CN103291594A CN2013102719344A CN201310271934A CN103291594A CN 103291594 A CN103291594 A CN 103291594A CN 2013102719344 A CN2013102719344 A CN 2013102719344A CN 201310271934 A CN201310271934 A CN 201310271934A CN 103291594 A CN103291594 A CN 103291594A
Authority
CN
China
Prior art keywords
pressure
trend
compressor
cycle
ductwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102719344A
Other languages
English (en)
Other versions
CN103291594B (zh
Inventor
许杨波
毛成自
杨帆
王磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Beiqing power smart energy Co.,Ltd.
Original Assignee
CHONGQING INDUSTRY ENERGY TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING INDUSTRY ENERGY TECHNOLOGY Co Ltd filed Critical CHONGQING INDUSTRY ENERGY TECHNOLOGY Co Ltd
Priority to CN201310271934.4A priority Critical patent/CN103291594B/zh
Publication of CN103291594A publication Critical patent/CN103291594A/zh
Application granted granted Critical
Publication of CN103291594B publication Critical patent/CN103291594B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Control Of Positive-Displacement Pumps (AREA)
  • Control Of Positive-Displacement Air Blowers (AREA)

Abstract

一种趋势控制空压机组供气方法,拓宽了压力控制区间,设定了5个压力区间:低压力区、低压力调节缓冲区、标准压力区、高压力调节缓冲区、高压力区。将压力的趋势变化量ΔP引入控制,引入了循环周期控制,在每个循环周期进行采样,首先判断管网压力对应的区间,再根据趋势变化量ΔP的大小启停压缩机。它可以适应不同时间段的变化用气工况,供气压力波动小,减少压缩机启停频率,延长压缩机使用寿命。同时压缩机不会处于卸载状态,节约能耗。

Description

一种趋势控制空压机组供气方法
技术领域
本发明涉及压缩机联机控制技术领域,特别涉及一种多台螺杆压缩机组控制方法。
背景技术
螺杆式压缩机以其优越的控制性能,在各行各业得到了广泛的运行。虽然单台螺杆压缩机的控制性能良好,但是在多台压缩机联机运行时,目前市场上主要采用的控制方法是:将1台压缩机设为主机,其它压缩机设为从机。主机中设定联机控制加载压力、卸载压力、联机台数及联机控制延时时间。主机启动后,自动进入联机控制模式。当管网压力高于设定最高压力时,延时一段时间后,主机控制一台从机卸载,卸载一定时间后停机。当管网压力高于设定最低压力时,延时一段时间后,主机控制一台从机加载。
传统原有联机控制方式只有3段压力区间:低压力区、标准压力区、高压力区,当压力处于低压力区延时一定时间就启动一台压缩机运行,当压力处于高压力区一段时间就停止一台压缩机运行,当压力处于标准压力区时保持当前运行方式。由于用气状况是在不断的变化的,这种控制方式设定的延时时间不能适应不同时间段的变化用气工况,造成供气压力波动大,压缩机启停频繁,影响压缩机使用寿命。同时压缩机会存在卸载状态,压缩机不产气,但是电机还是在运行,造成极大的能源浪费。
发明内容
本发明的目的就是提供一种趋势控制空压机组供气方法,它可以适应不同时间段的变化用气工况,减小压缩机启停频率,延长压缩机使用寿命。
本发明的目的是通过这样的技术方案实现的,它包括有1台作为主机的压缩机和1台以上作为从机的压缩机,实时监测管网压力P,将管网压力分成5个区间,分别为0~P2的低压力区、P2~P3的低压力调节缓冲区、P3~P4的标准压力区间、P4
~P5的高压力调节缓冲区和P5~∞的高压力区,预设下限段趋势判断压力P6和上限段趋势判断压力P7;将主机和从机的工作时间划分为循环周期T,每个循环周期T包括有Tk-1到Tk-1的采样周期和Tk-1到Tk的动作周期,k=1、2、3…n,k为周期数,预设低压力允许趋势调节时间T2和高压力允许趋势调节时间T3;在每个工作周期内,计算管网在采样周期内的趋势变化量ΔP,具体控制方法为:
1)当管网压力P位于0~P2的低压力区,若ΔP≤0或者ΔP>0且T4≥T2,则在动作周期启动一台压缩机运行,若ΔP>0且T4<T2,则在动作周期保持原有压缩机运行;T4为管网压力恢复到P2所需的时间;
2)当管网压力P位于P2~P3的低压力调节缓冲区,若ΔP≤0且|ΔP|≥P6,则在动作周期启动一台压缩机运行,若ΔP≤0且|ΔP|<P6,或者ΔP>0时,则在动作周期保持原有压缩机运行;
3)当管网压力P位于P3~P4的标准压力区间,在动作周期保持原有压缩机运行;
4)当管网压力P位于P4~P5的高压力调节缓冲区,若ΔP≥0且ΔP≥P7,则在动作周期停止一台压缩机运行,ΔP≥0且ΔP<P7或者ΔP<0时,则在动作周期保持原有压缩机运行;
5)当管网压力P位于P5~∞的高压力区,若ΔP≥0或者ΔP<0且T5≥T3,则在动作周期停止一台压缩机运行,ΔP<0且T5<T3,则在动作周期保持原有压缩机运行;T5为管网压力恢复到P5时需要的时间。
进一步,ΔP的计算方法为:
将时间周期平均分成20等分,每等分为按时间先后为:0、
Figure BDA00003433672800022
Figure BDA00003433672800023
共计20个时间节点,按时间先后顺序记录管网压力P1的值,分别为:P1t、P2t、P3t、P4t、P5t、······P18t、P19t、P20t
ΔP = ( P 11 t + P 12 t + P 13 t + . . . + P 18 t + P 19 t + P 20 t ) - ( P 1 t + P 2 t + P 3 t + . . . + P 8 t + P 9 t + P 10 t ) 10 .
进一步,T4的计算公式:
进一步,T5的计算公式:
由于采用了上述技术方案,本发明具有如下的优点:
本发明,拓宽了压力控制区间,设定了5个压力区间:低压力区、低压力调节缓冲区、标准压力区、高压力调节缓冲区、高压力区。将压力的趋势变化量ΔP引入控制,引入了循环周期控制,在每个循环周期进行采样判断输出。它可以适应不同时间段的变化用气工况,供气压力波动小,减少压缩机启停频率,延长压缩机使用寿命。同时压缩机不会处于卸载状态,节约能耗。
本发明的其他优点、目标和特征在某种程度上将在随后的说明书中进行阐述,并且在某种程度上,基于对下文的考察研究对本领域技术人员而言将是显而易见的,或者可以从本发明的实践中得到教导。本发明的目标和其他优点可以通过下面的说明书和权利要求书来实现和获得。
附图说明
本发明的附图说明如下。
图1为本发明的控制原理图。
具体实施方式
下面结合附图和实施例对本发明作进一步说明。
一种趋势控制空压机组供气方法,包括有1台作为主机的压缩机和1台以上作为从机的压缩机,实时监测管网压力P,将管网压力分成5个区间,分别为0~P2的低压力区、P2~P3的低压力调节缓冲区、P3~P4的标准压力区间、P4~P5的高压力调节缓冲区和P5~∞的高压力区,预设下限段趋势判断压力P6和上限段趋势判断压力P7;将主机和从机的工作时间划分为循环周期T,每个循环周期T包括有Tk-1到Tk-1的采样周期和Tk-1到Tk的动作周期,k=1、2、3…n,k为周期数,预设低压力允许趋势调节时间T2和高压力允许趋势调节时间T3;在每个工作周期内,计算管网在采样周期内的趋势变化量ΔP,具体控制方法为:
1)当管网压力P位于0~P2的低压力区,若ΔP≤0或者ΔP>0且T4≥T2,则在动作周期启动一台压缩机运行,若ΔP>0且T4<T2,则在动作周期保持原有压缩机运行;T4为管网压力恢复到P2所需的时间;在低压力区,只要趋势变化量ΔP在增加,并且在设定时间能增加到低压力调节缓冲区,就不会启动新的压缩机运行,压力只会短暂处于低压力区。优化了以前的盲目的只看压力的大小,不看压力是在增加还是减少。
2)当管网压力P位于P2~P3的低压力调节缓冲区,若ΔP≤0且|ΔP|≥P6,则在动作周期启动一台压缩机运行,若ΔP≤0且|ΔP|<P6,或者ΔP>0时,则在动作周期保持原有压缩机运行;在低压力调节缓冲区,趋势变化量ΔP在减少,且减少的幅度比预先设定的幅度大时,哪怕管网压力还处于低压力缓冲区,也会启动新的压缩机运行。这样起到了压力超前调节,只要有这种大的减少趋势,就会进行调节。
3)当管网压力P位于P3~P4的标准压力区间,在动作周期保持原有压缩机运行;
4)当管网压力P位于P4~P5的高压力调节缓冲区,若ΔP≥0且ΔP≥P7,则在动作周期停止一台压缩机运行,ΔP≥0且ΔP<P7或者ΔP<0时,则在动作周期保持原有压缩机运行;在高压力调节缓冲区,趋势变化量ΔP在增加,且增加的幅度比预先设定的幅度大时,哪怕管网压力还处于高压力缓冲区,也会停止一台压缩机运行。这样起到了压力超前调节,只要有这种大的增加趋势,就会进行调节。
5)当管网压力P位于P5~∞的高压力区,若ΔP≥0或者ΔP<0且T5≥T3,则在动作周期停止一台压缩机运行,ΔP<0且T5<T3,则在动作周期保持原有压缩机运行;T5为管网压力恢复到P5时需要的时间。在高压力区,只要趋势变化量ΔP在减少,并且在设定时间能减少到高压力调节缓冲区,就不会停止一台压缩机运行,压力只会短暂处于高压力区。优化了以前的盲目的只看压力的大小,不看压力是在增加还是减少。
ΔP的计算方法为:
将时间周期平均分成20等分,每等分为
Figure BDA00003433672800041
按时间先后为:0、
Figure BDA00003433672800042
Figure BDA00003433672800043
共计20个时间节点,按时间先后顺序记录管网压力P1的值,分别为:P1t、P2t、P3t、P4t、P5t、······P18t、P19t、P20t
ΔP = ( P 11 t + P 12 t + P 13 t + . . . + P 18 t + P 19 t + P 20 t ) - ( P 1 t + P 2 t + P 3 t + . . . + P 8 t + P 9 t + P 10 t ) 10 .
T4的计算公式: T 4 = P 2 - P 1 | ΔP | × T .
T5的计算公式: T 5 = P 1 - P 5 ΔP × T .
最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本技术方案的宗旨和范围,其均应涵盖在本发明的权利要求范围当中。

Claims (4)

1.一种趋势控制空压机组供气方法,包括有1台作为主机的压缩机和1台以上作为从机的压缩机,其特征在于,实时监测管网压力P,将管网压力分成5个区间,分别为0~P2的低压力区、P2~P3的低压力调节缓冲区、P3~P4的标准压力区间、P4~P5的高压力调节缓冲区和P5~∞的高压力区,预设下限段趋势判断压力P6和上限段趋势判断压力P7;将主机和从机的工作时间划分为循环周期T,每个循环周期T包括有Tk-1到Tk-1的采样周期和Tk-1到Tk的动作周期,k=1、2、3…n,k为周期数,预设低压力允许趋势调节时间T2和高压力允许趋势调节时间T3;在每个工作周期内,计算管网在采样周期内的趋势变化量ΔP,具体控制方法为:
1)当管网压力P位于0~P2的低压力区,若ΔP≤0或者ΔP>0且T4≥T2,则在动作周期启动一台压缩机运行,若ΔP>0且T4<T2,则在动作周期保持原有压缩机运行;T4为管网压力恢复到P2所需的时间;
2)当管网压力P位于P2~P3的低压力调节缓冲区,若ΔP≤0且|ΔP|≥P6,则在动作周期启动一台压缩机运行,若ΔP≤0且|ΔP|<P6,或者ΔP>0时,则在动作周期保持原有压缩机运行;
3)当管网压力P位于P3~P4的标准压力区间,在动作周期保持原有压缩机运行;
4)当管网压力P位于P4~P5的高压力调节缓冲区,若ΔP≥0且ΔP≥P7,则在动作周期停止一台压缩机运行,ΔP≥0且ΔP<P7或者ΔP<0时,则在动作周期保持原有压缩机运行;
5)当管网压力P位于P5~∞的高压力区,若ΔP≥0或者ΔP<0且T5≥T3,则在动作周期停止一台压缩机运行,ΔP<0且T5<T3,则在动作周期保持原有压缩机运行;T5为管网压力恢复到P5时需要的时间。
2.如权利要求1所述的一种趋势控制空压机组供气方法,其特征在于,ΔP的计算方法为:
将时间周期平均分成20等分,每等分为
Figure FDA00003433672700011
按时间先后为:0、
Figure FDA00003433672700012
Figure FDA00003433672700013
共计20个时间节点,按时间先后顺序记录管网压力P1的值,分别为:P1t、P2t、P3t、P4t、P5t、······P18t、P19t、P20t
ΔP = ( P 11 t + P 12 t + P 13 t + . . . + P 18 t + P 19 t + P 20 t ) - ( P 1 t + P 2 t + P 3 t + . . . + P 8 t + P 9 t + P 10 t ) 10 .
3.如权利要求1所述的一种趋势控制空压机组供气方法,其特征在于,T4的计算公式: T 4 = P 2 - P 1 | ΔP | × T .
4.如权利要求1所述的一种趋势控制空压机组供气方法,其特征在于,T5的计算公式: T 5 = P 1 - P 5 ΔP × T .
CN201310271934.4A 2013-06-28 2013-06-28 一种趋势控制空压机组供气方法 Active CN103291594B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310271934.4A CN103291594B (zh) 2013-06-28 2013-06-28 一种趋势控制空压机组供气方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310271934.4A CN103291594B (zh) 2013-06-28 2013-06-28 一种趋势控制空压机组供气方法

Publications (2)

Publication Number Publication Date
CN103291594A true CN103291594A (zh) 2013-09-11
CN103291594B CN103291594B (zh) 2015-07-22

Family

ID=49092994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310271934.4A Active CN103291594B (zh) 2013-06-28 2013-06-28 一种趋势控制空压机组供气方法

Country Status (1)

Country Link
CN (1) CN103291594B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104460727A (zh) * 2014-10-20 2015-03-25 西安工程大学 压缩空气系统稳压控制装置及稳压控制方法
CN104847637A (zh) * 2014-02-14 2015-08-19 刘佳霖 空气压缩站的压缩空气产量的控制方法
CN106438321A (zh) * 2016-07-12 2017-02-22 中车株洲电力机车有限公司 一种运行控制方法、系统和空气压缩机系统
CN106523329A (zh) * 2015-09-11 2017-03-22 宝山钢铁股份有限公司 一种多系统空压站压缩空气并网节能运行方法
CN106523330A (zh) * 2015-09-11 2017-03-22 宝山钢铁股份有限公司 一种多系统空压站压缩空气并网运行压差补偿控制方法
CN106640656A (zh) * 2016-12-07 2017-05-10 重庆美的通用制冷设备有限公司 螺杆压缩机的无级能量调节方法、装置及螺杆压缩机
CN109113978A (zh) * 2018-08-30 2019-01-01 中车株洲电力机车有限公司 一种压缩机控制方法、装置及轨道车辆
WO2023273685A1 (zh) * 2021-06-30 2023-01-05 美的集团股份有限公司 空调制冷控制方法、空调器及计算机可读存储介质

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02221691A (ja) * 1989-02-22 1990-09-04 Hokuetsu Kogyo Co Ltd コンプレッサ自動発停方法
JPH06221273A (ja) * 1993-01-25 1994-08-09 Tokico Ltd 圧縮機
JP2009036053A (ja) * 2007-07-31 2009-02-19 Hitachi Ltd 圧縮機
CN101526080A (zh) * 2008-03-05 2009-09-09 北京丰电科技发展有限公司 空气压缩机组节能控制系统及方法
CN101776068A (zh) * 2009-08-21 2010-07-14 重庆埃泰克能源科技有限公司 空压机组节能智能控制系统及方法
CN102713293A (zh) * 2011-07-22 2012-10-03 三浦工业株式会社 压缩机台数控制系统
JP2012251487A (ja) * 2011-06-03 2012-12-20 Max Co Ltd 空気圧縮機

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02221691A (ja) * 1989-02-22 1990-09-04 Hokuetsu Kogyo Co Ltd コンプレッサ自動発停方法
JPH06221273A (ja) * 1993-01-25 1994-08-09 Tokico Ltd 圧縮機
JP2009036053A (ja) * 2007-07-31 2009-02-19 Hitachi Ltd 圧縮機
CN101526080A (zh) * 2008-03-05 2009-09-09 北京丰电科技发展有限公司 空气压缩机组节能控制系统及方法
CN101776068A (zh) * 2009-08-21 2010-07-14 重庆埃泰克能源科技有限公司 空压机组节能智能控制系统及方法
JP2012251487A (ja) * 2011-06-03 2012-12-20 Max Co Ltd 空気圧縮機
CN102713293A (zh) * 2011-07-22 2012-10-03 三浦工业株式会社 压缩机台数控制系统

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
薛勍等: ""一拖多空调器基于压力预测的模糊控制"", 《制冷与空调》, vol. 2, no. 5, 31 October 2002 (2002-10-31), pages 35 - 40 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104847637A (zh) * 2014-02-14 2015-08-19 刘佳霖 空气压缩站的压缩空气产量的控制方法
CN104847637B (zh) * 2014-02-14 2016-06-29 刘佳霖 空气压缩站的压缩空气产量的控制方法
CN104460727A (zh) * 2014-10-20 2015-03-25 西安工程大学 压缩空气系统稳压控制装置及稳压控制方法
CN104460727B (zh) * 2014-10-20 2017-05-24 西安工程大学 压缩空气系统稳压控制装置及稳压控制方法
CN106523329B (zh) * 2015-09-11 2019-09-20 宝山钢铁股份有限公司 一种多系统空压站压缩空气并网节能运行方法
CN106523329A (zh) * 2015-09-11 2017-03-22 宝山钢铁股份有限公司 一种多系统空压站压缩空气并网节能运行方法
CN106523330A (zh) * 2015-09-11 2017-03-22 宝山钢铁股份有限公司 一种多系统空压站压缩空气并网运行压差补偿控制方法
CN106523330B (zh) * 2015-09-11 2019-09-20 宝山钢铁股份有限公司 一种多系统空压站压缩空气并网运行压差补偿控制方法
CN106438321A (zh) * 2016-07-12 2017-02-22 中车株洲电力机车有限公司 一种运行控制方法、系统和空气压缩机系统
CN106640656A (zh) * 2016-12-07 2017-05-10 重庆美的通用制冷设备有限公司 螺杆压缩机的无级能量调节方法、装置及螺杆压缩机
CN106640656B (zh) * 2016-12-07 2018-02-06 重庆美的通用制冷设备有限公司 螺杆压缩机的无级能量调节方法、装置及螺杆压缩机
CN109113978A (zh) * 2018-08-30 2019-01-01 中车株洲电力机车有限公司 一种压缩机控制方法、装置及轨道车辆
WO2023273685A1 (zh) * 2021-06-30 2023-01-05 美的集团股份有限公司 空调制冷控制方法、空调器及计算机可读存储介质

Also Published As

Publication number Publication date
CN103291594B (zh) 2015-07-22

Similar Documents

Publication Publication Date Title
CN103291594A (zh) 一种趋势控制空压机组供气方法
CN101769584B (zh) 变频空调器频率的智能控制方法
CN107621048B (zh) 一种空调的控制方法及装置
CN107676939B (zh) 一种定频空调的控制方法、控制系统及控制装置
CN103776234B (zh) 一种冰箱变频控制方法及其应用
CN103216911B (zh) 一种变频空调器及其节能运行控制方法
CN111023434B (zh) 一种空调器的运行控制方法、系统、空调器及存储介质
CN104457069B (zh) 制冷系统的能量调节方法
CN107036256A (zh) 排气温度的控制方法、排气温度的控制装置和空调器
CN105276914A (zh) 变频压缩机控制方法及冰箱
WO2020258873A1 (zh) 空调器及其控制方法和控制装置
CN102242996A (zh) 中央空调机组中电子膨胀阀的开度的控制方法
JP2007060848A (ja) 電力量制御装置および電力量制御方法ならびにプログラム
CN105387570A (zh) 冷水机组的执行能力调节方法和装置
CN105333563A (zh) 一种制冷控制方法、装置及空调器
CN106152399B (zh) 控制空调器电子膨胀阀的方法
CN109237743A (zh) 空调控制的方法、装置及计算机存储介质
CN105042787A (zh) 风冷热泵冷热水机中压缩机的控制方法和控制系统
CN109386930B (zh) 调节电控器温度的方法和装置、空调系统和存储介质
CN103759388A (zh) 一种空调器缓冲调温方法
CN106052215B (zh) 空调室外机电子膨胀阀的控制方法
WO2019148972A1 (zh) 空调防凝露控制的方法、装置及计算机存储介质
CN106352510A (zh) 适于空调器的自动模式控制方法及装置
CN102536767A (zh) 水冷多压缩机机组压缩机启停控制方法
JP2016061487A (ja) 空調システムの最適起動制御装置および空調システムの最適起動制御方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210830

Address after: 300456 Room 202, inspection warehouse office area, No. 6262, Australia Road, Tianjin pilot free trade zone (Dongjiang Bonded Port Area), Binhai New Area, Tianjin (trusteeship No. 449 of free trade division of Tianjin Dongjiang Business Secretary Service Co., Ltd.)

Patentee after: Tianjin Beiqing power smart energy Co.,Ltd.

Address before: 401122 floor 1, building 4, zone 1, Jinshan Industrial Park, No. 110, Jinyu Avenue, northern New Area, Chongqing

Patentee before: CHONGQING INDUSTRY ENERGY TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right