CN103016053B - 一种采空区局部充填控制地表沉陷的方法 - Google Patents

一种采空区局部充填控制地表沉陷的方法 Download PDF

Info

Publication number
CN103016053B
CN103016053B CN201210520446.8A CN201210520446A CN103016053B CN 103016053 B CN103016053 B CN 103016053B CN 201210520446 A CN201210520446 A CN 201210520446A CN 103016053 B CN103016053 B CN 103016053B
Authority
CN
China
Prior art keywords
filling
coal
cutting
gob
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210520446.8A
Other languages
English (en)
Other versions
CN103016053A (zh
Inventor
马立强
曹新奇
李盼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201210520446.8A priority Critical patent/CN103016053B/zh
Publication of CN103016053A publication Critical patent/CN103016053A/zh
Priority to PCT/CN2013/088618 priority patent/WO2014086296A1/zh
Priority to AU2013354613A priority patent/AU2013354613B2/en
Priority to ZA2015/00071A priority patent/ZA201500071B/en
Application granted granted Critical
Publication of CN103016053B publication Critical patent/CN103016053B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

一种采空区局部充填控制地表沉陷的方法,从开切眼起,随着采煤机开始割煤到工作面液压支架移架过程中,在工作面液压支架后方的顶板上间隔悬挂金属网,并设置充填袋;当采煤机割完一刀后停止割煤,依次向金属网内设置的充填袋中充填混凝土至接顶;采煤机继续割下一刀煤,在紧靠已充填的充填区域两侧的顶板上续挂金属网,继续充填完成一个循环的充填作业,在与工作面平行的采空区内形成一排充填体;采煤机连续割煤4~5刀后,再继续下一循环的充填作业,周而复始,直至完成整个采空区的充填作业,使采空区形成多排充填体。其方法简单易行,充填成本低,对采空区顶板均匀相间支撑,有利于上覆岩层特别是关键层的稳定,有效防治了地表沉陷和建筑物损害。

Description

一种采空区局部充填控制地表沉陷的方法
技术领域
本发明涉及煤炭开采技术领域,尤其是一种适用于矿井“三下”压煤开采、煤层顶板较稳定的采空区局部充填控制地表沉陷的方法。
技术背景
我国生产矿井“三下”压煤约为140亿t,可供10个年产1000万t的矿井生产140 a,其中建筑物下压煤约为90亿t。如何合理解决建筑物下压煤开采问题一直是困扰中国煤矿企业的重要课题之一。
针对采后地面沉陷控制,国内外主要从减沉开采和采空区顶板覆岩移动控制两方面入手:
减沉开采技术主要包括条带开采和房柱式开采两种,条带开采是把开采的煤层划分成较正规的条带,然后采一条留一条,以此来减少地表下沉。这种技术在我国应用较多,其最大优点是能沿用现有采煤工艺,成本增加少、便于生产管理,同时对减小地表沉降有明显作用,其缺点主要表现为采出率低(一般为30%~50%),资源损失严重。房柱式开采是美国、澳大利亚、南非等国应用比较成熟的一种采煤技术,既是一种常规采煤方法,也是地表沉陷控制的开采手段,该方法在我国部分矿区有应用,其经济效益较好,其缺点是资源采出率低,通风条件差,仅适用于地质条件相对简单的煤层;
采空区顶板覆岩移动控制技术主要包括全部充填技术、部分充填技术、离层注浆技术、冒落区充填注浆技术。全部充填技术是利用充填材料充入采空区形成充填体,以此阻止顶板垮落,限制顶板移动,该方法能有效减小地表下沉和提高煤炭采出率,但因其成本较高而受到很大限制。部分充填技术是对采空区的局部或离层区与冒落区进行充填,靠覆岩关键层结构、充填体及部分煤柱共同支撑覆岩来控制开采沉陷。离层注浆技术则从岩层内部移动规律出发,确定采后覆岩离层位置,从地表钻孔向离层内充填粉煤灰等介质,从而达到控制地表沉陷的目的,该方法可实现地表注浆与地下开采平行作业,互不干扰,但因离层位置和离层量难于准确判断而在应用上受到限制。冒落区注浆充填技术是在采空区冒落矸石未被压实前注入浆液予以充填加固,以此来支撑覆岩,从而减缓地表沉陷,该技术尚处于在研究阶段,尚未得到广泛应用。
从理论上来说,采用充填开采技术将煤矸石等固体废弃物作为主要充填材料充填到井下,一方面可以减少矸石等废物排放,另一方面可以减缓开采沉陷,实现建筑物下压煤开采,符合煤炭循环经济和绿色开采的要求。但如何发展适合煤矿特点与要求的充填开采技术的问题仍有待解决,其中如何降低充填开采成本,是煤矿充填开采技术需要解决的关键问题。
煤矿充填开采技术的研究应充分利用煤系层状岩层移动规律与控制特点。有关研究证明,覆岩主关键层对地表移动过程起控制作用,主关键层的破断将导致地表快速下沉及下沉量的明显增大,地表下沉速度随主关键层周期性破断而呈现跳跃性变化。因而,控制主关键层就可以有效地控制地表沉陷。
发明内容
技术问题:本发明的目的是克服已有技术中的不足之处,提供一种方法简单、操作方便、成本低的采空区局部充填控制地表沉陷的方法。
技术方案:本发明的采空区局部充填控制地表沉陷的方法,包括如下步骤:
a. 在工作面运输平巷中布置混凝土输送管道,同时在井下工作面设备列车上安装混凝土输送泵,在工作面液压支架尾梁上吊挂与混凝土输送管道相连接的充填管道,在工作面上下端头液压支架之间间隔设置多个充填区域,在每个充填区域对应的充填管道位置设置卸料口;
b. 从开切眼起,随着采煤机开始割煤到工作面液压支架移架过程中,在工作面液压支架后方的顶板上间隔悬挂金属网,在金属网内设置充填袋;
c. 当采煤机割完一刀煤并斜切进刀后停止割煤,打开混凝土输送泵,通过混凝土输送管道经充填管道将混凝土输送至充填区域;
d. 依次打开每个充填区域充填管道上的卸料口,向金属网内设置的充填袋中充填混凝土至接顶,并封闭充填袋;
e. 采煤机继续割下一刀煤,在紧靠已充填的充填区域两侧的顶板上续挂金属网,并在金属网内设置充填袋,重复步骤c、d,完成一个充填循环,在与工作面平行的采空区内形成一排充填体;
f. 采煤机连续割煤4~5刀后,重复步骤c、d、e,继续下一循环的充填作业,周而复始,直至完成整个采空区的充填作业,使采空区形成多排充填体。
有益效果:本发明在条带充填的基础上,采用部分充填开采方式,可以减少充填材料的用量和充填量,降低充填成本。通过改变充填体的布置方式,对采空区顶板均匀相间支撑,有利于顶板及关键层的稳定。在采空区内均匀相间布置矩形区域的充填体,既减少了充填量,降低了充填成本,提高了采出率,同时提高了覆岩关键层的稳定性,从而可以有效地控制地表沉陷。其方法简单、成本低。
附图说明
图1是本发明的综采工作面采空区局部充填布局示意图。
图中:1-工作面轨道平巷,2-工作面运输平巷,3-混凝土输送管道,4-充填管道,5-卸料口,6-工作面刮板输送机,7-采煤机,8-运输平巷胶带输送机,9-设备列车,10-充填体。
具体实施方式
下面结合附图对本发明的一个实施例作进一步的描述:
本发明的采空区局部充填控制地表沉陷的方法:
a. 首先在工作面运输平巷2中布置混凝土输送管道3,同时在井下工作面设备列车9上安装混凝土输送泵,在工作面液压支架尾梁上吊挂与混凝土输送管道3相连接的充填管道4,在工作面上下端头液压支架之间间隔设置多个充填区域,在每个充填区域对应的充填管道4位置设置有卸料口5;
b. 从开切眼起,随着采煤机开始割煤到工作面液压支架移架过程中,在工作面液压支架后方的顶板上间隔悬挂金属网,并在金属网内设置充填袋,所述的金属网在垂直于工作面推进方向一侧的长度为4~5 m,平行于推进方向两侧的宽度为0.6~0.8 m;
c. 当采煤机割完一刀煤并斜切进刀后停止割煤,打开混凝土输送泵,通过混凝土输送管道3经充填管道4将混凝土输送至充填区域;
d. 依次打开每个充填区域充填管道4上的卸料口5,向金属网内设置的充填袋中充填混凝土至接顶,并封闭充填袋;
e. 采煤机继续割下一刀煤,在紧靠已充填的充填区域两侧的顶板上续挂金属网,并在金属网内设置充填袋,重复步骤c、d,完成一个充填循环,在与工作面平行的采空区内形成一排充填体10,所述的充填循环步距为1.2~1.6 m,可以根据现场实际情况调整,最终形成具有一定强度充填体10;
f. 采煤机连续割煤4~5刀后,推进长度为2.4~4 m,可以根据实际情况调整,重复步骤c、d、e,继续下一个循环的充填作业,周而复始,直至完成整个采空区的充填作业,使采空区形成多排充填体10。

Claims (1)

1.一种采空区局部充填控制地表沉陷的方法,其特征在于,包括如下步骤:
a. 在工作面运输平巷(2)中布置混凝土输送管道(3),同时在井下工作面设备列车上安装混凝土输送泵,在工作面液压支架尾梁上吊挂与混凝土输送管道(3)相连接的充填管道(4),在工作面上下端头液压支架之间间隔设置多个充填区域,在每个充填区域对应的充填管道(4)位置设置卸料口(5);
b. 从开切眼起,随着采煤机开始割煤到工作面液压支架移架过程中,在工作面液压支架后方的顶板上间隔悬挂金属网,在金属网内设置充填袋;所述的金属网在垂直于工作面推进方向一侧的长度为4~5 m,平行于推进方向两侧的宽度为0.6~0.8 m;
c. 当采煤机割完一刀煤并斜切进刀后停止割煤,打开混凝土输送泵,通过混凝土输送管道(3)经充填管道(4)将混凝土输送至充填区域;
d. 依次打开每个充填区域充填管道(4)上的卸料口(5),向金属网内设置的充填袋中充填混凝土至接顶,并封闭充填袋;
e. 采煤机继续割下一刀煤,在紧靠已充填的充填区域两侧的顶板上续挂金属网,并在金属网内设置充填袋,重复步骤c、d,完成一个充填循环,在与工作面平行的采空区内形成一排充填体(10);所述的充填循环步距为1.2~1.6 m,根据现场实际情况调整,最终形成具有一定强度充填体(10);
f. 采煤机连续割煤4~5刀后,推进长度为2.4~4 m,根据实际情况调整,重复步骤c、d、e,继续下一循环的充填作业,周而复始,直至完成整个采空区的充填作业,使采空区形成多排充填体(10)。
CN201210520446.8A 2012-12-07 2012-12-07 一种采空区局部充填控制地表沉陷的方法 Active CN103016053B (zh)

Priority Applications (4)

Application Number Priority Date Filing Date Title
CN201210520446.8A CN103016053B (zh) 2012-12-07 2012-12-07 一种采空区局部充填控制地表沉陷的方法
PCT/CN2013/088618 WO2014086296A1 (zh) 2012-12-07 2013-12-05 一种采空区局部充填控制地表沉陷的方法
AU2013354613A AU2013354613B2 (en) 2012-12-07 2013-12-05 Method of local filling to control surface subsidence in worked-out area
ZA2015/00071A ZA201500071B (en) 2012-12-07 2015-01-06 Method of local filling to control surface subsidence in gob

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210520446.8A CN103016053B (zh) 2012-12-07 2012-12-07 一种采空区局部充填控制地表沉陷的方法

Publications (2)

Publication Number Publication Date
CN103016053A CN103016053A (zh) 2013-04-03
CN103016053B true CN103016053B (zh) 2015-03-04

Family

ID=47965096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210520446.8A Active CN103016053B (zh) 2012-12-07 2012-12-07 一种采空区局部充填控制地表沉陷的方法

Country Status (4)

Country Link
CN (1) CN103016053B (zh)
AU (1) AU2013354613B2 (zh)
WO (1) WO2014086296A1 (zh)
ZA (1) ZA201500071B (zh)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103016053B (zh) * 2012-12-07 2015-03-04 中国矿业大学 一种采空区局部充填控制地表沉陷的方法
CN104131829B (zh) * 2014-06-25 2016-05-04 中国矿业大学 一种固体充填采煤液压支架撤架方法
CN105525919A (zh) * 2014-09-29 2016-04-27 四川省华蓥山煤业股份有限公司绿水洞煤矿 一种急倾斜综采面切眼扩刷与设备安装交叉作业方法
CN104863591B (zh) * 2015-06-16 2017-12-08 东北大学 采空区控制冒落与地表充填治理方法
CN105332706A (zh) * 2015-11-03 2016-02-17 天地科技股份有限公司 一种村庄下压煤短长壁部分开采方法
CN105736045B (zh) * 2016-04-20 2018-09-11 山东科技大学 一种控制采空区底板突水的袋式充填系统及其充填方法
CN106150546B (zh) * 2016-08-05 2018-05-04 太原理工大学 一种根据地表沉陷特征进行采空区部分充填的方法
CN106150545B (zh) * 2016-08-05 2018-05-04 太原理工大学 一种根据顶板垮落特征进行采空区部分充填的方法
CN107916933A (zh) * 2017-11-20 2018-04-17 河南理工大学 一种坚硬顶板煤层采空区空间留设方法
CN109977453B (zh) * 2019-01-15 2023-04-18 河北工程大学 固体充填液压支架工作阻力设计方法
CN109707442B (zh) * 2019-03-08 2023-09-12 中煤科工集团北京华宇工程有限公司 一种与割煤同步的采空区快速注浆充填袋及其采煤方法
CN110145363B (zh) * 2019-04-30 2024-03-29 中国矿业大学(北京) 一种实现综采面垮落到充填开采过渡的顶板控制方法
CN110043260B (zh) * 2019-05-17 2020-10-13 中国矿业大学(北京) 一种利用常规液压支架进行充填采煤的方法
CN110318803A (zh) * 2019-07-12 2019-10-11 中国矿业大学 一种利用散体充填材料的条式间隔充填方法
CN111305896B (zh) * 2020-03-11 2022-02-22 西安科技大学 一种利用液压支架后囊袋充填点源式间隔支撑减损方法
CN112360549B (zh) * 2020-11-11 2023-01-13 国家能源投资集团有限责任公司 一种充填设备及充填方法
CN113756866A (zh) * 2021-09-24 2021-12-07 中北大学 单独采用粉煤灰作为煤矸石山覆盖层的施工参数确定方法
CN114776370B (zh) * 2022-05-18 2024-04-16 中煤地生态环境科技有限公司 一种处理煤矸石的方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5615979A (en) * 1995-08-14 1997-04-01 Lin; Fen-Fen Mine support bag
CN101701526A (zh) * 2009-11-05 2010-05-05 冀中能源邯郸矿业集团有限公司 一种采空区袋式充填方法
CN101975085A (zh) * 2010-09-09 2011-02-16 中国矿业大学 一种沿空留巷加固充填体结构及其施工方法
WO2011133798A1 (en) * 2010-04-22 2011-10-27 Micon Pumpable support with cladding
CN202467921U (zh) * 2011-12-31 2012-10-03 山东科技大学 一种薄煤层破碎顶板拖管式充填系统

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3413602C2 (de) * 1984-04-11 1986-04-24 Bergwerksverband Gmbh, 4300 Essen Verfahren zum Versetzen der Hohlräume eines Bruchfeldes
SU1308774A1 (ru) * 1985-12-24 1987-05-07 Всесоюзный научно-исследовательский и проектно-конструкторский угольный институт "КНИУИ" Способ закладки выработанного пространства при работе с механизированной крепью
CN101372891B (zh) * 2008-06-10 2010-08-11 沈阳市华祥矿山机械厂 条带充填整体回采采煤方法
CN101705838A (zh) * 2009-11-05 2010-05-12 冀中能源邯郸矿业集团有限公司 一种采空区阻隔式充填方法
CN201982138U (zh) * 2011-03-22 2011-09-21 三一重型综采成套装备有限公司 井下添加胶结料装置
CN102493838B (zh) * 2011-12-17 2014-01-15 湖南科技大学 一种急倾斜煤层综采连续充填采煤方法
CN103016053B (zh) * 2012-12-07 2015-03-04 中国矿业大学 一种采空区局部充填控制地表沉陷的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5615979A (en) * 1995-08-14 1997-04-01 Lin; Fen-Fen Mine support bag
CN101701526A (zh) * 2009-11-05 2010-05-05 冀中能源邯郸矿业集团有限公司 一种采空区袋式充填方法
WO2011133798A1 (en) * 2010-04-22 2011-10-27 Micon Pumpable support with cladding
CN101975085A (zh) * 2010-09-09 2011-02-16 中国矿业大学 一种沿空留巷加固充填体结构及其施工方法
CN202467921U (zh) * 2011-12-31 2012-10-03 山东科技大学 一种薄煤层破碎顶板拖管式充填系统

Also Published As

Publication number Publication date
CN103016053A (zh) 2013-04-03
WO2014086296A1 (zh) 2014-06-12
AU2013354613B2 (en) 2016-05-05
ZA201500071B (en) 2015-12-23
AU2013354613A1 (en) 2015-03-12

Similar Documents

Publication Publication Date Title
CN103016053B (zh) 一种采空区局部充填控制地表沉陷的方法
CN103306720B (zh) 一种特厚煤层倾斜分层固体充填采煤方法
CN103615250B (zh) 分条间柱全空场开采嗣后充填协同采矿法
CN103557002B (zh) 一种盘区机械化集中溜井上向水平分层充填采矿法
CN101105129B (zh) 采矿环境再造连续采矿嗣后充填采矿法
CN103527197B (zh) 一种特厚煤层固体胶结充填巷式开采方法
CN105971606B (zh) 一种巨厚煤层长壁工作面开采方法
CN104832178A (zh) 一种厚煤层分层部分充填采煤方法
CN105464700B (zh) 综采‑充填混合开采工作面充填段长度确定方法
CN105587318A (zh) 一种缓倾斜平行中厚矿体群连续回采的充填采矿法
CN106930763A (zh) 一种充填复采特厚煤层残采区护巷煤柱的方法
CN101586460A (zh) 一种采煤固体物充填方法
CN104500070B (zh) 一种连续采煤机膏体充填开采方法
CN109869150B (zh) 一种矿山资源分段全采局充开采方法
CN106761750B (zh) 急倾斜煤层纵向长壁刨铣建槽式开采方法
CN103993881A (zh) 一种长壁巷式胶结充填开采方法
CN201474347U (zh) 一种分段矿房
CN105003269A (zh) 一种巨厚煤层长壁工作面的开采方法
CN116163730A (zh) 一种薄煤层钻机双向前进充填开采及二氧化碳封存的方法
CN102418528B (zh) 使用钢混结构人工假顶的端部放矿崩落法开采工艺
CN105822305A (zh) 一种用于煤矿开采的覆岩隔离柱将充填减沉方法
CN103557001A (zh) 一种低段高无底柱留矿嗣后充填采矿法
CN105804752A (zh) 一种煤矿条带开采中覆岩离层注浆减沉工艺
CN108331580B (zh) 一种清洁高效的采煤方法
CN102943689A (zh) 一种煤矿散料充填开采的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant