CN102605698A - 冲击式压路机增强碾压软土路基施工工法 - Google Patents

冲击式压路机增强碾压软土路基施工工法 Download PDF

Info

Publication number
CN102605698A
CN102605698A CN2012100613209A CN201210061320A CN102605698A CN 102605698 A CN102605698 A CN 102605698A CN 2012100613209 A CN2012100613209 A CN 2012100613209A CN 201210061320 A CN201210061320 A CN 201210061320A CN 102605698 A CN102605698 A CN 102605698A
Authority
CN
China
Prior art keywords
impact
construction
rolling
subgrade
roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100613209A
Other languages
English (en)
Inventor
朱建国
陈荣凯
蔡志舰
段辉林
刘东鲁
张卫国
杨建松
王奋琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Beixin Road & Bridge Construction Co Ltd
Original Assignee
Xinjiang Beixin Road & Bridge Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Beixin Road & Bridge Construction Co Ltd filed Critical Xinjiang Beixin Road & Bridge Construction Co Ltd
Priority to CN2012100613209A priority Critical patent/CN102605698A/zh
Publication of CN102605698A publication Critical patent/CN102605698A/zh
Pending legal-status Critical Current

Links

Abstract

本发明公开了冲击式压路机增强碾压软土路基施工工法,包括以下步骤,(1)选择试验路段施工,确定路基施工参数,包括铺土厚度、碾压遍数、冲击式压路机频率、土的含水量;(2)将路基软弱土体挖除,路基基底挖至设计标高,(3)按照相关规定,确定砂砾含水量,并选取填料砂砾场地,(4)路基上料,砂砾填筑量分层按松铺厚度进行,现场控制的上料量为1米,(5)路基摊铺平整及初压,(6)布置沉降观测点,测设高程布设点并记录好高程,(7)使用冲击压实机进行冲击碾压,(8)检测压实度采用沉降差和施工工艺进行双控,(9)压实路基修整,施工结束。本发明工艺简单,各工序衔接紧凑,提高了工程质量,降低了成本。

Description

冲击式压路机增强碾压软土路基施工工法
技术领域
本发明涉及公路建筑技术领域,特别是涉及一种路基施工方法。 
背景技术
随着道路建设的发展,对路基压实的标准也越来越高,同时既有线路的安全也提出了更高的要求。尤其是下边为碎石土,地下水位较高的地质结构,传统施工工艺难以压实,不符合施工的技术要求。如采用常规的天然砂砾路基传统分层填筑方法施工,以压实度作为施工主要控制指标,要求每2000m2用灌砂法检测8个点,且灌砂底部应与压实底为同一平面,施工周期长、而且工后沉降量会较大,如何能省时省工,提高路基质量,大大降低工程费用,采用什么样的基底处理施工方法至关重要。 
发明内容
本发明在于克服了现有技术的缺陷,提供了一种施工周期短、前期投入量少的冲击式压路机增强碾压软土路基施工工法。 
为了解决上述技术问题,本发明提供了如下的技术方案: 
包括以下步骤,(1)选择试验路段施工,确定路基施工参数,包括铺土厚度、碾压遍数、冲击式压路机频率、土的含水量;(2)将路基软弱土体挖除,路基基底挖至设计标高,(3)按照相关规定,确定砂砾含水量,并选取填料砂砾场地,(4)路基上料,砂砾填筑量分层按松铺厚度进行,现场控制的上料量为1米,(5)路基摊铺平整及初压,(6)布置沉降观测点,测设高程布设点并记录好高程,(7)使用冲击压实机进行冲击碾压,(8)检测压实度采用沉降差和施工工艺进行双控,(9)压实路基修整,施工结束。
所述砂砾分层松铺厚度按100厘米计算获得。 
所述沉降观测点,按40米一个断面,每个断面5个沉降观测点,沉降观测点为埋入表层下30厘米的钢板。 
在冲击碾压前、冲击碾压中,根据路基最佳含水量5.4%±2%,检测并调整填料砂砾含水量。 
冲击碾压顺序为先两边后中间,转圈碾压,以轮迹覆盖整个填筑面层为一遍,分别在冲击碾压15遍、20遍、25遍后恢复高程测量点记录高程。 
所述压实度检测点按照沉降差≤5mm和施工工艺冲击碾压25遍进行检测。 
与现有技术相比较,本发明具有如下的有益效果: 
工艺简单易操作,各工序衔接紧凑、互为依托,缩短了施工时间提高了施工效率,提高了工程质量,降低了成本。施工后一年半的平均沉降量为6mm,提高了路基的整体性和承载能力。
具体实施方式
以下对本发明的优选实施例进行说明,应当理解,此处所描述的优选实施例仅用于说明和解释本发明,并不用于限定本发明。 
施工工法包括以下步骤: 
(1)选择能够代表本合同段路基施工要求的段落进行试验段施工,取得最佳机械组合及相关技术参数用于指导大面积施工。本工法选择具有代表性的K219+050—K219+200段作为本标段软土路基冲击碾压施工的试验路段,该段路基填方高度为7.6米,路基宽度43米。
(2)挖除软土路基层,将路基换填范围内的软弱土体挖除,用自卸车拉运到指定地点用于临时场地的复耕。路基基底挖至设计标高,进行试验路段路基检验。 
(3)按照相关规定确定砂砾含水量,选定采用K220+000左1.5公里填料场天然砂砾为填料砂砾。经取样检测,该料场砂砾为级配良好砾,砂砾最佳含水量为5.4%,天然含水量为5%,实测含泥量为1.2%。 
(4)路基上料,填料砂砾松铺厚度按100厘米进行上料,并确定上料量为1米进行现场卸料的控制。 
振动压路机初压山即推SR22M压路机静压一遍、弱振一遍。 
(5)路基平整初压,对填料砂砾推土机进行粗平,人工分解或拣除超粒径粒料, 山推180平地机进行精平;填料摊铺整平以后,首先用山推SR22M振动压路机初压(静压一遍,弱振一遍)。 
(6)路基表层有一定的密实度后,布置沉降观测点,所述沉降观测点,按40米一个断面,每个断面5个沉降观测点,沉降观测点为埋入表层下30厘米的钢板,沉降观测点布设完毕,测设并记录好高程。 
(7)在冲击碾压前、冲击碾压中,根据路基最佳含水量5.4%,检测并调整填料砂砾的合适含水量后,进行冲击碾压,使用宇通重工6830冲击压实机以10~12公里/每小时行驶速度,冲击碾压顺序为先两边后中间,转圈碾压,以轮迹覆盖整个填筑面层为一遍;在冲压过程中,若表面起伏较大时,采用平地机整平,表层干燥时按相关规定控制路基含水量为5.4±2%,依据水车的方量进行现场及时洒水。所述冲击碾压分别为在冲击碾压15遍、20遍、25遍后在高程布设测量点记录测量高程。两次高程之间的差值作为压实度控制的指标,当沉降差值≤5mm时,压实度满足要求。 
冲击压路机三叶形凸轮在滚动过程中,曲线形冲击轮在位能落差与行驶动能相结合下,产生瞬时冲击动荷载,冲击、搓揉土体。快速挤密深层土颗粒,同时冲击能量以震动波的形式在弹性半空间内传播,使土颗粒相互靠拢,排出空隙中的气体和水,土颗粒重新排列而挤密压实,冲击压实的压实原理可归类为轻型强夯,冲击压实法结合了压路机连续工作的特点,即把强夯用夯锤一点一点上下夯击的方式变为连续滚动式的夯击,方便简单、工作效率较高。 
宇通重工6830冲击式压路机以高振幅、低频率对工作面以下深层土体进行搓揉、冲击,使深层土体密实度不断增加,克服路基隐患,具有行驶速度快,冲击力大,其压实土石的效率提高3~4倍(考虑上料、摊铺、平整工序)的技术优势。 
冲击碾压是冲击轮在位能落差与行驶动能相结合下,产生瞬时冲击动荷载,冲击、搓揉土体。快速挤密深层土颗粒,加速了路基的沉降过程。对不同的土体和地质条件有不同的效果,必须根据不同的情况做试验段,取得指导施工的技术参数。冲击碾压速度以10~12km/h为宜,控制好碾压速度是达到土体压实效果的关键。 
(8)压实测试,在路基冲击碾压时,选择分别在路基填料表面下20cm、50cm、80cm深度处各选择4个点进行压实度检测,路基压实度指标采用沉降差和施工工艺进行双控。 
经实测计算冲击碾压15遍后压实沉降差平均值为60 ㎜,地表下50cm压实度平均值为98%~102%;冲击碾压15--20遍压实沉降差平均值为13 ㎜,地表下50cm压实度平均值为102%~106%;冲击碾压20--25遍压实沉降差平均值为5㎜,地表下50cm压实度平均值为104%~107%。由测量数据看出,当冲击碾压在20遍左右时,压实效果最好,压实度提高明显。超过25遍时,压沉量、压实度变化不特明显。 
(9)压实路基修整,施工结束。 
采用冲击碾压技术,完工后一年半的平均沉降量为6mm,缩短工期显著,提高路基的整体性和承载能力显著。 
本工法确定了采用沉降差≤5mm和施工工艺冲击碾压25遍双控的质量控制方法,方便易行,缩短了施工时间提高了施工效率。 
以上所述仅为说明本发明的实施方式,并不用于限制本发明,对于本领域的技术人员来说,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。 

Claims (6)

1.冲击式压路机增强碾压软土路基施工工法,其特征在于,包括以下步骤,(1)选择试验路段施工,确定路基施工参数,包括铺土厚度、碾压遍数、冲击式压路机频率、土的含水量;(2)将路基软弱土体挖除,路基基底挖至设计标高,(3)按照相关规定,确定砂砾含水量,并选取填料砂砾场地,(4)路基上料,砂砾填筑量分层按松铺厚度进行,现场控制的上料量为1米,(5)路基摊铺平整及初压,(6)布置沉降观测点,测设高程布设点并记录好高程,(7)使用冲击压实机进行冲击碾压,(8)检测压实度采用沉降差和施工工艺进行双控,(9)压实路基修整,施工结束。
2.根据权利要求1所述的冲击式压路机增强碾压软土路基施工工法,其特征在于:所述砂砾分层松铺厚度按100厘米计算获得。
3.根据权利要求1所述的冲击式压路机增强碾压软土路基施工工法,其特征在于:所述沉降观测点,按40米一个断面,每个断面5个沉降观测点,沉降观测点为埋入表层下30厘米的钢板。
4.根据权利要求1所述的冲击式压路机增强碾压软土路基施工工法,其特征在于:在冲击碾压前、冲击碾压中,根据路基最佳含水量5.4%±2%,检测并调整填料砂砾含水量。
5.根据权利要求1所述的冲击式压路机增强碾压软土路基施工工法,其特征在于:冲击碾压顺序为先两边后中间,转圈碾压,以轮迹覆盖整个填筑面层为一遍,分别在冲击碾压15遍、20遍、25遍后恢复高程测量点记录高程。
6.根据权利要求1所述的冲击式压路机增强碾压软土路基施工工法,其特征在于:所述压实度检测点按照沉降差≤5mm和施工工艺冲击碾压25遍进行检测。
CN2012100613209A 2012-03-09 2012-03-09 冲击式压路机增强碾压软土路基施工工法 Pending CN102605698A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100613209A CN102605698A (zh) 2012-03-09 2012-03-09 冲击式压路机增强碾压软土路基施工工法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100613209A CN102605698A (zh) 2012-03-09 2012-03-09 冲击式压路机增强碾压软土路基施工工法

Publications (1)

Publication Number Publication Date
CN102605698A true CN102605698A (zh) 2012-07-25

Family

ID=46523433

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100613209A Pending CN102605698A (zh) 2012-03-09 2012-03-09 冲击式压路机增强碾压软土路基施工工法

Country Status (1)

Country Link
CN (1) CN102605698A (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831597A (zh) * 2015-06-05 2015-08-12 合肥工业大学 一种用于确定冲击碾压最佳松铺厚度的方法
CN105239551A (zh) * 2015-09-30 2016-01-13 贵州正业工程技术投资有限公司 一种振动碾压质量控制方法
CN108867283A (zh) * 2018-08-17 2018-11-23 上海宝冶集团有限公司 用于路基填筑压实的在役质量检测方法
CN109024129A (zh) * 2018-08-21 2018-12-18 华东建工集团有限公司 高填方路基挤密施工方法
CN110411409A (zh) * 2019-08-09 2019-11-05 中国十七冶集团有限公司 一种石方路基填筑智能沉降观测仪器
CN112924310A (zh) * 2020-09-03 2021-06-08 中节能建设工程设计院有限公司 基于土体刚度的堆石坝料压实质量检测方法
CN112982054A (zh) * 2019-12-14 2021-06-18 浙江建腾建设有限公司 一种南京地区特有地质雨花石砂砾层路基加固处理施工方法
CN114755174A (zh) * 2022-06-13 2022-07-15 水利部交通运输部国家能源局南京水利科学研究院 模拟原应力状态粗粒土地基的冲击碾压试验装置及方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005127100A (ja) * 2003-10-27 2005-05-19 Nippon Mesaraito Kogyo Kk 人工軽量骨材を使用する路床路盤の締め固め方法
JP2009024460A (ja) * 2007-07-23 2009-02-05 Yuichi Tsukada 人工芝下地用路盤及びその造成方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005127100A (ja) * 2003-10-27 2005-05-19 Nippon Mesaraito Kogyo Kk 人工軽量骨材を使用する路床路盤の締め固め方法
JP2009024460A (ja) * 2007-07-23 2009-02-05 Yuichi Tsukada 人工芝下地用路盤及びその造成方法

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
喻志平: "路基冲击碾压试验及施工技术", 《山西建筑》, vol. 36, no. 4, 28 February 2010 (2010-02-28), pages 275 - 276 *
孙翰耕等: "《公路工程施工技术》", 31 August 2010, article "路面施工技术", pages: 109 *
汤振周等: "冲击压路机在高速公路高临段填方路基中的应用", 《长春工程学院学报(自然科学版)》, vol. 11, no. 4, 31 December 2010 (2010-12-31), pages 5 - 9 *
王冠欣等: "分析路基冲击压实效果与土基松铺厚度的关系", 《山西建筑》, vol. 37, no. 25, 30 September 2011 (2011-09-30), pages 136 - 137 *
王春玲: "冲击压实技术在滨海路堤中的应用", 《辽宁省交通高等专科学校学报》, vol. 12, no. 6, 31 December 2010 (2010-12-31), pages 13 - 15 *
程涛等: "浅谈路基原地基换填和填前碾压", 《科技信息》, no. 23, 21 August 2009 (2009-08-21), pages 903 *
胡伍生等: "《交通土建施工测量》", 31 December 2002, article "软土地基路基施工沉降观测", pages: 173-176 *
苟永斌: "浅析用冲击碾压方法处理路基杂填土区", 《科技资讯》, no. 3, 31 January 2011 (2011-01-31), pages 98 - 101 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104831597A (zh) * 2015-06-05 2015-08-12 合肥工业大学 一种用于确定冲击碾压最佳松铺厚度的方法
CN105239551A (zh) * 2015-09-30 2016-01-13 贵州正业工程技术投资有限公司 一种振动碾压质量控制方法
CN108867283A (zh) * 2018-08-17 2018-11-23 上海宝冶集团有限公司 用于路基填筑压实的在役质量检测方法
CN109024129A (zh) * 2018-08-21 2018-12-18 华东建工集团有限公司 高填方路基挤密施工方法
CN110411409A (zh) * 2019-08-09 2019-11-05 中国十七冶集团有限公司 一种石方路基填筑智能沉降观测仪器
CN112982054A (zh) * 2019-12-14 2021-06-18 浙江建腾建设有限公司 一种南京地区特有地质雨花石砂砾层路基加固处理施工方法
CN112924310A (zh) * 2020-09-03 2021-06-08 中节能建设工程设计院有限公司 基于土体刚度的堆石坝料压实质量检测方法
CN114755174A (zh) * 2022-06-13 2022-07-15 水利部交通运输部国家能源局南京水利科学研究院 模拟原应力状态粗粒土地基的冲击碾压试验装置及方法

Similar Documents

Publication Publication Date Title
CN102605698A (zh) 冲击式压路机增强碾压软土路基施工工法
CN101962928B (zh) 冲击碾压处理风积沙路基基底的施工方法
CN102900001B (zh) 一种道路地基的施工方法
CN106283944B (zh) 压填片石和/或块石加固浅层软基的方法
CN102747662A (zh) 一种填砂路基的施工方法
CN104358188A (zh) 湿陷性黄土路基填筑施工方法
CN109056439A (zh) 傍山高填方路基的多层次结构和施工方法
CN104894937A (zh) 淤泥质软土路基管桩施工方法
CN110777588A (zh) 一种土石混合高填路基的压填施工方法
CN103276649B (zh) 有侧限分层多厚度填石路堤施工方法
CN106522074A (zh) 一种高速公路砂砾卵石土路基的施工工艺
CN101122128B (zh) 一种冲击碾压施工方法
CN103510504B (zh) 高饱和不均匀吹填土地基处理方法
CN101591903A (zh) 长桩短墩复合地基处理方法
CN102644265A (zh) 一种夯锤及夯实路基的方法
CN103993533B (zh) 用于黄土地区高填方路堤的综合压实方法
CN103669329B (zh) 超深建筑垃圾坑直接强夯法治理工艺
CN102031743A (zh) 泥岩填筑路堤的施工方法
Miao et al. Application of dynamic compaction in highway: a case study
CN204343341U (zh) 阶梯式隔振沟
CN110029652A (zh) 一种减少湿陷性黄土工后沉降的施工工艺
Adam et al. Rapid Impact Compactor-An Innovative Dynamic Compaction Device for Soil Improvement
CN102635044B (zh) 一种强夯对路床挖方路基的处理方法
CN113235552B (zh) 一种利用大块径碎石强夯填筑路基的方法
CN100365210C (zh) 定位夯实路基施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120725