CN102721414A - Embedded part on settlement observation point and application method thereof - Google Patents

Embedded part on settlement observation point and application method thereof Download PDF

Info

Publication number
CN102721414A
CN102721414A CN2012102157272A CN201210215727A CN102721414A CN 102721414 A CN102721414 A CN 102721414A CN 2012102157272 A CN2012102157272 A CN 2012102157272A CN 201210215727 A CN201210215727 A CN 201210215727A CN 102721414 A CN102721414 A CN 102721414A
Authority
CN
China
Prior art keywords
settlement
buried sleeve
bolt
observation point
point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102157272A
Other languages
Chinese (zh)
Inventor
毕磊
高善友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN2012102157272A priority Critical patent/CN102721414A/en
Publication of CN102721414A publication Critical patent/CN102721414A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Force Measurement Appropriate To Specific Purposes (AREA)

Abstract

The invention provides an embedded part on a settlement observation point and an application method thereof. The embedded part on the settlement observation point consists of an embedded bushing, a bolt and a screwed plug. Before concrete is poured on a building wall or a building column on a position where a settlement observation point is arranged, the embedded bushing is embedded on the position of a corresponding settlement observation point, then concrete is poured, and a sheath of the embedded bushing is guaranteed to be leveled to the skin of the building wall and the building column; when the observation of the settlement point is not carried out, the screwed plug is screwed into the embedded bushing; and when the observation of the settlement point is needed, the screwed plug is unscrewed, the bolt is screwed into the embedded bushing, and then the settlement point is observed. Compared with the prior art, the sheath of the embedded bushing is guaranteed to be leveled to the skin of the building wall and the building column, so that the safety of the settlement observation point during the non-observation period is guaranteed, the overlong exposed length of the embedded bushing is prevented from influencing the walking of personnel, manmade destruction factors can be reduced, and the settlement observation point is more beautiful.

Description

Settlement observation point built-in fitting and method of application thereof
1, technical field
The present invention relates to building field, specifically a kind of settlement observation point built-in fitting and method of application thereof.
2, background technology
In order accurately to reflect the accurate sedimentation situation of buildings; Equally distributed settlement observation point need be set in the member of buildings; Because mostly existing settlement observation point apparatus is exposed; Influence very much personnel's walking, also influenced the attractive in appearance of buildings greatly, and received artificial destruction easily in construction period.
3, summary of the invention
The objective of the invention is to overcome the deficiency that exists in the prior art, a kind of settlement observation point built-in fitting and method of application thereof are provided.
Technical scheme of the present invention realizes that by following mode the settlement observation point built-in fitting is made up of pre-buried sleeve, bolt and plug, and pre-buried sleeve inner is set to hollow cylinder, and inwall is provided with mantle fiber; The end of bolt and plug is provided with the mantle fiber that adapts with pre-buried sleeve, and bolt and plug are screwed in the pre-buried sleeve through mantle fiber;
The method of application of settlement observation point built-in fitting is following:
(1), before needs are provided with the building wall, post deposit concrete at settlement observation point place, carry out concreting then to corresponding settlement observation point position with pre-buried sleeve is pre-buried, guarantee that the same building wall of pre-buried sleeve crust, post crust are concordant;
(2), when not carrying out settlement point observation, plug is screwed in the pre-buried sleeve;
(3), need carry out settlement point observation time, back out plug, bolt is screwed in the pre-buried sleeve, carry out settlement point observation.
The outer wall of above-mentioned pre-buried sleeve is provided with 2-5 road groove, to increase the anchor force of pre-buried sleeve and building wall, post.
The end end that above-mentioned bolt is provided with mantle fiber is the taper setting.
The arranged outside of above-mentioned bolt has air discharge duct.
Advantage of the present invention is:
The present invention compares with prior art, pre-buried sleeve protruded length is improved, and increased between non-observation and in pre-buried sleeve, screw in plug; Before the building wall at settlement observation point place, post deposit concrete, pre-buried sleeve is pre-buried, guarantee that the same building wall of sleeve crust, post crust are concordant; Guarantee the safety of settlement observation point position between non-observation; The long personnel's of the influence walking of the pre-buried sleeve of having avoided tradition to expose has reduced the artificial destruction factor, and has made settlement observation point more attractive in appearance; Follow-up Decorating Project had no influence; Between non-observation, adopt the form be screwed into plug, guaranteed between long-term non-observation in the getting rusty, pollute, problems such as rubbish filling of pre-buried sleeve.Avoid the loosening observation station that makes of pre-buried sleeve to damage, at sleeve outer wall groove is set, to increase the anchor force of pre-buried sleeve and xoncrete structure, make that pre-buried sleeve is more firm, permanance is better, and measurement data is more accurate.It is taper that bolt screws in sleeve inner branch tip designs, and has increased air discharge duct, makes when bolt rotates into pre-buried sleeve, in time the air in the pre-buried sleeve is discharged, and makes bolt rotate at the end more completely, and has guaranteed and the fitting tightly of pre-buried sleeve.
4, description of drawings
Fig. 1 is the cut-open view of pre-buried sleeve;
Structural representation when Fig. 2 is pre-buried sleeve and bolt installation;
Fig. 3 is pre-buried sleeve and bolt mounted configuration synoptic diagram;
Structural representation when Fig. 4 is pre-buried sleeve and plug installation;
Fig. 5 is pre-buried sleeve and plug mounted configuration synoptic diagram;
Mark in the accompanying drawing is represented respectively: 1, pre-buried sleeve; 2, building wall, post; 3, bolt; 4, air discharge duct; 5, plug.
5, embodiment
Below in conjunction with accompanying drawing settlement observation point built-in fitting of the present invention and method of application thereof are done following the detailed description.Shown in Fig. 1-5; Settlement observation point built-in fitting of the present invention and method of application thereof; The settlement observation point built-in fitting is made up of pre-buried sleeve 1, bolt 3 and plug 5, and pre-buried sleeve 1 set inside is a hollow cylinder, and inwall is provided with mantle fiber; Indulge conflicting of muscle for reducing pre-buried sleeve 1 with structure, pre-buried sleeve 1 diameter is confirmed as 27mm; The end of bolt 3 and plug 5 is provided with the mantle fiber that adapts with pre-buried sleeve 1, and bolt 3 is screwed in the pre-buried sleeve 1 through mantle fiber with plug 5; The end end that bolt 3 is provided with mantle fiber is the taper setting; The air discharge duct 4 that its arranged outside has 2 road 2mm is wide, 1mm is dark makes when bolt 3 is screwed into pre-buried sleeve 1, in time the air in the pre-buried sleeve 1 is discharged; Bolt 3 rotates at the end more completely, and has guaranteed and the fitting tightly of pre-buried sleeve 1.
The method of application of settlement observation point built-in fitting is following:
(1), before needs are provided with the building wall, post 2 deposit concretes at settlement observation point place, carry out concreting then to corresponding settlement observation point position with pre-buried sleeve 1 is pre-buried, guarantee that the same building wall of pre-buried sleeve 1 crust, post 2 crusts are concordant;
(2), when not carrying out settlement point observation, plug 5 is screwed in the pre-buried sleeve 1;
(3), need carry out settlement point observation time, back out plug 5, bolt 3 is screwed in the pre-buried sleeve 1, carry out settlement point observation.
Pre-buried sleeve 1 diameter, be of convenient length, the requirement of bearing load in the time of can satisfying settlement observation, can satisfy structure construction again during pre-buried sleeve 1 do not conflict with vertical muscle.It is wide that the outer wall of pre-buried sleeve 1 is provided with 3 road 6mm, and the groove that 2mm is dark is to increase the anchor force of pre-buried sleeve 1 and building wall, post 2; Make more firm, stable of pre-buried sleeve 1; The settlement observation point protection is better, and measurement data more continuously accurately can satisfy long needs of settlement observation cycle preferably.
Except that the described technical characterictic of instructions, be the known technology of those skilled in the art.

Claims (4)

1. settlement observation point built-in fitting and method of application thereof, the settlement observation point built-in fitting is made up of pre-buried sleeve, bolt and plug, and pre-buried sleeve inner is set to hollow cylinder, and inwall is provided with mantle fiber; The end of bolt and plug is provided with the mantle fiber that adapts with pre-buried sleeve, and bolt and plug are screwed in the pre-buried sleeve through mantle fiber;
The method of application of settlement observation point built-in fitting is following:
(1), before needs are provided with the building wall, post deposit concrete at settlement observation point place, carry out concreting then to corresponding settlement observation point position with pre-buried sleeve is pre-buried, guarantee that the same building wall of pre-buried sleeve crust, post crust are concordant;
(2), when not carrying out settlement point observation, plug is screwed in the pre-buried sleeve;
(3), need carry out settlement point observation time, back out plug, bolt is screwed in the pre-buried sleeve, carry out settlement point observation.
2. method according to claim 1 is characterized in that the outer wall of pre-buried sleeve is provided with 2-5 road groove, to increase the anchor force of pre-buried sleeve and building wall, post.
3. method according to claim 1 is characterized in that the end end that bolt is provided with mantle fiber is the taper setting.
4. according to claim 1 or 3 described methods, it is characterized in that the arranged outside of bolt has air discharge duct.
CN2012102157272A 2012-06-28 2012-06-28 Embedded part on settlement observation point and application method thereof Pending CN102721414A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102157272A CN102721414A (en) 2012-06-28 2012-06-28 Embedded part on settlement observation point and application method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102157272A CN102721414A (en) 2012-06-28 2012-06-28 Embedded part on settlement observation point and application method thereof

Publications (1)

Publication Number Publication Date
CN102721414A true CN102721414A (en) 2012-10-10

Family

ID=46947239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102157272A Pending CN102721414A (en) 2012-06-28 2012-06-28 Embedded part on settlement observation point and application method thereof

Country Status (1)

Country Link
CN (1) CN102721414A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103148835A (en) * 2013-02-28 2013-06-12 陈洪凯 Settlement observing pre-embedded piece, settlement observing device and installation device
CN105698753A (en) * 2016-03-14 2016-06-22 江苏建筑职业技术学院 Settlement observation device capable of preventing collision damage and use and safekeeping method
CN106289197A (en) * 2016-09-08 2017-01-04 中铁十九局集团第七工程有限公司 Tunnel non-prism monitoring parameter mark and tunnel non-prism monitoring measurement method
CN107621256A (en) * 2017-10-30 2018-01-23 安徽理工大学 Interior receipts formula building settlement observation nail
CN107738340A (en) * 2017-11-15 2018-02-27 安徽宝业建工集团有限公司 A kind of PC wallboard moulds for concrete prefabricated element production line
CN109357660A (en) * 2018-11-22 2019-02-19 国网天津市电力公司 Building drawing and pulling type settlement observation method
CN110345910A (en) * 2019-08-01 2019-10-18 中国三冶集团有限公司 A kind of settlement observation point mounting structure and method
CN111350521A (en) * 2020-03-09 2020-06-30 上海孚士德建筑科技有限公司 Pre-buried sleeve for shield interval

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2884135Y (en) * 2005-12-20 2007-03-28 山西科源建筑科研检测有限公司 Settlement obsergvation positioning rod set
CN201133816Y (en) * 2007-10-08 2008-10-15 中建一局集团建设发展有限公司 Settlement observation mark
CN101788292A (en) * 2010-01-25 2010-07-28 中铁十五局集团有限公司 Measurement centering device
CN202255393U (en) * 2011-09-19 2012-05-30 中国建筑第八工程局有限公司 Settlement observation device
CN202255397U (en) * 2011-10-31 2012-05-30 河北建设集团有限公司 Level mark for settlement observation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2884135Y (en) * 2005-12-20 2007-03-28 山西科源建筑科研检测有限公司 Settlement obsergvation positioning rod set
CN201133816Y (en) * 2007-10-08 2008-10-15 中建一局集团建设发展有限公司 Settlement observation mark
CN101788292A (en) * 2010-01-25 2010-07-28 中铁十五局集团有限公司 Measurement centering device
CN202255393U (en) * 2011-09-19 2012-05-30 中国建筑第八工程局有限公司 Settlement observation device
CN202255397U (en) * 2011-10-31 2012-05-30 河北建设集团有限公司 Level mark for settlement observation

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103148835A (en) * 2013-02-28 2013-06-12 陈洪凯 Settlement observing pre-embedded piece, settlement observing device and installation device
CN105698753A (en) * 2016-03-14 2016-06-22 江苏建筑职业技术学院 Settlement observation device capable of preventing collision damage and use and safekeeping method
CN106289197A (en) * 2016-09-08 2017-01-04 中铁十九局集团第七工程有限公司 Tunnel non-prism monitoring parameter mark and tunnel non-prism monitoring measurement method
CN107621256A (en) * 2017-10-30 2018-01-23 安徽理工大学 Interior receipts formula building settlement observation nail
CN107738340A (en) * 2017-11-15 2018-02-27 安徽宝业建工集团有限公司 A kind of PC wallboard moulds for concrete prefabricated element production line
CN109357660A (en) * 2018-11-22 2019-02-19 国网天津市电力公司 Building drawing and pulling type settlement observation method
CN110345910A (en) * 2019-08-01 2019-10-18 中国三冶集团有限公司 A kind of settlement observation point mounting structure and method
CN111350521A (en) * 2020-03-09 2020-06-30 上海孚士德建筑科技有限公司 Pre-buried sleeve for shield interval

Similar Documents

Publication Publication Date Title
CN102721414A (en) Embedded part on settlement observation point and application method thereof
CN204060114U (en) A kind of electric pole rectifier
CN203097307U (en) Horizontal adjuster for adjusting outer wallboard in installation of assembling type outer wallboard
CN202734828U (en) Novel settlement observation point embedded element
NZ603723A (en) Guy anchor reinforcement
CN203881339U (en) Detachable monitoring pier
CN203961322U (en) Prefabricated panel installation adjusting device
CN203639951U (en) Anti-settlement heavy-type complete-set well lid assembly
CN202709898U (en) Push rod explosive delivery device for charging ultra-deep horizontal blasting holes
CN204356712U (en) Tourist attractions road indicator
CN210221061U (en) Settlement observation point mounting structure
CN2884135Y (en) Settlement obsergvation positioning rod set
CN203741837U (en) Ground anchor
CN203893859U (en) Telescopic building settlement observation label
CN210262677U (en) Embedded part for laying cable bridge
CN204738468U (en) Prefabricated railing
CN209413254U (en) A kind of precast support device of achievable Fast Installation for building
CN105003036A (en) Prefabricated rail and its manufacturing method
CN203926599U (en) Screw pull rod
CN105932633A (en) Pay-off pulley
CN208235983U (en) A kind of vertical concrete structure curing means
CN206607753U (en) After pour beam steel anchor
CN203432575U (en) Novel scalable adjustable settlement observation device
CN204942180U (en) A kind of plastic dowel sleeve
CN205277018U (en) Prefabricated basis of cement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121010