CN102849180B - Launching process of jack-up offshore drilling platform by airbag - Google Patents

Launching process of jack-up offshore drilling platform by airbag Download PDF

Info

Publication number
CN102849180B
CN102849180B CN201210347402.XA CN201210347402A CN102849180B CN 102849180 B CN102849180 B CN 102849180B CN 201210347402 A CN201210347402 A CN 201210347402A CN 102849180 B CN102849180 B CN 102849180B
Authority
CN
China
Prior art keywords
platform
air bag
pier
water
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210347402.XA
Other languages
Chinese (zh)
Other versions
CN102849180A (en
Inventor
胡德祥
吕宏伟
赵京坤
张晓宇
王建才
许明玉
于鹏飞
杨丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LIAONING LUHAI PETROLEUM EQUIPMENT RESEARCH INSTITUTE CO LTD
China Petroleum Liaohe Equipment Co
Original Assignee
LIAONING LUHAI PETROLEUM EQUIPMENT RESEARCH INSTITUTE CO LTD
China Petroleum Liaohe Equipment Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIAONING LUHAI PETROLEUM EQUIPMENT RESEARCH INSTITUTE CO LTD, China Petroleum Liaohe Equipment Co filed Critical LIAONING LUHAI PETROLEUM EQUIPMENT RESEARCH INSTITUTE CO LTD
Priority to CN201210347402.XA priority Critical patent/CN102849180B/en
Publication of CN102849180A publication Critical patent/CN102849180A/en
Application granted granted Critical
Publication of CN102849180B publication Critical patent/CN102849180B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to the technical field of offshore oil drilling, in particular to a launching process of a jack-up offshore drilling platform by an airbag. The process includes the steps of firstly, horizontally constructing the platform on a building berth; secondly, using an over-sized and ultrahigh-pressure launching airbag; thirdly, lengthening a bearing segment of the structure of the building berth; fourthly, distributing a construction pier; fifthly, using a footing blocking fixture to block footings; sixthly, performing secondary pier reversing after closing the platform; seventhly, dragging the fixed platform; eighthly, distributing the airbag below a main hull of the platform; ninthly, removing the construction pier of the platform; tenthly, shifting the platform to the water edge after second pier reversing; eleventhly, releasing to launch; and twelfthly, recovering the airbag and the footing blocking fixture. The drilling platform uses the airbag which is stable, efficient and low in cost to launch, the airbag is stable and controllable, launching period of the platform is shortened, construction cost and difficulty in construction of the platform are greatly reduced, and requirements of the platform for shipyards are lowered effectively.

Description

Self-lifting type marine drilling platform air bag launching process
Technical field:
The present invention relates to a kind of offshore oil drilling technical field, particularly a kind of self-lifting type marine drilling platform air bag launching process.
Background technology:
Under self-lifting type marine drilling platform, water technology mainly to adopt at present both at home and abroad under building dock launching, arine railway water and refutes technology such as launching a ship.Building dock launching technology, requires higher to the capital construction of shipyard, and shipyard must possess the Large Ship Dock adapted with institute construct platform, and this technology is only applicable to have Large Ship Dock shipyard, and general middle boatyard cannot apply.Water technology under arine railway, needs to possess slideway needed for lower water, and needing increases extra investment cost; And the building berth of slideway has been installed, limit building berth and build the applicability of project, lower horizontal stability control ratio is more complicated, and in order to water steadying under ensureing platform is controlled, need the sliding system that design is complicated, platform construction difficulty is larger.Refute the technology of launching a ship, need to solve the complicated problem such as plateau levels translation, upper barge, need to possess large-scale partly diving and refute, require higher to the waters residing for shipyard, under platform, water process is consuming time longer.Other launching technology, cannot meet the particular/special requirement of water under platform.
Summary of the invention:
The technical problem to be solved in the present invention is to provide a kind of self-lifting type marine drilling platform air bag launching process, the method achieve the air bag launching that drilling platform adopts steady high efficiency, low cost, steadily controlled, the water cycle under shortening platform, greatly lower the laid down cost of platform and build difficulty, effectively reducing the door that construct platform requires shipyard.The large-scale capital construction facility that the construction overcoming the jack-up platform under existing self-lifting type marine drilling platform in water technology need possess Large Ship Dock, complicated slideway or half is dived refutes etc., laid down cost is high, builds the deficiency that difficulty is large.
The technical solution used in the present invention is: a kind of self-lifting type marine drilling platform air bag launching process, and the method step is as follows:
One, platform level on building berth is built: low different construction pier after high before arranging, platform keeps level to build;
Two, water ballonet under employing super large, superhigh pressure;
Three, carrying elongated segment is carried out to berth structure: according to water calculation sheet water level and requirement for bearing capacity under platform, prolongation building berth carrying segment length, and extra large operation is swept to Xia Shui waters, remove sharp-pointed hard foreign material, avoid hurting hull during lower water;
Four, construction pier is arranged;
Five, adopt shoe shutoff frock to implement shutoff to shoe: shoe shutoff frock adopts steel-wood structure design, adopt wire sling and platform to be reliably connected and fixed, main body and shoe shutoff frock adopt transition processing; Open wire sling after lower water, shoe shutoff frock can depart from hull, uses after reclaiming in order to follow-up secondary;
Six, platform closes up the process of falling pier of rear secondary: close up rear platform and carry out the process of secondary falling pier process, replace original construction pier, reach the platform after closing up and building berth keeping parallelism, required sliding force requirement when meeting water under platform;
Seven, fixed platform is drawn: secondary falls after pier completes, and carries out traction fixing, to prevent the uncontrollable downward slippage of airbag aeration rear platform with winch and trailer coupling to platform;
Eight, the layout of air bag under platform main body: according to the size of air bag and the feature of platform structure, carry out orderly layout to air bag, meets the requirement of platform structure to air bag bearing capacity; Air bag is inflated air bag, until reach lower water calculation sheet requirement pressure, is made platform main body be lifted away from construction pier completely after arranging;
Nine, platform construction pier is removed: air bag has been suppressed, and platform main body is removed all platform construction piers, and removed the hard implements of building berth upper gasbag rolling place after departing from construction pier, keeps building berth to clean smooth;
Ten, the secondary rear platform of falling pier is to the translation of waterside: secondary falls after pier, need to carry out to waterside translation to platform, operation adopts winch traction control retracting platform, step is divided into: pre-arranged air bag, platform translation certain distance, braking platform, supplementary airbag aeration pressurize, circulation comes and goes above-mentioned steps, until water is required to waterside translation distance under reaching platform;
11, water under threading off: dead work terminates, required water level is opened buckle release, is applied starting force by mechanism after meeting, and overcome platform movement friction dead point, before and after coordinating, the inflation/deflation of air bag operates, and implementation platform is flexible lower water steadily;
12, air bag and shoe shutoff frock reclaim: platform regains time water ballonet after descend water smoothly, removes and regains shoe shutoff frock, and avoiding affects spud leg standing at the bottom after water under platform, and so far platform air bag launching work all terminates.
The invention has the beneficial effects as follows: the present invention is owing to have employed the mode of the air bag launching of steady high efficiency, low cost, thus have steadily controlled, in the water cycle under shortening platform, greatly lower the laid down cost of platform and build the advantage of difficulty, effectively reducing the door that construct platform requires shipyard.
Detailed description of the invention:
A kind of self-lifting type marine drilling platform air bag launching process, the method step is as follows:
One, platform level on building berth is built: low different construction pier after high before arranging, platform keeps level to build;
Two, water ballonet under employing super large, superhigh pressure;
Three, carrying elongated segment is carried out to berth structure: according to water calculation sheet water level and requirement for bearing capacity under platform, prolongation building berth carrying segment length, and extra large operation is swept to Xia Shui waters, remove sharp-pointed hard foreign material, avoid hurting hull during lower water;
Four, construction pier is arranged;
Five, adopt shoe shutoff frock to implement shutoff to shoe: shoe shutoff frock adopts steel-wood structure design, adopt wire sling and platform to be reliably connected and fixed, main body and shoe shutoff frock adopt transition processing; Open wire sling after lower water, shoe shutoff frock can depart from hull, uses after reclaiming in order to follow-up secondary;
Six, platform closes up the process of falling pier of rear secondary: close up rear platform and carry out the process of secondary falling pier process, replace original construction pier, reach the platform after closing up and building berth keeping parallelism, required sliding force requirement when meeting water under platform;
Seven, fixed platform is drawn: secondary falls after pier completes, and carries out traction fixing, to prevent the uncontrollable downward slippage of airbag aeration rear platform with winch and trailer coupling to platform;
Eight, the layout of air bag under platform main body: according to the size of air bag and the feature of platform structure, carry out orderly layout to air bag, meets the requirement of platform structure to air bag bearing capacity; Air bag is inflated air bag, until reach lower water calculation sheet requirement pressure, is made platform main body be lifted away from construction pier completely after arranging;
Nine, platform construction pier is removed: air bag has been suppressed, and platform main body is removed all platform construction piers, and removed the hard implements of building berth upper gasbag rolling place after departing from construction pier, keeps building berth to clean smooth;
Ten, the secondary rear platform of falling pier is to the translation of waterside: secondary falls after pier, need to carry out to waterside translation to platform, operation adopts winch traction control retracting platform, step is divided into: pre-arranged air bag, platform translation certain distance, braking platform, supplementary airbag aeration pressurize, circulation comes and goes above-mentioned steps, until water is required to waterside translation distance under reaching platform;
11, water under threading off: dead work terminates, required water level is opened buckle release, is applied starting force by mechanism after meeting, and overcome platform movement friction dead point, before and after coordinating, the inflation/deflation of air bag operates, and implementation platform is flexible lower water steadily;
12, air bag and shoe shutoff frock reclaim: platform regains time water ballonet after descend water smoothly, removes and regains shoe shutoff frock, and avoiding affects spud leg standing at the bottom after water under platform, and so far platform air bag launching work all terminates.
Be understandable that, above about specific descriptions of the present invention, the technical scheme described by the embodiment of the present invention is only not limited to for illustration of the present invention, those of ordinary skill in the art is to be understood that, still can modify to the present invention or equivalent replacement, to reach identical technique effect; Needs are used, all within protection scope of the present invention as long as meet.

Claims (1)

1. a self-lifting type marine drilling platform air bag launching process, is characterized in that: the method step is as follows:
One, platform level on building berth is built: low different construction pier after high before arranging, platform keeps level to build;
Two, water ballonet under employing super large, superhigh pressure;
Three, carrying elongated segment is carried out to berth structure: according to water calculation sheet water level and requirement for bearing capacity under platform, prolongation building berth carrying segment length, and extra large operation is swept to Xia Shui waters, remove sharp-pointed hard foreign material, avoid hurting hull during lower water;
Four, construction pier is arranged;
Five, adopt shoe shutoff frock to implement shutoff to shoe: shoe shutoff frock adopts steel-wood structure design, adopt wire sling and platform to be reliably connected and fixed, main body and shoe shutoff frock adopt transition processing; Open wire sling after lower water, shoe shutoff frock can depart from hull, uses after reclaiming in order to follow-up secondary;
Six, platform closes up the process of falling pier of rear secondary: close up rear platform and carry out the process of secondary falling pier process, replace original construction pier, reach the platform after closing up and building berth keeping parallelism, required sliding force requirement when meeting water under platform;
Seven, fixed platform is drawn: secondary falls after pier completes, and carries out traction fixing, to prevent the uncontrollable downward slippage of airbag aeration rear platform with winch and trailer coupling to platform;
Eight, the layout of air bag under platform main body: according to the size of air bag and the feature of platform structure, carry out orderly layout to air bag, meets the requirement of platform structure to air bag bearing capacity; Air bag is inflated air bag, until reach lower water calculation sheet requirement pressure, is made platform main body be lifted away from construction pier completely after arranging;
Nine, platform construction pier is removed: air bag has been suppressed, and platform main body is removed all platform construction piers, and removed the hard implements of building berth upper gasbag rolling place after departing from construction pier, keeps building berth to clean smooth;
Ten, the secondary rear platform of falling pier is to the translation of waterside: secondary falls after pier, need to carry out to waterside translation to platform, operation adopts winch traction control retracting platform, step is divided into: pre-arranged air bag, platform translation certain distance, braking platform, supplementary airbag aeration pressurize, circulation comes and goes above-mentioned steps, until water is required to waterside translation distance under reaching platform;
11, water under threading off: dead work terminates, required water level is opened buckle release, is applied starting force by mechanism after meeting, and overcome platform movement friction dead point, before and after coordinating, the inflation/deflation of air bag operates, and implementation platform is flexible lower water steadily;
12, air bag and shoe shutoff frock reclaim: platform regains time water ballonet after descend water smoothly, removes and regains shoe shutoff frock, and avoiding affects spud leg standing at the bottom after water under platform, and so far platform air bag launching work all terminates.
CN201210347402.XA 2012-09-18 2012-09-18 Launching process of jack-up offshore drilling platform by airbag Expired - Fee Related CN102849180B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210347402.XA CN102849180B (en) 2012-09-18 2012-09-18 Launching process of jack-up offshore drilling platform by airbag

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210347402.XA CN102849180B (en) 2012-09-18 2012-09-18 Launching process of jack-up offshore drilling platform by airbag

Publications (2)

Publication Number Publication Date
CN102849180A CN102849180A (en) 2013-01-02
CN102849180B true CN102849180B (en) 2014-12-31

Family

ID=47396258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210347402.XA Expired - Fee Related CN102849180B (en) 2012-09-18 2012-09-18 Launching process of jack-up offshore drilling platform by airbag

Country Status (1)

Country Link
CN (1) CN102849180B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105586863A (en) * 2014-11-11 2016-05-18 江苏海王星海洋油气装备有限公司 Bottom hull type mobile platform and launching technology of bottom hull type mobile platform
CN104859788B (en) * 2015-05-08 2018-05-04 中国海洋石油集团有限公司 A kind of quick method of construction of octagonal FDPSO
CN105253270B (en) * 2015-10-30 2017-07-28 青岛海西重机有限责任公司 One kind combination floating box type maritime platform launching gear and maritime platform launching method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102424101A (en) * 2011-11-19 2012-04-25 南通贝斯特船舶与海洋工程设计有限公司 Technology for launching ship with airbags
CN202337334U (en) * 2012-03-27 2012-07-18 广新海事重工股份有限公司 Self-floating launching poppet platform

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01197196A (en) * 1988-02-02 1989-08-08 Mitsubishi Heavy Ind Ltd Launching way recovery method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102424101A (en) * 2011-11-19 2012-04-25 南通贝斯特船舶与海洋工程设计有限公司 Technology for launching ship with airbags
CN202337334U (en) * 2012-03-27 2012-07-18 广新海事重工股份有限公司 Self-floating launching poppet platform

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
JP平1-197196A 1989.08.08 *
气囊首次用于大型钻井平台下水获成功;张远平;《中国船舶报》;20111125;第006版 *
船舶与海洋平台平地建造及气囊下水研究;聂晓玲;《哈尔滨工程大学工程硕士学位论文》;20090630;全文 *
船舶气囊下水技术大步走向世界;孙菊香等;《中国修船》;20120630;第25卷(第3期);36-38 *
船舶气囊下水技术现状与展望;孙菊香;《军民两用技术与产品》;20101231(第8期);45-48 *

Also Published As

Publication number Publication date
CN102849180A (en) 2013-01-02

Similar Documents

Publication Publication Date Title
CN101492140B (en) Aluminum alloy catamaran whole-boat afloat process
CN101920771B (en) Method for undock ballasting in ship building
US20110129334A1 (en) Wind turbine holding and lifting system and movable operating platform above water
CN104229099B (en) A kind of ocean engineering ship carries the system and method for lower water
WO2017054575A1 (en) Submersible floating-moving transport platform having floating dock and tower and operation method thereof
CN101980917A (en) Liquid storing and offloading device and drilling and production installations on the sea based thereon
JP2011112045A (en) Wind turbine fixing and lifting apparatus and movable operating platform on water
CN102849180B (en) Launching process of jack-up offshore drilling platform by airbag
CN103452086A (en) Mat-assisted driving movable platform
CN104210627B (en) Build the device and method of lower water for jack-up unit level land
WO2021147684A1 (en) Rapidly arranged floating breakwater
CN105480380B (en) Tension leg platform (TLP) upper module and the closure workmanship of lower float structure
KR20200015935A (en) Decimal method
CN102582786A (en) Building process for deep sea spar platform
CN107856819A (en) Floating shipyard and floating type warship maintenance and method of construction
CN204023540U (en) A kind of drilling platform
WO2010109243A2 (en) Apparatus and method for handling a submersible item
CN109823484A (en) A kind of floating box structure inhibiting platform heaving
CN104554639A (en) Installation equipment for large offshore wind power equipment
CN204642060U (en) A kind of large-scale coastal waters wind power equipment installs equipment
CN203902800U (en) Semi-submersible type lifting platform for large floating offshore structure
CN102235156A (en) Stand pipe limiting device
CN204822024U (en) Device of turning on one's side is prevented to belt tightening pulley
WO2023040062A1 (en) Frame type floating island having air bag, semi-submerged ship, and semi-submerged ship control method
CN207670621U (en) A kind of offshore platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141231

Termination date: 20170918