Subsection-studding all-open-stoping backfilling collaborative mining method
CN104154830A (en) * 2014-08-08 2014-11-19 西北矿冶研究院 Medium-length hole blasting method for underground mining

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6848748B2 (en) * 2000-09-20 2005-02-01 Dbt Gmbh Mining system with drilling, loading, conveyor, and support
CN101737050A (en) * 2008-11-25 2010-06-16 宝钢集团上海梅山有限公司 Deep hole arranging method in mining
CN103527200A (en) * 2013-10-25 2014-01-22 河北省矾山磷矿有限公司 Sill-pillar-free sublevel rhombus room subsequent filling mining method
CN103615250A (en) * 2013-12-09 2014-03-05 中南大学 Subsection-studding all-open-stoping backfilling collaborative mining method
CN104154830A (en) * 2014-08-08 2014-11-19 西北矿冶研究院 Medium-length hole blasting method for underground mining

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
水平中深孔采矿方法应用;张敬东;《黑龙江冶金》;20060531(第2期);第26-28页 *
胡旭东等;胡旭东等;《企业技术开发》;20101031;第29卷(第19期);第52-54页,第98页 *

Also Published As

Publication number Publication date
CN106223956A (en) 2016-12-14

Similar Documents

Publication Publication Date Title
CN106223956B (en) Medium-length hole courtyard mining afterwards filling method
CN102635356B (en) Medium-length hole mining method in multiple blasting free faces of high dipping thin veins
CN108625856B (en) Mining method for one ore removal roadway of two adjacent stopes of underground mine
CN104863592B (en) A kind of big structure sublevel drill and benching ore removal afterwards filling mining method
CN108547618A (en) A kind of two steps mining methods leave the recovery process of studding
CN105952450B (en) A kind of new method of the double stope collaboration exploitations in underground mine underground
CN104989404A (en) Diagonal ore-break-down medium-length hole mining method for steeply-inclined thin vein ore body
CN104453901A (en) Sublevel open-stoping mining method with subsequent backfilling for long-hole caving in thin ore bodies
CN101509377B (en) High-dipping ore block house column mining method
CN101285384B (en) Large diameter, deep borehole and non undercutting mining method
CN106640080B (en) Under a kind of deep high stress environment mining methods are arranged from steady gallery shape stope
CN104481539A (en) Extruding blasting caving mining method for self-pulling slot
CN111058847B (en) Continuous large-aperture deep hole blasting mechanized mining method for thick and large ore body
CN108798672B (en) A kind of mining methods for the area&#39;s ore high-efficiency mining that collapses greatly
CN103362510A (en) Sublevel-drilling bench-combination ore-removal sublevel-room mining method
CN104481543A (en) Sub-level shrinkage caving method
CN105464700A (en) Method for determining length of filling segment of fully mechanized mining and filling mixed mining working face
CN112502709B (en) Pre-control top intelligent mining method for vertical medium-length hole VCR ore breaking and immediate filling after explosion
CN112746847A (en) Mining method for slowly-inclined to inclined medium-thickness ore body
CN104612692B (en) Formation continuous filling mining method followed by segmentation ore caving polycrystalline substance
CN101725351A (en) Filling stope pillar recovery mining method
CN106593447B (en) A kind of underground mining gently inclined medium thick orebody mining methods
CN101737051A (en) Covering layer forming method of blind ore bodies
CN1195149C (en) Roof bolt protection and sectioned empty field method for phosphorate rock mining
CN109630116B (en) Mining method for inclined medium-thickness blind ore body

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant