CN102424101A - Technology for launching ship with airbags - Google Patents

Technology for launching ship with airbags Download PDF

Info

Publication number
CN102424101A
CN102424101A CN2011103683923A CN201110368392A CN102424101A CN 102424101 A CN102424101 A CN 102424101A CN 2011103683923 A CN2011103683923 A CN 2011103683923A CN 201110368392 A CN201110368392 A CN 201110368392A CN 102424101 A CN102424101 A CN 102424101A
Authority
CN
China
Prior art keywords
air bag
ship
pier
pressure
air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103683923A
Other languages
Chinese (zh)
Other versions
CN102424101B (en
Inventor
郭连镇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Northeast Institute of oceanographic engineering Co., Ltd.
Original Assignee
NANJING BEST SHIPPING AND MARINE ENGINEERING DESIGN Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING BEST SHIPPING AND MARINE ENGINEERING DESIGN Co Ltd filed Critical NANJING BEST SHIPPING AND MARINE ENGINEERING DESIGN Co Ltd
Priority to CN201110368392.3A priority Critical patent/CN102424101B/en
Publication of CN102424101A publication Critical patent/CN102424101A/en
Application granted granted Critical
Publication of CN102424101B publication Critical patent/CN102424101B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)
  • Barrages (AREA)

Abstract

The invention discloses a technology for launching a ship with airbags. The technology comprises the following processes: 1, arranging the airbags; 2, inflating and inspecting the airbags: arranging pressure meters, inspecting a compressed air source, and inflating the airbags according to a sequence that airbags are sequentially, eudipleurally and synchronously inflated from the stern to the stem until the airbags are full of air; and 3, carrying out real-time monitoring on the air pressure in each airbag. The technology of the invention has the advantages of launching flow standardization and launching quality guarantee.

Description

Boats and ships utilize the technology of air bag launching
Technical field
The present invention relates to the technology that a kind of boats and ships utilize air bag launching.
Background technology
At present, launching is an important node in the ship building process, and the sign building berth carries and the hull main structure is accomplished, and fitting-out installations of project such as machine, pipe, electricity are accomplished, and possess the debugging condition basically.Under tradition in the water conservancy project skill, air bag launching can only be used for realizing water under the spitkit as the replenishing of water under dock, the arine railway.And down the water process receives the influence of uncontrollable factor bigger, through regular meeting occur down that halfway stops in the water process, balloon rupture, with the collision of building berth bulkhead wall or down behind the water stroke cross problems such as far away.
Summary of the invention
To the problems referred to above, the boats and ships that the invention provides quality under current journey under a kind of standard, the assurance utilize the technology of air bag launching.
In order to achieve the above object, the present invention has taked following technical scheme: a kind of boats and ships utilize the technology of air bag launching, may further comprise the steps:
A, lay air bag:
(1), lay air bag before, to using the air bag inspection that puts on the air one by one, stop or insecure air bag such as damage gets into on-the-spotly with Louing, it is regional that newly the preferential cloth of air bag is placed on the stem stern;
(2), according to the ship type with up-to-standard air bag divide port and starboard each half the lay to bow stern both direction by the ship midship;
(3), lay air bag before, also need confirm to lay the position of air bag and do sign, lay by sign;
(4), adopt gantry crane, tower crane or wheel crane to cooperate handling when laying air bag, air bag crosses hull bottom midship line and adopts 1.5 tons of small winch tractions, air bag is placed and will be guaranteed straight and vertically vertical with ship, inflation inlet will be convenient to manual operation and manometric checking;
The inflation of B, air bag and inspection:
(1), install cut-and-dried compression indicator one by one before the airbag aeration, manometric pressure is 0-0.25MPa;
(2), the inspection compressed air gas source, the valve of opening on the gas bag collector is checked bleed pressure and moisture situation through venting, puts residual normal until gaseous state if there is water then to open sufficient valve;
(3), through preprepared have joint 1/2 " sebific duct is connected the air source of the gas with want air bag, put on the air;
(4), airbag aeration order: carry out synchronously being full of gas entirely to stem left-right symmetric successively until air bag from the ship stern;
(5), air bag inflation pressure:
(a), stop inflation when for the first time pressure rises to 0.05MPa, whether the inspection air bag collides with each pier position, air bag and hull bottom be squareness longitudinally, adjusts immediately as if pinpointing the problems;
(b), for the second time pressure rises to 0.1MPa and stops inflation, inspection air bag pressurized situation changes with the ship attitude, reports the processing of on scene commander ground immediately if note abnormalities;
(c), pressure begins inflation from first air bag that contacts with boat body plane of stern for the third time, progressively increases air pressure to the bow air bag;
(d), first air bag that contacts with hull to midships section of stern is center line of boat gasbag pressure rises to 0.15-0.18MPa;
(e), midships section is that the gasbag pressure of center line of boat to 1 cargo hold antetheca rises to 0.15MPa;
When (f), the gasbag pressure of bow to bow rises to 0.13MPa; Whether boarding ship lifts; If ship is not lifted; The pressure of regulating air bag has only when ship integral body is lifted until ship is lifted, and will spend the pier complete removal rapidly; After treating that the flower pier has all been torn open; Observe whole ship attitude,, treat formally to descend water to remove in preceding 2 hours to ensure safety if apart from the long colored pier that then stays the 30m distance of Time Of Launching; When will treating after airbag aeration is accomplished ship to be lifted, the dismounting of flower pier can carry out; The flower pier is removed and is all taked manually-operated; The method of the dilatory traction of manila rope in adopting when tearing colored pier open; From the coherent building berth Po Qiang both sides that are put into of timber wedge that the flower pier is removed; The receipts pier is made in order, and it is all clean with the cleaning of pier bit plane smoothly whenever to tear a colored pier open, and the slag thing transports out of building berth; Necessarily polish flat if find overlap crator or acute angle ironware, prevent to injure air bag;
(g), launching moves: boats and ships are controlled by winch, and when the bow gasbag pressure rose to 0.18-0.20MPa, air bag rolled and makes the accommodation move 5-10m, when winch walk back, ship begin to move on the ship workmen cut cable and make ship be free to slide entry.
The present invention and similar compared with techniques have following advantage:
Standard of the present invention and clear and definite boats and ships utilize the flow process of air bag launching operation, have successfully guaranteed water under the smooth safety from pusher tug to nearly 30 boats and ships of 76500DWT bulge carrier.And can be implemented in the highest and round-the-clock water down of lowest water level in the Changjiang river, need not wait for the tide phase.With water ratio under dock and the building berth, saved a large amount of capital construction expenses, promoted the competitive power that shipyard is managed.
The specific embodiment:
In order to deepen to understanding of the present invention, will combine embodiment that the present invention is made further detailed description below, this embodiment only is used to explain the present invention, does not constitute the qualification to protection domain of the present invention.
A kind of boats and ships utilize the technology of air bag launching, may further comprise the steps:
A, lay air bag:
(1), lay air bag before, building berth should clean out, building berth does not have sharp object; Before laying air bag, to using the air bag inspection that puts on the air one by one, stop or insecure air bag such as damage gets into on-the-spotly, it is regional that newly the preferential cloth of air bag is placed on the stem stern with Louing;
(2), according to the ship type with up-to-standard air bag divide port and starboard each half the lay to bow stern both direction by the ship midship;
(3), lay air bag before, also need confirm to lay the position of air bag and do sign, lay by sign;
Adopt gantry crane, tower crane or wheel crane to cooperate handling when (4), laying air bag; Air bag crosses hull bottom midship line and adopts 1.5 tons of small winch tractions; The air bag placement will guarantee straight and be vertically vertical with ship; Inflation inlet will be convenient to manual operation and manometric checking, until pressing all air bags of scheme cloth foot;
Before the airbag aeration, prepare traction system, with the steel wire penetrating chain pipe, hang on the bollard (112t) on stem deck, this steel rope is connected on the movable pulley through the 80t shackle, about each one; Steel rope is connected fixed pulley and earth anchor, with steel rope through unloading buckle winch and earth anchor, about each one; Pull out winch cable, on assembly pulley (movable pulley and fixed pulley) at least around more than 3 groups, about each one group of winch; The traction of stem traction system puts in place before the airbag aeration, and makes winch stressed, confirms that the preparation of stem traction system puts in place, can begin airbag aeration.
The inflation of B, air bag and inspection:
(1), install cut-and-dried compression indicator one by one before the airbag aeration, manometric pressure is 0-0.25MPa;
(2), the inspection compressed air gas source, the valve of opening on the gas bag collector is checked bleed pressure and moisture situation through venting, puts residual normal until gaseous state if there is water then to open sufficient valve;
(3), through preprepared have joint 1/2 " sebific duct is connected the air source of the gas with want air bag, put on the air;
(4), airbag aeration order: carry out synchronously being full of gas entirely to stem left-right symmetric successively until air bag from the ship stern;
(5), air bag inflation pressure:
(a), stop inflation when for the first time pressure rises to 0.05MPa, whether the inspection air bag collides with each pier position, air bag and hull bottom be squareness longitudinally, adjusts immediately as if pinpointing the problems;
(b), for the second time pressure rises to 0.1MPa and stops inflation, inspection air bag pressurized situation changes with the ship attitude, reports the processing of on scene commander ground immediately if note abnormalities;
(c), pressure begins inflation from first air bag that contacts with boat body plane of stern for the third time, progressively increases air pressure to the bow air bag;
(d), first air bag that contacts with hull to midships section of stern is center line of boat gasbag pressure rises to 0.15-0.18MPa;
(e), midships section is that the gasbag pressure of center line of boat to 1 cargo hold antetheca rises to 0.15MPa;
When (f), the gasbag pressure of bow to bow rises to 0.13MPa; Whether boarding ship lifts; If ship is not lifted; The pressure of regulating air bag has only when ship integral body is lifted until ship is lifted, and will spend the pier complete removal rapidly; After treating that the flower pier has all been torn open; Observe whole ship attitude,, treat formally to descend water to remove in preceding 2 hours to ensure safety if apart from the long colored pier that then stays the 30m distance of Time Of Launching; When will treating after airbag aeration is accomplished ship to be lifted, the dismounting of flower pier can carry out; The flower pier is removed and is all taked manually-operated; The method of the dilatory traction of manila rope in adopting when tearing colored pier open; From the coherent building berth Po Qiang both sides that are put into of timber wedge that the flower pier is removed; The receipts pier is made in order, and it is all clean with the cleaning of pier bit plane smoothly whenever to tear a colored pier open, and the slag thing transports out of building berth; Necessarily polish flat if find overlap crator or acute angle ironware, prevent to injure air bag;
(g), launching moves: boats and ships are controlled by winch, and when the bow gasbag pressure rose to 0.18-0.20MPa, air bag rolled and makes the accommodation move 5-10m, when winch walk back, ship begin to move on the ship workmen cut cable and make ship be free to slide entry.
When walking to gate after launching a ship, the gate bottom is smooth with the groove place mat with the steel boxboard with the groove of the identical big small size in gate bottom together because of the waterproof measure construction need have, and this plate is claimed rebound; No. 1 building berth has three rebounds; Every rebound is 10000x1560x400mm, and rebound should place at the sluice gate place in advance, and gate is completed it after hanging and moving immediately; To place appropriately after gate hangs and moves, must not influence to put and launch a ship.
When the ship by a winch control, airbags rolling the boat displacement of 5-10m (depending on water level in the case may be) on board cutting cables, make the boat slide freely into the water when the ship freely into the water by inertia in the water drift, to be used to impact the peak high point boat anchored boat to stop, the ship anchored boat until the boat is stable with a tugboat into the prepared mooring dock with mooring cable personnel with the completion of the task, the ship into the water, immediately after the river rolled airbag recovery: the airbag in the water level by a work boat slipway by manual push push to roll ashore, airbag berth gates are moved within and orderly deflated recycling storage, according to the provisions store, hanging out the transition board, lifting gates to restore the original state.
The ship type that the present invention is fit to is the bulge carrier below 100,000 tons by the propelling of diesel-engined drive screw propeller of single deck, tail type, single-blade, single rudder, band weather tightness hatch cover.Has the first line style of ball nose; Be provided with forecastle, afterbody; Full ship is provided with 5 cargo holds, and cargo area is the single shell structure of double bottom and band bottom side tank, top side tank, Bunker Fuel Oil.Full ship is established 9 road watertight transcerse bulkheads altogether, lays respectively at the rib position 8,11,35,71,109,145,183, No. 217.Set gradually aft peak, cabin, 5 cargo holds, fresh water tank (left and right), the first Peak Tanks ballast tank of holding concurrently.
Standard of the present invention and clear and definite boats and ships utilize the flow process of air bag launching operation, have successfully guaranteed water under the smooth safety from pusher tug to nearly 30 boats and ships of 76500DWT bulge carrier.And can be implemented in the highest and round-the-clock water down of lowest water level in the Changjiang river, need not wait for the tide phase.With water ratio under dock and the building berth, saved a large amount of capital construction expenses, promoted the competitive power that shipyard is managed.

Claims (2)

1. boats and ships utilize the technology of air bag launching, it is characterized in that: may further comprise the steps:
A, lay air bag:
(1), lay air bag before, to using the air bag inspection that puts on the air one by one, stop or insecure air bag such as damage gets into on-the-spotly with Louing, it is regional that newly the preferential cloth of air bag is placed on the stem stern;
(2), according to the ship type with up-to-standard air bag divide port and starboard each half the lay to bow stern both direction by the ship midship;
(3), lay air bag before, also need confirm to lay the position of air bag and do sign, lay by sign;
(4), adopt gantry crane, tower crane or wheel crane to cooperate handling when laying air bag, air bag crosses hull bottom midship line and adopts 1.5 tons of small winch tractions, air bag is placed and will be guaranteed straight and vertically vertical with ship, inflation inlet will be convenient to manual operation and manometric checking;
The inflation of B, air bag and inspection:
(1), install cut-and-dried compression indicator one by one before the airbag aeration, manometric pressure is 0-0.25MPa;
(2), the inspection compressed air gas source, the valve of opening on the gas bag collector is checked bleed pressure and moisture situation through venting, puts residual normal until gaseous state if there is water then to open sufficient valve;
(3), through preprepared have joint 1/2 " sebific duct is connected the air source of the gas with want air bag, put on the air;
(4), airbag aeration order: carry out synchronously being full of gas entirely to stem left-right symmetric successively until air bag from the ship stern;
(5), air bag inflation pressure:
(a), stop inflation when for the first time pressure rises to 0.05MPa, whether the inspection air bag collides with each pier position, air bag and hull bottom be squareness longitudinally, adjusts immediately as if pinpointing the problems;
(b), for the second time pressure rises to 0.1MPa and stops inflation, inspection air bag pressurized situation changes with the ship attitude, reports the processing of on scene commander ground immediately if note abnormalities;
(c), pressure begins inflation from first air bag that contacts with boat body plane of stern for the third time, progressively increases air pressure to the bow air bag;
(d), first air bag that contacts with hull to midships section of stern is center line of boat gasbag pressure rises to 0.15-0.18MPa;
(e), midships section is that the gasbag pressure of center line of boat to 1 cargo hold antetheca rises to 0.15MPa;
When (f), the gasbag pressure of bow to bow rises to 0.13MPa; Whether boarding ship lifts; If ship is not lifted; The pressure of regulating air bag has only when ship integral body is lifted until ship is lifted, and will spend the pier complete removal rapidly; After treating that the flower pier has all been torn open; Observe whole ship attitude,, treat formally to descend water to remove in preceding 2 hours to ensure safety if apart from the long colored pier that then stays the 30m distance of Time Of Launching;
(g), launching moves: boats and ships are controlled by winch, and when the bow gasbag pressure rose to 0.18-0.20MPa, air bag rolled and makes the accommodation move 5-10m, when winch walk back, ship begin to move on the ship workmen cut cable and make ship be free to slide entry.
2. utilize the technology of air bag launching according to the said boats and ships of claim 1; It is characterized in that: can carry out when the dismounting of flower pier will be treated after airbag aeration is accomplished ship to be lifted, the flower pier is removed and is all taked manual operation, the method for the dilatory traction of Manila rope in adopting when tearing colored pier open; From the coherent building berth Po Qiang both sides that are put into of timber wedge that the flower pier is removed; The receipts pier is made in order, and it is all clean with the cleaning of pier bit plane smoothly whenever to tear a colored pier open, and the slag thing transports out of building berth; Necessarily polish flat if find overlap crator or acute angle ironware, prevent to injure air bag.
CN201110368392.3A 2011-11-19 2011-11-19 Technology for launching ship with airbags Active CN102424101B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110368392.3A CN102424101B (en) 2011-11-19 2011-11-19 Technology for launching ship with airbags

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110368392.3A CN102424101B (en) 2011-11-19 2011-11-19 Technology for launching ship with airbags

Publications (2)

Publication Number Publication Date
CN102424101A true CN102424101A (en) 2012-04-25
CN102424101B CN102424101B (en) 2014-07-16

Family

ID=45958165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110368392.3A Active CN102424101B (en) 2011-11-19 2011-11-19 Technology for launching ship with airbags

Country Status (1)

Country Link
CN (1) CN102424101B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102849180A (en) * 2012-09-18 2013-01-02 渤海装备辽河重工有限公司 Launching process of jack-up offshore drilling platform by airbag
CN103274017A (en) * 2013-03-01 2013-09-04 柳州市欧博科技有限公司 Device and method for detecting ship attitude in launching process of ship air bag
CN103803036A (en) * 2012-11-14 2014-05-21 中国石油化工股份有限公司 Technology for launching large shipping vessel through air bag
CN111268045A (en) * 2020-02-27 2020-06-12 广船国际有限公司 Method for adjusting ship undocking floating state
CN114802641A (en) * 2022-03-28 2022-07-29 宜昌一凡船舶设计有限公司 Method for building ship on flat ground

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01197196A (en) * 1988-02-02 1989-08-08 Mitsubishi Heavy Ind Ltd Launching way recovery method
CN101537875A (en) * 2008-05-05 2009-09-23 中交一航局第二工程有限公司 Process for shipping and launching wharfboat by floating same on vertical quay wall with assistance of airbag
KR100940795B1 (en) * 2008-10-28 2010-02-04 곽대진 Method for launching and transporting heavy weight structures using air bags
CN101857076A (en) * 2010-04-27 2010-10-13 通州海通船舶修造有限公司 Method for launching inland-river chemical carrier through airbag

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01197196A (en) * 1988-02-02 1989-08-08 Mitsubishi Heavy Ind Ltd Launching way recovery method
CN101537875A (en) * 2008-05-05 2009-09-23 中交一航局第二工程有限公司 Process for shipping and launching wharfboat by floating same on vertical quay wall with assistance of airbag
KR100940795B1 (en) * 2008-10-28 2010-02-04 곽대진 Method for launching and transporting heavy weight structures using air bags
CN101857076A (en) * 2010-04-27 2010-10-13 通州海通船舶修造有限公司 Method for launching inland-river chemical carrier through airbag

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中华人民共和国工业和信息化部: "CB/T 3837-2011 船舶用气囊上排、下水工艺要求", 《中华人民共和国船舶行业标准》 *
孙菊香: "船舶气囊下水技术现状与展望", 《军民两用技术与产品》 *
戴凤波等: "浅谈气囊下水造船技术的研究与应用", 《第十届全国内河船舶与航运技术学术会议论文集》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102849180A (en) * 2012-09-18 2013-01-02 渤海装备辽河重工有限公司 Launching process of jack-up offshore drilling platform by airbag
CN102849180B (en) * 2012-09-18 2014-12-31 渤海装备辽河重工有限公司 Launching process of jack-up offshore drilling platform by airbag
CN103803036A (en) * 2012-11-14 2014-05-21 中国石油化工股份有限公司 Technology for launching large shipping vessel through air bag
CN103803036B (en) * 2012-11-14 2016-06-01 中国石油化工股份有限公司 Large ship utilizes the technique of water under air bag
CN103274017A (en) * 2013-03-01 2013-09-04 柳州市欧博科技有限公司 Device and method for detecting ship attitude in launching process of ship air bag
CN111268045A (en) * 2020-02-27 2020-06-12 广船国际有限公司 Method for adjusting ship undocking floating state
CN114802641A (en) * 2022-03-28 2022-07-29 宜昌一凡船舶设计有限公司 Method for building ship on flat ground
CN114802641B (en) * 2022-03-28 2023-05-02 宜昌一凡船舶设计有限公司 Ship land leveling construction method

Also Published As

Publication number Publication date
CN102424101B (en) 2014-07-16

Similar Documents

Publication Publication Date Title
CN103112553B (en) The latent maintenance and repair ship of self-propulsion type half and using method
US3448712A (en) Buoyant floats for docking and towing seacraft
CN106167078B (en) A kind of ship and drilling platforms floating aid system and construction method
CN105026254B (en) Loaded on the berthing structure on ship
CN107719580B (en) Horizontal building berth method on 10 10,000 tons ships of one kind
CN102424101B (en) Technology for launching ship with airbags
US2908240A (en) Seaplane beaching apparatus
CN101537875B (en) Process for shipping and launching wharfboat by floating same on vertical quay wall with assistance of airbag
CN104002932B (en) Marine fault boats and ships are carried out the ship type of rapid uplift maintenance
CN104229099B (en) A kind of ocean engineering ship carries the system and method for lower water
US3648635A (en) Marine transport
CN204078021U (en) Marine fault boats and ships are carried out to the new herbicide of rapid uplift maintenance
CN103738477A (en) Method for replacing upper anchor cable of mooring anchor legs
CN103803036B (en) Large ship utilizes the technique of water under air bag
CN111017131A (en) Marine ball leaning system
CN106314707A (en) Gasbag type anti-sinking overturn-preventing device
CN104097750A (en) Multifunctional maintenance ship
CN106628041B (en) The anti-sinking of ship, pontoon, operation at sea platform, rollover, back-off system
CN204802046U (en) Anti sinking prevents toppling gasbag device
CN205916302U (en) Boats and ships and drilling platform help superficial system
CN102963509A (en) Traction method for enabling parallel built ships of 300,000 dry docks to undock
CN210712334U (en) Inflatable floating rope
WO2022019801A1 (en) Method for transporting a large iceberg
JP2017114268A (en) Floating facility construction method and floating structure for floating facility
JP2017114264A (en) Floating facility construction method and floating structure for floating facility

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 226000 No. 266 Century Avenue, Nantong High-tech Zone, Jiangsu Province

Patentee after: Nantong Northeast Institute of oceanographic engineering Co., Ltd.

Address before: 226000 Yongxing Road, Gangzha District, Nantong, Jiangsu Province, No. 14

Patentee before: Nanjing Best Shipping and Marine Engineering Design Co., Ltd.