CN102582799B - 浮箱水上合拢工艺 - Google Patents

浮箱水上合拢工艺 Download PDF

Info

Publication number
CN102582799B
CN102582799B CN 201210104393 CN201210104393A CN102582799B CN 102582799 B CN102582799 B CN 102582799B CN 201210104393 CN201210104393 CN 201210104393 CN 201210104393 A CN201210104393 A CN 201210104393A CN 102582799 B CN102582799 B CN 102582799B
Authority
CN
China
Prior art keywords
buoyancy tank
buoyancy tanks
joining
afloat
buoyancy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201210104393
Other languages
English (en)
Other versions
CN102582799A (zh
Inventor
宋建平
李统安
任刚
林从飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Guangxin Marine Engineering Equipment Research Institute Co. Ltd.
Original Assignee
Guangxin Shipbuilding and Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxin Shipbuilding and Heavy Industry Co Ltd filed Critical Guangxin Shipbuilding and Heavy Industry Co Ltd
Priority to CN 201210104393 priority Critical patent/CN102582799B/zh
Publication of CN102582799A publication Critical patent/CN102582799A/zh
Application granted granted Critical
Publication of CN102582799B publication Critical patent/CN102582799B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Bridges Or Land Bridges (AREA)
  • Application Of Or Painting With Fluid Materials (AREA)

Abstract

本发明公开浮箱,浮箱之间的连接结构设置在浮箱甲板之下、水面以上的浮箱外侧壁上。浮箱水上合拢工艺,包括如下步骤:(a)在浮箱甲板之下、水面以上的浮箱外侧壁上设置浮箱之间的连接结构;并且在在浮箱甲板之下、水面以上的浮箱外侧壁上设置格栅通道及管路电缆的连接接口;(b)在船坞分别进行各浮箱的独立建造,并按工艺要求处理结构的水上合拢缝和管线接口;(c)建造好的各浮箱依次下水后,进行水上浮箱合拢;(d)按工艺要求进行相关的装焊检验、无损探伤;(e)按涂装工艺要求完成相关涂装工作;(f)完工交船。本发明取消了水下合拢工艺,仅需在水面上使用常规工艺进行工作,改善工作环境,降低合拢难度,缩短合拢时间。

Description

浮箱水上合拢工艺
技术领域
本发明涉及一种浮箱,特别涉及一种浮箱及浮箱水上合拢工艺。
背景技术
目前,要进行超大尺寸浮箱或方驳的建造,首先需将浮箱按现有船坞的尺寸划分成若干总段,分别在船坞进行各总段的建造;下水后,再将各总段进行水下装配、焊接。将各总段合拢成形。现有建造方法和工艺,需有水下装配、焊接的特殊工装。工作环境差,对操作人员要求高。
发明内容
针对现有技术中存在的不足,本发明的目的在于提供一种能够改善工作环境、降低合拢难度和缩短合拢时间的浮箱及浮箱水上合拢工艺,取消了水下合拢工艺,仅需在水面上使用常规工艺进行浮箱合拢工作。
本发明的技术方案是这样实现的:浮箱,浮箱之间的连接结构设置在浮箱甲板之下、水面以上的所述浮箱外侧壁上。 
上述浮箱,在浮箱甲板之下、水面以上的所述浮箱外侧壁上还设置有格栅通道。 
上述浮箱,所述格栅通道的底面与所述浮箱甲板的距离大于等于1.8米。 
上述浮箱的浮箱水上合拢工艺,包括如下步骤:     (a)在浮箱甲板之下、水面以上的所述浮箱外侧壁上设置浮箱之间的连接结构;并且在在浮箱甲板之下、水面以上的所述浮箱外侧壁上设置格栅通道及管路电缆的连接接口;     (b)在船坞分别进行各浮箱的独立建造,并按工艺要求处理结构的水上合拢缝和管线接口;     (c)建造好的各浮箱依次下水后,进行水上浮箱合拢;     (d)按工艺要求进行相关的装焊检验、无损探伤;     (e)按涂装工艺要求完成相关涂装工作;     (f)完工交船。 
本发明的有益效果是:通过结构改造,将水下的工作移至水上进行,取消了水下合拢工艺,仅需在水面上使用常规工艺进行工作,工作环境得到改善,降低了合拢难度,合拢时间也缩短了。 
附图说明
图1为本发明浮箱合拢后的侧视图; 
图2为本发明浮箱合拢后的俯视图;
图3为图1所示B部放大结构示意图;
图4为本发明浮箱水上合拢工艺在水上进行两两合拢的示意图;
图5为本发明浮箱水上合拢工艺水上合拢后的示意图。
图中:1-浮箱甲板,2-格栅通道,3-浮箱外侧壁,4-水面,100-浮箱,5-船坞,6-码头。 
具体实施方式
结合附图对本发明做进一步的说明: 
如图1至图3所示,本实施例中的浮箱,浮箱100之间的连接结构设置在浮箱甲板1之下、水面4以上的浮箱外侧壁3上。在浮箱甲板1之下、水面4以上的所述浮箱外侧壁3上还设置有格栅通道2;所述格栅通道2的底面与所述浮箱甲板1的距离大于等于1.8米,以方便工作人员站立在所述格栅通道2进行合拢施工作业。
如图3、4和图5所示,上述浮箱的浮箱水上合拢工艺,包括如下步骤:     (a)在浮箱甲板1之下、水面4以上的浮箱外侧壁3上设置浮箱100之间的连接结构;并且在在浮箱甲板1之下、水面4以上的所述浮箱外侧壁3上设置格栅通道2及管路电缆的连接接口;     (b)在船坞分别进行各浮箱100的独立建造,并按工艺要求处理结构的水上合拢缝和管线接口;     (c)建造好的各浮箱100依次下水出坞后,首先是两两进行水上合拢,然后再全部合拢成形;     (d)按工艺要求进行相关的装焊检验、无损探伤;     (e)按涂装工艺要求完成相关涂装工作;     (f)完工交船。 
本发明在设计阶段时,根据船坞的尺寸将大浮箱设计成若干个小浮箱100,各小浮箱100间通过浮箱甲板1下、水面4上的连接结构进行永久性连接。在建造时,按常规工艺,先在船坞进行各小浮箱100的建造、下水。然后,在水上调整各小浮箱100的浮态后,进行水上装配、焊接,将各小浮箱100连接成大浮箱。对于浮船坞的建造可以采用本发明工艺。 
上述实施例仅仅是为清楚地说明本发明创造所作的举例,而并非对本发明创造具体实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明创造权利要求的保护范围之中。 

Claims (1)

1.一种浮箱水上合拢工艺,其中该浮箱的特征包括,浮箱(100)之间的连接结构设置在浮箱甲板(1)之下、水面(4)以上的浮箱外侧壁(3)上,在浮箱甲板(1)之下、水面(4)以上的所述浮箱外侧壁(3)上还设置有格栅通道(2),所述格栅通道(2)的底面与所述浮箱甲板(1)的距离大于等于1.8米;所述浮箱水上合拢工艺包括如下步骤:     (a)在浮箱甲板(1)之下、水面(4)以上的浮箱外侧壁(3)上设置浮箱(100)之间的连接结构;并且在在浮箱甲板(1)之下、水面(4)以上的所述浮箱外侧壁(3)上设置格栅通道(2)及管路电缆的连接接口;     (b)在船坞分别进行各浮箱(100)的独立建造,并按工艺要求处理结构的水上合拢缝和管线接口;     (c)建造好的各浮箱(100)依次下水后,首先是两两进行水上合拢、然后再全部合拢成形;     (d)按工艺要求进行相关的装焊检验、无损探伤;     (e)按涂装工艺要求完成相关涂装工作;     (f)完工交船。
CN 201210104393 2012-04-11 2012-04-11 浮箱水上合拢工艺 Expired - Fee Related CN102582799B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201210104393 CN102582799B (zh) 2012-04-11 2012-04-11 浮箱水上合拢工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201210104393 CN102582799B (zh) 2012-04-11 2012-04-11 浮箱水上合拢工艺

Publications (2)

Publication Number Publication Date
CN102582799A CN102582799A (zh) 2012-07-18
CN102582799B true CN102582799B (zh) 2013-04-17

Family

ID=46472196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201210104393 Expired - Fee Related CN102582799B (zh) 2012-04-11 2012-04-11 浮箱水上合拢工艺

Country Status (1)

Country Link
CN (1) CN102582799B (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107150761B (zh) * 2017-04-28 2019-04-12 深圳蓝色海洋工程发展有限公司 大型浮体的水面建造安装方法
CN111470001A (zh) * 2019-01-22 2020-07-31 中集海洋工程研究院有限公司 超大型船舶建造方法
CN110510062A (zh) * 2019-09-17 2019-11-29 上海振华重工启东海洋工程股份有限公司 一种浮船坞水下合拢工艺
CN114872857A (zh) * 2022-05-09 2022-08-09 大连中远海运重工有限公司 大型浮船坞水上合拢对接方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1012036B1 (en) * 1997-09-08 2004-09-29 J. Ray McDermott, S.A. Mobile offshore base
CN100478248C (zh) * 2005-02-22 2009-04-15 大连新船重工有限责任公司 半条船船台建造下水及坞内漂浮合拢工艺
CN100419164C (zh) * 2005-05-26 2008-09-17 广东省航盛工程有限公司 移运大体积重型构件下水、水上浮运和构件安装的方法
CN102328729B (zh) * 2011-05-31 2013-08-14 江苏熔盛造船有限公司 一种船舶水上双岛合拢工艺

Also Published As

Publication number Publication date
CN102582799A (zh) 2012-07-18

Similar Documents

Publication Publication Date Title
CN1955066B (zh) 分体建造坞内合拢的造船方法
CN102582799B (zh) 浮箱水上合拢工艺
CN110208100A (zh) 一种应用于深海油气管道试压作业的关键设备
CN106167077B (zh) 可自主航行的超大型海上钢结构浮体及其制造方法
CN103523168B (zh) Css平台连接桥区域分段制造工艺及专用斜切胎架
CN104913769A (zh) 沉管隧道建设中管段对接的水下高精度测控系统及测控方法
CN105947144B (zh) 一种船坞内实施钻井平台与多型船舶同时建造的方法
CN102357783A (zh) 风电安装船桩靴的制作工艺
CN101817393B (zh) 利用浮船坞造船的方法
CN104802928A (zh) 半潜式平台的建造合拢方法
CN102897298A (zh) 三艘艉半船在船坞内起浮、前移、定位、落敦的方法
CN102874388A (zh) 基于模块化建造上层建筑的全回转拖船结构
CN103921905B (zh) 用于在水上组合成大型浮体的半潜式模块及其组装方法
KR100785479B1 (ko) 선박용 stl 모듈화 설치방법 및 구조
CN105292378A (zh) 液化气船单元管架无余量对接的建造方法
KR20150023182A (ko) 도크 내의 운반용 바지를 이용한 해양구조물 건조방법
CN102092458A (zh) 超大型船舶坞内漂浮二次定位工艺
CN105775057A (zh) 一种模块化自升式海工平台
CN203939485U (zh) 用于水下结构物分块安装的导向结构
CN104029789A (zh) 一种海洋平台的建造实施方法
Truelock et al. Committee V. 5: Special Vessels
CN210332192U (zh) 一种船用供给水的输送装置
CN204575079U (zh) 沉管隧道建设中管段对接的水下高精度测控系统
CN103277583B (zh) 一种无安装残余应力的海底管道海上水平口对接方法
KR20150000187A (ko) 반잠수식 바지선 출입 게이트 테스트 방법

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170317

Address after: 528437 Guangdong province Zhongshan Torch Development Zone, Cheung Hing Road 6 No. 11 South trade building, floor 1206 card

Patentee after: Guangdong Guangxin Marine Engineering Equipment Research Institute Co. Ltd.

Address before: 528437 Zhongshan Industrial Park, Torch Development Zone, Guangdong Province, weft Road, ten

Patentee before: Guangxin Shipbuilding & Heavy Industry Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130417

Termination date: 20210411