CN103086232A CN2013100344230A CN201310034423A CN103086232A CN 103086232 A CN103086232 A CN 103086232A CN 2013100344230 A CN2013100344230 A CN 2013100344230A CN 201310034423 A CN201310034423 A CN 201310034423A CN 103086232 A CN103086232 A CN 103086232A
Authority
CN
China
Prior art keywords
bearing frame
carriage
guiding bearing
conveyer
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100344230A
Other languages
Chinese (zh)
Other versions
CN103086232B (en
Inventor
王东红
李志国
何劝云
鲍会丽
李育平
赵进昌
牛雅静
卢宏伟
吴臻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Construction Mechanization Research Institute Co ltd
Cabr Construction Machinery Technology Co ltd
Kembo Information Technology Co ltd
Original Assignee
Institute of Building Mechanization of Chinese Academy of Building Research
Langfang Kaibo Construction Machinery Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute of Building Mechanization of Chinese Academy of Building Research, Langfang Kaibo Construction Machinery Technology Co Ltd filed Critical Institute of Building Mechanization of Chinese Academy of Building Research
Priority to CN201310034423.0A priority Critical patent/CN103086232B/en
Publication of CN103086232A publication Critical patent/CN103086232A/en
Application granted granted Critical
Publication of CN103086232B publication Critical patent/CN103086232B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A multifunctional construction hoist for cargoes comprises, combines and utilizes a guide rail frame, a material conveying device, a steel bar conveying device, a concrete conveying device, a bottom guard rail, an under frame, a buffering device, a driving device, and a guide load bearing frame in the prior art, wherein the driving device drives the guide load bearing frame to slide, and the guide load bearing frame is provided with an overload protection device, a safety device and a guide roller. The overload protection device is connected to the guide bearing frame through a shaft pin. According to the multifunctional construction hoist for the cargoes, a rigid fixing mode is changed through the material conveying device, the steel bar conveying device and the concrete conveying device, and one conveying device can be chosen to be rapidly installed on the guide load bearing frame according to requirements. The steel bar conveying device can rotate within a range of 180 degrees, steel bars are placed horizontally, and the length of the steel bars can be adjusted. Compared with a fact that an existing hoist steel bar frame is additionally installed on a cage side face, the length is not changed, and steel bars are loaded and discharged in a vertical state, the multifunctional construction hoist for the cargoes reduces load of the driving device, saves energy, and reduces noise pollution. Conveying of the steel bars is convenient, and conveying efficiency and safety of a hoist are greatly improved.

Description

Multi-functional goods building hoist
Technical field
The present invention relates to the elevator that a kind of building engineering construction is used, particularly relate to a kind of multi-functional goods building hoist.
Background technology
Construction ground in less-developed place, building body are to lean on steel rope elevator lifting means and simple and easy weight-lifting equipment to complete the transportation of the materials such as reinforcing bar, concrete, the said equipment function singleness, inefficiency, poor stability basically.The existing elevator of developing is than common elevator, increased reinforcing bar and concrete delivery functions on former function basis, but material conveyer, reinforcing bar conveyer and the concrete delivery device installed on existing elevator are all non-dismountable on elevator.In operation process, as long as elevator starts, three devices just can carry out lifting work simultaneously, cause like this power resource waste, and inefficiency produces noise emission to ambient environment again in the time of high energy consumption.In addition in existing elevator, what the Transporting equipment of reinforcing bar adopted reinforcing bar is the transportation mode of vertically slinging, and reinforcing bar loading and unloading and the reinforcing bar lifting difficulty that carry out at this reinforcing bar conveyer scene are all larger, and safety problem is also more.
Summary of the invention
The objective of the invention is to overcome the deficiency of prior art, provide have material on a kind of elevator, reinforcing bar, three kinds of conveyers of cement concrete, every kind of device can carry out quick-detachment and assembling, material conveyer, reinforcing bar conveyer, concrete delivery device can be selected one and be arranged on elevator, and the reinforcing bar conveyer multi-functional goods building hoist that can tile and place allow the reinforcing bar in length range and the reinforcing bar that keeps flat can be rotated in 180 ° of scopes.
The objective of the invention is to realize.multi-functional goods of the present invention comprises with building hoist and makes up the guide rail bracket that has utilized prior art, material conveyer, the concrete delivery device, end guardrail, underframe, shock absorber, actuating device and driven device order about on its of slip overload protection device are installed, safety device, the guiding bearing frame of guide roller, wherein overload protection device is connected on the guiding bearing frame by pivot pin, the multi-functional goods of the present invention is characterised in that with building hoist: described guiding bearing frame main body is ' L ' type structure that the shaped steel welding consists of, carriage two parts by vertical balladeur train and level form, described guiding bearing frame is provided with material ear seat, described material ear seat connects described material conveyer by material device otic placode by the fast bolt axle of material,
Be provided with four carriage ear seats above the carriage of described guiding bearing frame, described four carriage ear seats connect turntable by eight turntable otic placodes on turntable by the fast bolt axle of turntable, be fixed with the reinforcing bar conveyer on described turntable, described reinforcing bar conveyer is by adding elongate bracket one, adding elongate bracket two and basic carriage consists of, describedly add elongate bracket one, add between elongate bracket two and basic carriage and connect by bearing pin
Also be provided with the digonal link upper ear seat on described guiding bearing frame, above the carriage of described guiding bearing frame, the both sides, outer end are provided with the digonal link lower ear base, be connected with the oblique pull adjust bar by the fast bolt axle of digonal link between described digonal link upper ear seat and described digonal link lower ear base, being provided with eight carriages below the carriage of described guiding bearing frame hangs, described carriage is hung by four concrete apparatus hangers on the concrete delivery device and is connected described concrete delivery device by the fast bolt axle of concrete apparatus
Described material conveyer, reinforcing bar conveyer, concrete delivery device are selected one and are arranged on described guiding bearing frame.
The multi-functional goods building hoist of the present invention, wherein said turntable have a round rotary motion trace in 180 ° of total pivot region.
The multi-functional goods building hoist of the present invention, wherein said concrete delivery device is comprised of oblique pull adjust bar, the fast bolt axle of digonal link, the fast bolt axle of concrete apparatus and hopper, and described hopper is made of the sheet material welding.
The multi-functional goods of the present invention is that with the building hoist difference from prior art the multi-functional goods of the present invention drives material conveyer, reinforcing bar conveyer or concrete delivery dress thrin with building hoist by a cover actuating device.Demands different from the scene are changed corresponding device quickly and easily, just can realize vertical transport constructional ornamental material, reinforcing bar, concrete functional requirement.Material conveyer, reinforcing bar conveyer and the independently working each other of concrete delivery device, mutually noninterfere, each installs easy installation and removal, is convenient to execute-in-place and changes operation.Can rotate platform center of reinforcing bar conveyer rotates in 180 degree scopes, is the level of state in the reinforcing bar transportation to place and reinforcing bar conveyer cross-directional length can be carried out the length variations combination with field operation space and reinforcing bar length.Be installed at the cage side with in the past elevator reinforced frame, the constant and plumbness loading and unloading reinforcing bar of length is compared, and the present invention has reduced the load of actuating device, saved the energy, reduce noise emission, facilitated the transportation of reinforcing bar, greatly improved conveying efficiency and safety.
Below in conjunction with accompanying drawing, multi-functional goods of the present invention is described further with building hoist.
Description of drawings
Fig. 1 is integral structure of the present invention and schematic diagram in three kinds of bont situations has been installed.
Fig. 2 is the scheme of installation of material conveyer.
Fig. 3 is the occurrence schematic diagram of reinforcing bar conveyer.
Fig. 4 is the scheme of installation of concrete delivery device.
Fig. 5 is the I detail drawing in Fig. 3.
Fig. 6 is the II detail drawing in Fig. 4.
The specific embodiment
As shown in Figure 1, the multi-functional goods of the present invention comprises with building hoist and makes up the guide rail bracket 1, material conveyer 8, reinforcing bar conveyer 9, concrete delivery device 10, end guardrail 11, underframe 12, shock absorber 13, actuating device 2 and the driven device 2 that have utilized prior art and order about the guiding bearing frame 6 that overload protection device 3, safety device 5, guide roller 7 are installed on its of slip.Actuating device 2 is arranged on guiding bearing frame 6 tops, by overload protection device 3 via bearing pin 4 and guiding bearing frame 6 top otic placodes are reliable connects and move up and down along guide rail bracket 1 together with guiding bearing frame 6.End guardrail 11 is intended to provide a closed region when elevator is worked, in order to avoid cause potential safety hazard.
As shown in Figure 1 and Figure 2, guiding bearing frame 6 main bodys are ' L ' type structure that the shaped steel welding consists of, and are comprised of carriage two parts of vertical balladeur train and level, and guiding bearing frame 6 is provided with material ear seat 25.Material ear seat 25 connects material conveyer 8 by material device otic placode 24 by the fast bolt axle 14 of material.Material conveyer 8 is welded by shaped steel, punched-plate, checkered steel plate, and both sides are provided with plate-turning door, and the front and back end is provided with clamshell doors.For the constructional ornamental material of conveniently packing into, plate-turning door and clamshell doors can be opened simultaneously, material conveyer 8 and guiding bearing frame 6 as a whole together with along guide rail bracket smooth running Shang Xia 1.Material conveyer 6 is mainly used in transporting in constructure construction procedure constructional ornamental material.
As Fig. 1, Fig. 3, shown in Figure 5, be provided with 27, four carriage ear seats of four carriage ear seats 27 above the carriage of guiding bearing frame 6 and connect turntable 19 by eight turntable otic placodes 26 on turntable 19 by the fast bolt axle 18 of turntable.Turntable 19 has a round rotary motion trace in 180 ° of total pivot region.Be fixed with reinforcing bar conveyer 9 on turntable 19.Reinforcing bar conveyer 9 is by adding elongate bracket 1, adding elongate bracket 2 16 and basic carriage 17 consists of.Add elongate bracket 1, add between elongate bracket 2 16 and basic carriage 17 and connect by bearing pin.Reinforcing bar conveyer 9 can come and go rotation around turntable 19 centers in 180 degree scopes.Reinforcing bar conveyer 9 can be according to on-site actual situations and user's needs, the independent assortment variation length, and due to the placement that is the level of state of reinforcing bar in the process of transporting, and firm locking.Greatly simplify the handling sequence of reinforcing bar in the site operation, improved the safety of transporting and the convenience of loading and unloading.
As Fig. 1, Fig. 4, shown in Figure 6, guiding bearing frame 6 balladeur train upper ends also are provided with digonal link upper ear seat 28, and above the carriage of guiding bearing frame 6, the both sides, outer end are provided with digonal link lower ear base 29.Be connected with oblique pull adjust bar 20 by the fast bolt axle 21 of digonal link between digonal link upper ear seat 28 and digonal link lower ear base 29.Be provided with eight carriages below the carriage of guiding bearing frame 6 and hang 30, carriage is hung 30 and is connected concrete delivery device 10 by four concrete apparatus hangers 31 on concrete delivery device 10 by the fast bolt axle 22 of concrete apparatus.Concrete delivery device 10 is comprised of oblique pull adjust bar 20, the fast bolt axle 21 of digonal link, the fast bolt axle 22 of concrete apparatus and hopper 23, and described hopper 23 is made of the sheet material welding.In order to keep the stability of equipment, during use, two oblique pull adjusts bar 20 need to be installed simultaneously, oblique pull adjust bar 20 reliably is connected with guiding bearing frame 6 by the fast bolt axle 21 of digonal link.
The multi-functional goods building hoist of the present invention, wherein material conveyer 8, reinforcing bar conveyer 9,10 3 kinds of conveyers of concrete delivery device select one be arranged on the guiding bearing frame 6 on.Reduce the load of actuating device 2, saved the energy, reduced noise emission.
The multi-functional goods of the present invention is as follows with the working process of building hoist:
After the installation of elevator main body, according to the concrete needs of building ground, select one of them of material conveyer, reinforcing bar conveyer, concrete delivery device, it reliably is connected on guiding bearing frame 6, its working process is divided into three kinds:
One, transport constructional ornamental material: when material conveyer 8 is positioned at guide rail bracket 1 bottom, open the plate-turning door of material conveyer 8 or the clamshell doors of side, constructional ornamental material is packed in material conveyer 8, close plate-turning door or clamshell doors, material conveyer 8 upwards starts, after arriving construction layer, material conveyer 8 is out of service, open plate-turning door, after building the finishing material completed loading, close material conveyer 8 plate-turning doors, material conveyer 8 moves to guide rail bracket 1 bottom downwards, completes the working cycle that a material transports.
Two, transport reinforcing bar: when reinforcing bar conveyer 9 is positioned at guide rail bracket 1 bottom, the reinforcing bar that binding on ground is good is the level of state and slings, lie in a horizontal plane on reinforcing bar conveyer 9, reinforcing bar conveyer 9 upwards starts, after arriving construction layer, 9 stop motions of reinforcing bar conveyer, along turntable 19 central rotation reinforcing bar conveyers 9 after appropriate orientation, reinforcing bar is discharged on construction layer, revolution reinforcing bar conveyer 9 is to running state, reinforcing bar conveyer 9 moves to guide rail bracket 1 bottom downwards, completes the working cycle that a reinforcing bar transports.
3, transport cement concrete: when concrete delivery device 10 is positioned at guide rail bracket 1 bottom, open movable discharging opening, with dolly or other device, cement concrete is poured in concrete delivery device 10, after hopper concrete delivery device 10 is filled, close movable discharging opening, upwards start concrete delivery device 10 to construction layer, concrete delivery device 10 will exceed construction layer one segment distance at this moment, make concrete delivery device 10 discharging openings and construction layer connect material dolly when concordant concrete delivery device 10 out of service, open movable discharging opening discharging, after finishing, discharging shuts movable discharging opening, concrete delivery device 10 moves to guide rail bracket 1 bottom downwards, complete a working cycle.
Above-described embodiment is described the preferred embodiment of the present invention; be not that scope of the present invention is limited; design under the prerequisite of spirit not breaking away from the present invention; various distortion and improvement that those of ordinary skills make technical scheme of the present invention all should fall in the definite protection domain of claims of the present invention.

Claims (3)

1. multi-functional goods building hoist, comprise that combination has utilized the guide rail bracket (1) of prior art, material conveyer (8), concrete delivery device (10), end guardrail (11), underframe (12), shock absorber (13), actuating device (2) and driven device 2 order about on its of slip overload protection device (3) are installed, safety device (5), the guiding bearing frame (6) of guide roller (7), wherein overload protection device (3) is connected on guiding bearing frame (6) by pivot pin (4), it is characterized in that: described guiding bearing frame (6) main body is ' L ' type structure that the shaped steel welding consists of, carriage two parts by vertical balladeur train and level form, described guiding bearing frame (6) is provided with material ear seat (25), described material ear seat (25) connects described material conveyer (8) by material device otic placode (24) by the fast bolt axle of material (14),
be provided with four carriage ear seats (27) above the carriage of described guiding bearing frame (6), described four carriage ear seats (27) connect turntable (19) by eight the turntable otic placodes (26) on turntable (19) by the fast bolt axle of turntable (18), be fixed with reinforcing bar conveyer (9) on described turntable (19), described reinforcing bar conveyer (9) is by adding elongate bracket one (15), adding elongate bracket two (16) and basic carriage (17) consists of, the described elongate bracket one (15) that adds, add between elongate bracket two (16) and basic carriage (17) and connect by bearing pin
also be provided with digonal link upper ear seat (28) on described guiding bearing frame (6), above the carriage of described guiding bearing frame (6), the both sides, outer end are provided with digonal link lower ear base (29), be connected with oblique pull adjust bar (20) by the fast bolt axle of digonal link (21) between described digonal link upper ear seat (28) and described digonal link lower ear base (29), be provided with eight carriages below the carriage of described guiding bearing frame (6) and hang (30), described carriage is hung (30) and is connected described concrete delivery device (10) by four the concrete apparatus hangers (31) on concrete delivery device (10) by the fast bolt axle of concrete apparatus (22),
Described material conveyer (8), reinforcing bar conveyer (9), concrete delivery device (10) are selected one and are arranged on described guiding bearing frame (6).
2. multi-functional goods building hoist according to claim 1, it is characterized in that: described turntable (19) has a round rotary motion trace in 180 ° of total pivot region.
3. multi-functional goods building hoist according to claim 1 and 2, it is characterized in that: described concrete delivery device (10) is comprised of oblique pull adjust bar (20), the fast bolt axle of digonal link (21), the fast bolt axle of concrete apparatus (22) and hopper (23), and described hopper (23) is made of the sheet material welding.
CN201310034423.0A 2013-01-30 2013-01-30 Multifunctional construction hoist for cargoes Active CN103086232B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310034423.0A CN103086232B (en) 2013-01-30 2013-01-30 Multifunctional construction hoist for cargoes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310034423.0A CN103086232B (en) 2013-01-30 2013-01-30 Multifunctional construction hoist for cargoes

Publications (2)

Publication Number Publication Date
CN103086232A true CN103086232A (en) 2013-05-08
CN103086232B CN103086232B (en) 2015-06-03

Family

ID=48199449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310034423.0A Active CN103086232B (en) 2013-01-30 2013-01-30 Multifunctional construction hoist for cargoes

Country Status (1)

Country Link
CN (1) CN103086232B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104590978A (en) * 2014-12-02 2015-05-06 西安京龙工程机械有限公司 Lifting cage structure of construction hoist
CN115180481A (en) * 2022-09-14 2022-10-14 大汉科技股份有限公司 Worm and gear transmission type three-transmission freight elevator

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2672011Y (en) * 2003-12-29 2005-01-19 中国建筑科学研究院建筑机械化研究分院 Multipurpose construction hoist
CN2778774Y (en) * 2005-03-07 2006-05-10 杨守荣 Rocking-turn platform capable of stabilizing pot
CN201400500Y (en) * 2009-03-24 2010-02-10 中国建筑科学研究院建筑机械化研究分院 Multifunctional lifter with platform for abnormal high building construction
WO2010132933A1 (en) * 2009-05-21 2010-11-25 Consep Pty Limited Self-climbing material hoist
CN203095343U (en) * 2013-01-30 2013-07-31 中国建筑科学研究院建筑机械化研究分院 Multifunctional construction hoist for cargoes

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2672011Y (en) * 2003-12-29 2005-01-19 中国建筑科学研究院建筑机械化研究分院 Multipurpose construction hoist
CN2778774Y (en) * 2005-03-07 2006-05-10 杨守荣 Rocking-turn platform capable of stabilizing pot
CN201400500Y (en) * 2009-03-24 2010-02-10 中国建筑科学研究院建筑机械化研究分院 Multifunctional lifter with platform for abnormal high building construction
WO2010132933A1 (en) * 2009-05-21 2010-11-25 Consep Pty Limited Self-climbing material hoist
CN203095343U (en) * 2013-01-30 2013-07-31 中国建筑科学研究院建筑机械化研究分院 Multifunctional construction hoist for cargoes

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李秀辉等: "平台式多功能升降机在烟囱施工中的应用", 《施工机械化新技术交流会论文集(第七辑)》 *
王东红: "异型高耸建筑施工多功能升降机的研究开发", 《建筑机械化》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104590978A (en) * 2014-12-02 2015-05-06 西安京龙工程机械有限公司 Lifting cage structure of construction hoist
CN115180481A (en) * 2022-09-14 2022-10-14 大汉科技股份有限公司 Worm and gear transmission type three-transmission freight elevator
CN115180481B (en) * 2022-09-14 2022-12-09 大汉科技股份有限公司 Worm and gear transmission type three-transmission freight elevator

Also Published As

Publication number Publication date
CN103086232B (en) 2015-06-03

Similar Documents

Publication Publication Date Title
US9845227B2 (en) Mobile crane
CN202148009U (en) Stair track conveying device
CN210457317U (en) Vertical transport vechicle is built in room
CN105083902A (en) Ground-type roller conveying mechanism suitable for floor slab arrangement
CN106429343A (en) Container overturning machine
CN204896637U (en) It constructs to paste ground formula roller conveyors suitable for floor is arranged
CN203095343U (en) Multifunctional construction hoist for cargoes
CN205114772U (en) Perpendicular conveyer of ready -package elevartor shaft material
CN103086232B (en) Multifunctional construction hoist for cargoes
CN107298368A (en) Hanging basket and suspension bracket for building
CN102602398B (en) Quick-transporting method and quick-transport device for foldable temporary cableways
CN204402555U (en) Efficient safe mine hydraulic bracket mounting transport vehicle
CN203033294U (en) Container wood floor automatic material trimming and feeding conveying device
CN103274310B (en) Self-lifting type cableway transporting device
CN102381539A (en) Multifunctional tower crane elevator
CN205526360U (en) Prefab conveyer
CN202321479U (en) Multifunctional tower crane hoist
CN205204312U (en) Container automatic loading machine
CN204876765U (en) Pneumatic lift tower of self -discharging cabin formula
CN204980884U (en) Lifting mechanism
CN209504097U (en) A kind of high-sided wagon vehicle door disassembling device
CN204297575U (en) Conveying lifting all-in-one
CN206645688U (en) More lifting component machines
CN205802393U (en) Air pressure drive transmission unit lowering or hoisting gear
CN104444183A (en) Conveying and lifting all-in-one machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No.61 Jinguang Road, Langfang City, Hebei Province

Patentee after: INSTITUTE OF BUILDING MECHANIZATION/CHINA ACADEMY OF BUILDING RESEARCH

Patentee after: CABR CONSTRUCTION MACHINERY TECHNOLOGY Co.,Ltd.

Address before: 065000 No. 61, Golden Road, Langfang, Hebei

Patentee before: INSTITUTE OF BUILDING MECHANIZATION OF CHINA ACADEMY OF BUILDING RESEARCH

Patentee before: CABR CONSTRUCTION MACHINERY TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210107

Address after: Chuangye Road, Langfang Development Zone, Hebei Province

Patentee after: CABR CONSTRUCTION MACHINERY TECHNOLOGY Co.,Ltd.

Patentee after: BEIJING CONSTRUCTION MECHANIZATION RESEARCH INSTITUTE CO.,LTD.

Address before: No.61 Jinguang Road, Langfang City, Hebei Province

Patentee before: INSTITUTE OF BUILDING MECHANIZATION/CHINA ACADEMY OF BUILDING RESEARCH

Patentee before: CABR CONSTRUCTION MACHINERY TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220901

Address after: 065000 Chuangye Road, development zone, Langfang City, Hebei Province

Patentee after: CABR CONSTRUCTION MACHINERY TECHNOLOGY Co.,Ltd.

Patentee after: BEIJING CONSTRUCTION MECHANIZATION RESEARCH INSTITUTE CO.,LTD.

Patentee after: Kembo Information Technology Co.,Ltd.

Address before: 065000 Chuangye Road, development zone, Langfang City, Hebei Province

Patentee before: CABR CONSTRUCTION MACHINERY TECHNOLOGY Co.,Ltd.

Patentee before: BEIJING CONSTRUCTION MECHANIZATION RESEARCH INSTITUTE CO.,LTD.