CN103061782B - 大断面机动车隧道土压平衡矩形顶管管节及其施工方法 - Google Patents
大断面机动车隧道土压平衡矩形顶管管节及其施工方法 Download PDFInfo
- Publication number
- CN103061782B CN103061782B CN201310030497.7A CN201310030497A CN103061782B CN 103061782 B CN103061782 B CN 103061782B CN 201310030497 A CN201310030497 A CN 201310030497A CN 103061782 B CN103061782 B CN 103061782B
- Authority
- CN
- China
- Prior art keywords
- jacking
- jacking pipe
- pipe joints
- earth pressure
- pipe joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310030497.7A CN103061782B (zh) | 2013-01-28 | 2013-01-28 | 大断面机动车隧道土压平衡矩形顶管管节及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310030497.7A CN103061782B (zh) | 2013-01-28 | 2013-01-28 | 大断面机动车隧道土压平衡矩形顶管管节及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103061782A CN103061782A (zh) | 2013-04-24 |
CN103061782B true CN103061782B (zh) | 2015-04-15 |
Family
ID=48104635
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310030497.7A Active CN103061782B (zh) | 2013-01-28 | 2013-01-28 | 大断面机动车隧道土压平衡矩形顶管管节及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103061782B (zh) |
Families Citing this family (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334384B (zh) * | 2013-07-29 | 2016-03-02 | 苏交科集团股份有限公司 | 预制混凝土涵洞组装结构 |
CN104234721B (zh) * | 2014-07-24 | 2017-02-08 | 中铁隧道集团有限公司 | 大断面矩形顶管管节及其对接施工方法 |
CN104110265A (zh) * | 2014-07-24 | 2014-10-22 | 中铁隧道集团有限公司 | 大断面矩形顶管管道的触变泥浆注浆系统 |
CN104265321B (zh) * | 2014-08-06 | 2016-04-13 | 上海隧道工程有限公司 | 超大型全断面矩形顶管掘进施工方法 |
CN104612720A (zh) * | 2014-12-22 | 2015-05-13 | 上海市政建设有限公司 | 矩形顶管的防水结构及顶管顶进施工方法 |
CN105043884B (zh) * | 2015-08-26 | 2017-11-10 | 宁波交通工程建设集团有限公司 | 综合管廊管节承载能力试验装置及使用方法 |
CN108266205A (zh) * | 2018-01-03 | 2018-07-10 | 上海市城市建设设计研究总院(集团)有限公司 | 利用复合管节结构实施非开挖地铁车站的施工方法 |
CN109372532A (zh) * | 2018-12-25 | 2019-02-22 | 中建四局第六建筑工程有限公司 | 复杂地址环境下顶管施工工法 |
CN109854272B (zh) * | 2019-01-31 | 2023-10-13 | 中国矿业大学 | 一种岩体小断面通道的顶管管节 |
CN109882195A (zh) * | 2019-03-27 | 2019-06-14 | 浙江大学城市学院 | 一种装配式大断面矩形顶管管节及施工方法 |
CN111335919A (zh) * | 2020-03-20 | 2020-06-26 | 重庆渝高科技产业(集团)股份有限公司 | 预制管节顶推方法 |
CN111764438A (zh) * | 2020-05-07 | 2020-10-13 | 中国一冶集团有限公司 | 顶管法预制管廊接头缝隙防水结构及方法 |
CN111910574A (zh) * | 2020-07-15 | 2020-11-10 | 中亿丰建设集团股份有限公司 | 河道的矩形顶管施工方法 |
CN113639097A (zh) * | 2021-08-13 | 2021-11-12 | 中亿丰建设集团股份有限公司 | 一种多曲线小半径微扰动管廊顶管施工工法 |
CN113586090B (zh) * | 2021-08-13 | 2024-03-05 | 郑州亚欧交通职业学院 | 一种地铁顶管施工中触变泥浆置换装置 |
CN114165255A (zh) * | 2021-12-03 | 2022-03-11 | 中国二十冶集团有限公司 | 一种矩形管节及其顶管施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101363320A (zh) * | 2007-08-08 | 2009-02-11 | 上海市机械施工有限公司 | 顶盾合一隧道掘进机 |
CN102042020A (zh) * | 2010-12-30 | 2011-05-04 | 上海交通大学 | 防止顶管机与管道下沉的施工装置与施工方法 |
CN203050736U (zh) * | 2013-01-25 | 2013-07-10 | 中铁隧道勘测设计院有限公司 | 大断面机动车隧道防水型土压平衡矩形顶管管节 |
CN203050729U (zh) * | 2013-01-28 | 2013-07-10 | 中铁隧道勘测设计院有限公司 | 大断面机动车隧道土压平衡矩形顶管管节 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4137776B2 (ja) * | 2003-12-02 | 2008-08-20 | 石川島建材工業株式会社 | トンネル覆工用角型鋼管の推進方法およびトンネル覆工用角形鋼管 |
WO2012098531A1 (en) * | 2011-01-21 | 2012-07-26 | Fourie Albert William Francis | Tunnelling apparatus and method therefor |
-
2013
- 2013-01-28 CN CN201310030497.7A patent/CN103061782B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101363320A (zh) * | 2007-08-08 | 2009-02-11 | 上海市机械施工有限公司 | 顶盾合一隧道掘进机 |
CN102042020A (zh) * | 2010-12-30 | 2011-05-04 | 上海交通大学 | 防止顶管机与管道下沉的施工装置与施工方法 |
CN203050736U (zh) * | 2013-01-25 | 2013-07-10 | 中铁隧道勘测设计院有限公司 | 大断面机动车隧道防水型土压平衡矩形顶管管节 |
CN203050729U (zh) * | 2013-01-28 | 2013-07-10 | 中铁隧道勘测设计院有限公司 | 大断面机动车隧道土压平衡矩形顶管管节 |
Also Published As
Publication number | Publication date |
---|---|
CN103061782A (zh) | 2013-04-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103061782B (zh) | 大断面机动车隧道土压平衡矩形顶管管节及其施工方法 | |
CN203050729U (zh) | 大断面机动车隧道土压平衡矩形顶管管节 | |
CN203583498U (zh) | 一种微型桩组合墙支护结构 | |
CN105041337A (zh) | 一种地下盾构隧道衬砌管片的接缝拼接结构及防水方法 | |
CN104234721B (zh) | 大断面矩形顶管管节及其对接施工方法 | |
CN105240024A (zh) | 一种平行盾构法扩建施工地铁车站的方法 | |
CN111395391B (zh) | 一种多孔矩形顶管与明暗挖交接管廊接头施工方法 | |
CN102535519A (zh) | 地下连续墙工字钢接头结构及其施工方法 | |
CN203050736U (zh) | 大断面机动车隧道防水型土压平衡矩形顶管管节 | |
CN105672351A (zh) | 扣接式预制带肋钢筋混凝土综合管廊结构施工方法 | |
CN203066987U (zh) | 防错位大断面机动车隧道土压平衡矩形顶管管节 | |
CN111576488A (zh) | 污水管顶管施工装配式工作井结构及建造工艺 | |
CN105240023A (zh) | 一种曲线顶管支护结构扩建盾构施工地铁车站的方法 | |
CN102518129B (zh) | 后压浆预应力空心方桩的制作方法 | |
CN110886289A (zh) | 一种暗挖工程内转角处地下连续墙结构及施工方法 | |
CN204097891U (zh) | 钢筋混凝土预制方形涵洞 | |
CN203530959U (zh) | 一种高强度的地下连续墙 | |
CN213776657U (zh) | 一种插口端带钢接头的多重密封钢筋混凝土管涵 | |
CN210315657U (zh) | 一种整节段预制管廊用钢承插口拼装缝结构 | |
CN105155867A (zh) | 一种隧道穿越既有大直径桩建筑物的托换装置 | |
CN205742150U (zh) | 高容错性可回收钢桩套接结构 | |
CN204899937U (zh) | 一种地下盾构隧道衬砌管片的接缝拼接结构 | |
KR20130030702A (ko) | 비개착식 터널형성용 구조물 조립체 및 이의 축조방법 | |
CN204960366U (zh) | 一种隧道穿越既有大直径桩建筑物的托换装置 | |
CN209839370U (zh) | 一种钢纤维混凝土管 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C53 | Correction of patent for invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Zhang Jundai Inventor after: Zhao Xiuwang Inventor after: Ma Ning Inventor after: Peng Lin Inventor after: Huang Wei Inventor after: Ni Weiwei Inventor after: Zhang Zonggang Inventor after: Zhang Yanling Inventor after: Zhu Yongshi Inventor after: Cheng Peng Inventor after: Yang Chuanyong Inventor after: Fu Zeng Inventor before: Zhang Xianfeng Inventor before: Cheng Peng Inventor before: Tan Ziyuan Inventor before: Yang Chuanyong Inventor before: Fu Zeng Inventor before: Zhao Xiuwang Inventor before: Ma Ning Inventor before: Peng Lin Inventor before: Lv Jianying Inventor before: Song Yi Inventor before: Zhang Jundai Inventor before: Huang Wei Inventor before: Ni Weiwei Inventor before: Yan Wenbo Inventor before: Zhang Yanling Inventor before: Zhu Yongshi |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: ZHANG XIANFENG LV JIANYING SONG YI ZHANG JUNDAI HUANG WEI NI WEIWEI YAN WENBO ZHANG YANLING ZHU YONGSHI CHENG PENG TAN ZIYUAN YANG CHUANYONG FU ZENG ZHAO XIUWANG MA NING PENG LIN TO: ZHANG JUNDAI HUANG WEI NI WEIWEI ZHANG ZONGGANG ZHANG YANLING ZHU YONGSHI CHENG PENG YANG CHUANYONG FU ZENG ZHAO XIUWANG MA NING PENG LIN |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180619 Address after: 300000 Tianjin free trade zone (Airport Economic Zone), 2-3116 South Road 88. Patentee after: CHINA RAILWAY LIUYUAN GROUP CO., LTD. Address before: 300132 Tianjin Hongqiao District Bridge South East Railway Tunnel hospital Patentee before: Zhongtie Tunnel Survey and Design Inst., Ltd. |