CN103132458A - 双幅分离式组合梁整幅安装方法 - Google Patents

双幅分离式组合梁整幅安装方法 Download PDF

Info

Publication number
CN103132458A
CN103132458A CN2013100983592A CN201310098359A CN103132458A CN 103132458 A CN103132458 A CN 103132458A CN 2013100983592 A CN2013100983592 A CN 2013100983592A CN 201310098359 A CN201310098359 A CN 201310098359A CN 103132458 A CN103132458 A CN 103132458A
Authority
CN
China
Prior art keywords
bolt
compound beam
section
compound
type combination
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100983592A
Other languages
English (en)
Other versions
CN103132458B (zh
Inventor
李军堂
谭国顺
陶建山
马涛
涂满明
刘灿
万成刚
张瑞霞
姚发海
张克
许佳平
姚森
方小林
黄剑锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CN201310098359.2A priority Critical patent/CN103132458B/zh
Publication of CN103132458A publication Critical patent/CN103132458A/zh
Application granted granted Critical
Publication of CN103132458B publication Critical patent/CN103132458B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及双幅分离式组合梁整幅安装方法,通过在待安装的组合梁(100)节段后端的左右分离式钢箱梁之间设置临时连接系(200),并在左右分离式钢箱梁的腹板处设置匹配连接件(300),使待架梁段与已架梁段之间横断面能匹配对接。在待安装的组合梁(100)的节段安装过程中,架梁吊机(400)吊起待安装的组合梁(100),缓慢靠近已安装的组合梁(100)前端,通过匹配连接件(300)及螺栓进行待架节段和已架节段对位,实现梁端面精确定位。本发明所述的双幅分离式组合梁整幅安装方法,减小了起吊状态下的双幅分离式组合梁两侧翼缘之间的相对变形,解决了待架梁段与已架梁段之间横断面匹配对接的问题。

Description

双幅分离式组合梁整幅安装方法
技术领域
本发明涉及桥梁工程中双幅分离式组合梁的安装,具体说是双幅分离式组合梁整幅安装方法。
背景技术
双幅分离式组合梁包括左分离式钢箱梁和右分离式钢箱梁共两幅,其整幅安装在国内外还没有先例,由于架梁吊机站位在已架梁的中部附近,常规法悬臂安装时会造成左右分离式钢箱梁的两侧翼缘相对变形大,加上已架双幅分离式组合梁两端与待架双幅分离式组合梁梁端间横向变形方向不一致,造成双向变形不协调,常规法悬臂安装不适用于双幅分离式组合梁的整幅安装,不能适应双幅分离式组合梁整幅安装时,待架双幅分离式组合梁梁段(简称为待架梁段)与已架双幅分离式组合梁梁段(简称为已架梁段)之间横断面匹配对接施工。
发明内容
针对现有技术中存在的缺陷,本发明的目的在于提供双幅分离式组合梁整幅安装方法,减小了起吊状态下的双幅分离式组合梁两侧翼缘之间的相对变形,解决了待架梁段与已架梁段之间横断面匹配对接的问题。
为达到以上目的,本发明采取的技术方案是:
双幅分离式组合梁整幅安装方法,其特征在于:通过在待安装的组合梁100节段后端的左右分离式钢箱梁之间设置临时连接系200,并在左右分离式钢箱梁的腹板处设置匹配连接件300,使待架梁段与已架梁段之间横断面能匹配对接。
在上述技术方案的基础上,临时连接系200设置在左右分离式钢箱梁后横梁处的普通隔板断面上。
在上述技术方案的基础上,所述临时连接系200为型钢桁梁结构,通过第一螺栓201与左右分离式钢箱梁后横梁处的普通隔板连接。
在上述技术方案的基础上,匹配连接件300通过第二螺栓301与左右分离式钢箱梁两端上口处的腹板相连。
在上述技术方案的基础上,在待安装的组合梁100的节段安装过程中,架梁吊机400吊起待安装的组合梁100,缓慢靠近已安装的组合梁100前端,通过匹配连接件300及高强度螺栓302进行待架节段和已架节段对位,实现梁端面精确定位。
在上述技术方案的基础上,所述临时连接系200包括:连接件202,其两端分别设有拼接板203,拼接板203上设有用于穿装第一螺栓201的螺栓孔。
在上述技术方案的基础上,所述匹配连接件300包括:截面呈L形的连接构件303,连接构件303上设有用于穿装第二螺栓301和高强度螺栓302的螺栓孔。
在上述技术方案的基础上,具体施工步骤如下:
步骤1、完成墩顶两节段组合梁100架设并设置好斜拉索500后,在已安装的组合梁100的梁面安装架梁吊机400,所述架梁吊机400设有一吊具401,在已安装的组合梁100两侧已设置好匹配连接件300;
步骤2、待安装的组合梁100在预制场制造并拼装完成,分别用第一螺栓201、第二螺栓301将临时连接系200和匹配连接件300固定到待安装的组合梁100上;
步骤3、用运输船将待安装的组合梁100运至施工桥位,用架梁吊机400的吊具401将其垂直起吊;
步骤4、将待安装的组合梁100与已安装的组合梁100初步对位后,停止架梁吊机400的起吊工作,用倒链和马板辅助微调组合梁100,实现待安装的组合梁100与已安装的组合梁100上的匹配连接件300的精确对位,打入一定数量的冲钉,穿入高强度螺栓302;
步骤5、匹配连接件300之间的高强度螺栓302穿入数量达到要求后,用马板对组合梁100进行限位,限位完成后,松掉高强度螺栓302和第二螺栓301,拆除匹配连接件300;
步骤6、焊接待安装的组合梁100与已安装的组合梁100之间的连接焊缝,此时,架梁吊机400逐步松钩,减小前后梁段的相对变形,松钩完成后,用马板辅助焊接桥面板进行焊接;
步骤7、拆除原安装在待安装的组合梁100上的临时连接系200,循环倒用至下一节待安装的组合梁100。
本发明所述的双幅分离式组合梁整幅安装方法,减小了起吊状态下的双幅分离式组合梁两侧翼缘之间的相对变形,解决了待架梁段与已架梁段之间横断面匹配对接的问题。
附图说明
本发明有如下附图:
图1双幅分离式组合梁架设立面布置图
图2图1中1---1剖面图
图3图1中2---2剖面图(未示架梁吊机400)
图4图1中3---3剖面图
图5匹配连接件与双幅分离式组合梁连接图
图6图5中4---4剖面图
图7临时连接系结构图
图8匹配连接件结构图及图8中1---1剖面图
具体实施方式
以下结合附图对本发明作进一步详细说明。
本发明所述的双幅分离式组合梁整幅安装方法,通过在待安装的组合梁100节段后端的左右分离式钢箱梁之间设置临时连接系200,并在左右分离式钢箱梁的腹板处设置匹配连接件300,使待架梁段与已架梁段之间横断面能匹配对接。所述临时连接系200横桥向设置,所述匹配连接件300纵桥向设置。
在上述技术方案的基础上,临时连接系200设置在左右分离式钢箱梁后横梁处的普通隔板(横隔板)断面上。
在上述技术方案的基础上,所述临时连接系200为型钢桁梁结构,通过第一螺栓201与左右分离式钢箱梁后横梁处的普通隔板连接,方便拆除倒用。
在上述技术方案的基础上,匹配连接件300通过第二螺栓301与左右分离式钢箱梁两端上口处的腹板相连。
在上述技术方案的基础上,在待安装的组合梁100的节段安装过程中,架梁吊机400吊起待安装的组合梁100,缓慢靠近已安装的组合梁100前端,通过匹配连接件300及高强度螺栓302进行待架节段和已架节段对位,实现梁端面精确定位。
在上述技术方案的基础上,如图7所示,所述临时连接系200包括:连接件202,其两端分别设有拼接板203,拼接板203上设有用于穿装第一螺栓201的螺栓孔。
在上述技术方案的基础上,如图8所示,所述匹配连接件300包括:截面呈L形的连接构件303,连接构件303上设有用于穿装第二螺栓301和高强度螺栓302的螺栓孔。
以下通过一具体实施例进一步说明本发明的具体施工步骤:
1、完成墩顶两节段组合梁100架设并设置好斜拉索500后,在已安装的组合梁100(即已架梁段)的梁面安装架梁吊机400,所述架梁吊机400设有一吊具401,在已安装的组合梁100两侧已设置好匹配连接件300。参见图1、2。
2、待安装的组合梁100(即待架梁段)在预制场制造并拼装完成,分别用第一螺栓201、第二螺栓301将临时连接系200和匹配连接件300固定到待安装的组合梁100上。参见图3、4、8。
3、用运输船将待安装的组合梁100运至施工桥位,用架梁吊机400的吊具401将其垂直起吊。
4、将待安装的组合梁100与已安装的组合梁100初步对位后,停止架梁吊机400的起吊工作,用倒链和马板辅助微调组合梁100,实现待安装的组合梁100与已安装的组合梁100上的匹配连接件300的精确对位,打入一定数量的冲钉,穿入高强度螺栓302。参见图5、6、8。
5、匹配连接件300之间的高强度螺栓302穿入数量达到要求后,用马板对组合梁100进行限位,限位完成后,松掉高强度螺栓302和第二螺栓301,拆除匹配连接件300。
6、焊接待安装的组合梁100与已安装的组合梁100之间的连接焊缝,此时,架梁吊机400逐步松钩,减小前后梁段的相对变形,松钩完成后,用马板辅助焊接桥面板进行焊接。
7、拆除原安装在待安装的组合梁100上的临时连接系200,循环倒用至下一节待安装的组合梁100。
本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术。

Claims (8)

1.双幅分离式组合梁整幅安装方法,其特征在于:通过在待安装的组合梁(100)节段后端的左右分离式钢箱梁之间设置临时连接系(200),并在左右分离式钢箱梁的腹板处设置匹配连接件(300),使待架梁段与已架梁段之间横断面能匹配对接。
2.如权利要求1所述的双幅分离式组合梁整幅安装方法,其特征在于:临时连接系(200)设置在左右分离式钢箱梁后横梁处的普通隔板断面上。
3.如权利要求2所述的双幅分离式组合梁整幅安装方法,其特征在于:所述临时连接系(200)为型钢桁梁结构,通过第一螺栓(201)与左右分离式钢箱梁后横梁处的普通隔板连接。
4.如权利要求1所述的双幅分离式组合梁整幅安装方法,其特征在于:匹配连接件(300)通过第二螺栓(301)与左右分离式钢箱梁两端上口处的腹板相连。
5.如权利要求1所述的双幅分离式组合梁整幅安装方法,其特征在于:在待安装的组合梁(100)的节段安装过程中,架梁吊机(400)吊起待安装的组合梁(100),缓慢靠近已安装的组合梁(100)前端,通过匹配连接件(300)及高强度螺栓(302)进行待架节段和已架节段对位,实现梁端面精确定位。
6.如权利要求1所述的双幅分离式组合梁整幅安装方法,其特征在于:所述临时连接系(200)包括:连接件(202),其两端分别设有拼接板(203),拼接板(203)上设有用于穿装第一螺栓(201)的螺栓孔。
7.如权利要求1所述的双幅分离式组合梁整幅安装方法,其特征在于:所述匹配连接件(300)包括:截面呈L形的连接构件(303),连接构件(303)上设有用于穿装第二螺栓(301)和高强度螺栓(302)的螺栓孔。
8.如权利要求1所述的双幅分离式组合梁整幅安装方法,其特征在于,具体施工步骤如下:
步骤1、完成墩顶两节段组合梁(100)架设并设置好斜拉索(500)后,在已安装的组合梁(100)的梁面安装架梁吊机(400),所述架梁吊机(400)设有一吊具(401),在已安装的组合梁(100)两侧已设置好匹配连接件(300);
步骤2、待安装的组合梁(100)在预制场制造并拼装完成,分别用第一螺栓(201)、第二螺栓(301)将临时连接系(200)和匹配连接件(300)固定到待安装的组合梁(100)上;
步骤3、用运输船将待安装的组合梁(100)运至施工桥位,用架梁吊机(400)的吊具(401)将其垂直起吊;
步骤4、将待安装的组合梁(100)与已安装的组合梁(100)初步对位后,停止架梁吊机(400)的起吊工作,用倒链和马板辅助微调组合梁(100),实现待安装的组合梁(100)与已安装的组合梁(100)上的匹配连接件(300)的精确对位,打入一定数量的冲钉,穿入高强度螺栓(302);
步骤5、匹配连接件(300)之间的高强度螺栓(302)穿入数量达到要求后,用马板对组合梁(100)进行限位,限位完成后,松掉高强度螺栓(302)和第二螺栓(301),拆除匹配连接件(300);
步骤6、焊接待安装的组合梁(100)与已安装的组合梁(100)之间的连接焊缝,此时,架梁吊机(400)逐步松钩,减小前后梁段的相对变形,松钩完成后,用马板辅助焊接桥面板进行焊接;
步骤7、拆除原安装在待安装的组合梁(100)上的临时连接系(200),循环倒用至下一节待安装的组合梁(100)。
CN201310098359.2A 2013-03-26 2013-03-26 双幅分离式组合梁整幅安装方法 Active CN103132458B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310098359.2A CN103132458B (zh) 2013-03-26 2013-03-26 双幅分离式组合梁整幅安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310098359.2A CN103132458B (zh) 2013-03-26 2013-03-26 双幅分离式组合梁整幅安装方法

Publications (2)

Publication Number Publication Date
CN103132458A true CN103132458A (zh) 2013-06-05
CN103132458B CN103132458B (zh) 2015-06-10

Family

ID=48492867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310098359.2A Active CN103132458B (zh) 2013-03-26 2013-03-26 双幅分离式组合梁整幅安装方法

Country Status (1)

Country Link
CN (1) CN103132458B (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018426A (zh) * 2014-05-14 2014-09-03 中铁大桥勘测设计院集团有限公司 一种钢桁梁安装方法
CN104389871A (zh) * 2014-09-29 2015-03-04 南通振华重型装备制造有限公司 一种井架立柱专用法兰及其贴合方法
CN106744351A (zh) * 2016-11-24 2017-05-31 中交路桥华南工程有限公司 利用缆索吊机进行斜拉桥主梁吊装的方法
CN106968182A (zh) * 2017-05-12 2017-07-21 陈海永 一种公路桥梁用悬吊设备防倾倒组件
CN107761570A (zh) * 2017-09-30 2018-03-06 中铁大桥局集团有限公司 一种用于大跨度钢桁梁的精确定位吊架
CN108505445A (zh) * 2018-04-16 2018-09-07 中铁二局集团有限公司 一种跨线桥梁架桥施工方法
CN108867383A (zh) * 2018-06-25 2018-11-23 中铁三局集团有限公司 一种双塔五跨钢箱桁梁斜拉桥快速施工方法
CN109629450A (zh) * 2019-01-29 2019-04-16 中铁大桥局集团有限公司 钢箱梁悬臂拼装横向线形匹配调整装置、系统及方法
CN109914265A (zh) * 2019-04-16 2019-06-21 合建卡特工业股份有限公司 一种桥面吊机
CN112112074A (zh) * 2020-08-18 2020-12-22 中铁九局集团第四工程有限公司 无支撑大跨度双曲线跨城市高架桥钢箱梁分段施工的方法
CN113026528A (zh) * 2021-03-10 2021-06-25 浙江中天恒筑钢构有限公司 一种山林空间曲线钢结构栈道安装方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006132276A (ja) * 2004-11-09 2006-05-25 Zenitaka Corp 複合pc橋梁の鋼部材先行送出し架設工法
CN101078198A (zh) * 2007-07-04 2007-11-28 湖南省交通规划勘察设计院 一种应用于自锚式悬索桥的钢箱梁架设方法
KR20080111973A (ko) * 2007-06-20 2008-12-24 주식회사 건영이엔씨 프리스트레스 강합성빔 및 그 제작 방법
KR20100111550A (ko) * 2009-04-07 2010-10-15 주식회사 에이스이엔씨 아치형 피에스씨 빔 제작 방법
CN102828469A (zh) * 2012-08-31 2012-12-19 中铁三局集团有限公司 斜腿钢箱三角刚构墩定位安装施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006132276A (ja) * 2004-11-09 2006-05-25 Zenitaka Corp 複合pc橋梁の鋼部材先行送出し架設工法
KR20080111973A (ko) * 2007-06-20 2008-12-24 주식회사 건영이엔씨 프리스트레스 강합성빔 및 그 제작 방법
CN101078198A (zh) * 2007-07-04 2007-11-28 湖南省交通规划勘察设计院 一种应用于自锚式悬索桥的钢箱梁架设方法
KR20100111550A (ko) * 2009-04-07 2010-10-15 주식회사 에이스이엔씨 아치형 피에스씨 빔 제작 방법
CN102828469A (zh) * 2012-08-31 2012-12-19 中铁三局集团有限公司 斜腿钢箱三角刚构墩定位安装施工方法

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018426A (zh) * 2014-05-14 2014-09-03 中铁大桥勘测设计院集团有限公司 一种钢桁梁安装方法
CN104389871A (zh) * 2014-09-29 2015-03-04 南通振华重型装备制造有限公司 一种井架立柱专用法兰及其贴合方法
CN106744351A (zh) * 2016-11-24 2017-05-31 中交路桥华南工程有限公司 利用缆索吊机进行斜拉桥主梁吊装的方法
CN106968182B (zh) * 2017-05-12 2019-07-30 殷立军 一种公路桥梁用悬吊设备防倾倒组件
CN106968182A (zh) * 2017-05-12 2017-07-21 陈海永 一种公路桥梁用悬吊设备防倾倒组件
CN107761570A (zh) * 2017-09-30 2018-03-06 中铁大桥局集团有限公司 一种用于大跨度钢桁梁的精确定位吊架
CN108505445A (zh) * 2018-04-16 2018-09-07 中铁二局集团有限公司 一种跨线桥梁架桥施工方法
CN108867383A (zh) * 2018-06-25 2018-11-23 中铁三局集团有限公司 一种双塔五跨钢箱桁梁斜拉桥快速施工方法
CN109629450A (zh) * 2019-01-29 2019-04-16 中铁大桥局集团有限公司 钢箱梁悬臂拼装横向线形匹配调整装置、系统及方法
CN109629450B (zh) * 2019-01-29 2024-02-27 中铁大桥局集团有限公司 钢箱梁悬臂拼装横向线形匹配调整装置、系统及方法
CN109914265A (zh) * 2019-04-16 2019-06-21 合建卡特工业股份有限公司 一种桥面吊机
CN112112074A (zh) * 2020-08-18 2020-12-22 中铁九局集团第四工程有限公司 无支撑大跨度双曲线跨城市高架桥钢箱梁分段施工的方法
CN113026528A (zh) * 2021-03-10 2021-06-25 浙江中天恒筑钢构有限公司 一种山林空间曲线钢结构栈道安装方法

Also Published As

Publication number Publication date
CN103132458B (zh) 2015-06-10

Similar Documents

Publication Publication Date Title
CN103132458B (zh) 双幅分离式组合梁整幅安装方法
CN100572256C (zh) 特大型吊车梁的安装方法
CN203594213U (zh) 灵活拆装式承重桁架
CN204081078U (zh) 连接组件及模块化建筑
CN204737609U (zh) 一种欧式起重机主梁连接结构
CN105970819A (zh) 一种钢锚梁的安装施工方法
CN109334858A (zh) 一种船舶上层建筑建造的方法
CN108517961A (zh) 一种快速装配钢结构梁柱直插式安装节点及其安装方法
CN204266124U (zh) 大节段钢箱梁预拼装胎架
CN105803948B (zh) 斜拉桥宽幅pk组合箱梁的防错台施工方法
CN103015596A (zh) 可拆装式钢结构平台及其构造方法
CN109338886B (zh) 一种用于钢箱梁节段的对位匹配装置及其对位匹配方法
CN108086478A (zh) 方钢管柱与工字梁平推式燕尾榫装配式框架节点设计方法
CN110258794B (zh) 钢梁的全螺栓连接节点及其施工方法
CN208649894U (zh) 一种钢锚梁和钢牛腿单元组拼胎架
CN104583496B (zh) 无弦杆桁元法与组合式节点桥梁
CN106320699A (zh) 桁架式模板支架体系的快速拆装方法
CN205348414U (zh) 一种钢结构连接件
CN208396306U (zh) 易拆条组件
CN209194318U (zh) 一种型钢桁架的接长连接结构
CN208994958U (zh) 模块起吊组件
CN201525697U (zh) 起重机桥架
CN203612052U (zh) 横梁
CN202809843U (zh) 卡马临时连接板
CN202265317U (zh) 一种门式起重机主梁连接装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150415

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430074 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20150415

Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No.

Applicant after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 430074 Hubei province Wuhan Dongxin East Lake New Technology Development Zone Road SBI Venture Street No. 6 Building 12 layer

Applicant before: China Zhongtie Major Bridge Engineering Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant