CN110345910A - A kind of settlement observation point mounting structure and method - Google Patents
A kind of settlement observation point mounting structure and method Download PDFInfo
- Publication number
- CN110345910A CN110345910A CN201910707495.4A CN201910707495A CN110345910A CN 110345910 A CN110345910 A CN 110345910A CN 201910707495 A CN201910707495 A CN 201910707495A CN 110345910 A CN110345910 A CN 110345910A
- Authority
- CN
- China
- Prior art keywords
- plastic base
- bar
- screw
- observation point
- screw thread
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title abstract description 7
- 229920003023 plastic Polymers 0.000 claims abstract description 35
- 239000004033 plastic Substances 0.000 claims abstract description 35
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 22
- 239000010959 steel Substances 0.000 claims abstract description 22
- 238000010276 construction Methods 0.000 claims abstract description 9
- 238000005553 drilling Methods 0.000 claims abstract description 7
- 230000002787 reinforcement Effects 0.000 claims abstract description 6
- 238000005266 casting Methods 0.000 claims description 8
- 125000003003 spiro group Chemical group 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 238000009434 installation Methods 0.000 abstract description 4
- 239000011159 matrix material Substances 0.000 abstract description 3
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 238000009435 building construction Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C5/00—Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Architecture (AREA)
- General Physics & Mathematics (AREA)
- Radar, Positioning & Navigation (AREA)
- Remote Sensing (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
A kind of settlement observation point mounting structure and method, settlement observation point mounting structure includes steel plate, pre-buried plastic base, screw thread observation bar, screw shell, steel plate is fixed on the pre-buried plastic base, pre-buried plastic base is weldingly fixed on steel reinforcement cage by steel plate, the screw shell is fixed in pre-buried plastic base, for the screw thread observation bar by being screwed in screw shell, the external of the pre-buried plastic base is poured concrete.Compared with prior art, the beneficial effects of the present invention are: a kind of settlement observation point structure and installation and application, use plastics as installation matrix, it is easy drilling, easy for construction, the installed height mark for observing bar is easier to be controlled, it stretches out, hides when not in use, and can replace when observing bar use.
Description
Technical field
The present invention relates to technical field of building construction more particularly to a kind of settlement observation point mounting structure and methods.
Background technique
Settlement observation point, which refers to, changes observation point used in carried out measurement to the elevation for being observed object.It is existing
Settlement observation point in building mostly uses rod-like structure, is fixed in wall for a long time, non-dismountable.And in construction, usually
It is to drill in concrete after being cast, is then fixedly mounted.Settlement observation is the observation work of a long-term system, can not
The observation bar of dismounting and change, it is beautiful that long-time wind and weather is easy old influence exterior wall.In addition, concrete drill hole difficulty of construction compared with
Greatly, observation bar installed height mark precision is limited.
Summary of the invention
The object of the present invention is to provide a kind of settlement observation point mounting structure and methods, use plastics as installation matrix, hold
Easily drilling, easy for construction, the installed height mark for observing bar is easier to be controlled, and stretches out when observing bar use, hides when not in use, and
It can replace.
In order to achieve the above object, the present invention is implemented with the following technical solutions:
A kind of settlement observation point mounting structure, including steel plate, pre-buried plastic base, screw thread observe bar, screw shell, described
Steel plate is fixed on pre-buried plastic base, pre-buried plastic base is weldingly fixed on steel reinforcement cage by steel plate, the screw shell
It is fixed in pre-buried plastic base, the screw thread observation bar is by being screwed in screw shell, the pre-buried plastic base
External be poured concrete.
The screw thread observation bar includes screw rod, end cap, retaining ring, length mark, and the screw rod is screwed in screw shell, end
Lid is fixed on one end of screw rod, and the retaining ring is hinged on end cap, and length mark is additionally provided on screw rod.
The length mark is 115mm-125mm with end cap distance L.
The depth of the screw shell is identical as spiro rod length or is greater than spiro rod length.
A kind of construction method of settlement observation point mounting structure, specifically includes:
1) before building concrete casting, pre-buried plastic base is weldingly fixed on by steel plate according to drawings marked position
On steel reinforcement cage;
2) after the completion of building concrete casting and constructing, according to the absolute altitude of settlement observation point, wall is being exposed to by electric drill
It drills, screw shell is adhesively fixed in the drilling of pre-buried plastic base on the pre-buried plastic base of body;
3) screw thread observation bar is screwed into screw shell, when needing to observe, is screwed out screw thread observation bar by retaining ring
Come, screw rod extension elongation is the length at length mark;
4) when not needing observation, screw thread observation bar is screwable into screw shell by retaining ring.
Compared with prior art, the beneficial effects of the present invention are:
A kind of settlement observation point mounting structure and method use plastics as installation matrix, are easy drilling, easy for construction, see
The installed height mark of measuring staff is easier to be controlled, and stretches out, hides when not in use, and can replace when observing bar use.
Detailed description of the invention
Fig. 1 is working condition when screw thread observation bar stretches out in the present invention;
Fig. 2 is working condition when screw thread observation bar retracts in the present invention;
Fig. 3 is the partial enlarged view of settlement observation point structure of the invention;
Fig. 4 is the main view of cover board.
In figure: the pre-buried plastic base of 1-, 2- screw thread observation bar, 3- steel plate, 4- concrete, 5- sleeve fixed glue, 6- length
Label, 7- end cap, 8- retaining ring, 9- screw shell, 10- steel reinforcement cage, 11- screw rod.
Specific embodiment
Specific embodiments of the present invention will be further explained with reference to the accompanying drawing:
See Fig. 1-Fig. 4, a kind of settlement observation point mounting structure, including steel plate 3, pre-buried plastic base 1, screw thread observation bar 2,
Screw shell 9, steel plate 3 is fixed on the pre-buried plastic base 1, and pre-buried plastic base 1 is weldingly fixed on reinforcing bar by steel plate 3
On cage 10, the screw shell 9 is fixed in pre-buried plastic base 1, and the screw thread observation bar 2 is by being screwed in thread bush
In cylinder 9, the external of the pre-buried plastic base 1 is poured concrete 4.
The screw thread observation bar 2 includes screw rod 2, end cap 7, retaining ring 8, length mark 6, and the screw rod 2 is screwed in thread bush
In cylinder 9, end cap 7 is fixed on one end of screw rod 2, and the retaining ring 8 is hinged on end cap 7, and length mark 6 is additionally provided on screw rod 2.
The outer of cover board 7 can be made chamfering, when cover board 7 is buckled on metope, can play the role of the outside water conservancy diversion of rainwater.
The length mark 6 is 115mm-125mm with 7 distance L of end cap.Length mark 6 can be existed using colored paint
The mode painted on screw rod 11.
The depth of the screw shell 9 is identical as 11 length of screw rod or is greater than 11 length of screw rod.Cover board 7 it is outer diametrically big
In the diameter of screw shell 9, when screw rod 11 is screwed into screw shell 9, cover board 7 is buckled on wall face.
A kind of construction method of settlement observation point mounting structure, specifically includes:
1) before building concrete casting, pre-buried plastic base 1 is welded and fixed by steel plate 3 according to drawings marked position
On steel reinforcement cage 10;Template is normally built according to Construction Design Schemes, and carries out concrete casting, pre-buried plastic base 1 is pre-
It is embedded in the wall of the casting of concrete 4.
2) after the completion of building concrete casting and constructing, according to the absolute altitude of settlement observation point, wall is being exposed to by electric drill
It drills, screw shell 9 is adhesively fixed in the drilling of pre-buried plastic base 1 on the pre-buried plastic base 1 of body;Screw shell 9
2 accessory processing of bar can be observed with screw thread, be directly mounted in the drilling of pre-buried plastic base 1.
3) screw thread observation bar 2 is screwed into screw shell 9, when needing to observe, is revolved screw thread observation bar 2 by retaining ring 8
Back-out and, 11 extension elongation of screw rod is the length at length mark 6;It, can be to screw thread when discovery screw rod 11, which has, gets rusty sign
Observation bar 2 is timely replaced.
4) when not needing observation, screw thread observation bar 2 is screwable into screw shell 9 by retaining ring 8.
Claims (5)
1. a kind of settlement observation point mounting structure, which is characterized in that observe bar, screw thread including steel plate, pre-buried plastic base, screw thread
Sleeve is fixed with steel plate on the pre-buried plastic base, and pre-buried plastic base is weldingly fixed on steel reinforcement cage by steel plate, described
Screw shell is fixed in pre-buried plastic base, and the screw thread observation bar is described pre-buried by being screwed in screw shell
The external of plastic base is poured concrete.
2. a kind of settlement observation point mounting structure according to claim 1, which is characterized in that the screw thread observes bar and includes
Screw rod, end cap, retaining ring, length mark, the screw rod are screwed in screw shell, and end cap is fixed on one end of screw rod, the button
Ring is hinged on end cap, and length mark is additionally provided on screw rod.
3. a kind of settlement observation point mounting structure according to claim 2, which is characterized in that the length mark and end cap
Distance L be 115mm-125mm.
4. a kind of settlement observation point mounting structure according to claim 2, which is characterized in that the depth of the screw shell
It is identical as spiro rod length or be greater than spiro rod length.
5. it is a kind of claim 1-4 its any one of as described in settlement observation point mounting structure construction method, feature
It is, specifically includes:
1) before building concrete casting, pre-buried plastic base is weldingly fixed on reinforcing bar by steel plate according to drawings marked position
On cage;
2) after the completion of building concrete casting and constructing, according to the absolute altitude of settlement observation point, wall is being exposed to by electric drill
It drills, screw shell is adhesively fixed in the drilling of pre-buried plastic base on pre-buried plastic base;
3) screw thread observation bar is screwed into screw shell, when needing to observe, is screwed out screw thread observation bar come spiral shell by retaining ring
Bar extension elongation is the length at length mark;
4) when not needing observation, screw thread observation bar is screwable into screw shell by retaining ring.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910707495.4A CN110345910A (en) | 2019-08-01 | 2019-08-01 | A kind of settlement observation point mounting structure and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910707495.4A CN110345910A (en) | 2019-08-01 | 2019-08-01 | A kind of settlement observation point mounting structure and method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110345910A true CN110345910A (en) | 2019-10-18 |
Family
ID=68183602
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910707495.4A Pending CN110345910A (en) | 2019-08-01 | 2019-08-01 | A kind of settlement observation point mounting structure and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110345910A (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101545271A (en) * | 2009-03-21 | 2009-09-30 | 标力建设集团有限公司 | Telescopic type settlement observer |
US20110192111A1 (en) * | 2010-02-05 | 2011-08-11 | Sam White | Cast-in Shear Wall Anchor |
CN202255397U (en) * | 2011-10-31 | 2012-05-30 | 河北建设集团有限公司 | Level mark for settlement observation |
CN102721414A (en) * | 2012-06-28 | 2012-10-10 | 中建八局第二建设有限公司 | Embedded part on settlement observation point and application method thereof |
CN104631644A (en) * | 2015-01-09 | 2015-05-20 | 上海大学 | Novel connection node structure |
CN205246081U (en) * | 2015-10-29 | 2016-05-18 | 山东科技大学 | Hidden stainless steel settlement observation point marks piece |
CN208501905U (en) * | 2018-07-07 | 2019-02-15 | 上海宝冶集团有限公司 | A kind of building safety guard rail built-in type component |
CN210221061U (en) * | 2019-08-01 | 2020-03-31 | 中国三冶集团有限公司 | Settlement observation point mounting structure |
-
2019
- 2019-08-01 CN CN201910707495.4A patent/CN110345910A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101545271A (en) * | 2009-03-21 | 2009-09-30 | 标力建设集团有限公司 | Telescopic type settlement observer |
US20110192111A1 (en) * | 2010-02-05 | 2011-08-11 | Sam White | Cast-in Shear Wall Anchor |
CN202255397U (en) * | 2011-10-31 | 2012-05-30 | 河北建设集团有限公司 | Level mark for settlement observation |
CN102721414A (en) * | 2012-06-28 | 2012-10-10 | 中建八局第二建设有限公司 | Embedded part on settlement observation point and application method thereof |
CN104631644A (en) * | 2015-01-09 | 2015-05-20 | 上海大学 | Novel connection node structure |
CN205246081U (en) * | 2015-10-29 | 2016-05-18 | 山东科技大学 | Hidden stainless steel settlement observation point marks piece |
CN208501905U (en) * | 2018-07-07 | 2019-02-15 | 上海宝冶集团有限公司 | A kind of building safety guard rail built-in type component |
CN210221061U (en) * | 2019-08-01 | 2020-03-31 | 中国三冶集团有限公司 | Settlement observation point mounting structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102721414A (en) | Embedded part on settlement observation point and application method thereof | |
CN102493471A (en) | Suspending installation construction process method of structural foot margin anchor bolt | |
CN110345910A (en) | A kind of settlement observation point mounting structure and method | |
CN210221061U (en) | Settlement observation point mounting structure | |
CN204098489U (en) | A kind of mould making concrete floorslab preformed hole | |
CN201574583U (en) | Simple pipe hole preformed mould | |
CN105257003A (en) | Tool for rapidly fixing grout sleeve and using method of tool | |
CN208983987U (en) | A kind of measuring tool of concreting thickness and flatness | |
CN208996103U (en) | A kind of cast-in-place concrete pile hole bottom slurry pick-up | |
CN210014786U (en) | Measuring device for bridge construction | |
CN204356712U (en) | Tourist attractions road indicator | |
CN206348164U (en) | A kind of spiral soil sampling apptss | |
CN215052138U (en) | Accurate positioner of adjustable festival section roof beam built-in fitting | |
CN201280821Y (en) | Ruler for examining thickness of cast-in-situ reinforced concrete slab | |
CN210922582U (en) | Level mark | |
CN204142254U (en) | A kind of interior decoration surveying setting-out device | |
CN201397139Y (en) | Expansion type settlement observation device | |
CN203430034U (en) | Fixing tool for locating pre-buried sleeve of cast-in-place slab | |
CN207763714U (en) | Construction and lifting wire device for supervision | |
CN207582978U (en) | A kind of floorslab thickness control device | |
CN211421897U (en) | Building engineering datum line pay-off | |
CN211904143U (en) | Be fit for hoist and mount wall components of a whole that can function independently settlement monitoring mark | |
CN206095872U (en) | Sludge settling ratio measuring device | |
CN201126358Y (en) | Settlement observation structure | |
CN206113946U (en) | A repeatedly usable monitoring point device for concrete structure component |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |