CN103009474A - 箱梁预制蒸汽养生设备及养生方法 - Google Patents

箱梁预制蒸汽养生设备及养生方法 Download PDF

Info

Publication number
CN103009474A
CN103009474A CN2012105847405A CN201210584740A CN103009474A CN 103009474 A CN103009474 A CN 103009474A CN 2012105847405 A CN2012105847405 A CN 2012105847405A CN 201210584740 A CN201210584740 A CN 201210584740A CN 103009474 A CN103009474 A CN 103009474A
Authority
CN
China
Prior art keywords
steam curing
temperature
prefabricated
steam
case
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012105847405A
Other languages
English (en)
Inventor
李洪林
杨继禹
卢立军
陈立波
宋喜文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Longjian Road & Bridge Of Second Branch Co Ltd
Original Assignee
Heilongjiang Longjian Road & Bridge Of Second Branch Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang Longjian Road & Bridge Of Second Branch Co Ltd filed Critical Heilongjiang Longjian Road & Bridge Of Second Branch Co Ltd
Priority to CN2012105847405A priority Critical patent/CN103009474A/zh
Publication of CN103009474A publication Critical patent/CN103009474A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

箱梁预制蒸汽养生设备及养生方法 我国北方冬季气温较低,但许多桥梁梁板预制限于工期要求,必须进行冬季施工。在低温状态下,混凝土形成的强度低,模板周转的日期长,不利于提高箱梁预制施工进度。本发明的组成包括:箱梁( 1 ),所述的箱梁内部安装有蒸汽养生管( 2 )、温控感应元件( 3 ),所述的蒸汽养生管通过蒸汽管道( 4 )与蒸汽机( 5 )连接,所述的温控感应元件与温度仪表( 6 )连接。 本发明用于 箱梁预制蒸汽养生

Description

箱梁预制蒸汽养生设备及养生方法
技术领域:
本发明涉及一种箱梁预制蒸汽养生设备及养生方法。
背景技术:
我国北方冬季气温较低,但许多桥梁梁板预制限于工期要求,必须进行冬季施工。在低温状态下,混凝土形成的强度低,模板周转的日期长,不利于提高箱梁预制施工进度。
发明内容:
本发明的目的是提供一种箱梁预制蒸汽养生设备及养生方法,在低温状态下箱梁预制采用蒸汽养生办法施工,既能满足工期要求,又能确保预制板梁的质量。
上述的目的通过以下的技术方案实现:
一种箱梁预制蒸汽养生设备,其组成包括:箱梁,所述的箱梁内部安装有蒸汽养生管、温控感应元件,所述的蒸汽养生管通过蒸汽管道与蒸汽机连接,所述的温控感应元件与温度仪表连接。
箱梁预制蒸汽养生设备,所述的箱梁四面具有密封保温帘布,所述的保温帘布上开有观察窗。
一种箱梁预制蒸汽养生方法,在温度不低于5℃时完成混凝土浇筑,覆盖养生,并在预制箱梁内部布设蒸汽养生管与温控感应元件,将蒸汽养生管通过蒸汽管道与蒸汽机连接,通过温度感应元件适时掌握所述的预制箱梁的养生温度,并根据温度变化,调整蒸汽流量,确保所述的预制箱梁随时保持适宜的养生温度,以满足所述的预制箱梁冬期施工要求。
有益效果:
1. 本发明通过温度感应元件适时掌握预制箱梁的养生温度,并根据温度变化,调整蒸汽流量,确保预制箱梁随时保持适宜的养生温度,以满足冬期箱梁预制的施工要求。
本发明确保冬期箱梁预制施工质量,加快预制混凝土强度的形成,缩短模板周转的日期,同时,提高箱梁预制施工进度,为确保工期目标的实现提供有效的保障。
附图说明:
附图1是本发明的结构示意图。
具体实施方式:
实施例1:
一种箱梁预制蒸汽养生设备,其组成包括:箱梁1,所述的箱梁内部安装有蒸汽养生管2、温控感应元件3,所述的蒸汽养生管通过蒸汽管道4与蒸汽机5连接,所述的温控感应元件与温度仪表6连接。
箱梁预制蒸汽养生设备,所述的箱梁四面具有密封保温帘布,与钢结构形成5个面的箱体,保证热气流在特定区域内停留,所述的保温帘布上开有带密封圈的观察窗。
所述的密封保温帘布为涂胶布、亚麻布、帆布。
实施例2:
一种箱梁预制蒸汽养生方法,在温度不低于5℃时完成混凝土浇筑,在浇筑后的表面覆盖含湿水5-20%的织物进行养生,并在预制箱梁内部布设蒸汽养生管与温控感应元件随时监控器中的温度变化,将蒸汽养生管通过蒸汽管道与蒸汽机连接,通过箱梁四面的密封保温帘布进行保温,通过温度感应元件适时掌握所述的预制箱梁的养生温度,当温度降至5℃,调整蒸汽流量,确保所述的预制箱梁随时保持适宜的养生温度,以满足所述的预制箱梁冬期施工要求。

Claims (3)

1.一种箱梁预制蒸汽养生设备,其组成包括:箱梁,其特征是:所述的箱梁内部安装有蒸汽养生管、温控感应元件,所述的蒸汽养生管通过蒸汽管道与蒸汽机连接,所述的温控感应元件与温度仪表连接。
2.根据权利要求1所述的箱梁预制蒸汽养生设备,其特征是:所述的箱梁四面具有密封保温帘布,所述的保温帘布上开有观察窗。
3.一种箱梁预制蒸汽养生方法,其特征是:在温度不低于5℃时完成混凝土浇筑,覆盖养生,并在预制箱梁内部布设蒸汽养生管与温控感应元件,将蒸汽养生管通过蒸汽管道与蒸汽机连接,通过温度感应元件掌握所述的预制箱梁的养生温度,并根据温度变化,调整蒸汽流量,确保所述的预制箱梁随时保持适宜的养生温度,以满足所述的预制箱梁冬期施工要求。
CN2012105847405A 2012-12-30 2012-12-30 箱梁预制蒸汽养生设备及养生方法 Pending CN103009474A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012105847405A CN103009474A (zh) 2012-12-30 2012-12-30 箱梁预制蒸汽养生设备及养生方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012105847405A CN103009474A (zh) 2012-12-30 2012-12-30 箱梁预制蒸汽养生设备及养生方法

Publications (1)

Publication Number Publication Date
CN103009474A true CN103009474A (zh) 2013-04-03

Family

ID=47958853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012105847405A Pending CN103009474A (zh) 2012-12-30 2012-12-30 箱梁预制蒸汽养生设备及养生方法

Country Status (1)

Country Link
CN (1) CN103009474A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106939555A (zh) * 2017-03-21 2017-07-11 中交二航局第四工程有限公司安徽分公司 一种短线匹配法箱梁施工的冬季养护方法
CN107486936A (zh) * 2016-06-13 2017-12-19 中铁十二局集团有限公司 一种快速电热单孔箱梁预制方法
CN109183798A (zh) * 2018-08-17 2019-01-11 上海二十冶建设有限公司 一种综合管廊现浇混凝土施工的密闭蒸养装置及施工方法
CN111519540A (zh) * 2020-04-29 2020-08-11 中国水利水电第八工程局有限公司 一种连续梁悬臂保温施工装置
CN113027156A (zh) * 2021-03-10 2021-06-25 中铁二十局集团第六工程有限公司 一种箱梁冬季施工用养护系统

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002086437A (ja) * 2000-09-20 2002-03-26 Boiler Engineering:Kk コンクリート養生装置
CN1830644A (zh) * 2006-04-17 2006-09-13 上海隧道工程股份有限公司 现浇箱梁低温蒸汽养护施工方法
CN101224597A (zh) * 2007-12-25 2008-07-23 中铁四局集团有限公司 箱梁蒸汽养护自动化控制装置及其温度控制方法
CN101244607A (zh) * 2008-03-17 2008-08-20 中铁二局股份有限公司 预制梁养护装置及其养护方法
CN201169009Y (zh) * 2008-03-18 2008-12-24 中铁二局股份有限公司 预制梁养护装置
CN202985754U (zh) * 2012-12-30 2013-06-12 黑龙江省龙建路桥第二工程有限公司 箱梁预制蒸汽养生设备

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002086437A (ja) * 2000-09-20 2002-03-26 Boiler Engineering:Kk コンクリート養生装置
CN1830644A (zh) * 2006-04-17 2006-09-13 上海隧道工程股份有限公司 现浇箱梁低温蒸汽养护施工方法
CN101224597A (zh) * 2007-12-25 2008-07-23 中铁四局集团有限公司 箱梁蒸汽养护自动化控制装置及其温度控制方法
CN101244607A (zh) * 2008-03-17 2008-08-20 中铁二局股份有限公司 预制梁养护装置及其养护方法
CN201169009Y (zh) * 2008-03-18 2008-12-24 中铁二局股份有限公司 预制梁养护装置
CN202985754U (zh) * 2012-12-30 2013-06-12 黑龙江省龙建路桥第二工程有限公司 箱梁预制蒸汽养生设备

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107486936A (zh) * 2016-06-13 2017-12-19 中铁十二局集团有限公司 一种快速电热单孔箱梁预制方法
CN106939555A (zh) * 2017-03-21 2017-07-11 中交二航局第四工程有限公司安徽分公司 一种短线匹配法箱梁施工的冬季养护方法
CN109183798A (zh) * 2018-08-17 2019-01-11 上海二十冶建设有限公司 一种综合管廊现浇混凝土施工的密闭蒸养装置及施工方法
CN111519540A (zh) * 2020-04-29 2020-08-11 中国水利水电第八工程局有限公司 一种连续梁悬臂保温施工装置
CN113027156A (zh) * 2021-03-10 2021-06-25 中铁二十局集团第六工程有限公司 一种箱梁冬季施工用养护系统

Similar Documents

Publication Publication Date Title
CN103009474A (zh) 箱梁预制蒸汽养生设备及养生方法
CN205259609U (zh) 冬季混凝土施工智能温控模板加热保温系统
CN106592430A (zh) 一种挂篮悬臂现浇冬季施工方法
CN108342986A (zh) 一种简易高墩塔柱混凝土侧面养生施工方法
CN106032707A (zh) 一种混凝土局部加热养护方法及装置
CN101761194B (zh) 一种屋面防水结构及其制造方法
CN203125684U (zh) 混凝土预制构件用养护棚
CN201991234U (zh) 高空冬季施工成套装置
CN204326262U (zh) Sy-k补偿收缩混凝土膨胀加强带
CN202985754U (zh) 箱梁预制蒸汽养生设备
CN208717952U (zh) 一种地下室后浇带预留通道施工装置
CN106939555A (zh) 一种短线匹配法箱梁施工的冬季养护方法
CN103882836B (zh) 一种控制水闸闸墩裂缝的方法及填充装置
CN203347031U (zh) 无机保温砂浆外墙保温系统
CN202577951U (zh) 保温型爬模
CN204149305U (zh) 桥梁墩身养护设备
CN203403549U (zh) 屋面变形缝
CN202810007U (zh) 一种屋面防水保温构造
CN203585579U (zh) 一种建筑物穿墙管线外防水结构
CN205857196U (zh) 车站低温施工专用保温屋盖
CN201981681U (zh) 一种金属格栅板的绝缘结构
CN208563997U (zh) 一种木模板用混凝土构筑物降温抗裂装置
CN204328234U (zh) 一种下水管组件
CN204673773U (zh) 一种高效蒸压加气混凝土砌块用发酵箱
CN204645685U (zh) 一种混凝土施工加热板

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20130403

RJ01 Rejection of invention patent application after publication