CN102561117A - 双线隧道内无碴轨道施工的物流传送方法 - Google Patents
双线隧道内无碴轨道施工的物流传送方法 Download PDFInfo
- Publication number
- CN102561117A CN102561117A CN2011104116183A CN201110411618A CN102561117A CN 102561117 A CN102561117 A CN 102561117A CN 2011104116183 A CN2011104116183 A CN 2011104116183A CN 201110411618 A CN201110411618 A CN 201110411618A CN 102561117 A CN102561117 A CN 102561117A
- Authority
- CN
- China
- Prior art keywords
- construction
- line
- tunnel
- logistics
- sand
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Machines For Laying And Maintaining Railways (AREA)
Abstract
本发明公开了一种双线隧道内无碴轨道施工的物流传送方法,I线施工时,借用尚未施工的II线位置,作为I线施工的无轨物流通道;II线施工时,将计划用于铺设在I线电缆槽内的砂子,借用铺在已完工的I线道床板外侧700mm宽的巡道槽内,在砂子上铺设木板,让运输车辆一侧车轮行驶在I线道床板中心,另一侧车轮行驶在木板上,形成临时无轨物流通道,待II线施工结束后,拆除木板,将砂子填铺回电缆槽内;隧道内每隔1km~2km设车辆调头位置,即留出50~100m范围暂不施工,供车辆调头用,待整个隧道内工程接近完工前补做;所述物流包括施工消耗性材料和周转工器具,施工消耗性材料由洞外根据需要通过运输车辆随时供应;周转性工器具由施工后方向前方作业区倒运。
Description
技术领域
本发明涉及一种双线隧道内高速铁路CRST I型双块式无碴轨道施工过程中的混凝土等物流输送方法。
背景技术
CRTS I型双块式无碴轨道技术,是在引进德国Rehda2000无碴轨道技术基础上,通过再创新形成的国内无碴轨道技术。此项技术为多工序连续流水作业,工效较高。但物流组织往往是制约施工效率的关键,需要根据现场实际进行合理组织调配。
高速铁路分为路基、桥梁、隧道三种类型,路基、桥梁可借助平行施工便道,其物流组织相对容易。但隧道工程只能借助洞内的有限空间,其物流组织相对困难。
高速铁路隧道大多为双线隧道,净宽9.2m(扣除水沟电缆槽宽度)。在双线隧道内组织无碴轨道施工,目前主要采用分步施工和同步施工两种方法:
1.分步施工法
借助尚未施工的II线位置作为I线无轨运输通道,为I线无碴轨道施工服务;当I线施工完成后,在建好的I线无碴轨道道床板上铺设临时运输轨,采用有轨运输方式作为II线施工的物流通道,为II线施工提供服务。该方法的优点是:I线施工效率高,II线施工效率较高;缺点:II线需配置临时运输轨、有轨运输设备和倒装设备,成本较高。
2.同步施工法
由隧道中心分别向洞口后退式双线同时施工,物料由汽车运送至洞内作业区域附近,利用双线宽度调头;作业区域以内由龙门吊进行立体运输;由混凝土罐车运送混凝土至作业区域附近的混凝土泵,作业区域内由混凝土泵泵送入模;小型工器具等由人工倒运。该方法的优点是:双线并行施工,便于集中管理;缺点:大部分材料、工器具需要立体倒运,所有物流车辆需在洞内调头。施工干扰大、工效低、成本高。
发明内容
针对背景技术所存在的缺陷,本发明的目的是提供一种结合现场实际和合理利用既有资源的一种双线隧道内无碴轨道施工的物流传送方法,同时具有施工效率高,投入小、成本低优点。
为达到以上目的,本发明是采取如下技术方案予以实现的:
一种双线隧道内无碴轨道施工的物流传送方法,I线施工时,借用尚未施工的II线位置,作为I线施工的无轨物流通道;其特征在于,II线施工时,将计划用于铺设在I线电缆槽内的砂子,借用铺在已完工的I线道床板外侧700mm宽的巡道槽内,在砂子上铺设木板,让运输车辆一侧车轮行驶在I线道床板中心,另一侧车轮行驶在木板上,形成临时无轨物流通道,待II线施工结束后,拆除木板,将砂子填铺回电缆槽内;隧道内每隔1km~2km设车辆调头位置,即留出50~100m范围暂不施工,供车辆调头用,待整个隧道内工程接近完工前补做;所述物流包括施工消耗性材料和周转工器具,施工消耗性材料由洞外根据需要通过运输车辆随时供应;周转性工器具由施工后方向前方作业区倒运。
上述方案中,所述消耗性材料包括双块式轨枕、结构钢筋、混凝土等,消耗性材料运输由无轨物流通道直接运送至作业区,其中双块式轨枕、结构钢筋提前由运输车辆送至洞内,所述双块式轨枕由后向前临时摆放在水沟电缆槽上,结构钢筋按一定间距摆放在作业区域,随用随取;所述混凝土用混凝土罐车直接自洞外运送至浇注工位。
所述周转性工器具包括工具轨、模板、螺杆调节器,其中工具轨、模板用随车吊在后方逐根、逐块拆除并装在车上,运送至前方施工位置,按顺序吊装就位;螺杆调节器用集装筒就地集散,用随车吊收集后方集装筒到车上,并运送至前方按间距分散摆放在作业区内。
本发明与原分步施工法相比,节省临时运输轨租赁费、运输费、铺设和拆除费用;轨道式随车吊、混凝土罐车等轨行设备购置费;工效提高20%以上;
与同步施工法相比,节省跨双线龙门吊购置费、运输费、龙门吊走形轨铺设拆除费用;混凝土泵购置费、混凝土管道安装拆除费用、湿润管道砂浆费用;工效提高35%以上;
采用本发明方法,具有投入少、工效高、充分利用既有设备资源的特点,符合大部分施工单位的管理模式,可在同类CRTS I型双块式无碴轨道施工中大力推广应用。
附图说明
以下结合附图及具体实施方式对本发明作进一步的详细说明。
图1为本发明双线隧道内无碴轨道施工的横截面布置示意图。
图中:1.无碴轨道道床板;2.承轨台;3.排水沟;4.电缆槽;5.中心排水沟;6.巡道槽;7.木板。
具体实施方式
无碴轨道施工消耗性材料主要有双块式轨枕、结构钢筋、承轨台2(预留铺设钢轨的平台)、混凝土等,由洞外根据需要随时供应;周转工器具主要有工具轨(施工用的12.5m长度的标准新钢轨)、模板、螺杆调节器等,由施工后方向前方作业区倒运;
如图1所示,本发明包括物流通道和物流方案。
物流通道:I线施工物流通道:借用尚未施工的II线位置,作为I线施工的物流通道;II线施工物流通道:将计划用于铺设在电缆槽4内的砂子,借用铺在已完工的I线道床板1外侧700mm宽的巡道槽6内,高度略低于道床板1~2cm,在砂子上铺设2cm厚的木板7(或利用小型组合钢模板、扎成捆的稻草等)防止车轮下陷,木板纵向之间用扒钉临时固定。让车辆一侧车轮行驶在道床板1中心,另一侧车轮行驶在铺设的木板7上,形成临时无轨物流通道。待II线施工结束后,拆除木板7,将砂子填铺回电缆槽4内。
当隧道较短(<2km)时,车辆一律在洞外实现调头;当隧道较长(>2km)时,应每隔1km~2km设置调头位置,即留出50~100m范围暂不施工,供车辆调头使用,待整个隧道内工程接近完工前补做。
物流方案:
(1)双块式轨枕提前由汽车送至洞内,用叉车按间距临时摆放在水沟3电缆槽4之上,开工后,用叉车按施工进度完成轨枕布设;
(2)结构钢筋提前由汽车送至洞内,按一定间距摆放在作业区域,由人工随用随取;
(3)工具轨用随车吊在后方逐根拆除并装在车上,运送至前方施工位置,按顺序吊装就位,吊装采用专用吊具辅助完成;
(4)螺杆调节器用集装筒就地集散,用随车吊收集后方集装筒到车上,并运送至前方按间距分散摆放在作业区内;
(5)模板用随车吊在后方逐块拆除并装在车上,运送至前方施工位置,按顺序吊装就位,吊装采用专用吊具辅助完成;
(6)混凝土用混凝土罐车直接自洞外运送混凝土至浇注工位,用侧向溜槽使混凝土直接入模。
在武广高铁黄秋山隧道(5.3km)、大瑶山隧道(10.5km)内施工无碴轨道时,工期紧迫、物流组织十分困难的条件下,采用了此方法进行物流组织,取得了物流顺畅、组织有序的理想效果,均提前完成了无碴轨道的施工任务。采用此法,在不增加设备投入的前提下,充分利用既有资源和洞内条件,借用I线道心及外侧作为物流通道解决II线施工问题,预留调头位置后期补做解决了车辆调头浪费时间和能耗高的问题,大大降低了施工成本,使隧道内无碴轨道物流组织更趋合理。
Claims (3)
1.一种双线隧道内无碴轨道施工的物流传送方法,I线施工时,借用尚未施工的II线位置,作为I线施工的无轨物流通道;其特征在于,II线施工时,将计划用于铺设在I线电缆槽内的砂子,借用铺在已完工的I线道床板外侧700mm宽的巡道槽内,在砂子上铺设木板,让运输车辆一侧车轮行驶在I线道床板中心,另一侧车轮行驶在木板上,形成临时无轨物流通道,待II线施工结束后,拆除木板,将砂子填铺回电缆槽内;隧道内每隔1km~2km设车辆调头位置,即留出50~100m范围暂不施工,供车辆调头时使用,待整个隧道内工程接近完工前补做;所述物流包括施工消耗性材料和周转性工器具,施工消耗性材料由洞外根据需要通过运输车辆随时供应;周转工器具由施工后方向前方作业区倒运。
2.如权利要求1所述的双线隧道内无碴轨道施工的物流传送方法,其特征在于,所述消耗性材料包括双块式轨枕、结构钢筋、混凝土,消耗性材料运输由无轨物流通道直接运送至作业区,其中双块式轨枕、结构钢筋提前由运输车辆送至洞内,所述双块式轨枕由后向前临时摆放在水沟电缆槽上;结构钢筋按一定间距摆放在作业区域,随用随取;所述混凝土用混凝土罐车直接自洞外运送至浇注工位。
3.如权利要求1所述的双线隧道内无碴轨道施工的物流传送方法,其特征在于,所述周转性工器具包括工具轨、模板、螺杆调节器,其中工具轨、模板用随车吊在后方逐根、逐块拆除后装在车上,运送至前方施工位置按顺序吊装就位;螺杆调节器用集装筒就地集散,用随车吊收集后方集装筒到车上,并运送至前方按间距分散摆放在作业区内。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011104116183A CN102561117B (zh) | 2011-12-09 | 2011-12-09 | 双线隧道内无碴轨道施工的物流传送方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011104116183A CN102561117B (zh) | 2011-12-09 | 2011-12-09 | 双线隧道内无碴轨道施工的物流传送方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102561117A true CN102561117A (zh) | 2012-07-11 |
CN102561117B CN102561117B (zh) | 2013-11-27 |
Family
ID=46407605
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011104116183A Active CN102561117B (zh) | 2011-12-09 | 2011-12-09 | 双线隧道内无碴轨道施工的物流传送方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102561117B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106758555A (zh) * | 2017-01-13 | 2017-05-31 | 中铁工程机械研究设计院有限公司 | 地铁板式道床施工方法 |
CN106988165A (zh) * | 2017-04-10 | 2017-07-28 | 中铁二院工程集团有限责任公司 | 一种用于多线高速铁路桥梁的轨道线形控制方法 |
CN107128656A (zh) * | 2017-06-26 | 2017-09-05 | 中铁十六局集团第三工程有限公司 | 一种crtsⅰ型双块式无砟轨道封闭层施工材料运输结构 |
CN110512476A (zh) * | 2019-09-05 | 2019-11-29 | 北京建工土木工程有限公司 | 一种双连拱富水隧道中软基双线轨道铺设方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2884531A1 (fr) * | 2005-04-13 | 2006-10-20 | Tso Sa | Procede de pose de voies ferrees |
-
2011
- 2011-12-09 CN CN2011104116183A patent/CN102561117B/zh active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2884531A1 (fr) * | 2005-04-13 | 2006-10-20 | Tso Sa | Procede de pose de voies ferrees |
Non-Patent Citations (1)
Title |
---|
叶敏: "浅谈客运专线隧道无砟轨道洞内施工组织", 《中小企业管理与科技》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106758555A (zh) * | 2017-01-13 | 2017-05-31 | 中铁工程机械研究设计院有限公司 | 地铁板式道床施工方法 |
CN106988165A (zh) * | 2017-04-10 | 2017-07-28 | 中铁二院工程集团有限责任公司 | 一种用于多线高速铁路桥梁的轨道线形控制方法 |
CN106988165B (zh) * | 2017-04-10 | 2018-10-19 | 中铁二院工程集团有限责任公司 | 一种用于多线高速铁路桥梁的轨道线形控制方法 |
CN107128656A (zh) * | 2017-06-26 | 2017-09-05 | 中铁十六局集团第三工程有限公司 | 一种crtsⅰ型双块式无砟轨道封闭层施工材料运输结构 |
CN107128656B (zh) * | 2017-06-26 | 2023-09-08 | 中铁十六局集团第三工程有限公司 | 一种crtsⅰ型双块式无砟轨道封闭层施工材料运输结构 |
CN110512476A (zh) * | 2019-09-05 | 2019-11-29 | 北京建工土木工程有限公司 | 一种双连拱富水隧道中软基双线轨道铺设方法 |
Also Published As
Publication number | Publication date |
---|---|
CN102561117B (zh) | 2013-11-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107653755B (zh) | 地铁区间分离式隧道内整体道床浇筑逆作式施工方法 | |
CN102146799B (zh) | 一种用于高速铁路双线隧道仰拱的施工设备 | |
CN101050615B (zh) | Cpg500型无缝线路长轨条铺轨机组铺设无缝线路轨道施工方法 | |
CN103485288A (zh) | 一种穿越既有线的双层顶进涵施工工艺 | |
CN102561117B (zh) | 双线隧道内无碴轨道施工的物流传送方法 | |
CN111852521B (zh) | 大断面盾构隧道内部结构施工用口字件拼装台车及同步施工方法 | |
CN109518544A (zh) | 一种地铁预制轨道板道床铺设方法 | |
CN103924985A (zh) | 一种与tbm掘进同步施工的现浇仰拱衬砌台车及混凝土养护系统 | |
CN203476349U (zh) | 隧道通风斜井一次性成形衬砌台车 | |
CN102174790B (zh) | 盾构施工用装配式轨枕及其施工方法 | |
CN204662270U (zh) | 一种箱梁转运系统 | |
CN203847130U (zh) | 一种与tbm掘进同步施工的现浇仰拱衬砌台车及混凝土养护系统 | |
CN103469705B (zh) | 轨排铺轨机及其铺轨方法 | |
CN202063155U (zh) | 矿井空车平移换道装置 | |
CN203419675U (zh) | 用于提梁机的行车轨道 | |
CN104929045B (zh) | 一种箱梁转运平台以及喂梁、取梁方法 | |
CN111851155A (zh) | 基于线隧同心隧道的钢弹簧浮置板施工方法 | |
CN100447029C (zh) | 地下矿石运输列车检修方法 | |
CN112962366A (zh) | 一种山区crtsⅲ型轨道板倒铺施工方法 | |
CN102747693B (zh) | 基于连续梁布设换装点的铁路t型梁架设施工方法 | |
CN205474639U (zh) | 一种用于桥面铁路铺设钢轨焊轨生产线的钢轨运输小车 | |
CN110512476B (zh) | 一种双连拱富水隧道中软基双线轨道铺设方法 | |
CN204311418U (zh) | 一种用于高陡边坡混凝土浇筑的反轨液压爬模 | |
CN207314166U (zh) | 一种跨电气化铁路营业线转体槽形连续梁中跨合拢装置 | |
CN205576656U (zh) | 一种桥面铁路铺设的钢轨焊轨生产线 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |