CN103233574A - 一种外墙仿真石漆面层施工方法 - Google Patents
一种外墙仿真石漆面层施工方法 Download PDFInfo
- Publication number
- CN103233574A CN103233574A CN2013101653138A CN201310165313A CN103233574A CN 103233574 A CN103233574 A CN 103233574A CN 2013101653138 A CN2013101653138 A CN 2013101653138A CN 201310165313 A CN201310165313 A CN 201310165313A CN 103233574 A CN103233574 A CN 103233574A
- Authority
- CN
- China
- Prior art keywords
- spray
- spraying
- construction
- mineral varnish
- true mineral
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Application Of Or Painting With Fluid Materials (AREA)
Abstract
本发明涉及一种外墙仿真石漆面层施工方法,包括步骤:(1)基层处理,(2)涂封闭底漆两遍,(3)弹分格线和分色线,(4)喷涂中层真石漆,(5)打磨,(6)喷罩面漆,(7)处理分格线条。本发明的方法广泛用在建筑物室内外水泥抹灰墙面、水泥纤维板、石膏板、木板等各类基材。
Description
技术领域
本发明涉及建筑装修领域。
背景技术
在民用建筑外墙装饰施工中,这几年仿真石漆涂料高层的施工已得到广泛应用,涂层显天然石材的麻石质感和自然色泽,具有典雅和谐的、庄重之感。生动逼真,有回归大自然之功效。
仿真石漆系列是一种可塑出天然石材质感的水性建筑漆,精选天然岩石晶体颗粒及进口合成树脂乳液,参照花岗岩晶体结构加工制作而成,适合各类建筑物的室内外装饰装修。
涂层防火、耐水、耐碱、耐污染,无毒无味,具有良好的附着性和抗冻融性能。颜色丰富、持久,保色性能优异。喷涂施工,简便快捷。
采用仿真石漆具有施工简便,降低造价和节省石材资源的特点
发明内容
本发明的一个目的是提供了一种外墙仿真石漆面层施工方法,包括步骤:(1)基层处理,(2)涂封闭底漆两遍,(3)弹分格线和分色线,(4)喷涂中层真石漆,(5)打磨,(6)喷罩面漆,(7)处理分格线条。
具体地,包括:
1、基层处理:将墙面上的灰渣与油污等杂物清理干净,用扫帚将墙面上浮土清扫干净。用聚合物砂浆或石膏腻子将墙面、门窗口、角等磕碰破损处、麻面、风裂、接磋缝隙等分别找平补好,干燥后用砂纸将凸起处磨平。
2、涂封闭底漆两遍:喷涂(刷涂、滚涂均可)用无气喷枪均匀薄喷两遍,施工温度10℃以上,喷涂量0.3~0.4kg/m2。
3、弹分格线和分色线:在涂真石漆前,弹分格线和分色线,先涂刷浅色涂料,后涂刷深色涂料。分格线条宽度为8mm~10mm。
4、喷涂中层真石漆:采用喷涂方法,喷涂压力在0.5-1.0mPa/cm2,根据样板要求选择合适喷嘴,施工温度在10℃以上,厚度1-2mm,涂抹两道,间隔两小时,干燥24小时后打磨。喷枪应垂直于待喷涂面施工,距离约60厘米。对于阴阳角施工过程中,喷涂时特别注意不能一次喷厚,采用薄喷多层法,即表面干燥后重喷,喷枪距离为80厘米,运动速度快,且不能垂直阴阳角喷,只能采用散射,即喷涂两个面,上雾花的边缘扫入阴阳角。喷涂量3-5kg/m2。
5、打磨:采用400--600目砂纸,轻轻抹平真石漆表面凸起的砂粒即可。注意用力不可太猛,否则会破坏漆膜,引起底部松动,严重时会造成附着力不良,真石漆脱落。
6、喷罩面漆:选用下壶喷枪,压力4-7千克/平方厘米,施工不低于10摄氏度,喷涂两遍,间隔2小时,厚度约30微米,完全干燥需7天。
7、处理分格线条:将分格缝两边的毛刺及飞溅物清理干净,用油刷或排笔将分格缝用高级涂料(一般醇酸漆涂料)涂刷。
本发明的优点有:施工速度快,造价低,减少建设单位对工程建设项目的投资,施工产生的振动、噪音、粉尘等公害也得到了最大限度的降低。外墙真石漆具有天然石材的麻石质感和天然色泽,且天然石材是一种不可再生资源,本方法在一般工程上可替代天然石材。对于节省利用资源也是一件好事。新颖的工法技术将促进建筑业的发展,社会效益和经济效益显著。
本发明的方法广泛用在建筑物室内外水泥抹灰墙面、水泥纤维板、石膏板、木板等各类基材。
具体实施方式
实施例1:对于不同颜色真石漆施工,本发明优化的方法:
1、白色、浅色的真石漆施工:
墙体先批刮一遍白水泥,要求平整、无明显批痕;或者直接涂刷有色液体底漆,再按规定喷涂中层、面层;
2、深色的真石漆施工:
底漆按规定喷涂,在施工中层时,只需薄喷一层,厚度控制在1-2mm,再罩面
实施例2:对于不同喷涂对象的真石漆施工,本发明优化的方法:
1、砖形真石漆:先按要求设计好砖形尺寸,然后在已涂好底油的墙面用木框架做好砖形模型,在喷上真石漆,在真石漆还没有表干前取下木框即可。
2、垂直面喷涂:采用划圈法,距离30cm-40cm,以半径约15cm横向划圈喷涂,并不时上下抖动喷枪,这样喷速度快而均匀,且易控制,如果采用一排一排的主式重叠喷涂,速度慢,上下交接处难控制均匀,将影响外观,造成涂料缺陷。
3、罗马圆柱喷涂:因其是圆柱形,所以采用″M″线形喷涂,距离略远约40cm,喷枪要垂直柱面喷涂,自上而下,喷好一面再转向另一面,转向角度约60度为宜。
4、方形柱喷涂:方形柱棱角分明,很容易因喷涂不匀而使棱角模糊,为了喷涂方便,以约50cm的距离喷涂棱角,远距离喷涂,雾花散得开,面积大而均匀,如果距离太近,稍不注意就会喷厚,喷不均匀,使棱角线条显现不出来,失去了原有建筑的整体外观关感。
5、圆柱形小葫芦喷涂:现代建筑采用圆柱形小葫芦做栏杆装饰,大都要求喷上真石漆,因其小巧玲珑,极具装饰性,对它们的喷涂工艺也更为细致。做栏杆装饰的葫芦柱,距离太近,有些地方根本无法正面喷涂,所以按一般常规喷法是无法达到理想效果的。喷涂选用小喷嘴,距离约40cm,快速散喷真石漆,自上而下一面一面来喷,不能正面喷涂的,用抖动喷枪的方法,令其周围尽量喷上真石漆,然后用毛刷刷平真石漆,没有喷到的地方也可以用毛刷略微抹上一层,再用喷枪散喷一遍,不能太薄,也不能太厚,盖住刷痕即可,薄了不能起到很好的保护效果,厚了则遮盖住了原有的线条美感,也可能出现裂缝等不良表面现象。
实施例3:检测技术与分析:
在施工开始前,应先检查其原材料材质单,所选用的涂料其品种、型号、和性能应符合设计和国家行业规范的标准要求。需要复检的材料交有资质的实验室进行复检,复检合格后方可使用。项目部及公司技术部门对施工方案应进行审核认证。在施工过程中,项目部质检人员应对每道、每步架体进行跟踪检查。主要检查内容参见表1
表1、检查项目汇总表
实施例4:材料与设备
4.1本发明可用真石漆材料见表2
表2、真石漆材料表
4.2本发明可用机具表3
表3、每班组主要机具配备一览表
实施例5:质量控制
5.1工程质量控制标准
真石漆施工质量标准执行GB50300-2001《建筑工程施工质量验收统一标准》和GB50210-2001《建筑装饰装修工程质量验收规范》。
5.2质量保证措施
5.2.1强化质量意识,工人进场后,必须由施工技术负责人进行书面和口头的技术交底。严格控制每道工序,做到过程中有检查与记录,每道工序完成后有验收。
5.2.2严格控制真石漆阴阳角裂缝:如发现裂缝的阴阳角,用喷枪再一次薄薄的覆喷,隔半小时再喷一遍,直至盖住裂缝;对于新喷涂的阴阳角,则在喷涂时特别注意不能一次喷厚,采取薄喷多层法,即表面干燥后重喷,喷枪距离要远,运动速度要快,且不能垂直阴阳角喷,只能采取散射,即喷涂两个面,让雾花的边缘扫入阴阳角。
5.2.3平面出现裂缝是因为天气温差大,突然变冷,致使内外层干燥速度不同,表干里不干而形成裂缝,现场解决方法是改用小嘴喷枪,薄喷多层,尽量控制每层的干燥速度,喷涂距离以略远为好。
5.2.4在喷涂时,覆盖不够均匀或者太厚,在涂层表面成膜后出现裂缝,施工时注意喷涂方法外,必要时应改变配方,重新试制。严格控制成膜过程中出现裂缝。
5.2.5做好成品保护工作,严禁互相污染。
实施例6:安全措施
6.1认真贯彻“安全第一,预防为主”的方针,根据国家有关规定、条例,结合施工单位实际情况和工程的具体特点,组成专职安全员和班组兼职安全员以及工地安全用电负责人参加的安全生产管理网络,执行安全生产责任制,明确各级人员的职责,全面、全员、全过程的进行安全教育培训,确保培训合格人员才能上岗。抓好工程的安全生产。
6.2施工现场按符合防火、防风、防雷、防触电等安全规定及安全施工要求进行布置,并完善布置各种安全标示。
6.3各类房屋、库房、料场等的消防安全距离做到符合公安部门的规定,室内不堆放易燃品;严格做到不在木工加工场、料库等处吸烟;随时清除现场的易燃杂物;不在有火种的场所或其近旁对方生产物资。
6.4氧气瓶和乙炔瓶隔离存放,严格保证氧气瓶不沾染油污、乙炔发生器有防止回火的安全装置。
6.5施工现场的临时用电严格按照《施工现场临时用电安全技术规范》的有关规定执行。
6.6电缆线路严格采用“三相五线”连线方式,电气设备和电气线路必须绝缘性能良好,场内架设的电力线路其悬挂高度和线间距除按安全规定要求外,将其布置在专用电杆上。
6.7施工现场使用的手持照明灯使用36V以下的安全电压。
6.8室内配电柜、配电箱前要有绝缘垫,并安装漏电保护装置。
6.9吊篮和架体要经常派人检查,安全绳和安全带要正确佩带,并检查其有效性和可塑性。
6.10建立完善的施工安全保证体系,加强施工作业中的安全检查,确保作业标准化、规范化。
实施例7:环保措施
7.1成立对应的施工环境卫生管理机构,在工程施工过程中严格遵守国家和地方政府下发的有关环境保护的法律、法规和规章,加强对施工燃油、工程材料、设备、废水、生产生活垃圾、弃渣的控制和治理,遵守有防火及废弃物处理的规章制度,做好交通环境疏导,充分满足便民要求,认真接受城市交通管理,随时接受相关单位的检查监督。
7.2将施工场地和作业限制在工程建设允许的范围内,合理布置、规范围挡,做到标牌清楚、齐全,各种标示醒目,施工场地整洁文明。
7.3对施工中可能影响到的各种公共设施制定可靠的防止损坏和位移的实施措施,加强实施中的监测、应对和验证。同时将相关方案和要求向全体施工人员详细交底。
7.4设立专用排浆沟、集浆池,对废浆、污水进行集中,认真做好无害化处理,从根本上防止施工废浆乱流。
7.5定期清运废弃材料,做好废弃材料及其他工程材料运输过程中的防散落与沿途污染措施,废水除按环境卫生指标进行处理达标外,并按当地环保要求的指定地点排放。其他的工程废弃物按工程的建设指定的地点和方案进行合理的堆放和治理。
7.6优化选用先进的环保机械与设备,采取设立隔音墙、隔音罩等消音措施降低施工噪音到允许值以下,同时尽可能避免夜间施工。
7.7对施工场地道路进行硬化,并在干燥天气中经常进行洒水,防止尘土飞扬,污染周围环境。
实施例8:工程监测与结果评价
采用外墙仿真石漆面层施工方法后,为保证施工质量,并及时监测各主要工序施工阶段的质量,内蒙古建筑质量检测中心和施工单位监测组对本方法行全过程的监控与检测。
质量监测结果显示:仿真石漆施工质量结构达到了高级涂料的施工标准:颜色均匀一致,表面光滑,光泽均匀一致;无刷纹;无裹楞、流坠、皱皮现象;装饰线、分格线、分色线直线度控制在1mm以内。
施工全过程处于安全、稳定、和谐、快速、优质的可控状态中。完工检查157点,其中优良点151点,优良率达96%。无安全事故发生,得到各方好评。
Claims (2)
1.一种外墙仿真石漆面层施工方法,包括步骤:(1)基层处理,(2)涂封闭底漆两遍,(3)弹分格线和分色线,(4)喷涂中层真石漆,(5)打磨,(6)喷罩面漆,(7)处理分格线条。
2.根据权利要求1的方法,各步骤具体包括:
1)基层处理:将墙面上的杂物清理干净,用扫帚将墙面上浮土清扫干净,用聚合物砂浆或石膏腻子将磕碰破损处、麻面、风裂、接磋缝隙分别找平补好,干燥后用砂纸将凸起处磨平;
2)涂封闭底漆两遍:用无气喷枪均匀薄喷两遍,施工温度10℃以上,喷涂量0.3~0.4kg/m2;
3)弹分格线和分色线:在涂真石漆前,弹分格线和分色线,先涂刷浅色涂料,后涂刷深色涂料,分格线条宽度为8mm~10mm;
4)喷涂中层真石漆:采用喷涂方法,喷涂压力在0.5-1.0mPa/cm2,施工温度在10℃以上,厚度1-2mm,涂抹两道,间隔两小时,干燥24小时后打磨,喷枪应垂直于待喷涂面施工,距离约60厘米;
5)打磨:采用400--600目砂纸,轻轻抹平真石漆表面凸起的砂粒即可;。
6)喷罩面漆:选用下壶喷枪,压力4-7千克/平方厘米,不低于10摄氏度,喷涂两遍,间隔2小时,厚度约30微米,完全干燥需7天;
7)处理分格线条:将分格缝两边的毛刺及飞溅物清理干净,用油刷或排笔将分格缝用高级涂料涂刷。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013101653138A CN103233574A (zh) | 2013-05-08 | 2013-05-08 | 一种外墙仿真石漆面层施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013101653138A CN103233574A (zh) | 2013-05-08 | 2013-05-08 | 一种外墙仿真石漆面层施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103233574A true CN103233574A (zh) | 2013-08-07 |
Family
ID=48881638
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013101653138A Pending CN103233574A (zh) | 2013-05-08 | 2013-05-08 | 一种外墙仿真石漆面层施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103233574A (zh) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104110112A (zh) * | 2014-07-21 | 2014-10-22 | 浙江自力建设集团有限公司 | 建筑墙体装饰砂浆施工工艺 |
CN104387115A (zh) * | 2014-10-20 | 2015-03-04 | 浙江华特实业集团华特化工有限公司 | 一种砂岩石的仿真方法 |
CN104775575A (zh) * | 2015-02-13 | 2015-07-15 | 中冶建工集团有限公司 | 真石漆施工工艺方法 |
CN106437053A (zh) * | 2016-11-16 | 2017-02-22 | 中冶建筑研究总院有限公司 | 一种带主题效果的油漆装饰体结构及其施工方法 |
CN106499157A (zh) * | 2016-11-29 | 2017-03-15 | 赵彦伟 | 一种用于仿面砖墙面的分格贴纸装置 |
CN107023130A (zh) * | 2017-05-24 | 2017-08-08 | 君旺节能科技股份有限公司 | 多种涂料墙面粉刷方法 |
CN108930374A (zh) * | 2017-05-26 | 2018-12-04 | 五冶集团上海有限公司 | 一种具有隔热反射功能的环保型真石漆外墙施工方法 |
CN109372204A (zh) * | 2018-10-26 | 2019-02-22 | 安徽安兴装饰工程有限责任公司 | 无机干粉条纹状外墙装饰砂浆涂料系统施工工法 |
CN110700526A (zh) * | 2019-10-16 | 2020-01-17 | 江苏久诺建材科技股份有限公司 | 一种外墙干挂板面喷涂真石漆的施工方法 |
CN110700427A (zh) * | 2019-10-16 | 2020-01-17 | 江苏久诺建材科技股份有限公司 | 一种真石漆保温板的制备工艺 |
CN112726983A (zh) * | 2020-12-24 | 2021-04-30 | 重庆永联达涂装工程股份有限公司 | 一种分格缝开槽工艺 |
CN113445715A (zh) * | 2021-07-14 | 2021-09-28 | 万坤坤 | 一种混凝土震动式混凝土抹平机 |
CN114718283A (zh) * | 2021-01-04 | 2022-07-08 | 广东博智林机器人有限公司 | 一种装饰材料喷涂方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101319552A (zh) * | 2008-07-23 | 2008-12-10 | 勾希杰 | 真石漆仿面砖建筑外墙施工方法 |
CN101899899A (zh) * | 2009-05-26 | 2010-12-01 | 内蒙古兴泰建筑有限责任公司 | 外墙仿真石漆面层的施工方法 |
-
2013
- 2013-05-08 CN CN2013101653138A patent/CN103233574A/zh active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101319552A (zh) * | 2008-07-23 | 2008-12-10 | 勾希杰 | 真石漆仿面砖建筑外墙施工方法 |
CN101899899A (zh) * | 2009-05-26 | 2010-12-01 | 内蒙古兴泰建筑有限责任公司 | 外墙仿真石漆面层的施工方法 |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104110112A (zh) * | 2014-07-21 | 2014-10-22 | 浙江自力建设集团有限公司 | 建筑墙体装饰砂浆施工工艺 |
CN104387115A (zh) * | 2014-10-20 | 2015-03-04 | 浙江华特实业集团华特化工有限公司 | 一种砂岩石的仿真方法 |
CN104387115B (zh) * | 2014-10-20 | 2016-03-09 | 浙江华特实业集团华特化工有限公司 | 一种砂岩石的仿真方法 |
CN104775575A (zh) * | 2015-02-13 | 2015-07-15 | 中冶建工集团有限公司 | 真石漆施工工艺方法 |
CN104775575B (zh) * | 2015-02-13 | 2017-02-01 | 中冶建工集团有限公司 | 真石漆施工工艺方法 |
CN106437053A (zh) * | 2016-11-16 | 2017-02-22 | 中冶建筑研究总院有限公司 | 一种带主题效果的油漆装饰体结构及其施工方法 |
CN106499157B (zh) * | 2016-11-29 | 2019-04-05 | 赵彦伟 | 一种用于仿面砖墙面的分格贴纸装置 |
CN106499157A (zh) * | 2016-11-29 | 2017-03-15 | 赵彦伟 | 一种用于仿面砖墙面的分格贴纸装置 |
CN107023130A (zh) * | 2017-05-24 | 2017-08-08 | 君旺节能科技股份有限公司 | 多种涂料墙面粉刷方法 |
CN108930374A (zh) * | 2017-05-26 | 2018-12-04 | 五冶集团上海有限公司 | 一种具有隔热反射功能的环保型真石漆外墙施工方法 |
CN109372204A (zh) * | 2018-10-26 | 2019-02-22 | 安徽安兴装饰工程有限责任公司 | 无机干粉条纹状外墙装饰砂浆涂料系统施工工法 |
CN110700526A (zh) * | 2019-10-16 | 2020-01-17 | 江苏久诺建材科技股份有限公司 | 一种外墙干挂板面喷涂真石漆的施工方法 |
CN110700427A (zh) * | 2019-10-16 | 2020-01-17 | 江苏久诺建材科技股份有限公司 | 一种真石漆保温板的制备工艺 |
CN112726983A (zh) * | 2020-12-24 | 2021-04-30 | 重庆永联达涂装工程股份有限公司 | 一种分格缝开槽工艺 |
CN114718283A (zh) * | 2021-01-04 | 2022-07-08 | 广东博智林机器人有限公司 | 一种装饰材料喷涂方法 |
CN113445715A (zh) * | 2021-07-14 | 2021-09-28 | 万坤坤 | 一种混凝土震动式混凝土抹平机 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103233574A (zh) | 一种外墙仿真石漆面层施工方法 | |
CN103952052A (zh) | 仿洞石弹性质感涂料及其制备方法 | |
CN103375000B (zh) | 一种水性氟碳金属漆在弹性中涂拉毛表面的施工工艺 | |
CN109797920A (zh) | 一种室内涂饰施工方法 | |
CN101899899A (zh) | 外墙仿真石漆面层的施工方法 | |
CN104110112B (zh) | 建筑墙体装饰砂浆施工工艺 | |
CN103195218B (zh) | 一种墙体陶砂砂浆外抹灰施工工法 | |
CN102704635A (zh) | 一种涂料粉刷施工的方法 | |
CN104356832A (zh) | 柔性拉毛真石漆的制备方法 | |
Rivas et al. | Forms and factors of deterioration of urban art murals under humid temperate climate; influence of environment and material properties | |
CN103015643A (zh) | 金属屋面防水隔热处理系统 | |
CN102786827A (zh) | 液体花岗岩涂料 | |
CN203891380U (zh) | 外墙天然真石涂层结构 | |
CN106866025A (zh) | 无机硅真石漆及其制备方法 | |
CN102259085A (zh) | 一种水性金属漆在拉毛涂装工艺中的应用 | |
CN105110727A (zh) | 一种覆盖型的装饰性混凝土及其施工方法 | |
CN109797922A (zh) | 一种砂壁质感外墙面及其施工方法 | |
CN109651905A (zh) | 一种新型双组份防水装饰一体化涂料及其施工方法 | |
CN109853888A (zh) | 一种历史建筑拉毛墙面施工工艺 | |
CN104372877A (zh) | 高大垂直石材水幕墙施工工法 | |
CN105804411A (zh) | 一种保温装饰一体板安装工艺 | |
CN103790386A (zh) | 一种加砼砌块墙面抹灰裂缝的控制方法 | |
CN112081334A (zh) | 一种建筑外立面装饰构造及其施工方法 | |
CN105113730B (zh) | 防裂保色零voc零泛碱水性干粉建筑彩色涂料外墙施工方法 | |
CN115093729B (zh) | 一种自发光耐污防火材料及其制备方法和应用 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20130807 |