CN103306683A - 一种开挖深埋隧道时洞内综合降水的施工方法 - Google Patents
一种开挖深埋隧道时洞内综合降水的施工方法 Download PDFInfo
- Publication number
- CN103306683A CN103306683A CN2013102409884A CN201310240988A CN103306683A CN 103306683 A CN103306683 A CN 103306683A CN 2013102409884 A CN2013102409884 A CN 2013102409884A CN 201310240988 A CN201310240988 A CN 201310240988A CN 103306683 A CN103306683 A CN 103306683A
- Authority
- CN
- China
- Prior art keywords
- hole
- precipitation
- deep
- predicament
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
一种开挖深埋隧道时洞内综合降水的施工方法,涉及隧道开挖领域,本发明通过在深埋隧道(5)的开挖面上挖出上台阶(7)、中台阶(8)和下台阶(9),并在上台阶、中台阶和下台阶上分别设置超前深孔降水孔(2)、轻型井点降水管(3)、初期支护(6)和垂直降水井(10),有效的降低了在施工过程中出现涌砂和溜塌的现象,大大提高了施工的安全性,本发明具有结构简单,操作方便等特点,能够有效达到降低隧道施工范围内地下水的目的,从而为深埋隧道的后续开挖提供了安全保证。
Description
【技术领域】
本发明涉及隧道开挖领域,尤其涉及一种开挖深埋隧道时洞内综合降水的施工方法,具体涉及一种在开挖深埋隧道时遭遇富水粉细砂层时使用的洞内三级综合降水的施工方法。
【背景技术】
已知的,富水未成岩粉细砂岩层又称富水粉细砂层,由于该岩层因富含水份而极不稳定,当在深埋隧道的施工过程中开挖到该岩层时,该岩层极易呈流塑状变型,从而导致在施工中出现涌砂、溜塌等现象,轻则造成隧道的初期支护变形,危及施工安全,重则导致隧道坍塌,引发安全事故,进而严重影响到深埋隧道的施工工期、工程质量以及生产安全和生产成本等,为避免富水粉细砂层对正在施工的隧道产生影响,目前国内用于降低隧道围岩地下水含量,即降低隧道施工范围内地层的地下水而对富水粉细砂层中富含的水份进行综合降水,而目前隧道开挖的方法仅有垂直降水井降水、结合洞内轻型井点降水和工作面超前降水等方法,然而实际施工中,由于深井降水主要适用于浅埋隧道的施工降水,在隧道内进行垂直降水井降水效果也是有效限的,如果仅采用洞内轻型井点降水的话,对于深埋隧道而言,其排水效果又十分有限,虽然工作面超前降水有一定效果,但是,在深埋隧道的开挖施工中采取单一降水措施是不能很好的达到施工要求的,所以现在极需提供一种能够针对富水粉细砂层的洞内综合降水方法。
【发明内容】
为了克服背景技术中存在的不足,本发明提供了一种开挖深埋隧道时洞内综合降水的施工方法,本发明通过在深埋隧道的开挖面上挖出上台阶、中台阶和下台阶,并在上台阶、中台阶和下台阶上分别设置超前深孔降水孔、轻型井点降水管、初期支护和垂直降水井,有效的降低了在施工过程中出现涌砂和溜塌的现象,大大提高了施工的安全性,本发明具有结构简单,操作方便等特点。
为实现如上所述的发明目的,本发明采用如下所述的技术方案:
一种开挖深埋隧道时洞内综合降水的施工方法,所述方法包括如下步骤:
第一步、首先对深埋隧道的开挖面分上、中、下三部分进行开挖,挖取后形成上台阶、中台阶和下台阶,然后分别对上台阶、中台阶和下台阶的底面进行平整,以便为上台阶开挖面的初期支护轮廓外侧施做超前深孔降水孔,上台阶、中台阶和下台阶边墙底部处施做轻型井点降水管和下台阶地面施做垂直降水井提供作业平台;
第二步、对深埋隧道中的上台阶、中台阶和下台阶分别设置初期支护,即进行立拱,每节拱架之间采用连接板连接拼装,拱架外侧铺设钢筋网片,两环拱架之间采用U型连接装置连接,喷射混凝土,施做锁脚锚杆;
第三步、在深埋隧道开挖断面上台阶的初期支护轮廓外侧设定超前深孔降水孔的位置、在上台阶、中台阶和下台阶的边墙底部设定轻型井点降水孔的位置和在下台阶的地面设定垂直降水井的位置;
第四步、在钻机作业平台设置钻机,并利用钻机按深埋隧道开挖的方向,沿上台阶的初期支护的轮廓外侧间隔钻设复数个超前深孔降水孔;
第五步、在超前深孔降水孔钻孔结束时,在钻孔的钻设套管拆除前,先向钻孔内插入超前深孔降水管,然后在降水管插入完毕后拨出套管,将降水管外端管壁与其周边富水粉细砂层之间的间隙密封回填,完成该钻孔内超前深孔降水管安装,直到全部超前深孔降水管的安装完成;
第六步、在上台阶、中台阶和下台阶的边墙底部,按照轻型井点降水管的预设位置,采用高压风或高压水冲孔,轻型井点降水管紧跟的方式埋设,直到全部轻型井点管完成埋设;
第七步、在下台阶底面的位置,通过钻机钻设垂直降水井,同时采用泥浆护壁,在设垂直降水井钻设完成后,下入垂直降水井管,井管下端设置有滤水孔的部分周边采用粗砂回填,管端与周边地层进行密封回填,完成垂直降水井埋设;
第八步、待所有降水管埋设完成后,把降水管分类与对应排水主管连接,保证各类型降水管抽水的独立性;
第九步、连续抽水,并在通过检测含水量的变化确认富水粉细砂层具有自稳性后,沿钻孔的长度方向进行隧道开挖,并在开挖过程中及时进行初期支护;
第十步、重复上述步,直至挖过富水粉细砂层或是深埋隧道开挖完成。
所述的开挖深埋隧道时洞内综合降水的施工方法,所述上台阶、中台阶和下台阶的台阶长度分别为4~5米,高度分别为3~5米。
所述的开挖深埋隧道时洞内综合降水的施工方法,所述超前深孔降水孔设置在上台阶的初期支护的外侧,所述超前深孔降水孔内的超前深孔降水管直径65毫米,环向间距为1米,长度为10~20米,超前深孔降水管滤水端长6~8米,包裹两层80~100目滤网。
所述的开挖深埋隧道时洞内综合降水的施工方法,所述轻型井点降水管设置在上台阶、中台阶和下台阶的边墙底部,轻型井点降水管的长度为3~5米,直径为Φ32毫米,材质为PVC管,轻型井点降水管滤水端长2米,外插角30~60°,纵向间距为0.5~0.75米。
所述的开挖深埋隧道时洞内综合降水的施工方法,所述垂直降水井设置在开挖仰拱前下台阶是底面位置,沿深埋隧道方向左右梅花形按间距10米设置,垂直降水井的直径为15~30厘米,深度为5~10米,垂直降水井的滤水端长3~5米。
所述的开挖深埋隧道时洞内综合降水的施工方法,所述的超前深孔降水孔的直径为5~10厘米,钻孔深度为8~30米,每两个超前深孔降水孔之间的孔间距为30~200厘米。
所述的开挖深埋隧道时洞内综合降水的施工方法,所述降水管外端管壁与周边100厘米范围内的富水粉细砂层之间的区域均密封回填。
采用如上所述的技术方案,本发明具有如下所述的优越性:
本发明所述的一种开挖深埋隧道时洞内综合降水的施工方法,本发明通过在深埋隧道的开挖面上挖出上台阶、中台阶和下台阶,并在上台阶、中台阶和下台阶上分别设置超前深孔降水孔、轻型井点降水管、初期支护和垂直降水井,有效的降低了在施工过程中出现涌砂和溜塌的现象,大大提高了施工的安全性,本发明具有结构简单,操作方便等特点,能够有效达到降低隧道施工范围内地下水的目的,从而为深埋隧道的后续开挖提供了安全保证。
【附图说明】
图1是本发明的施工方法的示意图;
图2是本发明图1的纵剖面示意图;
在图中:1、富水粉细砂层;2、超前深孔降水孔;3、轻型井点降水管;4、仰拱;5、深埋隧道;6、初期支护;7、上台阶;8、中台阶;9、下台阶;10、垂直降水井。
【具体实施方式】
通过下面的实施例可以更详细的解释本发明,本发明并不局限于下面的实施例;
结合附图1和2所述的一种开挖深埋隧道时洞内综合降水的施工方法,所述方法包括如下步骤:
第一步、首先对深埋隧道5的开挖面分上、中、下三部分进行开挖,挖取后形成上台阶7、中台阶8和下台阶9,所述上台阶7、中台阶8和下台阶9的台阶长度分别为4~5米,高度分别为3~5米,然后分别对上台阶7、中台阶8和下台阶9的底面进行平整,以便为上台阶7开挖面的初期支护6轮廓外侧施做超前深孔降水孔2,上台阶7、中台阶8和下台阶9边墙底部处施做轻型井点降水管3和下台阶9地面施做垂直降水井10提供作业平台;
第二步、对深埋隧道5中的上台阶7、中台阶8和下台阶9分别设置初期支护6,即进行立拱,每节拱架之间采用连接板连接拼装,拱架外侧铺设钢筋网片,两环拱架之间采用U型连接装置连接,喷射混凝土,施做锁脚锚杆;
第三步、在深埋隧道5开挖断面上台阶7的初期支护6轮廓外侧设定超前深孔降水孔2的位置、在上台阶7、中台阶8和下台阶9的边墙底部设定轻型井点降水孔3的位置和在下台阶9的地面设定垂直降水井10的位置,所述超前深孔降水孔2设置在上台阶7的初期支护6的外侧,所述超前深孔降水孔2内的超前深孔降水管直径65毫米,环向间距为1米,长度为10~20米,超前深孔降水管滤水端长6~8米,包裹两层80~100目滤网,所述轻型井点降水管3设置在上台阶7、中台阶8和下台阶9的边墙底部,轻型井点降水管3的长度为3~5米,直径为Φ32毫米,材质为PVC管,轻型井点降水管3滤水端长2米,外插角30~60°,纵向间距为0.5~0.75米,所述垂直降水井10设置在开挖仰拱4前下台阶9是底面位置,沿深埋隧道5方向左右梅花形按间距10米设置,垂直降水井10的直径为15~30厘米,深度为5~10米,垂直降水井10的滤水端长3~5米;
第四步、在钻机作业平台设置钻机,并利用钻机按深埋隧道5开挖的方向,沿上台阶7的初期支护6的轮廓外侧间隔钻设复数个超前深孔降水孔2,所述超前深孔降水孔2的直径为5~10厘米,钻孔深度为8~30米,每两个超前深孔降水孔2之间的孔间距为30~200厘米;
第五步、在超前深孔降水孔2钻孔结束时,在钻孔的钻设套管拆除前,先向钻孔内插入超前深孔降水管,然后在降水管插入完毕后拨出套管,将降水管外端管壁与其周边富水粉细砂层之间的间隙密封回填,完成该钻孔内超前深孔降水管安装,直到全部超前深孔降水管的安装完成;
第六步、在上台阶7、中台阶8和下台阶9的边墙底部,按照轻型井点降水管3的预设位置,采用高压风或高压水冲孔,轻型井点降水管3紧跟的方式埋设,直到全部轻型井点管完成埋设;
第七步、在下台阶9底面的位置,通过钻机钻设垂直降水井10,同时采用泥浆护壁,在设垂直降水井10钻设完成后,下入垂直降水井管,井管下端设置有滤水孔的部分周边采用粗砂回填,管端与周边地层进行密封回填,完成垂直降水井埋设;
第八步、待所有降水管埋设完成后,把降水管分类与对应排水主管连接,保证各类型降水管抽水的独立性,所述降水管外端管壁与周边100厘米范围内的富水粉细砂层1之间的区域均密封回填;
第九步、连续抽水,并在通过检测含水量的变化确认富水粉细砂层1具有自稳性后,沿钻孔的长度方向进行隧道开挖,并在开挖过程中及时进行初期支护;
第十步、重复上述步,直至挖过富水粉细砂层1或是深埋隧道开挖完成。
本发明在具体实施过程中,同样可以按照如下步骤进行操作:
第一步、在开挖深埋隧道5遭遇到富水粉细砂层1时,首先在与预设超前深孔降水孔2处,即与准备超前深孔降水孔2的位置相对应的隧道施工作业面内设置一个钻机作业平台,在钻机作业平台上稳定牢固的设置相应的钻机;
第二步、在隧道施工作业面进行立拱、钻设锚杆和喷射混凝土的初期支护6设置;
第三步、初期支护6设置完毕后,在钻机作业平台上设置相应的钻机,并使用钻机按隧道开挖的方向,沿隧道上台阶初期支护6的轮廓外侧有间距的钻设若干个超前深孔降水孔2,即每个超前深孔降水孔2的轴线均与深埋隧道5的轴线呈3~5°夹角呈发散布置状态,当超前深孔降水孔2钻设结束,在钻设中的套管拆除之前,先向该超前深孔降水孔2内插入降水管,然后在降水管插入完毕后再拨出套管,且按此操作完成所有超前深孔降水孔2内的降水管安装,将每一根降水管外端管壁与其周边富水粉细砂层1之间的间隙进行密封回填;
第四步、当所有超前深孔降水孔2内均安装完降水管,在上台阶7、中台阶8和下台阶9的边墙底部位置,高压风或高压水冲孔、轻型井点降水管3紧跟的方式埋设轻型井点降水管3,轻型井点降水管3与隧道垂直方向夹角30~60°夹角布置;
第五步、当所有轻型井点降水管3安装完成后,再下台阶9底面位置布置垂直降水井10,垂直降水井10采用钻机钻孔,泥浆护壁,钻孔完成后,下入钢制或混凝土制降水井管,垂直降水井10降水井管与周边富水粉细砂层砂层1之间的空隙用粗砂填充,垂直降水井10端部密封回填,完成垂直降水井埋设;
第六步、在超前深孔降水孔2降水管、轻型井点降水管3和垂直降水井10降水井管埋设完成后,把降水管分类与对应排水主管连接,保证各类型降水管抽水的独立性;
第七步、连续抽水,并在通过检测含水量的变化确认富水粉细砂层1具有自稳性后,沿超前深孔降水孔2的长度方向进行隧道开挖,轻型井点降水管3和垂直降水井10降水井接续施做抽水,直到挖至超前深孔降水孔2的孔底位置,在开挖过程中要及时进行设置初期支护6;
第八步、重复上述步骤,直至挖过富水粉细砂层1或是深埋隧道5开挖完成。
本发明也能够直接在开挖深埋隧道5时使用。
本发明未详述部分为现有技术。
为了公开本发明的目的而在本文中选用的实施例,当前认为是适宜的,但是,应了解的是,本发明旨在包括一切属于本构思和发明范围内的实施例的所有变化和改进。
Claims (7)
1.一种开挖深埋隧道时洞内综合降水的施工方法,其特征是:所述方法包括如下步骤:
第一步、首先对深埋隧道(5)的开挖面分上、中、下三部分进行开挖,挖取后形成上台阶(7)、中台阶(8)和下台阶(9),然后分别对上台阶(7)、中台阶(8)和下台阶(9)的底面进行平整,以便为上台阶(7)开挖面的初期支护(6)轮廓外侧施做超前深孔降水孔(2),上台阶(7)、中台阶(8)和下台阶(9)边墙底部处施做轻型井点降水管(3)和下台阶(9)地面施做垂直降水井(10)提供作业平台;
第二步、对深埋隧道(5)中的上台阶(7)、中台阶(8)和下台阶(9)分别设置初期支护(6),即进行立拱,每节拱架之间采用连接板连接拼装,拱架外侧铺设钢筋网片,两环拱架之间采用U型连接装置连接,喷射混凝土,施做锁脚锚杆;
第三步、在深埋隧道(5)开挖断面上台阶(7)的初期支护(6)轮廓外侧设定超前深孔降水孔(2)的位置、在上台阶(7)、中台阶(8)和下台阶(9)的边墙底部设定轻型井点降水孔(3)的位置和在下台阶(9)的地面设定垂直降水井(10)的位置;
第四步、在钻机作业平台设置钻机,并利用钻机按深埋隧道(5)开挖的方向,沿上台阶(7)的初期支护(6)的轮廓外侧间隔钻设复数个超前深孔降水孔(2);
第五步、在超前深孔降水孔(2)钻孔结束时,在钻孔的钻设套管拆除前,先向钻孔内插入超前深孔降水管,然后在降水管插入完毕后拨出套管,将降水管外端管壁与其周边富水粉细砂层之间的间隙密封回填,完成该钻孔内超前深孔降水管安装,直到全部超前深孔降水管的安装完成;
第六步、在上台阶(7)、中台阶(8)和下台阶(9)的边墙底部,按照轻型井点降水管(3)的预设位置,采用高压风或高压水冲孔,轻型井点降水管(3)紧跟的方式埋设,直到全部轻型井点管完成埋设;
第七步、在下台阶(9)底面的位置,通过钻机钻设垂直降水井(10),同时采用泥浆护壁,在设垂直降水井(10)钻设完成后,下入垂直降水井管,井管下端设置有滤水孔的部分周边采用粗砂回填,管端与周边地层进行密封回填,完成垂直降水井埋设;
第八步、待所有降水管埋设完成后,把降水管分类与对应排水主管连接,保证各类型降水管抽水的独立性;
第九步、连续抽水,并在通过检测含水量的变化确认富水粉细砂层(1)具有自稳性后,沿钻孔的长度方向进行隧道开挖,并在开挖过程中及时进行初期支护;
第十步、重复上述步,直至挖过富水粉细砂层1或是深埋隧道开挖完成。
2.根据权利要求1所述的开挖深埋隧道时洞内综合降水的施工方法,其特征是:所述上台阶(7)、中台阶(8)和下台阶(9)的台阶长度分别为4~5米,高度分别为3~5米。
3.根据权利要求1所述的开挖深埋隧道时洞内综合降水的施工方法,其特征是:所述超前深孔降水孔(2)设置在上台阶(7)的初期支护(6)的外侧,所述超前深孔降水孔(2)内的超前深孔降水管直径65毫米,环向间距为1米,长度为10~20米,超前深孔降水管滤水端长6~8米,包裹两层80~100目滤网。
4.根据权利要求1所述的开挖深埋隧道时洞内综合降水的施工方法,其特征是:所述轻型井点降水管(3)设置在上台阶(7)、中台阶(8)和下台阶(9)的边墙底部,轻型井点降水管(3)的长度为3~5米,直径为Φ32毫米,材质为PVC管,轻型井点降水管(3)滤水端长2米,外插角30~60°,纵向间距为0.5~0.75米。
5.根据权利要求1所述的开挖深埋隧道时洞内综合降水的施工方法,其特征是:所述垂直降水井(10)设置在开挖仰拱(4)前下台阶(9)是底面位置,沿深埋隧道(5)方向左右梅花形按间距10米设置,垂直降水井(10)的直径为15~30厘米,深度为5~10米,垂直降水井(10)的滤水端长3~5米。
6.根据权利要求1所述的开挖深埋隧道时洞内综合降水的施工方法,其特征是:所述的超前深孔降水孔(2)的直径为5~10厘米,钻孔深度为8~30米,每两个超前深孔降水孔(2)之间的孔间距为30~200厘米。
7.根据权利要求1所述的开挖深埋隧道时洞内综合降水的施工方法,其特征是:所述降水管外端管壁与周边100厘米范围内的富水粉细砂层(1)之间的区域均密封回填。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310240988.4A CN103306683B (zh) | 2013-06-18 | 2013-06-18 | 一种开挖深埋隧道时洞内综合降水的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310240988.4A CN103306683B (zh) | 2013-06-18 | 2013-06-18 | 一种开挖深埋隧道时洞内综合降水的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103306683A true CN103306683A (zh) | 2013-09-18 |
CN103306683B CN103306683B (zh) | 2015-08-12 |
Family
ID=49132358
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310240988.4A Active CN103306683B (zh) | 2013-06-18 | 2013-06-18 | 一种开挖深埋隧道时洞内综合降水的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103306683B (zh) |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103628887A (zh) * | 2013-11-28 | 2014-03-12 | 中铁十三局集团有限公司 | 大断面富水饱和粉细砂铁路隧道开挖方法 |
CN103628916A (zh) * | 2013-11-28 | 2014-03-12 | 中铁十三局集团有限公司 | 一种高压涌水隧道的开挖施工方法 |
CN103821525A (zh) * | 2014-03-10 | 2014-05-28 | 山西太钢不锈钢股份有限公司 | 高水位地质条件下电缆隧道快速施工方法 |
CN104234726A (zh) * | 2014-08-26 | 2014-12-24 | 中国路桥工程有限责任公司 | 一种穿越富水不整合接触带隧道的洞内降排水施工方法 |
CN104454001A (zh) * | 2014-12-11 | 2015-03-25 | 中铁十九局集团有限公司 | 低渗透性粉细砂地层隧道内降水系统及降水方法 |
CN104790419A (zh) * | 2015-03-24 | 2015-07-22 | 中铁三局集团有限公司 | 一种适用于富水流沙地层隧道的降水施工方法 |
CN105484791A (zh) * | 2016-01-16 | 2016-04-13 | 中铁十九局集团第二工程有限公司 | 一种隧道综合泄水、降水、减压施工方法 |
CN105804754A (zh) * | 2016-05-16 | 2016-07-27 | 中国矿业大学 | 一种煤层为主含水层矿井井筒揭煤方法 |
CN105840211A (zh) * | 2016-06-12 | 2016-08-10 | 中铁二院工程集团有限责任公司 | π形板与仰拱组合式隧底衬砌构造 |
CN105927272A (zh) * | 2016-06-12 | 2016-09-07 | 中铁二院工程集团有限责任公司 | 底板锚固约束型隧道衬砌构造 |
CN105986836A (zh) * | 2016-06-14 | 2016-10-05 | 中铁隧道勘测设计院有限公司 | 一种单线铁路隧道基底防排水加强系统 |
CN106917626A (zh) * | 2017-05-04 | 2017-07-04 | 西安理工大学 | 基于饱和黄土隧道的双侧壁洞内降水施工方法 |
CN107120140A (zh) * | 2017-07-06 | 2017-09-01 | 中国铁路设计集团有限公司 | 隧道仰拱下保温中心沟台阶式检查井结构 |
CN107143345A (zh) * | 2017-05-17 | 2017-09-08 | 熊伟 | 浅埋暗挖钻孔支护装置及其支护方法 |
CN107201908A (zh) * | 2017-06-16 | 2017-09-26 | 中铁五局集团有限公司 | 一种酷寒地区隧道深埋中心水沟的施工方法 |
CN107227961A (zh) * | 2017-06-29 | 2017-10-03 | 中铁十二局集团有限公司 | 地铁暗挖隧道洞内大口径降水井施工方法 |
CN108661662A (zh) * | 2018-05-17 | 2018-10-16 | 中铁十二局集团有限公司 | 富水地层新增隧道钻孔成井治水方法 |
CN109555528A (zh) * | 2018-11-26 | 2019-04-02 | 中铁二十局集团有限公司 | 穿越高角度逆冲富水富砂断层隧道开挖及支护方法 |
CN109630193A (zh) * | 2019-01-11 | 2019-04-16 | 中建八局轨道交通建设有限公司 | 地铁区间联络通道开挖出现涌水现象的治理方法 |
CN110541721A (zh) * | 2019-09-11 | 2019-12-06 | 中国建筑土木建设有限公司 | 一种富水流砂地层全风化围岩隧道的支护体系及施工方法 |
CN111058482A (zh) * | 2020-02-26 | 2020-04-24 | 福州市规划设计研究院 | 一种适用于明挖隧道拱底快速降水的施工方法 |
CN113431628A (zh) * | 2021-04-13 | 2021-09-24 | 西南交通大学 | 一种流沙地层立体式降水方法 |
CN114060084A (zh) * | 2021-11-16 | 2022-02-18 | 中铁北京工程局集团有限公司 | 一种用于开挖深埋隧道洞内综合降水的操作方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002242580A (ja) * | 2001-02-15 | 2002-08-28 | Kajima Corp | トンネルの構築方法、水抜き工法およびトンネル |
CN102278142A (zh) * | 2011-05-04 | 2011-12-14 | 中铁隧道集团二处有限公司 | 真空轻型井点降水方法 |
CN102661172A (zh) * | 2012-05-09 | 2012-09-12 | 中铁隧道集团有限公司 | 一种深埋隧道超前降水方法 |
CN103032097A (zh) * | 2012-12-26 | 2013-04-10 | 湖南省交通规划勘察设计院 | 适用于偏压富水地层的隧道排水结构及其施工方法 |
CN103088836A (zh) * | 2012-12-15 | 2013-05-08 | 天津大学 | 一种井管内同时抽水和回灌的沉降控制方法 |
-
2013
- 2013-06-18 CN CN201310240988.4A patent/CN103306683B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002242580A (ja) * | 2001-02-15 | 2002-08-28 | Kajima Corp | トンネルの構築方法、水抜き工法およびトンネル |
CN102278142A (zh) * | 2011-05-04 | 2011-12-14 | 中铁隧道集团二处有限公司 | 真空轻型井点降水方法 |
CN102661172A (zh) * | 2012-05-09 | 2012-09-12 | 中铁隧道集团有限公司 | 一种深埋隧道超前降水方法 |
CN103088836A (zh) * | 2012-12-15 | 2013-05-08 | 天津大学 | 一种井管内同时抽水和回灌的沉降控制方法 |
CN103032097A (zh) * | 2012-12-26 | 2013-04-10 | 湖南省交通规划勘察设计院 | 适用于偏压富水地层的隧道排水结构及其施工方法 |
Non-Patent Citations (1)
Title |
---|
王菀等: "真空轻型井点降水在深埋隧道未成岩富水粉细砂层施工中的应用", 《国防交通工程与技术》 * |
Cited By (30)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103628887A (zh) * | 2013-11-28 | 2014-03-12 | 中铁十三局集团有限公司 | 大断面富水饱和粉细砂铁路隧道开挖方法 |
CN103628916A (zh) * | 2013-11-28 | 2014-03-12 | 中铁十三局集团有限公司 | 一种高压涌水隧道的开挖施工方法 |
CN103821525A (zh) * | 2014-03-10 | 2014-05-28 | 山西太钢不锈钢股份有限公司 | 高水位地质条件下电缆隧道快速施工方法 |
CN103821525B (zh) * | 2014-03-10 | 2015-10-28 | 山西太钢不锈钢股份有限公司 | 高水位地质条件下电缆隧道快速施工方法 |
CN104234726A (zh) * | 2014-08-26 | 2014-12-24 | 中国路桥工程有限责任公司 | 一种穿越富水不整合接触带隧道的洞内降排水施工方法 |
CN104454001A (zh) * | 2014-12-11 | 2015-03-25 | 中铁十九局集团有限公司 | 低渗透性粉细砂地层隧道内降水系统及降水方法 |
CN104790419A (zh) * | 2015-03-24 | 2015-07-22 | 中铁三局集团有限公司 | 一种适用于富水流沙地层隧道的降水施工方法 |
CN105484791A (zh) * | 2016-01-16 | 2016-04-13 | 中铁十九局集团第二工程有限公司 | 一种隧道综合泄水、降水、减压施工方法 |
CN105484791B (zh) * | 2016-01-16 | 2018-08-21 | 中铁十九局集团第二工程有限公司 | 一种隧道综合泄水、降水、减压施工方法 |
CN105804754A (zh) * | 2016-05-16 | 2016-07-27 | 中国矿业大学 | 一种煤层为主含水层矿井井筒揭煤方法 |
CN105927272A (zh) * | 2016-06-12 | 2016-09-07 | 中铁二院工程集团有限责任公司 | 底板锚固约束型隧道衬砌构造 |
CN105927272B (zh) * | 2016-06-12 | 2019-01-04 | 中铁二院工程集团有限责任公司 | 底板锚固约束型隧道衬砌构造 |
CN105840211A (zh) * | 2016-06-12 | 2016-08-10 | 中铁二院工程集团有限责任公司 | π形板与仰拱组合式隧底衬砌构造 |
CN105986836A (zh) * | 2016-06-14 | 2016-10-05 | 中铁隧道勘测设计院有限公司 | 一种单线铁路隧道基底防排水加强系统 |
CN105986836B (zh) * | 2016-06-14 | 2018-12-14 | 中铁隧道勘测设计院有限公司 | 一种单线铁路隧道基底防排水加强系统 |
CN106917626A (zh) * | 2017-05-04 | 2017-07-04 | 西安理工大学 | 基于饱和黄土隧道的双侧壁洞内降水施工方法 |
CN107143345A (zh) * | 2017-05-17 | 2017-09-08 | 熊伟 | 浅埋暗挖钻孔支护装置及其支护方法 |
CN107201908A (zh) * | 2017-06-16 | 2017-09-26 | 中铁五局集团有限公司 | 一种酷寒地区隧道深埋中心水沟的施工方法 |
CN107201908B (zh) * | 2017-06-16 | 2023-10-31 | 中铁五局集团有限公司 | 一种酷寒地区隧道深埋中心水沟的施工方法 |
CN107227961A (zh) * | 2017-06-29 | 2017-10-03 | 中铁十二局集团有限公司 | 地铁暗挖隧道洞内大口径降水井施工方法 |
CN107120140A (zh) * | 2017-07-06 | 2017-09-01 | 中国铁路设计集团有限公司 | 隧道仰拱下保温中心沟台阶式检查井结构 |
CN108661662A (zh) * | 2018-05-17 | 2018-10-16 | 中铁十二局集团有限公司 | 富水地层新增隧道钻孔成井治水方法 |
CN109555528B (zh) * | 2018-11-26 | 2019-10-11 | 中铁二十局集团有限公司 | 穿越高角度逆冲富水富砂断层隧道开挖及支护方法 |
CN109555528A (zh) * | 2018-11-26 | 2019-04-02 | 中铁二十局集团有限公司 | 穿越高角度逆冲富水富砂断层隧道开挖及支护方法 |
CN109630193A (zh) * | 2019-01-11 | 2019-04-16 | 中建八局轨道交通建设有限公司 | 地铁区间联络通道开挖出现涌水现象的治理方法 |
CN110541721A (zh) * | 2019-09-11 | 2019-12-06 | 中国建筑土木建设有限公司 | 一种富水流砂地层全风化围岩隧道的支护体系及施工方法 |
CN111058482A (zh) * | 2020-02-26 | 2020-04-24 | 福州市规划设计研究院 | 一种适用于明挖隧道拱底快速降水的施工方法 |
CN111058482B (zh) * | 2020-02-26 | 2022-03-08 | 福州市规划设计研究院集团有限公司 | 一种适用于明挖隧道拱底快速降水的施工方法 |
CN113431628A (zh) * | 2021-04-13 | 2021-09-24 | 西南交通大学 | 一种流沙地层立体式降水方法 |
CN114060084A (zh) * | 2021-11-16 | 2022-02-18 | 中铁北京工程局集团有限公司 | 一种用于开挖深埋隧道洞内综合降水的操作方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103306683B (zh) | 2015-08-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103306683B (zh) | 一种开挖深埋隧道时洞内综合降水的施工方法 | |
CN102661172B (zh) | 一种深埋隧道超前降水方法 | |
CN107762533B (zh) | 一种高压富水软弱围岩山岭隧道的超前预注浆方法 | |
CN104863629B (zh) | 一种利用复合钻孔抽覆岩下离层瓦斯及排水注浆的方法 | |
CN103334770B (zh) | 一种长大反坡隧道超高水压富水破碎带施工方法 | |
CN106761835B (zh) | 一种岩溶隧道漏水分段注浆施工方法 | |
CN105863648B (zh) | 一种暗挖浅覆大断面隧道施工方法 | |
CN104389618B (zh) | 一种连拱隧道洞身无室大管棚支护施工方法 | |
CN101701646B (zh) | 地下管道的泥水平衡式拉管施工方法 | |
CN202117686U (zh) | 铁路隧道深埋富水软弱带围岩超前支护构造 | |
CN103114599A (zh) | 深基坑封闭降水装置及其施工方法 | |
WO2017198109A1 (zh) | 一种煤层为主含水层矿井井筒揭煤方法 | |
CN101793154A (zh) | 利用隧道围岩地质参数和设置分流孔的注浆堵水方法 | |
CN204940315U (zh) | 一种用于富水地区大型竖井的止水系统 | |
CN103276741B (zh) | 水平钢管咬合止水管幕及其施工方法 | |
CN108756893A (zh) | 一种城区浅埋隧道拱顶土体加固方法 | |
CN201183950Y (zh) | 无缝钢管自进式锚杆 | |
CN102102503A (zh) | 4吋小井眼防砂方法 | |
CN105909262B (zh) | 一种暗挖隧道掘进方法 | |
CN108180018A (zh) | 一种浅埋湿陷性黄土隧道核心土与玻纤锚杆加固施工方法 | |
CN207406345U (zh) | 富水砂卵石地层盾构隧道端头水平注浆加固结构 | |
CN105040705A (zh) | 多溶洞地质条件下地基基础处理施工工艺 | |
CN110985002B (zh) | 一种用于横向半软半硬断面地层中的隧道施工方法 | |
CN109235507B (zh) | 一种加固既有隧道的地层加固体系及方法 | |
CN203113361U (zh) | 深基坑封闭降水装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |