CN102535476A - 减少边荷载影响的方法 - Google Patents

减少边荷载影响的方法 Download PDF

Info

Publication number
CN102535476A
CN102535476A CN2010106066589A CN201010606658A CN102535476A CN 102535476 A CN102535476 A CN 102535476A CN 2010106066589 A CN2010106066589 A CN 2010106066589A CN 201010606658 A CN201010606658 A CN 201010606658A CN 102535476 A CN102535476 A CN 102535476A
Authority
CN
China
Prior art keywords
construction
backfill
side load
gsz
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010106066589A
Other languages
English (en)
Other versions
CN102535476B (zh
Inventor
万里飘
米有明
刘勇
沈波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Investigation Design and Research Institute Co Ltd SIDRI
Original Assignee
Shanghai Investigation Design and Research Institute Co Ltd SIDRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Investigation Design and Research Institute Co Ltd SIDRI filed Critical Shanghai Investigation Design and Research Institute Co Ltd SIDRI
Priority to CN201010606658.9A priority Critical patent/CN102535476B/zh
Publication of CN102535476A publication Critical patent/CN102535476A/zh
Application granted granted Critical
Publication of CN102535476B publication Critical patent/CN102535476B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种减少边荷载影响的方法,其特征是按以下步骤进行:(1)基坑放坡开挖;(2)在靠近主体结构边墙位置,先期施工回填土,形成近似垂直边坡;(3)主体结构施工;(4)结构边墙与垂直边坡间缝隙填满。以往对于回填土的施工通常在主体结构施工后进行,而在本发明中,回填土要于主体结构施工前先做,这样可以达到对地基土形成预压,减少甚至基本消除垂直边载影响;而且由于垂直边坡自稳,对结构的边墙产生的土压力极小。整个施工方案经济、方便、安全、可靠。

Description

减少边荷载影响的方法
技术领域
本发明涉及土木工程技术领域,具体说运用地下结构开挖后进行回填的一种减少边荷载影响的方法。
背景技术
目前水闸、泵站、挡土墙或其它地下结构,常采用的基坑开挖方式为放坡大开挖,待主体结构完工后再进行回填。基坑大开挖方式较其它维护开挖方式具有施工方便、投资节约的优点,但对结构常带来以下缺点:
(1)填土对结构侧壁产生很大的水平土压力。
(2)填土自重引起的竖向边荷载,致使底板顶面所受拉力明显增大。
(3)填土竖向边荷载带动相邻土体沉降,致使位于桩顶的底板与地基土体脱开,形成渗漏通道。
(4)填土竖向边荷载带动相邻土体沉降,致使临土侧结构沉降大于远离填土侧结构沉降,导致不均匀沉降。
(5)填土竖向边荷载对欠固结土和软弱土上的基桩产生负摩阻力等,带来很多不利因素。
鉴于此,有必要设计一种新的方法以解决上述问题。
发明内容
本发明要解决的技术问题是提供一种用于地下结构开挖,可以减少边荷载影响的方法,以克服现有技术中存在的缺陷。
本发明采用以下技术方案:
一种减少边荷载影响的方法,按以下步骤进行:
(1)基坑放坡开挖;
(2)在靠近主体结构边墙位置,先期施工回填土,形成近似垂直边坡;
(3)主体结构施工;
(4)结构边墙与垂直边坡间缝隙填满。
进一步地,所述垂直边坡为内置土工合成材料的土体结构。
优选地,所述土工合成材料为土工格栅。
进一步地,在施工回填土时,计算土工格栅层高、回填土中土工格栅的抗拉强度、及地基承载力。
进一步地,所述土工格栅穿过回填土土体的破裂面。
进一步地,所述土工格栅端部由土工布包裹。
以往对于回填土的施工通常在主体结构施工后进行,而在本发明中,回填土要于主体结构施工前先做,这样可以达到对地基土形成预压,减少甚至基本消除垂直边载影响;而且由于垂直边坡自稳,对结构的边墙产生的土压力极小。整个施工方案经济、方便、安全、可靠。
附图说明
图1为运用本发明涉及的减少边荷载影响的方法的施工示意图。
图2为砂质粉土地基上的挡墙施工示意图。
具体实施方式
结合图1对本发明涉及的减少边荷载影响的方法作进一步说明。图1为运用本方法的施工示意图。本方法依次按如下步骤进行:
(1)基坑正常放坡开挖(见图1中开挖面11);
(2)在靠近主体结构13边墙位置,先期施工回填土,形成近似垂直边坡12;
(3)主体结构13施工;
(4)结构边墙与垂直边坡间缝隙填满(图1中为空档回填土14)。
以往对于回填土的施工通常在主体结构施工后进行,而在本发明中,回填土要于主体结构施工前先做,越早越好,这样可以达到对地基土形成预压,减少甚至基本消除垂直边载影响;而且由于垂直边坡自稳,对结构的边墙产生的土压力极小。
另外,在实施第(2)步骤中,可以在回填土中加入土工合成材料,使回填土土体结构成为直立挡墙。优选地,可以内置土工格栅,如图1所示,土工格栅15分层置于垂直边坡内,更好地加强和保护了土体。
以图2所示的砂质粉土地基上的挡墙施工为例:
a.首先,基坑开挖至底板底高程(见图2中开挖面21);
b.然后施工直立回填土22(即垂直边坡),须分析计算土体筋材内部稳定性,包括计算土工格栅层高、回填土土体结构的抗拉强度、及土体外部稳定性,包括地基承载力;而且布置土工格栅25时必须穿过破裂面27,并延伸超过筋材有效长度,有效长度根据格栅与周围土体间的摩擦力确定,所述破裂面27与大主应力面(本图即水平面)间的夹角为回填土土体的破裂角α,见图2;考虑到格栅土体的垂直面为临时结构面,土工格栅25靠近主体结构的端部仅由土工布26包裹,不需要像永久结构那样采用钢筋混凝土板、预制混凝土模块、挂网喷浆式墙面等结构,故更加简单、经济,根据施工工期长短,可以对土工布提出抗紫外线要求。
c.主体结构23正常施工;
d.最后将主体结构与垂直边坡间的空隙用土填满即可(图2中为空档回填土24)。

Claims (6)

1.一种减少边荷载影响的方法,其特征是按以下步骤进行:
(1)基坑放坡开挖;
(2)在靠近主体结构边墙位置,先期施工回填土,形成近似垂直边坡;
(3)主体结构施工;
(4)结构边墙与垂直边坡间缝隙填满。
2.根据权利要求1所述的减少边荷载影响的方法,其特征是:所述垂直边坡为内置土工合成材料的土体结构。
3.根据权利要求2所述的减少边荷载影响的方法,其特征是:所述土工合成材料为土工格栅。
4.根据权利要求3所述的减少边荷载影响的方法,其特征是:在施工回填土时,计算土工格栅层高、回填土中土工格栅的抗拉强度、及地基承载力。
5.根据权利要求4所述的减少边荷载影响的方法,其特征是:所述土工格栅穿过回填土土体的破裂面。
6.根据权利要求5所述的减少边荷载影响的方法,其特征是:所述土工格栅端部由土工布包裹。
CN201010606658.9A 2010-12-27 2010-12-27 减少边荷载影响的方法 Active CN102535476B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010606658.9A CN102535476B (zh) 2010-12-27 2010-12-27 减少边荷载影响的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010606658.9A CN102535476B (zh) 2010-12-27 2010-12-27 减少边荷载影响的方法

Publications (2)

Publication Number Publication Date
CN102535476A true CN102535476A (zh) 2012-07-04
CN102535476B CN102535476B (zh) 2014-06-18

Family

ID=46343381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010606658.9A Active CN102535476B (zh) 2010-12-27 2010-12-27 减少边荷载影响的方法

Country Status (1)

Country Link
CN (1) CN102535476B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107330146A (zh) * 2017-05-26 2017-11-07 昆明理工大学 一种同时考虑平动和转动效应的节理岩质边坡极限承载力分析上限法

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0754365A (ja) * 1993-08-19 1995-02-28 Tokyo Gas Co Ltd 大深度埋め戻し工事における埋め戻し材の投入方法及び その装置
JPH0988103A (ja) * 1995-09-20 1997-03-31 Shimizu Corp 地中構造物の施工方法
CN1730841A (zh) * 2005-08-05 2006-02-08 贾燎 一种压密石灰土换填实体边坡支护方法
CN2851347Y (zh) * 2005-12-27 2006-12-27 四平市水利勘测设计研究院 新型加筋土结构护岸挡墙
CN101024964A (zh) * 2007-03-14 2007-08-29 姚攀峰 吸力调节支护结构及其施工方法
CN201106179Y (zh) * 2007-10-29 2008-08-27 朱逸义 一种生态加筋挡土墙结构
CN101289866A (zh) * 2007-04-16 2008-10-22 上海市第七建筑有限公司 软土地基下基坑工程中局部深坑预制混凝土胎模施工方法
CN201158826Y (zh) * 2008-02-25 2008-12-03 山东玮丰达建筑工程有限公司 土工格栅加筋挡土墙
CN101624830A (zh) * 2009-08-11 2010-01-13 长江水利委员会长江科学院 土工格栅处理膨胀土渠道边坡的方法
CN101725149A (zh) * 2009-12-15 2010-06-09 中铁二局股份有限公司 长大明挖隧道施工方法

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0754365A (ja) * 1993-08-19 1995-02-28 Tokyo Gas Co Ltd 大深度埋め戻し工事における埋め戻し材の投入方法及び その装置
JPH0988103A (ja) * 1995-09-20 1997-03-31 Shimizu Corp 地中構造物の施工方法
CN1730841A (zh) * 2005-08-05 2006-02-08 贾燎 一种压密石灰土换填实体边坡支护方法
CN2851347Y (zh) * 2005-12-27 2006-12-27 四平市水利勘测设计研究院 新型加筋土结构护岸挡墙
CN101024964A (zh) * 2007-03-14 2007-08-29 姚攀峰 吸力调节支护结构及其施工方法
CN101289866A (zh) * 2007-04-16 2008-10-22 上海市第七建筑有限公司 软土地基下基坑工程中局部深坑预制混凝土胎模施工方法
CN201106179Y (zh) * 2007-10-29 2008-08-27 朱逸义 一种生态加筋挡土墙结构
CN201158826Y (zh) * 2008-02-25 2008-12-03 山东玮丰达建筑工程有限公司 土工格栅加筋挡土墙
CN101624830A (zh) * 2009-08-11 2010-01-13 长江水利委员会长江科学院 土工格栅处理膨胀土渠道边坡的方法
CN101725149A (zh) * 2009-12-15 2010-06-09 中铁二局股份有限公司 长大明挖隧道施工方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107330146A (zh) * 2017-05-26 2017-11-07 昆明理工大学 一种同时考虑平动和转动效应的节理岩质边坡极限承载力分析上限法
CN107330146B (zh) * 2017-05-26 2020-08-25 昆明理工大学 一种考虑转动效应的岩质边坡极限承载力分析上限法

Also Published As

Publication number Publication date
CN102535476B (zh) 2014-06-18

Similar Documents

Publication Publication Date Title
CN106150506B (zh) 一种出入口明挖段倒挂井壁施工方法
CN204645075U (zh) 一种城市道路软土地基地下管道加固装置
CN104234080B (zh) 用于防止在高水位液化地区发生变形的地下综合管廊结构
CN104234056B (zh) 用于防止高水位液化地区地下综合管廊变形的施工方法
CN105953078B (zh) 高压燃气管道的保护装置及保护方法
CN105239586A (zh) 一种支护基坑的支撑结构及其支护基坑的方法
CN103410152B (zh) 一种用于狭长深基坑土方开挖的施工方法
CN106869138A (zh) 一种衡重式双排桩支护结构及其基坑开挖方法
CN107165173A (zh) 一种基坑支护体系及其施工方法
CN206902734U (zh) 一种软基地区的地面结构
CN108330963A (zh) 一种用于土体内部既有桩基接桩的施工装置
CN110241863B (zh) 软土基坑开挖过程管廊变形控制装置及其控制方法
CN106149624B (zh) 一种适用于淤泥质土地基的重力式码头及其施工方法
CN204343341U (zh) 阶梯式隔振沟
RU2371547C1 (ru) Способ укрепления откосов и щелеобразователь для его осуществления
CN102535476B (zh) 减少边荷载影响的方法
RU121275U1 (ru) Армированная грунтоцементная стена для защиты зданий и сооружений от откапываемого вблизи котлована
CN205557535U (zh) 拱形排桩式复合挡土墙
CN204940310U (zh) 一种组合支挡结构
CN212642730U (zh) 一种湿陷性黄土地区隧道穿越人防结构
CN105019462B (zh) 吊脚嵌岩灌注桩围护基坑开挖方法
CN208441113U (zh) 一种土工袋加固地基并维护地下管道基础
CN202402795U (zh) 在富水流砂地层中开挖隧道所遇管线的支护装置
CN107447775A (zh) 滑坡灾害体造地排水加筋土挡墙结构
CN204401661U (zh) 套叠式隔振沟

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant